W912PL-18-B-0005_Solicitation_Specifications.pdf
PDF 3 MB Posted
- Attached to
- Mechanical and Electrical Work Whittier Narrows Dam Federal contract opportunity
- Solicitation number
- W912PL-18-B-0005
About this file
Solicitation - Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.pdf | ||
| W912PL-18-B-0005_Amendment0002.pdf | ||
| W912PL-18-B-0005_Amendment0001_Specifications.pdf | ||
| W912PL-18-B-0005_Amendment0001_Plans.pdf | ||
| FIO-W912PL-18-B-0005_SiteVisit_AttendeeList.pdf | ||
| W912PL-18-B-0005_Solicitation_Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB NO: W912PL-18-B-0005
U.S. ARMY CORPS OF ENGINEERS
LOS ANGELES DISTRICT
Whittier Narrows Dam, El Monte, Interim Risk Reduction Measure (IRRM), El Monte, CA
Los Angeles County, California
Construction Solicitation and Specifications
Unrestricted-Full and Open Competition
Solicitation July 2018
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
IMPORTANT - The "offer" section on the reverse must be fully completed by the offeror.
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
9. FOR INFORMATION CALL
A. NAME B. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date):
11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12B. CALENDAR DAYS
YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212
Designed using Perform Pro, WHS/DIOR, Oct 96
1442-103 STANDARD FORM 1442 (REV. 4-85) (EG)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
W912PL-18-B-0005 x 23 July 2018 1 OF 2
USACE, Los Angeles District Contracting Division, West Region Branch 915 Wilshire Blvd, Ste 1400 Los Angeles, CA 90017 wendell.l.mendoza@usace.army.mil
See Item 7
Wendell L. Mendoza 213-452-3308
Whittier Narrows Dam, El Monte, Interim Risk Reduction Measure (IRRM), El Monte, CA (LA County)
The Government is seeking qualified, experienced sources capable of replacing the existing mechanical system for controlling the Tainter gates with a redundant and resilient electromechanical system, including a Programmable Logic Controller (PLC). Work includes removing the existing gate height instrumentation and sheaves, associated ropes/chains, and weights in the existing Control Well that is approximately 18 feet in depth. A 6-inch motor actuated valve, a 6-inch manual valve, a 90 degree elbow, instrumentation (inside the pier control wells, within the basin, and on the Tainter gates), and a primary PLC with a backup PLC and Human-Machine Interface in the control house will all need to be installed, programmed, calibrated, and tested. The site of the project is Whittier Narrows Dam, El Monte, CA.
The estimated cost range of this procurement is $5,000,000 - $10,000,000.
This solicitation is issued as a full and open competition under The NAICS code is 237990 - Other Heavy and Civil Engineering Construction. The size standard for this code is $36,500,000.
This project may be revised, delayed, postponed, or canceled until the final award is made.
10 see 007300
X X *Section 00 73 00
X 10
0 2:00 PM
August 23 2018
X
OFFER (Must be fully completed by offeror)
STANDARD FORM 1442 BACK (REV. 4-85)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal or greater than the minimum requirement stated in 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24.SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BYCODE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to the issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and
(c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD. (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN
(Type or print)
30B. SIGNATURE 30C. DATE
31A. NAME OF CONTRACTING OFFICER (Type or print)
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
DUNS NO.: TAX ID NO.:
CAGE CODE NO.:
( ) - ; FAX ( ) -
SEE PRICING SCHEDULE
Whittier Narrows Interim Risk Reduction Measure W912PL-18-B-0005
PROJECT TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 05 CERTIFICATION PAGE
00 10 00 CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
00 21 13 INNSTRUCTIONS TO BIDDERS
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 70 00 CONDITIONS OF THE CONTRACT
00 73 00 SUPPLEMENTARY CONDITIONS
00 73 46 WAGE DETERMINATIONS (RATES)
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 30 DIVERSION AND CONTROL OF WATER
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 05 - METALS
05 05 23 STRUCTURAL WELDING
05 50 03 METALWORK FABRICATION, MACHINE WORK, MISCELLANEOUS
PROVISIONS
DIVISION 09 - FINISHES
09 97 02 PAINTING: HYDRAULIC STRUCTURES
DIVISION 26 - ELECTRICAL
26 05 00 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19 INSULATED WIRE AND CABLE
26 20 00 INTERIOR DISTRIBUTION SYSTEM
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 01 43 WIRE ROPE FOR GATE OPERATING DEVICES
DIVISION 40 - PROCESS INTERCONNECTIONS
40 05 13 PIPELINES, LIQUID PROCESS PIPING
40 95 00 PROCESS CONTROL
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
Section 00 01 05 - Page 1 of 1
SECTION 00 01 05
Certification Page
CERTIFICATE OF OFFEROR’S PRINCIPAL
(1) IF THE OFFEROR IS PARTNERSHIP OR JOINT VENTURE, LIST FULL NAME OF ALL
PARTNERS/ JOINT VENTURERS (Add addendum as necessary):
(Company Name) (Signature) (Title)
(Company Name) (Signature) (Title)
(Company Name) (Signature) (Title)
(2) IF THE OFFEROR IS A CORPORATION, THE FOLLOWING CERTIFICATION SHOULD BE
COMPLETED:
CERTIFICATION AS TO CORPORATE PRINCIPAL
I, , certify that I am the Secretary of the corporation named as principal in the within SF 1442; that , who signed the SF 1442 at Block 20B on behalf of the principal, was the of the corporation; that I know the individual’s signature and that his/her signature is genuine; and that said Offer was duly signed, sealed and attested for on behalf of said corporation by authority of its governing body.
CORPORATE PRINCIPAL
CORPORATE SEAL
SECRETARY
(3) IF THE OFFEROR IS A LIMITED LIABILITY COMPANY/PARTNERSHIP, LIST FULL NAME OF
ALL MANAGERS BELOW (Add addendum as necessary). SIGNATURES BY ALL MANAGERS HERE
SIGNIFY THAT THAT THE INDIVIDUAL WHO SIGNED THE OFFER IN BLOCK 20B OF THE
SF 1442 HAS THE AUTHORITY TO BIND THE LIMITED LIABILITY COMPANY/PARTNERSHIP.
(Officer’s Name) (Signature) (Title)
(Officer’s Name) (Signature) (Title)
(Officer’s Name) (Signature) (Title)
Section 00 10 00 - Page 1 of 6
SECTION 00 10 00
SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, MATERIAL, EQUIPMENT, ETC.
NECESSARY TO PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS
AND CONDITIONS SET FORTH IN THE CONTRACT TO INCLUDE ALL
ATTACHMENTS THERETO.
BASE ITEMS:
Line Item Estimated Unit of Unit Total No. Description Quantity Measure Price Price
0001 Control Well Demolition 9 EA $__________ $__________
0002 Gate Indicator Demolition 9 EA $__________ $__________
0003 Installation of New Mechanical 9 EA $__________ $__________ Components in the Control Well
0004 Installation of New Electrical 1 EA $__________ $__________ Control System, Power and PLC
ESTIMATED AMOUNT BASE BID: $_______________
(Line Items 0001 through 0004)
OPTION ITEMS:
0005 (OPTION 1) Wire Rope 1 JOB JA $__________ Assembly for Gate No. 8
0006 (OPTION 2) Wire Rope 1 JOB JA $__________ Assembly for Gate Nos. 1 thru 7, and Gate No. 9
0007 (OPTION 3) 18 Each, 36-Inch 1 JOB JA $__________ Float Sheave Assemblies, 18 Each, 30-Inch Float Sheave Assemblies and 18 Each, 8-inch Directional Sheave Assemblies
ESTIMATED AMOUNT OF OPTION ITEMS: $_______________
(Line Items 0005 through 0007)
TOTAL ESTIMATED AMOUNT BASE BID PLUS OPTION ITEMS: $_______________
(Line Items 0001 through 0007)
Section 00 10 00 - Page 2 of 6
252.236-7008 CONTRACT PRICES - BIDDING SCHEDULES. (DEC 1991)
(a) The Government's payment for the items listed in the Bidding Schedule shall constitute full compensation to the Contractor for --
(1) Furnishing all plant, labor, equipment, appliances, and materials; and
(2) Performing all operations required to complete the work in conformity with the drawings and specifications.
(b) The Contractor shall include in the prices for the items listed in the Bidding Schedule all costs for work in the specifications, whether or not specifically listed in the Bidding Schedule.
(End of provision) Directions for delivery OF OFFERS
Envelopes/Packages Sealed and Marked as follows: Envelopes/packages containing offers must be sealed; marked showing the time and date specified for receipt; the solicitation number; and the name and address of the Offeror.
Solicitation No. W912PL-18-B-0005
Closing Date and Time: See SF-1442, Block 13.
Name of the firm submitting the Offer
Addressed to:
USACE, LOS ANGELES DISTRICT,
CONTRACTING DIVISION, WEST REGION BRANCH,
ATTN: Wendell L. Mendoza/Patricia Bonilla
915 WILSHIRE BLVD, SUITE 930,
LOS ANGELES, CA 90017
Section 00 10 00 - Page 3 of 6
SPECIAL INSTRUCTIONS PERTAINING TO HAND-CARRIED OFFERS:
Due to security precautions, offerors are no longer permitted to hand-carry their offers directly to Contacting Division. All deliveries of offers are now required to arrive on the 11th floor at 915 Wilshire Blvd, Los Angeles, California 90017 and contact the Contracting Division, Wendell L. Mendoza at 213-452-3308 to meet you at the 11th floor elevator lobby. Offerors will be required to go through a security screening. Due to the limited space of the bid room, bidders are requested to bring no more than 2 personnel per firm. A wall telephone is provided in the elevator lobby on the 11th floor for official use only. Use this phone to contact the Contract Specialist listed above. Security personnel on the 11th floor can assist.
For those offers to be submitted prior to the scheduled day of receipt please must notify the Contracting Division to arrange for receipt of their Offer by Contracting Division personnel. Normally the contact will be the Contract Specialist(s) as designated above, but any of the telephone extensions for the Contracting Division can be dialed (see USACE Los Angeles District telephone listing next to wall telephone). In the event the Contract Specialist(s) cannot be reached, please call the following Contracting Division telephone number, 213-452-3670
At approximately 15 minutes prior to the scheduled Offer time/date deadline, Contracting Division personnel will be on the 11th floor elevator lobby to collect remaining offers and call the official closing time.
OFFEROR'S CHECKLIST
PART 1 GENERAL
1.1 OFFEROR'S CHECKLIST
All information required by the terms of the Solicitation must be furnished. MISTAKES OR OMISSIONS CAN BE COSTLY. Important items for you to check are included in but not limited to, those listed below. This checklist is furnished only to assist you in submitting a complete Bid. Check as you read.
Section 00 10 00 - Page 4 of 6
|_| Have you acknowledged all amendments?
|_| Is your SF-1442, Certificate of Corporate Principal and CLIN sheet properly completed and signed?
[ ] Is a bid bond included with your bid? (A late bid bond is treated the same as a late bid.)
[ ] Is your bid bond in the proper amount?
[ ] Is the bond properly signed by both the Offeror and Surety and are all required seals affixed?
[ ] Is the name in which you submitted the bid the same on your bid as on your bid bond?
[ ] Are all erasures or corrections initialed by the person signing the bid?
[ ] Have you restricted your bid by altering the provisions of the solicitation?
[ ] Is the envelope containing your bid properly identified that it is a bid and does it contain the correct solicitation number and bid due date and time?
Section 00 10 00 - Page 5 of 6
[ ] Will your bid arrive on time? Late hand-carried bids will not be considered. Late bids or modifications will be handled in accordance with FAR 52.214-1 Submissions, Modifications, Revisions, and Withdrawals of bids.
ADDITIONAL BIDDER'S NOTES:
1. All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the bid.
2. Prices must be submitted on all individual items of the Solicitation, Contract Line Item Number (CLIN) Schedule. Failure to do so may cause the bid to be determined “non-responsive.”
3. For the purpose of initial evaluation of bids, the following will be utilized in resolving arithmetic discrepancies found on the face of the Price Schedule as submitted by the bidder:
a. Obviously misplaced decimal points will be corrected;
b. In case of discrepancy between the unit price and the extended price, the unit price will govern;
c. Apparent errors in extensions of unit prices will be corrected;
d. Apparent errors in addition of lump sum and extended prices will be corrected.
4. The Contract Clause 52.232-27, "Prompt Payment for Construction Contracts" requires that the name and address of the contractor official, to whom payment is to be sent, be the same as that in the contract or in a proper Notice of Assignment.
5. Principal Contracting Officer. The Contracting Officer who signs this contract will be the Principal Contracting Officer for this contract. However, any Contracting Officer assigned to the Los Angeles District, Contracting within his authority, may take formal action on this contract when the Principal Contracting Officer is unavailable and the action needs to be taken.
6. Amounts and prices shall be indicated in either words or figures, NOT BOTH.
7. The bidder/offeror shall distribute indirect costs (overhead, profit, bond, etc) over all items in the Contract Line Item Number (CLIN) Schedule. The Government will review all submitted Solicitation, Contract Line Item Number (CLIN) Schedules for any unbalancing of the items. Any submitted Solicitation, Contract Line Item Number (CLIN) Schedule determined to be unbalanced may cause the bidder to be ineligible for award.
Section 00 10 00 - Page 6 of 6
8. The bidder shall furnish all plant, labor, material, equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in the contract in include all attachments thereto.
9. Some quantities are ESTIMATED, the bidders prices MUST BE FIRM.
10. Bidder is cautioned to check his Price Schedule carefully prior to submission. If the Price Schedule contains unit prices, they should be round off to the second decimal point only NOT EXTENDED FURTHER.
11. Payment of Electronic Funds Transfer (EFT) is the mandatory method of payment. The Contractors attention is directed to Contract Clause NO. 52.232-33 “Mandatory Information for Electronic Funds Transfer” located in Section 00 70 00 Conditions of the Contract.
12. Contractor is required to fill in Cage code, TIN and DUNS Number in Block No. 14 on Standard Form 1442, the Name and Address Block.
Section 00 21 13 - Page 1 of 15
Section 00 21 13 Instructions to Bidders
Table of Contents
52.0000-4010 INQUIRIES
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2016) 252.204-7004 ALTERNATE A, SYSTEM FOR
AWARD MANAGEMENT (FEB 2014)
52.209-4501 CONTRACTOR REPONSIBILITY, PRE-AWARD SURVEY
52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL
SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-29 (AUG 1998)
52.211-2 AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA ITEM DESCRIPTIONS
LISTED IN THE ACQUISITION STREAMLINING AND STANDARDIZATION INFORMATION SYSTEM
(ASSIST) (APR 2014)
52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
52.214-5 SUBMISSION OF BIDS (DEC 2016)
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)
52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991)
52.0214-4599 EVALUATION FOR AWARD
52.216-1 TYPE OF CONTRACT (APR 1984)
52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL BUSINESS
CONCERNS (OCT 2014)
52.219-4003 SMALL BUSINESS AND SMALL DISADVANTAGED BUSINESS SUBCONTRACTING
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)12
52.225-12 NOTICE OF BUY AMERICAN ACT REQUIREMENT-- CONSTRUCTION MATERIALS (MAY
2014) - ALTERNATE I (MAY 2014)
52.228-1 BID GUARANTEE (SEP 1996)
52.233-2 SERVICE OF PROTEST (SEP 2006)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Section 00 21 13 - Page 2 of 15
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
52.0000-4010 INQUIRIES
Any prospective offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders/offerors before submission of their bids/offers. Oral explanations or instructions given before award of a contract are not binding. Any information given to a prospective offeror concerning a solicitation will be furnished promptly to all other prospective offerors as an amendment to the solicitation, if that information is necessary in submitting offers or if lack of it would be prejudicial to other prospective bidders/offerors.
1. All inquiries relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet/
A. To submit and review bid inquiry items, offerors will need to be a current registered user, self register into the ProjNet system.
To access the Bid Inquiry system, go to the ProjNet web page and fill in:
- Managing Agency – USACE
- Email address
- Key Access (this is the Bidder Inquiry Key – see below for key)
- Click on “Sign In”
- You will be prompted for the answer to your secret question on the next screen
If this is your first time accessing ProjNet, you will be directed to a screen titled, “User account not found. Please create one using the form below.” Fill in the requested information (name, company, city, phone #, etc.).
B. From this page, you may view all bidder inquiries or add an inquiry. Please note: Offerors shall only submit one question per inquiry. All inquiries containing multiple questions may be rejected.
C. Offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
The Solicitation Number is: W912PL-18-B-0005
The Bidder Inquiry Key is: VKT2AH-68HI6R
2. The Bidder Inquiry System will be unavailable for new inquires up to 5 business days prior to bid/proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary.
Section 00 21 13 - Page 3 of 15
3. Offerors are requested to review the specifications in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
4. The ProjNet call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the ProjNet Call Center is 800-428-HELP.
5. Responses on the Bidder Inquiry System do not revise, change, amend or supersede the provisions of the solicitation. Changes to the solicitation must be by written amendment thereto.
Any Bidder Inquiry System response that can be interpreted to be in conflict with the solicitation or amendment, shall be subordinate to the conflicting provision, term, and/or note, wherever it appears in the solicitation, until revised or altered by a written amendment to the solicitation.
Additionally, offerors may not anticipate a change to the solicitation until the change, revision, correction, or alteration of the solicitation is actually made, in writing and published as an amendment to the solicitation.
(End of Provision)
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2016) 252.204-7004 ALTERNATE A,
SYSTEM FOR AWARD MANAGEMENT (FEB 2014)
(a) Definitions. As used in this provision—
“System for Award Management (SAM) database” means the primary Government repository for contractor information required for the conduct of business with the Government.
“Commercial and Government Entity (CAGE) code” means—
(1) A code assigned by the Defense Logistics Information Service (DLIS) to identify a commercial or Government entity; or
(2) A code assigned by a member of the North Atlantic Treaty Organization that DLIS records and maintains in the CAGE master file. This type of code is known as an “NCAGE code.”
“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.
“Data Universal Numbering System +4 (DUNS+4) number” means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts (see FAR 32.11) for the same parent concern.
Section 00 21 13 - Page 4 of 15
“Registered in the System for Award Management (SAM) database” means that—
(1) The contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, and Contractor and Government Entity (CAGE) code into the SAM database; and
(2) The contractor has completed the Core Data, Assertions, Representations and Certifications, and Points of Contact sections of the registration in the SAM database;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The Contractor will be required to provide consent for TIN validation to the Government as part of the SAM registration process; and
(4) The Government has marked the record “Active.”
(b)(1) By submission of an offer, the Offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ``Unique Entity Identifier'' followed by the unique entity identifier that identifies the Offeror's name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the Contracting Officer to verify that the Offeror is registered in the SAM database.
(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:
(1) Company legal business name.
(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(3) Company physical street address, city, state, and Zip Code.
(4) Company mailing address, city, state and Zip Code (if separate from physical).
(5) Company telephone number.
(6) Date the company was started.
(7) Number of employees at your location.
(8) Chief executive officer/key manager.
(9) Line of business (industry).
(10) Company headquarters name and address (reporting relationship within your entity).
(d) If the Offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) Offerors may obtain information on registration at https://www.acquisition.gov.
(End of clause)
Section 00 21 13 - Page 5 of 15
52.209-4501 CONTRACTOR REPONSIBILITY, PRE-AWARD SURVEY
In order to determine a contractor’s responsibility for purposes of contract award in accordance with FAR Part 9, a statement regarding previous experience in performing comparable work, and/or plant to be used in performing the work is required. After the bid opening, the Government will request this information and set a due date for its submission.
52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL
SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-
29 (AUG 1998)
(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to--GSA Federal Supply Service, Specifications Section, Suite 8100, 470 East L'Enfant Plaza, SW, Washington, DC 20407, Telephone (202) 619-8925, Facsimile (202) 619-8978.
(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision.
Additional copies will be issued for a fee.
52.211-2 AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA ITEM
DESCRIPTIONS LISTED IN THE ACQUISITION STREAMLINING AND STANDARDIZATION
INFORMATION SYSTEM (ASSIST) (APR 2014)
(a) Most unclassified Defense specifications and standards may be downloaded from the following ASSIST websites:
(1) ASSIST (https://assist.dla.mil/online/start/);
(2) Quick Search (http://quicksearch.dla.mil/);
(3) ASSISTdocs.com (http://assistdocs.com).
(b) Documents not available from ASSIST may be ordered from the Department of Defense Single Stock Point (DoDSSP) by--
(1) Using the ASSIST Shopping Wizard (https://assist.dla.mil/wizard/index.cfm);
(2) Phoning the DoDSSP Customer Service Desk (215) 697-2179, Mon-Fri, 0730 to 1600 EST; or
(3) Ordering from DoDSSP, Building 4, Section D, 700 Robbins Avenue, Philadelphia, PA 19111-5094, Telephone
(215) 697-2667/2179, Facsimile (215) 697-1462.
(End of provision)
Section 00 21 13 - Page 6 of 15
52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY
PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)
Any contract awarded as a result of this solicitation will be DX rated order; X DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation. [Contracting Officer check appropriate box.]
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.
(b) (1) Bidders shall acknowledge receipt of any amendment to this solicitation--
(i) By signing and returning the amendment;
(ii) By identifying the amendment number and date in space provided for this purpose on the form for submitting a bid;
(iii) By letter;
(iv) By facsimile, if facsimile bids are authorized in the solicitation; or
(v) By email, if email bids are authorized in the solicitation.
(2) The Government must receive the acknowledgement by the time and at the place specified for receipt of bids.
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments.
The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.
52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
Section 00 21 13 - Page 7 of 15
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV
1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
Section 00 21 13 - Page 8 of 15
(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for receipt of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including--
(1) Lump sum bidding;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of subparagraphs (1) through (3) above.
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
(a) The Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government, considering only price and the price-related factors specified elsewhere in the solicitation.
(b) The Government may reject any or all bids, and waive informalities or minor irregularities in bids received.
(c) The Government may accept any item or combination of items, unless doing so is precluded by a restrictive limitation in the solicitation or the bid.
(d) The Government may reject a bid as nonresponsive if the prices bid are materially unbalanced between line items or subline items. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated in relation to cost for other work, and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low evaluated bid, or if it is so unbalanced as to be tantamount to allowing an advance payment.
(End of provison)
Section 00 21 13 - Page 9 of 15
52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)
Offers submitted in response to this solicitation shall be in the English language. Offers received in other than English shall be rejected.
52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991)
Offers submitted in response to this solicitation shall be in terms of U.S. dollars. Offers received in other than U.S.
dollars shall be rejected.
52.0214-4599 EVALUATION FOR AWARD
The Government contemplates award of one contract to the responsive, responsible bidder who submits the low bid for the total of all the items in the Bidding Schedule.
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a FIRM FIXED PRICE contract resulting from this solicitation.
52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE
SMALL BUSINESS CONCERNS (OCT 2014)
(a) Definitions. See 13 CFR 125.6(e) for definitions of terms used in paragraph (d).
(b) Evaluation preference. (1) Offers will be evaluated by adding a factor of 10 percent to the price of all offers, except--
(i) Offers from HUBZone small business concerns that have not waived the evaluation preference; and
(ii) Otherwise successful offers from small business concerns.
(2) The factor of 10 percent shall be applied on a line item basis or to any group of items on which award may be made. Other evaluation factors described in the solicitation shall be applied before application of the factor.
(3) When the two highest rated offerors are a HUBZone small business concern and a large business, and the evaluated offer of the HUBZone small business concern is equal to the evaluated offer of the large business after considering the price evaluation preference, award will be made to the HUBZone small business concern.
Section 00 21 13 - Page 10 of 15
(c) Waiver of evaluation preference. A HUBZone small business concern may elect to waive the evaluation preference, in which case the factor will be added to its offer for evaluation purposes. The agreements in paragraphs
(d) and (e) of this clause do not apply if the offeror has waived the evaluation preference.
___ Offeror elects to waive the evaluation preference.
(d) Agreement. A HUBZone small business concern agrees that in the performance of the contract, in the case of a contract for
(1) Services (except construction), at least 50 percent of the cost of personnel for contract performance will be spent for employees of the concern or employees of other HUBZone small business concerns;
(2) Supplies (other than procurement from a nonmanufacturer of such supplies), at least 50 percent of the cost of manufacturing, excluding the cost of materials, will be performed by the concern or other HUBZone small business concerns;
(3) General construction. (i) At least 15 percent of the cost of contract performance to be incurred for personnel will be spent on the prime contractor's employees;
(ii) At least 50 percent of the cost of the contract performance to be incurred for personnel will be spent on the prime contractor's employees or on a combination of the prime contractor's employees and employees of HUBZone small business concern subcontractors;
(iii) No more than 50 percent of the cost of contract performance to be incurred for personnel will be subcontracted to concerns that are not HUBZone small business concerns; or
(4) Construction by special trade contractors. (i) At least 25 percent of the cost of contract performance to be incurred for personnel will be spent on the prime contractor's employees;
(ii) At least 50 percent of the cost of the contract performance to be incurred for personnel will be spent on the prime contractor's employees or on a combination of the prime contractor's employees and employees of HUBZone small business concern subcontractors;
(iii) No more than 50 percent of the cost of contract performance to be incurred for personnel will be subcontracted to concerns that are not HUBZone small business concerns.
(e) A HUBZone joint venture agrees that the aggregate of the HUBZone small business concerns to the joint venture, not each concern separately, will perform the applicable percentage of work requirements.
(f)(1) When the total value of the contract exceeds $25,000, a HUBZone small business concern nonmanufacturer agrees to furnish in performing this contract only end items manufactured or produced by HUBZone small business concern manufacturers.
(2) When the total value of the contract is equal to or less than $25,000, a HUBZone small business concern nonmanufacturer may provide end items manufactured by other than a HUBZone small business concern manufacturer provided the end items are produced or manufactured in the United States.
(3) Paragraphs (f)(1) and (f)(2) of this section do not apply in connection with construction or service contracts.
(g) Notice. The HUBZone small business offeror acknowledges that a prospective HUBZone awardee must be a HUBZone small business concern at the time of award of this contract. The HUBZone offeror shall provide the Contracting Officer a copy of the notice required by 13 CFR 126.501 if material changes occur before contract award
Section 00 21 13 - Page 11 of 15 that could affect its HUBZone eligibility. If the apparently successful HUBZone offeror is not a HUBZone small business concern at the time of award of this contract, the Contracting Officer will proceed to award to the next otherwise successful HUBZone small business concern or other offeror.
52.219-4003 SMALL BUSINESS AND SMALL DISADVANTAGED BUSINESS
SUBCONTRACTING
Offerors are cautioned that failure to comply in good faith with the CONTRACT CLAUSE entitled (1) "Utilization of Small, Small Disadvantaged and Women- Owned Small Business Concerns, FAR 52-219-8" and (2) Small, Small Disadvantaged and Women-Owned Small Business Subcontracting Plan, FAR 52.219- 9 (Alternate I)," when applicable, will be a material breach of contract. In order to assist prime contractors in developing a source list of Small and Small Disadvantaged Business Concerns, you are encouraged to contact Minority Contractor Associations, the Minority Business Development Agency, and the appropriate General Business Service Centers in your standard Metropolitan Statistical Area, addresses of which may be obtain from:
Write: US Army Engineer District, Los Angeles ATTN: Small Business Specialist 915 Wilshire Blvd Suite 930 Los Angeles, California 90017
Telephone: Eric Ravelli Small and Disadvantaged Business Utilization Specialist Area Code (213) 452-3938
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
28.3% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in
Section 00 21 13 - Page 12 of 15 the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Los Angeles County, California.
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS
(MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
Section 00 21 13 - Page 13 of 15
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
52.225-12 NOTICE OF BUY AMERICAN ACT REQUIREMENT-- CONSTRUCTION
MATERIALS (MAY 2014) - ALTERNATE I (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American-- Construction Materials Under Trade Agreements” (Federal…