AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 77
0002 Jul 11, 2017
W912PL
USACE, Los Angeles District 915 Wilshire Boulevard, Suite 930 Los Angeles, California 90017-3401 Attn:Contracting Division CESPL-CT-W
SEE ITEM 6
W912PL-17-B-0002
Jun 13, 2017
Sediment Removal, San Luis Rey River Flood Control Project, City of Oceanside, San Diego County,California
Amendment issued to revise the bid opening date to 27 July 2017, 1:00 PM, see the SF 30 Block 14 Continuation Page regarding other sections changed.
INSTRUCTIONS
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code) . Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date) .
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By) . Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor) . For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Item 9, (Amendment of Solicitation No. - Dated), and 10, (Modification of Contract/Order No. - Dated ). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data) .
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries.
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B . The contracting officer's signature is not required on solicitation amendments. The contracting offier's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13 . Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification) .
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
Total contract price increased by $
Total contract price decreased by $
Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
A reference to the letter determination; and
A statement of the net amount determined to be due in settlement of the contract.
(g)
(h)
(i)
(ii)
(1)
(2)
(3)
(4)
(5)
(6)
(i)
(ii)
(iii)
STANDARD FORM 30 (REV. 10-83) BACK
(1) Accounting classification Net increase $
Replace With Project Header
SF 30 CONTINUATION PAGE 1 OF 1
SF 30 BLOCK 14 CONTINUATION
SUMMARY OF CHANGES
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
Section Number Section Title
SF1442 SOLICITATION, OFFER AND AWARD
00 10 00 CONTRACT LINE ITEM PRICING SCHEDULE
00 73 00 SUPPLEMENTARY CONDITIONS
00 73 46 DAVIS BACON WAGES
DIVISION 01 – 48 - TECHNICAL SPECIFICATIONS
Section Number Section Title
01 11 00 SUMMARY OF WORK
01 57 23.00 10 TEMPORARY STORM WATER POLLUTION CONTROL
San Luis Rey River Flood Control Project W912PL-17-B-0002 Sediment Removal and Beach Fill Placement - Oceanside, California
PROJECT TABLE OF CONTENTS Page 1 11 July 2017 Amendment 0002
PROJECT TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
SF 1442 SOLICITATION, OFFER AND AWARD
00 01 05 CERTIFICATION PAGE
00 10 00 CONTRACT LINE ITEM PRICING SCHEDULE
00 21 00 INSTRUCTIONS
00 21 13 INSTRUCTIONS TO BIDDERS
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 70 00 CONDITIONS OF THE CONTRACT
00 73 00 SUPPLEMENTARY CONDITIONS
00 73 16 INSURANCE REQUIREMENTS
00 73 46 DAVIS BACON WAGES
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 CONTRACTOR QUALITY CONTROL
01 45 00.10 QUALITY CONTROL SYSTEM (QCS)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 23.00 10 TEMPORARY STORM WATER POLLUTION CONTROL
01 57 30 DEWATERING AND DIVERSION AND CONTROL OF WATER
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
-- End of Project Table of Contents --
Am1
Am2
Am2
Am2
Am2
Am2
Am2
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
IMPORTANT - The "offer" section on the reverse must be fully completed by the offeror.
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
9. FOR INFORMATION CALL
A. NAME B. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date):
11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12B. CALENDAR DAYS
YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212
Designed using Perform Pro, WHS/DIOR, Oct 96
1442-103 STANDARD FORM 1442 (REV. 4-85) (EG)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
W912PL-17-B-0002 x 13 June 2017 1 OF 2
U.S. Army Corps of Engineers Los Angeles District 915 Wilshire Boulevard, Suite 930 Los Angeles, California 90017-3401 Attn:Contracting Division CESPL-CT-W
See Item 7
Carlos Antonio/Pat Bonilla 213-452-3252/213-452-3255
SAN LUIS REY RIVER FLOOD CONTROL PROJECT, SEDIMENT REMOVAL, CITY OF OCEANSIDE, SAN DIEGO COUNTY, CA Project consists of removal of approximately 210,000 BCY of sediment from the San Luis Rey riverbed and disposal of excavated material at the El Corazon disposal site and local beach.
Sediment compatible with local beach sand will be transported from the San Luis Rey riverbed to the beach and spread, as directed. Magnitude of the Proposed Project: $5,000,000.00 to $10,000,000.00. Estimated Duration of the Contract: 200 calendar days from the date of Notice to Proceed. This procurement will be conducted under FAR Part 14 Sealed Bidding, FSC CODE: Z2PZ, NAICS Code: 237990 Other Heavy and Civil Engineering Construction. The size standard for NAICS code 237990 is $36,500,000.
This solicitation is 100% set-aside for Small Business. Only Small Businesses will be considered for award. All offerors are advised that this project may be delayed,cancelled or revised at any time during the solicitation,selection, evaluation, negotiation and/or final award process.
SPECIAL NOTE: This project contains environmental considerations not finalized at the time of issuance, upon finalization of these considerations, the solicitation shall be amended as needed, to provide additional environmental considerations for the performance of work. This project may be delayed, cancelled or revised at any time prior to award.
10 see 007300
X X *Section 00 73 00
X 10
0 1:00 PM
July 27, 2017
X
OFFER (Must be fully completed by offeror)
STANDARD FORM 1442 BACK (REV. 4-85)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal or greater than the minimum requirement stated in 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24.SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BYCODE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to the issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and
(c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD. (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN
(Type or print)
30B. SIGNATURE 30C. DATE
31A. NAME OF CONTRACTING OFFICER (Type or print)
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
DUNS NO.: TAX ID NO.:
CAGE CODE NO.:
( ) - ; FAX ( ) -
See Section 00 10 00 Solicitation Contract Line Item Number (CLIN) Schedule
USACE Los Angeles District San Diego Resident Office 8775 Aero Drive, Suite 232 San Diego, CA 92123
USACE, Finance Center
ATTN: CEFCO-AO-D
5722 Integrity Drive Millington, TN 38054-5005
San Luis Rey River Flood Control Project Sediment Removal and Beach Fill Placement, Oceanside, California
W912PL-17-B-0002
Item Description Quantity Unit Unit Price
Amount
0001 Diversion and Control of Water 1 Job JA $
0002 Dewatering of Groundwater 1 Job JA $
0003 Traffic Control Plan and Bikeway Closure
1 Job JA
0004 Restore Access Ramps and Bikeway/Maintenance Road
1 Job JA
0005 El-Corazon Stockpile Site Management 1 Job JA
0006 Clearing and Grubbing 65 AC $ $
0007 Excavation and Place at El-Corazon 130,000 CY $ $
0008 Excavation and Place at Beach 80,000 CY $ $
$ TOTAL ESTIMATED AMOUNT:
(Line Items 0001 through 0008)
SECTION 00 10 00
Solicitation Contract Line Item (CLIN) Schedule
Bidding Schedule
11 July 2017 1 Amendment 0002
San Luis Rey River Flood Control Project W912PL‐17‐B‐0002 Sediment Removal and Beach Fill Placement – Oceanside, CA
00 10 00 ‐ 2
Amendment 0002
OFFERORS NOTES
1. All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.
2. If a modification to a offer based on unit prices is submitted which provides for a job amount adjustment to the total estimated amount, the application of the job amount adjustment to each unit price in the Price Schedule must be stated. If it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the Price Schedule.
3. Prices must be submitted on all individual items of the Solicitation, Contract Line Item Number (CLIN) Schedule. Failure to do so may cause the offer to be determined “non-responsive.”
4. For the purpose of initial evaluation of offers, the following will be utilized in resolving arithmetic discrepancies found on the face of the Price Schedule as submitted by the offerder:
a. Obviously misplaced decimal points will be corrected;
b. In case of discrepancy between the unit price and the extended price, the unit price will govern;
c. Apparent errors in extensions of unit prices will be corrected;
d. Apparent errors in addition of lump sum and extended prices will be corrected.
5. For the purpose of offer evaluation, the Government will proceed on the assumption that the offeror intends the offer to be evaluated on the basis of unit prices the totals arrived at by the resolution of arithmetic discrepancies as provided above and the offer will be so reflected on the abstract of offers.
6. The job amount "JA" line items in the Price Schedule are not "Estimated Quantity" line items and are not subject to the "Variation in Estimated Quantity" contract clause.
7. The Contract Clause 52.232‐27, "Prompt Payment for Construction Contracts" requires that the name and address of the contractor official, to whom payment is to be sent, be the same as that in the contract or in a proper Notice of Assignment.
8. Principal Contracting Officer. The Contracting Officer who signs this contract will be the Principal Contracting Officer for this contract. However, any Contracting Officer assigned to the Los Angeles District, Contracting within his authority, may take formal action on this contract when the Principal Contracting Officer is unavailable and the action needs to be taken.
9. Amounts and prices shall be indicated in either words or figures, NOT BOTH.
10. The offeror/offeror shall distribute indirect costs (overhead, profit, bond, etc) over all items in the Contract Line Item Number (CLIN) Schedule. The Government will review all submitted Solicitation, Contract Line Item Number (CLIN) Schedules for any unbalancing of the items. Any submitted Solicitation, Contract Line Item Number (CLIN) Schedule determined to be unbalanced may cause the offerder to be ineligible for award.
San Luis Rey River Flood Control Project W912PL‐17‐B‐0002 Sediment Removal and Beach Fill Placement – Oceanside, CA
00 10 00 ‐ 3
Amendment 0002
11. The offeror shall furnish all plant, labor, material, equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in the contract in include all attachments thereto.
12. Some quantities are ESTIMATED, the offerors prices MUST BE FIRM.
13. Offeror is cautioned to check his Price Schedule carefully prior to submission. If the Price Schedule contains unit prices, they should be round off to the second decimal point only NOT EXTENDED FURTHER.
14. Payment of Electronic Funds Transfer (EFT) is the mandatory method of payment. The Contractors attention is directed to Contract Clause NO. 52.232‐33 “Mandatory Information for Electronic Funds Transfer” located in Section 00 70 00 Conditions of the Contract.
15. Contractor is required to fill in Cage code, TIN and DUNS Number in Block No. 14 on Standard Form 1442, the Name and Address Block.
252.236‐7008 Contract Prices ‐ Bidding Schedules (Dec 1991)
a. The Government's payment for the items listed in the CLIN Schedule shall constitute full compensation to the Contractor for ‐‐
(1) Furnishing all plant, labor, equipment, appliances, and materials; and
(2) Performing all operations required to complete the work in conformity with the drawings and specifications.
b. The Contractor shall include in the prices for the items listed in the Pricing Schedule all costs for work in the specifications, whether or not specifically listed in the Pricing Schedule.
‐‐ End of Section –
11 July 2017 SECTION 00 73 00 Page 3 Amendment 0002
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR
1984)
The Contractor shall be required to (a) commence work under this contract within 1 calendar days after the date the Contractor receives the Notice of Award/Notice to Proceed at the time of award. The contractor will be required to submit executed performance and payment bonds prior to commencing with the work; (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 200 calendar days after Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,488.00 per day for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.211-13 TIME EXTENSIONS (SEP 2000)
Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.
(End of clause)
52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to
11 July 2017 SECTION 00 73 46 Page 1 Amendment 0002
SECTION 00 73 46
DAVIS BACON WAGE DECISION
General Decision Number: CA170001 07/07/2017 CA1
Superseded General Decision Number: CA20160001
State: California
Construction Types: Building, Heavy (Heavy and Dredging), Highway and Residential
County: San Diego County in California.
BUILDING CONSTRUCTION PROJECTS; DREDGING PROJECTS (does not include hopper dredge work); HEAVY CONSTRUCTION PROJECTS (does not include water well drilling); HIGHWAY CONSTRUCTION PROJECTS; RESIDENTIAL CONSTRUCTION PROJECTS (consisting of single family homes and apartments up to and including 4 stories)
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/06/2017 1 01/27/2017 2 02/17/2017 3 02/24/2017 4 03/03/2017 5 03/10/2017 6 03/24/2017 7 05/05/2017 8 05/12/2017 9 05/26/2017 10 06/09/2017 11 06/30/2017 12 07/07/2017
ASBE0005-002 07/04/2016
Rates Fringes
11 July 2017 SECTION 00 73 46 Page 2 Amendment 0002
Asbestos Workers/Insulator(Includes the application of all insulating materials, protective coverings, coatings, and finishes to all types of mechanical systems).....$ 38.37 20.13
Fire Stop Technician(Application of Firestopping Materials for wall openings and penetrations in walls,floors, ceilings and curtain walls)...........................$ 26.15 17.31
ASBE0005-004 07/04/2016
Rates Fringes
Asbestos Removal worker/hazardous material handler (Includes preparation, wetting,stripping, removal,scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not)....$ 18.38 10.82
BOIL0092-003 10/01/2012
Rates Fringes
BOILERMAKER......................$ 41.17 28.27
BRCA0004-008 11/01/2016
Rates Fringes
BRICKLAYER; MARBLE SETTER........$ 35.30 17.35
BRCA0018-004 06/01/2016
Rates Fringes
MARBLE FINISHER..................$ 29.20 12.93
TILE FINISHER....................$ 24.53 11.08
TILE LAYER.......................$ 35.89 16.24
BRCA0018-010 09/01/2016
Rates Fringes
TERRAZZO FINISHER................$ 28.53 12.27
TERRAZZO WORKER/SETTER...........$ 35.57 13.14
CARP0409-002 07/01/2008
Rates Fringes
Diver
(1) Wet.....................$ 663.68 9.82
(2) Standby.................$ 331.84 9.82
(3) Tender..................$ 323.84 9.82
(4) Assistant Tender........$ 299.84 9.82
Amounts in "Rates' column are per day
11 July 2017 SECTION 00 73 46 Page 3 Amendment 0002
CARP0409-008 08/01/2010
Rates Fringes
Modular Furniture Installer......$ 17.00 7.41
CARP0547-001 07/01/2016
Rates Fringes
CARPENTER
(1) Bridge.................$ 40.33 17.03
(2) Commercial Building....$ 35.10 17.03
(3) Heavy & Highway........$ 40.20 17.03
(4) Residential Carpenter..$ 28.08 17.03
(5) Residential Insulation Installer........$ 18.00 8.16
MILLWRIGHT.......................$ 46.70 17.03
PILEDRIVERMAN....................$ 40.33 17.03
CARP0547-002 07/01/2016
Rates Fringes
Drywall (1) Work on wood framed construction of single family residences, apartments or condominiums under four stories Drywall Installer/Lather...$ 30.15 16.03 Drywall Stocker/Scrapper...$ 10.00 6.67
(2) All other work Drywall Installer/Lather...$ 27.35 9.58 Drywall Stocker/Scrapper...$ 11.00 6.67
ELEC0569-001 06/05/2017
Rates Fringes
Electricians (Tunnel Work) Cable Splicer...............$ 49.41 3%+12.63 Electrician.................$ 46.97 3%+12.63 Electricians: (All Other Work, Including 4 Stories Residential) Cable Splicer...............$ 44.00 3%+12.63 Electrician.................$ 43.25 3%+12.63
ELEC0569-004 06/05/2017
Rates Fringes
ELECTRICIAN (Sound & Communications Sound Technician)......................$ 31.00 3%+11.53 SOUND TECHNICIAN: Terminating, operating and performing final check-out
ELEC0569-005 06/05/2017
Sound & Communications
11 July 2017 SECTION 00 73 46 Page 4 Amendment 0002
Sound Technician............$ 31.00 3%+11.53
SOUND TECHNICIAN: Terminating, operating and performing final check-out
ELEC0569-006 02/27/2017
Work on street lighting; traffic signals; and underground systems and/or established easements outside of buildings
Traffic signal, street light and underground work Utility Technician #1.......$ 30.48 3%+7.70 Utility Technician #2.......$ 25.45 3%+7.70
STREET LIGHT & TRAFFIC SIGNAL WORK:
UTILITY TECHNICIAN #1: Installation of street lights and traffic signals, including electrical circuitry,programmable controller, pedestal-mounted electrical meter enclosures and laying of pre-assembled cable in ducts. The layout of electrical systems and communication installation including proper position of trench depths, and radius at duct banks, location for manholes, street lights and traffic signals.
UTILITY TECHNICIAN #2: Distribution of material at jobsite, installation of underground ducts for electrical, telephone, cable TV land communication systems. The setting, leveling, grounding and racking of precast manholes, handholes and transformer pads.
ELEC0569-008 06/05/2017
Rates Fringes
ELECTRICIAN (Residential, 1-3 Stories).........................$ 32.81 3%+6.61
ELEC1245-001 06/01/2015
Rates Fringes
LINE CONSTRUCTION
(1) Lineman; Cable splicer..$ 52.85 15.53
(2) Equipment specialist(operates crawler tractors, commercial motor vehicles, backhoes, trenchers, cranes (50 tons and below), overhead & underground distribution line equipment)...........$ 42.21 14.32
(3) Groundman...............$ 32.28 14.03
(4) Powderman...............$ 47.19 14.60
HOLIDAYS: New Year's Day, M.L. King Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and day after Thanksgiving, Christmas Day
11 July 2017 SECTION 00 73 46 Page 5 Amendment 0002
ELEV0018-001 01/01/2017
Rates Fringes
ELEVATOR MECHANIC................$ 52.21 31.585
FOOTNOTE:
PAID VACATION: Employer contributes 8% of regular hourly rate as vacation pay credit for employees with more than 5 years of service, and 6% for 6 months to 5 years of service.
PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, Friday after Thanksgiving, and Christmas Day.
ENGI0012-003 07/01/2016
Rates Fringes
OPERATOR: Power Equipment (All Other Work)
GROUP 1....................$ 39.95 23.35
GROUP 2....................$ 40.73 23.35
GROUP 3....................$ 41.02 23.35
GROUP 4....................$ 42.51 23.35
GROUP 5....................$ 41.86 23.35
GROUP 6....................$ 41.83 23.35
GROUP 8....................$ 42.84 23.35
GROUP 9....................$ 42.19 23.35
GROUP 10....................$ 42.96 23.35
GROUP 11....................$ 42.31 23.35
GROUP 12....................$ 43.13 23.35
GROUP 13....................$ 43.23 23.35
GROUP 14....................$ 43.26 23.35
GROUP 15....................$ 43.34 23.35
GROUP 16....................$ 43.46 23.35
GROUP 17....................$ 43.63 23.35
GROUP 18....................$ 43.73 23.35
GROUP 19....................$ 43.84 23.35
GROUP 20....................$ 43.96 23.35
GROUP 21....................$ 44.13 23.35
GROUP 22....................$ 44.23 23.35
GROUP 23....................$ 44.34 23.35
GROUP 24....................$ 44.46 23.35
GROUP 25....................$ 44.63 23.35
OPERATOR: Power Equipment (Cranes, Piledriving & Hoisting)
GROUP 1....................$ 43.20 22.15
GROUP 2....................$ 43.98 22.15
GROUP 3....................$ 44.27 22.15
GROUP 4....................$ 44.41 22.15
GROUP 5....................$ 44.63 22.15
GROUP 6....................$ 44.74 22.15
GROUP 7....................$ 44.86 22.15
GROUP 8....................$ 45.03 22.15
GROUP 9....................$ 45.20 22.15
11 July 2017 SECTION 00 73 46 Page 6 Amendment 0002
GROUP 10....................$ 46.20 22.15
GROUP 11....................$ 47.20 22.15
GROUP 12....................$ 48.20 22.15
GROUP 13....................$ 49.20 22.15
OPERATOR: Power Equipment (Tunnel Work)
GROUP 1....................$ 41.80 23.35
GROUP 2....................$ 42.58 23.35
GROUP 3....................$ 42.87 23.35
GROUP 4....................$ 43.01 23.35
GROUP 5....................$ 43.23 23.35
GROUP 6....................$ 43.34 23.35
GROUP 7....................$ 43.46 23.35
PREMIUM PAY:
$3.75 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp Pendleton
Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator.
SEE ZONE DEFINITIONS AFTER CLASSIFICATIONS
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Bargeman; Brakeman; Compressor operator; Ditch Witch, with seat or similar type equipment; Elevator operator-inside; Engineer Oiler; Forklift operator (includes loed, lull or similar types under 5 tons;
Generator operator; Generator, pump or compressor plant operator; Pump operator; Signalman; Switchman
GROUP 2: Asphalt-rubber plant operator (nurse tank operator);
Concrete mixer operator-skip type; Conveyor operator;
Fireman; Forklift operator (includes loed, lull or similar types over 5 tons; Hydrostatic pump operator; oiler crusher (asphalt or concrete plant); Petromat laydown machine; PJU side dum jack; Screening and conveyor machine operator (or similar types); Skiploader (wheel type up to 3/4 yd.
without attachment); Tar pot fireman; Temporary heating plant operator; Trenching machine oiler
GROUP 3: Asphalt-rubber blend operator; Bobcat or similar type (Skid steer); Equipment greaser (rack); Ford Ferguson (with dragtype attachments); Helicopter radioman (ground);
Stationary pipe wrapping and cleaning machine operator
GROUP 4: Asphalt plant fireman; Backhoe operator (mini-max or similar type); Boring machine operator; Boxman or mixerman (asphalt or concrete); Chip spreading machine operator;
Concrete cleaning decontamination machine operator;
11 July 2017 SECTION 00 73 46 Page 7 Amendment 0002
Concrete Pump Operator (small portable); Drilling machine operator, small auger types (Texoma super economatic or similar types - Hughes 100 or 200 or similar types -drilling depth of 30' maximum); Equipment greaser (grease truck); Guard rail post driver operator; Highline cableway signalman; Hydra-hammer-aero stomper; Micro Tunneling (above ground tunnel); Power concrete curing machine operator; Power concrete saw operator; Power-driven jumbo form setter operator; Power sweeper operator; Rock Wheel Saw/Trencher; Roller operator (compacting); Screed operator (asphalt or concrete); Trenching machine operator (up to 6 ft.); Vacuum or much truck
GROUP 5: Equipment Greaser (Grease Truck/Multi Shift).
GROUP 6: Articulating material hauler; Asphalt plant engineer; Batch plant operator; Bit sharpener; Concrete joint machine operator (canal and similar type); Concrete planer operator; Dandy digger; Deck engine operator;
Derrickman (oilfield type); Drilling machine operator, bucket or auger types (Calweld 100 bucket or similar types
- Watson 1000 auger or similar types - Texoma 330, 500 or 600 auger or similar types - drilling depth of 45' maximum); Drilling machine operator; Hydrographic seeder machine operator (straw, pulp or seed), Jackson track maintainer, or similar type; Kalamazoo Switch tamper, or similar type; Machine tool operator; Maginnis internal full slab vibrator, Mechanical berm, curb or gutter(concrete or asphalt); Mechanical finisher operator (concrete, Clary-Johnson-Bidwell or similar); Micro tunnel system (below ground); Pavement breaker operator (truck mounted);
Road oil mixing machine operator; Roller operator (asphalt or finish), rubber-tired earth moving equipment (single engine, up to and including 25 yds. struck); Self-propelled tar pipelining machine operator; Skiploader operator (crawler and wheel type, over 3/4 yd. and up to and including 1-1/2 yds.); Slip form pump operator (power driven hydraulic lifting device for concrete forms);
Tractor operator-bulldozer, tamper-scraper (single engine, up to 100 h.p. flywheel and similar types, up to and including D-5 and similar types); Tugger hoist operator (1 drum); Ultra high pressure waterjet cutting tool system operator; Vacuum blasting machine operator
GROUP 8: Asphalt or concrete spreading operator (tamping or finishing); Asphalt paving machine operator (Barber Greene or similar type); Asphalt-rubber distribution operator;
Backhoe operator (up to and including 3/4 yd.), small ford, Case or similar; Cast-in-place pipe laying machine operator; Combination mixer and compressor operator (gunite work); Compactor operator (self-propelled); Concrete mixer operator (paving); Crushing plant operator; Drill Doctor;
Drilling machine operator, Bucket or auger types (Calweld 150 bucket or similar types - Watson 1500, 2000 2500 auger or similar types - Texoma 700, 800 auger or similar types -drilling depth of 60' maximum); Elevating grader operator;
11 July 2017 SECTION 00 73 46 Page 8 Amendment 0002
Grade checker; Gradall operator; Grouting machine operator;
Heavy-duty repairman; Heavy equipment robotics operator;
Kalamazoo balliste regulator or similar type; Kolman belt loader and similar type; Le Tourneau blob compactor or similar type; Loader operator (Athey, Euclid, Sierra and similar types); Mobark Chipper or similar; Ozzie padder or similar types; P.C. slot saw; Pneumatic concrete placing machine operator (Hackley-Presswell or similar type);
Pumpcrete gun operator; Rock Drill or similar types; Rotary drill operator (excluding caisson type); Rubber-tired earth-moving equipment operator (single engine, caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. up to and including 50 cu.
yds. struck); Rubber-tired earth-moving equipment operator (multiple engine up to and including 25 yds. struck);
Rubber-tired scraper operator (self-loading paddle wheel type-John Deere, 1040 and similar single unit); Self-propelled curb and gutter machine operator; Shuttle buggy;
Skiploader operator (crawler and wheel type over 1-1/2 yds.
up to and including 6-1/2 yds.); Soil remediation plant operator; Surface heaters and planer operator; Tractor compressor drill combination operator; Tractor operator (any type larger than D-5 - 100 flywheel h.p. and over, or similar-bulldozer, tamper, scraper and push tractor single engine); Tractor operator (boom attachments), Traveling pipe wrapping, cleaning and bendng machine operator;
Trenching machine operator (over 6 ft. depth capacity, manufacturer's rating); trenching Machine with Road Miner attachment (over 6 ft depth capacity): Ultra high pressure waterjet cutting tool system mechanic; Water pull (compaction) operator
GROUP 9: Heavy Duty Repairman
GROUP 10: Drilling machine operator, Bucket or auger types (Calweld 200 B bucket or similar types-Watson 3000 or 5000 auger or similar types-Texoma 900 auger or similar types-drilling depth of 105' maximum); Dual drum mixer, dynamic compactor LDC350 (or similar types); Monorail locomotive operator (diesel, gas or electric); Motor patrol-blade operator (single engine); Multiple engine tractor operator (Euclid and similar type-except Quad 9 cat.); Rubber-tired earth-moving equipment operator (single engine, over 50 yds. struck); Pneumatic pipe ramming tool and similar types; Prestressed wrapping machine operator;
Rubber-tired earth-moving equipment operator (single engine, over 50 yds. struck); Rubber tired earth moving equipment operator (multiple engine, Euclid, caterpillar and similar over 25 yds. and up to 50 yds. struck), Tower crane repairman; Tractor loader operator (crawler and wheel type over 6-1/2 yds.); Woods mixer operator (and similar Pugmill equipment)
GROUP 11: Heavy Duty Repairman - Welder Combination, Welder - Certified.
11 July 2017 SECTION 00 73 46 Page 9 Amendment 0002
GROUP 12: Auto grader operator; Automatic slip form operator;
Drilling machine operator, bucket or auger types (Calweld, auger 200 CA or similar types - Watson, auger 6000 or similar types - Hughes Super Duty, auger 200 or similar types - drilling depth of 175' maximum); Hoe ram or similar with compressor; Mass excavator operator less tha 750 cu.
yards; Mechanical finishing machine operator; Mobile form traveler operator; Motor patrol operator (multi-engine);
Pipe mobile machine operator; Rubber-tired earth- moving equipment operator (multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck); Rubber-tired self- loading scraper operator (paddle-wheel-auger type self-loading - two (2) or more units)
GROUP 13: Rubber-tired earth-moving equipment operator operating equipment with push-pull system (single engine, up to and including 25 yds. struck)
GROUP 14: Canal liner operator; Canal trimmer operator;
Remote- control earth-moving equipment operator (operating a second piece of equipment: $1.00 per hour additional);
Wheel excavator operator (over 750 cu. yds.)
GROUP 15: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. and up to and including 50 yds. struck); Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple engine-up to and including 25 yds. struck)
GROUP 16: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (single engine, over 50 yds. struck); Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds. struck)
GROUP 17: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple engine, Euclid, Caterpillar and similar, over 50 cu. yds. struck);
Tandem tractor operator (operating crawler type tractors in tandem - Quad 9 and similar type)
GROUP 18: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units -single engine, up to and including 25 yds. struck)
GROUP 19: Rotex concrete belt operator (or similar types);
Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units - single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds.and up to and including 50
cu. yds. struck); Rubber-tired earth-moving equipment
11 July 2017 SECTION 00 73 46 Page 10 Amendment 0002 operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units - multiple engine, up to and including 25 yds. struck)
GROUP 20: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units -single engine, over 50 yds. struck); Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps, and similar types in any combination, excluding compaction units - multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds. struck)
GROUP 21: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units -multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck)
GROUP 22: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (single engine, up to and including 25 yds. struck)
GROUP 23: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. and up to and including 50 yds. struck); Rubber-tired earth-moving equipment operator, operating with the tandem push-pull system (multiple engine, up to and including 25 yds. struck)
GROUP 24: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (single engine, over 50 yds. struck); Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds.
struck)
GROUP 25: Concrete pump operator-truck mounted; Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck)
CRANES, PILEDRIVING AND HOISTING EQUIPMENT CLASSIFICATIONS
GROUP 1: Engineer oiler; Fork lift operator (includes loed, lull or similar types)
GROUP 2: Truck crane oiler
GROUP 3: A-frame or winch truck operator; Ross carrier operator (jobsite)
11 July 2017 SECTION 00 73 46 Page 11 Amendment 0002
GROUP 4: Bridge-type unloader and turntable operator;
Helicopter hoist operator
GROUP 5: Hydraulic boom truck; Stinger crane (Austin-Western or similar type); Tugger hoist operator (1 drum)
GROUP 6: Bridge crane operator; Cretor crane operator; Hoist operator (Chicago boom and similar type); Lift mobile operator; Lift slab machine operator (Vagtborg and similar types); Material hoist and/or manlift operator; Polar gantry crane operator; Self Climbing scaffold (or similar type); Shovel, backhoe, dragline, clamshell operator (over 3/4 yd. and up to 5 cu. yds. mrc); Tugger hoist operator
GROUP 7: Pedestal crane operator; Shovel, backhoe, dragline, clamshell operator (over 5 cu. yds. mrc); Tower crane repair; Tugger hoist operator (3 drum)
GROUP 8: Crane operator (up to and including 25 ton capacity); Crawler transporter operator; Derrick barge operator (up to and including 25 ton capacity); Hoist operator, stiff legs, Guy derrick or similar type (up to and including 25 ton capacity); Shovel, backhoe, dragline, clamshell operator (over 7 cu. yds., M.R.C.)
GROUP 9: Crane operator (over 25 tons and up to and including 50 tons mrc); Derrick barge operator (over 25 tons up to and including 50 tons mrc); Highline cableway operator;
Hoist operator, stiff legs, Guy derrick or similar type (over 25 tons up to and including 50 tons mrc); K-crane operator; Polar crane operator; Self erecting tower crane operator maximum lifting capacity ten tons
GROUP 10: Crane operator (over 50 tons and up to and including 100 tons mrc); Derrick barge operator (over 50 tons up to and including 100 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 50 tons up to and including 100 tons mrc), Mobile tower crane operator (over 50 tons, up to and including 100 tons M.R.C.); Tower crane operator and tower gantry
GROUP 11: Crane operator (over 100 tons and up to and including 200 tons mrc); Derrick barge operator (over 100 tons up to and including 200 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 100 tons up to and including 200 tons mrc); Mobile tower crane operator (over 100 tons up to and including 200 tons mrc)
GROUP 12: Crane operator (over 200 tons up to and including 300 tons mrc); Derrick barge operator (over 200 tons up to and including 300 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 200 tons, up to and including 300 tons mrc); Mobile tower crane operator (over 200 tons, up to and including 300 tons mrc)
GROUP 13: Crane operator (over 300 tons); Derrick barge
11 July 2017 SECTION 00 73 46 Page 12 Amendment 0002 operator (over 300 tons); Helicopter pilot; Hoist operator, stiff legs, Guy derrick or similar type (over 300 tons);
Mobile tower crane operator (over 300 tons)
TUNNEL CLASSIFICATIONS
GROUP 1: Skiploader (wheel type up to 3/4 yd. without attachment)
GROUP 2: Power-driven jumbo form setter operator
GROUP 3: Dinkey locomotive or motorperson (up to and including 10 tons)
GROUP 4: Bit sharpener; Equipment greaser (grease truck);
Slip form pump operator (power-driven hydraulic lifting device for concrete forms); Tugger hoist operator (1 drum);
Tunnel locomotive operator (over 10 and up to and including 30 tons)
GROUP 5: Backhoe operator (up to and including 3/4 yd.);
Small Ford, Case or similar; Drill doctor; Grouting machine operator; Heading shield operator; Heavy-duty repairperson;
Loader operator (Athey, Euclid, Sierra and similar types);
Mucking machine operator (1/4 yd., rubber-tired, rail or track type); Pneumatic concrete placing machine operator (Hackley-Presswell or similar type); Pneumatic heading shield (tunnel); Pumpcrete gun operator; Tractor compressor drill combination operator; Tugger hoist operator (2 drum);
Tunnel locomotive operator (over 30 tons)
GROUP 6: Heavy Duty Repairman
GROUP 7: Tunnel mole boring machine operator
ENGINEERS ZONES
$1.00 additional per hour for all of IMPERIAL County and the portions of KERN, RIVERSIDE & SAN BERNARDINO Counties as defined below:
That area within the following Boundary: Begin in San Bernardino County, approximately 3 miles NE of the intersection of I-15 and the California State line at that point which is the NW corner of Section 1, T17N,m R14E, San Bernardino Meridian. Continue W in a straight line to that point which is the SW corner of the northwest quarter of Section 6, T27S, R42E, Mt. Diablo Meridian. Continue North to the intersection with the Inyo County Boundary at that point which is the NE corner of the western half of the northern quarter of Section 6, T25S, R42E, MDM. Continue W along the Inyo and San Bernardino County boundary until the intersection with Kern County, as that point which is the SE corner of Section 34, T24S, R40E, MDM. Continue W along the Inyo and Kern County boundary until the intersection with Tulare County, at that point which is the SW corner of the SE quarter of Section 32, 11 July 2017 SECTION 00 73 46 Page 13 Amendment 0002
T24S, R37E, MDM. Continue W along the Kern and Tulare County boundary, until that point which is the NW corner of T25S, R32E, MDM. Continue S following R32E lines to the NW corner of T31S, R32E, MDM. Continue W to the NW corner of T31S, R31E, MDM. Continue S to the SW corner of T32S, R31E, MDM. Continue W to SW corner of SE quarter of Section 34, T32S, R30E, MDM.
Continue S to SW corner of T11N, R17W, SBM.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .