Am3_W912PL-16-R-0018.pdf

PDF 73 KB Posted

Attached to
Two Step Design-Build for a 20, 000 square foot space related site at Vandenberg AFB
Solicitation number
W912PL-16-R-0018
Issued by

About this file

Amendment 3. Section 00 22 16 - Supplementary Instructions to Proposers. Page 7 modified.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 3

0003 Mar 18, 2016

USACE-LOS ANGELES DISTRICT

CONTRACTING DIVISION, WEST REGION BRANCH

915 WILSHIRE BLVD, SUITE 1440

LOS ANGELES, CA 90017

W912PL-16-R-0018

Feb 17, 2016

Design-Build, construction of 20,000ft Technical Support Facility(TCF), B2510 Addition, to include a Sensitive Compartmented information Facility (SCIF), at Vandenberg Air Force Base, California.

The following section has been updated

* Section 00 22 16 - Replace page 7. (Paragraph 5.4.1.2.1 revised to correct a typo error)

The due date for receipt of proposals remains 23 March 2016, 2:00pm local time.

l1eddjar Inserted Text

B2510 Addition W912PL-16-R-0018 Vandenberg AFB, CA Phase I

Section 00 01 00 - 2 Amendment 3

SECTION 00 01 00 - TABLE OF CONTENTS

DIVISION 00 - BIDDING REQUIREMENTS, CONTRACTS FORMS AND CONTRACT CONDITIONS

00 01 00 Table of Contents

SF-1442 Solicitation, Offer and Award

00 01 05 Certification Page 00 21 16 Instructions to Proposers 00 22 00 Supplementary Instructions Am1 00 22 16 Supplementary Instructions to Proposers Am1 Am3

00 45 00 Representations and Certifications 00 70 00 Conditions of the Contract 00 73 00 Supplementary Conditions

Technical Specification Prepared by Sacramento District

Division 01 – General Requirements

Note: Section 01 10 10 Technical Engineering and Design Criteria amended Am2

Drawings – 15 sheets

Contract Attachments – provided as 2 separate files

B2510 Addition W912PL-16-R-0018 Vandenberg AFB, CA Phase I in the past five (5) years. Multiple projects can demonstrate an experience and capability or an example project can demonstrate multiple experiences and capabilities.

5.4.1.1.1. At least one with no more than three example projects demonstrating the offeror’s design-build project management experience and capability as a prime contractor on a construction project of similar type and scope;

5.4.1.1.2. At least one with no more than three example projects demonstrating the experience and capability of the Architect-Engineer Design Firm (prime or subcontractor) on a design effort of similar type and scope;

5.4.1.1.3. One example project each demonstrating the offeror’s key subcontractors experience and capability in the following efforts on a construction project of similar type and scope, with at least one on a military installation:

5.4.1.1.3.1. Design & construction for Special Access Program Facility (SAPF) and/or Sensitive Compartmented Information Facilities (SCIF) construction effort

5.4.1.1.3.2. Electrical construction effort

5.4.1.1.3.3. Fire Suppression Mass Notification System (Notifier) and Security Alarms construction effort

5.4.1.1.3.4. Heating, Ventilating, Air Conditioning and Direct Digital Controls construction effort

5.4.1.1.3.5. Earthwork and Foundation System/Fastrak

5.4.1.1.3.6. Architectural Innovation and Design

5.4.1.1.3.7. Construction effort on a military installation

5.4.1.1.3.8. USA Green Council’s LEED Silver Certification

5.4.1.2. Formatting and Other Restrictions.

5.4.1.2.1. Provide a Summary Matrix that indicates which submitted example project(s) demonstrates the experience(s) and capability (ies) of which firm (i.e. prime, subcontractor) will perform the capability area identified in paragraph “5.4.1.1.3” above.

Use an X for completed project, use M for completed project on a Military installation.

For example:

Amendment 0003

00 22 16 - 7

SF-30 - Amendment 3
Table of Contents
00 22 16 - Supplemenatry Instructions to Proposers - Page 7

File details come from the government source that posted it. Updated .