AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
0001 Jul 19, 2013
USACE, Los Angeles District Contracting Division, West Region branch 915 Wilshire Bl,14th Floor P.O. Box 532711 Los Angeles, CA 90053-2325
W912PL-13-B-0004
Jul 14, 2013
Lower Santa Ana River Channel reach 9 - Phase 3, (Gypsum Canyon Road to Coal Canyon Road), Orange County, California
The Bid Opening Date is changed to August 14th, 2013 at 1:00 p.m. See attached SF-1442.
See SF-30 Continuation sheet for other changes to the plans & specifications..
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004 Gypsum Canyon Road to Coal Canyon Road Orange County, CA
SF-30 Continuation – page 2 Amendment 1
SF 30 Continuation – Amendment 1
Specification:
Replace the following sections:
Table of Contents SF-1442 Solicitation, Offer and Award 00010 Bid Schedule 00850 Wage Rates
01 10 01 GENERAL REQUIREMENTS
01 22 00 MEASUREMENT AND PAYMENT
31 11 00 CLEARING AND GRUBBING
32 92 19 HYDROSEEDING
Plans:
Replace the following Drawings:
Sheet Drawing Name
G02 INDEX TO CONTRACT DRAWINGS & ABBREVIATIONS
G07 STAGING AREA ACCESS PLAN (2)
C01 PLAN AND PROFILE (1)
C02 PLAN AND PROFILE (2)
C09 TYPICAL SECTIONS AND DETAILS
Attachment added to end of Section 01 10 01:
State of California Department of Transportation Encroachment Permit Rider
Appendix:
Geotechnical Appendix of Design Documentation Report, Lower Santa Ana River Channel Reach 9 – Phase 3, Orange County, California, dated November 23, 2011 (revised August 28, 2012).
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
TOC - 1
Amendment 1
PROJECT TABLE OF CONTENTS
DIVISION 00 - BIDDING REQUIREMENTS, CONTRACT FORMS AND CONTRACT CONDITIONS
SF-1442 SOLICITATION, OFFER AND AWARD
00010 BID SCHEDULE Am1
00100 INSTRUCTIONS TO BIDDERS
00600 REPRESENTATIONS AND CERTIFICATIONS
00700 CONTRACT CLAUSES
00800 SPECIAL CONTRACT REQUIREMENTS
00850 WAGE RATES Am1
DIVISION 01 – GENERAL REQUIREMENTS
01 10 01 GENERAL REQUIREMENTS Am1 01 22 00 MEASUREMENT AND PAYMENT Am1
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 00a SUBMITTAL REGISTER
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 CONTRACTOR QUALITY CONTROL
01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)
01 50 02 TEMPORARY CONSTRUCTION FACILITIES
01 57 20 ENVIRONMENTAL PROTECTION
01 57 23.00 10 STORM WATER POLLUTION PREVENTION MEASURES
01 57 30 DIVERSION AND CONTROL OF WATER
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 02 – EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 – CONCRETE
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
03 37 28 SOIL CEMENT
DIVISION 05 - METALS
05 50 13 METALWORK FABRICATION
DIVISION 31 - EARTHWORK
31 05 22 GEOTEXTILES USED AS FILTERS
31 11 00 CLEARING AND GRUBBING Am1
31 23 13 FILLS AND SUBGRADE PREPARATION
31 23 16 EXCAVATION
31 32 11 SOIL SURFACE EROSION CONTROL
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 11 23 AGGREGATE BASE COURSE
32 12 10 BITUMINOUS TACK COATS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 17 24.00 10 PAVEMENT MARKINGS
32 21 00 INSTRUMENTATION
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
TOC - 2
32 92 19 HYDROSEEDING Am1
32 93 00 EXTERIOR PLANTING (SANTA ANA RIVER)
DIVISION 33 – UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION
33 31 19 STONE PROTECTION
APPENDIX Am1
Geotechnical Appendix of Design Documentation Report, Lower Santa Ana River Channel Reach 9 – Phase 3, Orange County, California, dated November 23, 2011 (revised August 28, 2012).
-- End of Project Table of Contents –
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
IMPORTANT - The "offer" section on the reverse must be fully completed by the offeror.
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
9. FOR INFORMATION CALL
A. NAME B. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date):
11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12B. CALENDAR DAYS
YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212
Designed using Perform Pro, WHS/DIOR, Oct 96
1442-103 STANDARD FORM 1442 (REV. 4-85) (EG)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
W912PL-13-B-0004 X 14 July 2013 1 OF 2
USACE, Los Angeles District Contracting Division, West Region Branch 915 Wilshire Blvd P. O. Box 532711 Los Angeles, CA 90053-2325
See Item 7
Julie Ayala/Patricia Bonilla 213/452-3241 or 213/452-3255
Lower Santa Ana River Channel Reach 9 - Phase 3, (Gypsum Canyon Road to Coal Canyon Road), Orange County, California
Project consists of construction of approximately 1,500 LF of soil cement revetment. The revetment is 10 feet wide by approximately 30 feet in height at a 1H:1V slope. Half of the revetment will be buried. The construction activities also include clearing and grubbing, diversion of water, control of water, excavation, backfill, extension of 3 side drains, and other miscellaneous tasks. Option items include removal existing bike path segment, construction of bike segment path, hydroseeding, and other tasks.
This is a 100% Small Business Set-Aside procurement.
The estimated cost range of this acquisition is $5,000,000 - $10,000,000.
BIDDERS PLEASE NOTE: This project may be delayed, cancelled or revised at any time prior to award.
10 *Sect00800
X X *Section 00800
X 10
0 1:00 PM
14 August 2013
X
OFFER (Must be fully completed by offeror)
STANDARD FORM 1442 BACK (REV. 4-85)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal or greater than the minimum requirement stated in 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24.SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BYCODE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to the issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and
(c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD. (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN
(Type or print)
30B. SIGNATURE 30C. DATE
31A. NAME OF CONTRACTING OFFICER (Type or print)
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
DUNS NO.: TAX ID NO.:
CAGE CODE NO.:
( ) - ; FAX ( ) -
SEE PRICING SCHEDULE
USACE, FINANCE CENTER
5722 INTEGRITY DRIVE, ATTN: CEFCO-AO-P
MILLINGTON, TN 38054-5005
Lower Santa Ana River Channel, Reach 9 - Phase 3
Orange County, CA
W912PL-13-B-0004
00010 - 1 Amendment 01
CERTIFICATE OF CORPORATE PRINCIPAL
1) IF THE OFFEROR IS A JOINT VENTURE, COMPLETE THE FOLLOWING:
(Company Name) (Signature) (Title)
2) IF THE OFFEROR IS PARTNERSHIP, LIST FULL NAME OF ALL PARTNERS:
3) IF THE OFFEROR IS A CORPORATION, THE FOLLOWING CERTIFICATION SHOULD BE COMPLETED:
CERTIFICATION AS TO CORPORATE PRINCIPAL
I, , certify that I am the Secretary of the corporation named as principal in the within contract; that , who signed the said contract on behalf of the principal, was the of the corporation; that I know his signature and that his signature is genuine; and that said contract was duly signed, sealed and attested for in behalf of said corporation by authority of its governing body.
CORPORATE PRINCIPAL
CORPORATE SEAL
SECRETARY
Orange County, CA
00010 - 2 Amendment 01
PRICE SCHEDULE
Estimated
Item Description Quantity Unit Price Amount
BASE BID
0001 MOBILIZATION AND DEMOBILIZATION 1 JOB LS __________
0002 DIVERSION OF WATER 1 JOB LS __________
0003 CONTROL OF WATER 1 JOB LS __________
0004 EROSION CONTROL 1 JOB LS __________
0005 TRAFFIC CONTROL 1 JOB LS __________
0006 CLEARING 26.2 AC _______ __________
0007 GRUBBING 2.5 AC _______ __________
0008 EXCAVATION 40,550 CY _______ __________
0009 BACKFILL - EXISTING SOIL
CEMENT EMBANKMENT 14,400 CY _______ __________
0010 BACKFILL - ON SITE 22,300 CY _______ __________
0011 BACKFILL - BORROW SITE 16,350 CY _______ __________
0012 SOIL CEMENT 17,250 CY _______ __________
0013 OUTLET STRUCTURE - 18" RCP 1 EA _______ __________
0014 OUTLET STRUCTURE - 60" RCP 2 EA _______ __________
0015 VEHICLE GATE 1 EA _______ __________
0016 AS-BUILT DRAWINGS 1 JOB LS __________
0017 HYDROSEEDING AND EXTERIOR
PLANTS- RIPARIAN AREA 8 AC _______ __________
0018 TEMPORARY IRRIGATION SYSTEM -
RIPARIAN AREA 8 AC _______ __________
0019 LANDSCAPE MAINTENANCE -
RIPARIAN AREA 8 AC _______ __________
0020 GUARD CABLE FENCE 1,460 LF _______ __________
0021 INCLINOMETERS 1 JOB LS __________
0022 CALTRANS POST-CONSTRUCTION
DEFLECTION STUDY 1 JOB LS $ 12,000.00
TOTAL ESTIMATED BASE $__________________
Orange County, CA
00010 - 3 Amendment 01
OPTION ITEMS
0023 HYDROSEEDING AND EXTERIOR
PLANTS - UPLAND AREA (OPTION) 9 AC _______ __________
0024 TEMPORARY IRRIGATION SYSTEM -
UPLAND AREA (OPTION) 9 AC _______ __________
0025 LANDSCAPE MAINTENANCE -
UPLAND AREA (OPTION) 9 AC _______ __________
0026 REMOVE TEMPORARY BIKE PATH (OPTION) 7,350 LF _______ __________
0027 PERMANENT BIKE PATH (OPTION) 6,665 LF _______ __________
0028 DECOMPOSED GRANITE (OPTION) 5,810 SY _______ __________
0029 SOUND WALL (OPTION) 5,470 LF _______ __________
0030 CALTRANS PRE-CONSTRUCTION
DEFLECTION STUDY (OPTION) 1 JOB LS $12,000.00
0031 COAL CANYON ON/OFF RAMPS
RESURFACING (OPTION) 1,600 LF _______ __________
0032 DIVERSION STRUCTURE 1B (OPTION) 1 JOB LS __________
TOTAL ESTIMATED OPTION ITEMS $____________________
TOTAL ESTIMATED, BASE PLUS OPTION ITEMS $____________________
Abbreviations:
AC = Acre CY = Cubic Yard EA = Each LF = Linear Foot LS = Lump Sum SY = Square Yard TON = 2000 pounds
Orange County, CA
00010 - 4 Amendment 01
BIDDERS NOTES
1. All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the bid.
2. If a modification to a bid based on unit prices is submitted which provides for a lump sum adjustment to the total estimated amount, the application of the lump sum adjustment to each unit price in the Price Schedule must be stated.
If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the Price Schedule.
3. Prices must be submitted on all individual items of the Price Schedule, otherwise the bid will be considered non-responsive and will be rejected.
4. For the purpose of initial evaluation of bids, the following will be utilized in resolving arithmetic discrepancies found on the face of the Price Schedule as submitted by the bidder:
a. Obviously misplaced decimal points will be corrected;
b. In case of discrepancy between the unit price and the extended price, the unit price will govern;
c. Apparent errors in extensions of unit prices will be corrected;
d. Apparent errors in addition of lump sum and extended prices will be corrected.
5. For the purpose of bid evaluation, the Government will proceed on the assumption that the bidder intends the bid to be evaluated on the basis of unit prices the totals arrived at by the resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.
6. The lump sum “LS” line items in the Price Schedule are not “Estimated Quantity” line items and are not subject to the “Variation in Estimated Quantity” contract clause.
7. The Contract Clause 52.232-27, “Prompt Payment for Construction Contracts” requires that the name and address of the contractor official, to whom payment is to be sent, be the same as that in the contract or in a proper Notice of Assignment.
8. Procuring Contracting Officer. The Contracting Officer who signs this contract will be the Pocuring Contracting Officer for this contract. However, any Contracting Officer assigned to the Los Angeles District, contracting within his authority, may take formal action on this contract when the Principal Contracting Officer is unavailable and the action needs to be taken.
9. Amounts and prices shall be indicated in either words or figures, NOT BOTH.
10. Payment of Electronic Funds Transfer (EFT) is the mandatory method of payment. The Contractors attention is directed to Contract Clause NO. 52.232-33 “Payment by Electronic Funds Transfer-Central Contractor Registration” and Contract Clause No. 52.232-34, “Payment by Electronic Funds Transfer-Other Than Central Contractor Registration” located in Section 00700.Mandatory Information for Electronic Funds Transfer” located in Section 00700.
11. The bidder shall distribute his indirect costs (overhead, profit, bond, etc.,) over all items in the Price Schedule.
The Government will review all submitted Price Schedules for any unbalancing of the items. Any submitted Price Schedule determined to be unbalanced may be considered nonresponsive and cause the bidder to be ineligible for contract award.
Orange County, CA
00010 - 5 Amendment 01
12. The bidder shall furnish all plant, labor, material, equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in the contract in include all attachments thereto.
13. Some quantities are ESTIMATED, the bidders prices MUST BE FIRM.
14. Bidder is cautioned to check his Price Schedule carefully prior to submission.
15. Please Note: All inquiries must be submitted in accordance with the instructions found in the solicitation, Section 00100, paragraph titled, “Inquiries.” The Bidder Inquiry System will be unavailable for new inquiries five business days prior to submission of bids, in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary.
16. The Government contemplates award on one contract to the responsive, responsible bidder who submits the low bid for the total of all the items in the Price Schedule.
17. The Geotechnical Appendix of Design Documentation Report for the Lower Santa Ana River Channel Reach 9 – Phase 3, Orange County, California, revised August 28, 2012, is posted on the project’s bid package website (FedBizOps). This Geotechnical Report is made available for information purposes. All bidders are responsible for downloading the report, for their use, prior to bid opening. All bidders are notified that the Geotechnical Study Report is provided for information purposes only. Any discrepancies found between the geotechnical Study Report and the specification, the specifications will govern.
This page was intentionally left blank for duplex printing.
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-1 Amendment 1
SECTION 00850 WAGE RATES
General Decision Number: CA130035 07/19/2013 CA35
Superseded General Decision Number: CA20120035
State: California
Construction Types: Building, Heavy (Heavy and Dredging) and Highway
County: Orange County in California.
BUILDING CONSTRUCTION PROJECTS; DREDGING PROJECTS (does not include hopper dredge work); HEAVY CONSTRUCTION PROJECTS (does not include water well drilling); HIGHWAY CONSTRUCTION PROJECTS
Modification Number Publication Date 0 01/04/2013 1 01/11/2013 2 03/01/2013 3 03/08/2013 4 04/12/2013 5 05/10/2013 6 07/05/2013 7 07/19/2013
ASBE0005-002 06/28/2010
Rates Fringes
Asbestos Workers/Insulator (Includes the application of all insulating materials, protective coverings, coatings, and finishes to all types of mechanical systems).....$ 32.79 16.31 Fire Stop Technician (Application of Firestopping Materials for wall openings and penetrations in walls, floors, ceilings and curtain walls)...........................$ 24.21 13.76
ASBE0005-004 06/28/2010
Rates Fringes
Asbestos Removal worker/hazardous material handler (Includes preparation, wetting, stripping, removal, Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-2 Amendment 1 scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not)....$ 18.70 8.65
* BRCA0004-010 05/01/2012
Rates Fringes
BRICKLAYER; MARBLE SETTER........$ 35.26 12.26
*The wage scale for prevailing wage projects performed in Blythe, China lake, Death Valley, Fort Irwin, Twenty-Nine Palms, Needles and 1-15 corridor (Barstow to the Nevada State Line) will be Three Dollars ($3.00) above the standard San Bernardino/Riverside County hourly wage rate
BRCA0018-004 06/01/2012
Rates Fringes
MARBLE FINISHER..................$ 27.04 10.66
TILE FINISHER....................$ 22.37 9.19
TILE LAYER.......................$ 33.55 13.55
BRCA0018-010 09/01/2009
Rates Fringes
TERRAZZO FINISHER................$ 26.59 9.62
TERRAZZO WORKER/SETTER...........$ 33.63 10.46
CARP0409-001 07/01/2010
Rates Fringes
CARPENTER
(1) Carpenter, Cabinet Installer, Insulation Installer, Hardwood Floor Worker and acoustical installer...................$ 37.35 11.08
(2) Millwright..............$ 37.85 11.08
(3) Piledriver/Derrick Bargeman, Bridge or Dock Carpenter, Heavy Framer, Rock Bargeman or Scowman, Rockslinger, Shingler (Commercial)................$ 37.48 10.58
(3) Piledrivermen/Derrick Bargeman, Bridge or Dock Carpenter, Heavy Framer, Rock Bargeman or Scowman, Rockslinger, Shingler
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-3 Amendment 1
(Commercial)................$ 37.48 11.08
(4) Pneumatic Nailer, Power Stapler...............$ 37.60 11.08
(5) Sawfiler...............$ 37.44 11.08
(6) Scaffold Builder.......$ 28.55 11.08
(7) Table Power Saw Operator....................$ 37.45 11.08
FOOTNOTE: Work of forming in the construction of open cut sewers or storm drains, on operations in which horizontal lagging is used in conjunction with steel H-Beams driven or placed in pre- drilled holes, for that portion of a lagged trench against which concrete is poured, namely, as a substitute for back forms (which work is performed by piledrivers): $0.13 per hour additional.
CARP0409-005 07/01/2010
Rates Fringes
Drywall
DRYWALL INSTALLER/LATHER....$ 37.35 11.08
STOCKER/SCRAPPER............$ 10.00 6.67
CARP0409-008 08/01/2010
Rates Fringes
Modular Furniture Installer......$ 17.00 7.41
ELEC0011-002 11/26/2012
COMMUNICATIONS AND SYSTEMS WORK
Rates Fringes
Communications System Installer...................$ 27.25 12.25 Technician..................$ 29.05 12.30
SCOPE OF WORK:
Installation, testing, service and maintenance of systems utilizing the transmission and/or transference of voice, sound, vision and digital for commercial, educational, security and entertainment purposes for the following: TV monitoring and surveillance, background-foreground music, intercom and telephone interconnect, inventory control systems, microwave transmission, multi-media, multiplex, nurse call systems, radio page, school intercom and sound, burglar alarms, fire alarm (see last paragraph below) and low voltage master clock systems in commercial buildings.
Communication Systems that transmit or receive information and/or control systems that are intrinsic to the above listed systems; inclusion or exclusion of terminations and testings of conductors determined by their function;
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-4 Amendment 1 excluding all other data systems or multiple systems which include control function or power supply; excluding installation of raceway systems, conduit systems, line voltage work, and energy management systems. Does not cover work performed at China Lake Naval Ordnance Test Station. Fire alarm work shall be performed at the current inside wireman total cost package.
ELEC0441-001 02/25/2013
Rates Fringes
CABLE SPLICER....................$ 43.03 14.04
ELECTRICIAN......................$ 41.14 13.98
* ELEC0441-003 11/26/2012
COMMUNICATIONS & SYSTEMS WORK (excludes any work on Intelligent Transportation Systems or CCTV highway systems)
Rates Fringes
Communications System Installer...................$ 28.32 11.15 Technician..................$ 30.12 11.20
SCOPE OF WORK The work covered shall include the installation, testing, service and maintenance, of the following systems that utilize the transmission and/or transference of voice, sound, vision and digital for commercial, education, security and entertainment purposes for TV monitoring and surveillance, background foreground music, intercom and telephone interconnect, inventory control systems, microwave transmission, multi-media, multiplex, nurse call system, radio page, school intercom and sound, burglar alarms and low voltage master clock systems.
A. Communication systems that transmit or receive information and/or control systems that are intrinsic to the above listed systems SCADA (Supervisory control/data acquisition PCM (Pulse code modulation) Inventory control systems Digital data systems Broadband & baseband and carriers Point of sale systems VSAT data systems Data communication systems RF and remote control systems Fiber optic data systems
B. Sound and Voice Transmission/Transference Systems Background-Foreground Music Intercom and Telephone Interconnect Systems Sound and Musical Entertainment Systems Nurse Call Systems Radio Page Systems School Intercom and Sound Systems Burglar Alarm Systems Low-Voltage Master Clock Systems Multi-Media/Multiplex Systems Telephone Systems RF Systems and Antennas and Wave
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-5 Amendment 1
Guide
C. *Fire Alarm Systems-installation, wire pulling and testing.
D. Television and Video Systems Television Monitoring and Surveillance Systems Video Security Systems Video Entertainment Systems Video Educational Systems CATV and
CCTV
E. Security Systems, Perimeter Security Systems, Vibration Sensor Systems Sonar/Infrared Monitoring Equipment, Access Control Systems, Card Access Systems
*Fire Alarm Systems
1. Fire Alarms-In Raceways: Wire and cable pulling in raceways performed at the current electrician wage rate and fringe benefits. Installation and termination of devices, panels, startup, testing and programmming performed by the Technician.
2. Fire Alarms-Open Wire Systems: installed by the Technician.
ELEC0441-004 11/26/2012
Rates Fringes
ELECTRICIAN (TRANSPORTATION
SYSTEMS, TRAFFIC SIGNALS &
STREET LIGHTING)
Cable Splicer/Fiber Optic Splicer.....................$ 40.74 13.77 Electrician.................$ 40.14 13.75 Technician..................$ 30.12 11.20
SCOPE OF WORK: Electrical work on public streets, freeways, toll-ways, etc, above or below ground. All work necessary for the installation, renovation, repair or removal of Intelligent Transportation Systems, Video Surveilance Systems (CCTV), Street Lighting and and Traffic Signal work or systems whether underground or on bridges. Includes dusk to dawn lighting installations and ramps for access to or egress from freeways, toll-ways, etc.
Intelligent Transportation Systems shall include all systems and components to control, monitor, and communicate with pedestrian or vehicular traffic, included but not limited to: installation, modification, removal of all Fiber optic Video System, Fiber Optic Data Systems, Direct interconnect and Communications Systems, Microwave Data and Video Systems, Infrared and Sonic Detection Systems, Solar Power Systems, Highway Advisory Radio Systems, highway Weight and Motion Systems, etc.
Any and all work required to install and maintain any specialized or newly developed systems. All cutting, fitting and bandaging of ducts, raceways, and conduits.
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-6 Amendment 1
The cleaning, rodding and installation of "fish and pull wires". The excavation, setting, leveling and grouting of precast manholes, vaults, and pull boxes including ground rods or grounding systems, rock necessary for leveling and drainagae as well as pouring of a concrete envelope if needed.
JOURNEYMAN TRANSPORTATION ELECTRICIAN shall perform all tasks necessary toinstall the complete transportation system.
JOURNEYMAN TECHNICIAN duties shall consist of: Distribution of material at job site, manual excavation and backfill, installation of system conduits and raceways for electrical, telephone, cable television and comnmunication systems. Pulling, terminating and splicing of traffic signal and street lighting conductors and electrical systems including interconnect, dector loop, fiber optic cable and video/data.
ELEC1245-001 06/01/2012
Rates Fringes
LINE CONSTRUCTION
(1) Lineman; Cable splicer..$ 48.95 14.05
(2) Equipment specialist (operates crawler tractors, commercial motor vehicles, backhoes, trenchers, cranes (50 tons and below), overhead & underground distribution line equipment)...........$ 39.09 12.97
(3) Groundman...............$ 29.91 12.70
(4) Powderman...............$ 43.71 13.15
HOLIDAYS: New Year's Day, M.L. King Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and day after Thanksgiving, Christmas Day
ELEV0018-001 01/01/2013
Rates Fringes
ELEVATOR MECHANIC................$ 48.23 25.185
FOOTNOTE:
PAID VACATION: Employer contributes 8% of regular hourly rate as vacation pay credit for employees with more than 5 years of service, and 6% for 6 months to 5 years of service.
PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, Friday after Thanksgiving, and Christmas Day.
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-7 Amendment 1
ENGI0012-003 07/01/2012
Rates Fringes
OPERATOR: Power Equipment (All Other Work)
GROUP 1....................$ 37.40 20.00
GROUP 2....................$ 38.18 20.00
GROUP 3....................$ 38.47 20.00
GROUP 4....................$ 39.96 20.00
GROUP 5....................$ 41.06 20.00
GROUP 6....................$ 40.18 20.00
GROUP 8....................$ 41.39 20.00
GROUP 9....................$ 40.41 20.00
GROUP 10....................$ 40.41 20.00
GROUP 11....................$ 40.58 20.00
GROUP 12....................$ 40.58 20.00
GROUP 13....................$ 40.68 20.00
GROUP 14....................$ 40.71 20.00
GROUP 15....................$ 40.79 20.00
GROUP 16....................$ 40.91 20.00
GROUP 17....................$ 41.08 20.00
GROUP 18....................$ 41.18 20.00
GROUP 19....................$ 41.29 20.00
GROUP 20....................$ 41.41 20.00
GROUP 21....................$ 41.58 20.00
GROUP 22....................$ 41.68 20.00
GROUP 23....................$ 41.79 20.00
GROUP 24....................$ 41.91 20.00
GROUP 25....................$ 42.08 20.00
OPERATOR: Power Equipment (Cranes, Piledriving & Hoisting)
GROUP 1....................$ 38.75 20.00
GROUP 2....................$ 39.53 20.00
GROUP 3....................$ 39.82 20.00
GROUP 4....................$ 39.96 20.00
GROUP 5....................$ 40.18 20.00
GROUP 6....................$ 40.29 20.00
GROUP 7....................$ 40.41 20.00
GROUP 8....................$ 40.58 20.00
GROUP 9....................$ 40.75 20.00
GROUP 10....................$ 41.75 20.00
GROUP 11....................$ 42.75 20.00
GROUP 12....................$ 43.75 20.00
GROUP 13....................$ 44.75 20.00
OPERATOR: Power Equipment (Tunnel Work)
GROUP 1....................$ 39.25 20.00
GROUP 2....................$ 40.03 20.00
GROUP 3....................$ 40.32 20.00
GROUP 4....................$ 40.46 20.00
GROUP 5....................$ 40.68 20.00
GROUP 6....................$ 40.79 20.00
GROUP 7....................$ 40.91 20.00
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-8 Amendment 1
PREMIUM PAY:
$3.75 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp Pendleton
Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator.
SEE ZONE DEFINITIONS AFTER CLASSIFICATIONS
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Bargeman; Brakeman; Compressor operator; Ditch Witch, with seat or similar type equipment; Elevator operator-inside; Engineer Oiler; Forklift operator (includes loed, lull or similar types under 5 tons;
Generator operator; Generator, pump or compressor plant operator; Pump operator; Signalman; Switchman
GROUP 2: Asphalt-rubber plant operator (nurse tank operator);
Concrete mixer operator-skip type; Conveyor operator;
Fireman; Forklift operator (includes loed, lull or similar types over 5 tons; Hydrostatic pump operator; oiler crusher (asphalt or concrete plant); Petromat laydown machine; PJU side dum jack; Screening and conveyor machine operator (or similar types); Skiploader (wheel type up to 3/4 yd.
without attachment); Tar pot fireman; Temporary heating plant operator; Trenching machine oiler
GROUP 3: Asphalt-rubber blend operator; Bobcat or similar type (Skid steer); Equipment greaser (rack); Ford Ferguson (with dragtype attachments); Helicopter radioman (ground);
Stationary pipe wrapping and cleaning machine operator
GROUP 4: Asphalt plant fireman; Backhoe operator (mini-max or similar type); Boring machine operator; Boxman or mixerman (asphalt or concrete); Chip spreading machine operator;
Concrete cleaning decontamination machine operator;
Concrete Pump Operator (small portable); Drilling machine operator, small auger types (Texoma super economatic or similar types - Hughes 100 or 200 or similar types -drilling depth of 30' maximum); Equipment greaser (grease truck); Guard rail post driver operator; Highline cableway signalman; Hydra-hammer-aero stomper; Micro Tunneling (above ground tunnel); Power concrete curing machine operator; Power concrete saw operator; Power-driven jumbo form setter operator; Power sweeper operator; Rock Wheel Saw/Trencher; Roller operator (compacting); Screed operator (asphalt or concrete); Trenching machine operator (up to 6 ft.); Vacuum or much truck
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-9 Amendment 1
GROUP 5: Equipment Greaser (Grease Truck/Multi Shift).
GROUP 6: Articulating material hauler; Asphalt plant engineer; Batch plant operator; Bit sharpener; Concrete joint machine operator (canal and similar type); Concrete planer operator; Dandy digger; Deck engine operator;
Derrickman (oilfield type); Drilling machine operator, bucket or auger types (Calweld 100 bucket or similar types
- Watson 1000 auger or similar types - Texoma 330, 500 or 600 auger or similar types - drilling depth of 45' maximum); Drilling machine operator; Hydrographic seeder machine operator (straw, pulp or seed), Jackson track maintainer, or similar type; Kalamazoo Switch tamper, or similar type; Machine tool operator; Maginnis internal full slab vibrator, Mechanical berm, curb or gutter(concrete or asphalt); Mechanical finisher operator (concrete, Clary-Johnson-Bidwell or similar); Micro tunnel system (below ground); Pavement breaker operator (truck mounted);
Road oil mixing machine operator; Roller operator (asphalt or finish), rubber-tired earth moving equipment (single engine, up to and including 25 yds. struck); Self-propelled tar pipelining machine operator; Skiploader operator (crawler and wheel type, over 3/4 yd. and up to and including 1-1/2 yds.); Slip form pump operator (power driven hydraulic lifting device for concrete forms);
Tractor operator-bulldozer, tamper-scraper (single engine, up to 100 h.p. flywheel and similar types, up to and including D-5 and similar types); Tugger hoist operator (1 drum); Ultra high pressure waterjet cutting tool system operator; Vacuum blasting machine operator
GROUP 8: Asphalt or concrete spreading operator (tamping or finishing); Asphalt paving machine operator (Barber Greene or similar type); Asphalt-rubber distribution operator;
Backhoe operator (up to and including 3/4 yd.), small ford, Case or similar; Cast-in-place pipe laying machine operator; Combination mixer and compressor operator (gunite work); Compactor operator (self-propelled); Concrete mixer operator (paving); Crushing plant operator; Drill Doctor;
Drilling machine operator, Bucket or auger types (Calweld 150 bucket or similar types - Watson 1500, 2000 2500 auger or similar types - Texoma 700, 800 auger or similar types -drilling depth of 60' maximum); Elevating grader operator;
Grade checker; Gradall operator; Grouting machine operator;
Heavy-duty repairman; Heavy equipment robotics operator;
Kalamazoo balliste regulator or similar type; Kolman belt loader and similar type; Le Tourneau blob compactor or similar type; Loader operator (Athey, Euclid, Sierra and similar types); Mobark Chipper or similar; Ozzie padder or similar types; P.C. slot saw; Pneumatic concrete placing machine operator (Hackley-Presswell or similar type);
Pumpcrete gun operator; Rock Drill or similar types; Rotary drill operator (excluding caisson type); Rubber-tired earth-moving equipment operator (single engine, caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. up to and including 50 cu.
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-10 Amendment 1 yds. struck); Rubber-tired earth-moving equipment operator (multiple engine up to and including 25 yds. struck);
Rubber-tired scraper operator (self-loading paddle wheel type-John Deere, 1040 and similar single unit); Self-propelled curb and gutter machine operator; Shuttle buggy;
Skiploader operator (crawler and wheel type over 1-1/2 yds.
up to and including 6-1/2 yds.); Soil remediation plant operator; Surface heaters and planer operator; Tractor compressor drill combination operator; Tractor operator (any type larger than D-5 - 100 flywheel h.p. and over, or similar-bulldozer, tamper, scraper and push tractor single engine); Tractor operator (boom attachments), Traveling pipe wrapping, cleaning and bendng machine operator;
Trenching machine operator (over 6 ft. depth capacity, manufacturer's rating); trenching Machine with Road Miner attachment (over 6 ft depth capacity): Ultra high pressure waterjet cutting tool system mechanic; Water pull (compaction) operator
GROUP 9: Heavy Duty Repairman
GROUP 10: Drilling machine operator, Bucket or auger types (Calweld 200 B bucket or similar types-Watson 3000 or 5000 auger or similar types-Texoma 900 auger or similar types-drilling depth of 105' maximum); Dual drum mixer, dynamic compactor LDC350 (or similar types); Monorail locomotive operator (diesel, gas or electric); Motor patrol-blade operator (single engine); Multiple engine tractor operator (Euclid and similar type-except Quad 9 cat.); Rubber-tired earth-moving equipment operator (single engine, over 50 yds. struck); Pneumatic pipe ramming tool and similar types; Prestressed wrapping machine operator;
Rubber-tired earth-moving equipment operator (single engine, over 50 yds. struck); Rubber tired earth moving equipment operator (multiple engine, Euclid, caterpillar and similar over 25 yds. and up to 50 yds. struck), Tower crane repairman; Tractor loader operator (crawler and wheel type over 6-1/2 yds.); Woods mixer operator (and similar Pugmill equipment)
GROUP 11: Heavy Duty Repairman - Welder Combination, Welder - Certified.
GROUP 12: Auto grader operator; Automatic slip form operator;
Drilling machine operator, bucket or auger types (Calweld, auger 200 CA or similar types - Watson, auger 6000 or similar types - Hughes Super Duty, auger 200 or similar types - drilling depth of 175' maximum); Hoe ram or similar with compressor; Mass excavator operator less tha 750 cu.
yards; Mechanical finishing machine operator; Mobile form traveler operator; Motor patrol operator (multi-engine);
Pipe mobile machine operator; Rubber-tired earth- moving equipment operator (multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck); Rubber-tired self- loading scraper operator (paddle-wheel-auger type self-loading - two (2) or more units)
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-11 Amendment 1
GROUP 13: Rubber-tired earth-moving equipment operator operating equipment with push-pull system (single engine, up to and including 25 yds. struck)
GROUP 14: Canal liner operator; Canal trimmer operator;
Remote- control earth-moving equipment operator (operating a second piece of equipment: $1.00 per hour additional);
Wheel excavator operator (over 750 cu. yds.)
GROUP 15: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. and up to and including 50 yds. struck); Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple engine-up to and including 25 yds. struck)
GROUP 16: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (single engine, over 50 yds. struck); Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds. struck)
GROUP 17: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple engine, Euclid, Caterpillar and similar, over 50 cu. yds. struck);
Tandem tractor operator (operating crawler type tractors in tandem - Quad 9 and similar type)
GROUP 18: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units -single engine, up to and including 25 yds. struck)
GROUP 19: Rotex concrete belt operator (or similar types);
Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units - single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds.and up to and including 50
cu. yds. struck); Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units - multiple engine, up to and including 25 yds. struck)
GROUP 20: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units -single engine, over 50 yds. struck); Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps, and similar types in any combination, excluding compaction units - multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds. struck)
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-12 Amendment 1
GROUP 21: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units -multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck)
GROUP 22: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (single engine, up to and including 25 yds. struck)
GROUP 23: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. and up to and including 50 yds. struck); Rubber-tired earth-moving equipment operator, operating with the tandem push-pull system (multiple engine, up to and including 25 yds. struck)
GROUP 24: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (single engine, over 50 yds. struck); Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds.
struck)
GROUP 25: Concrete pump operator-truck mounted; Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck)
CRANES, PILEDRIVING AND HOISTING EQUIPMENT CLASSIFICATIONS
GROUP 1: Engineer oiler; Fork lift operator (includes loed, lull or similar types)
GROUP 2: Truck crane oiler
GROUP 3: A-frame or winch truck operator; Ross carrier operator (jobsite)
GROUP 4: Bridge-type unloader and turntable operator;
Helicopter hoist operator
GROUP 5: Hydraulic boom truck; Stinger crane (Austin-Western or similar type); Tugger hoist operator (1 drum)
GROUP 6: Bridge crane operator; Cretor crane operator; Hoist operator (Chicago boom and similar type); Lift mobile operator; Lift slab machine operator (Vagtborg and similar types); Material hoist and/or manlift operator; Polar gantry crane operator; Self Climbing scaffold (or similar type); Shovel, backhoe, dragline, clamshell operator (over 3/4 yd. and up to 5 cu. yds. mrc); Tugger hoist operator
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-13 Amendment 1
GROUP 7: Pedestal crane operator; Shovel, backhoe, dragline, clamshell operator (over 5 cu. yds. mrc); Tower crane repair; Tugger hoist operator (3 drum)
GROUP 8: Crane operator (up to and including 25 ton capacity); Crawler transporter operator; Derrick barge operator (up to and including 25 ton capacity); Hoist operator, stiff legs, Guy derrick or similar type (up to and including 25 ton capacity); Shovel, backhoe, dragline, clamshell operator (over 7 cu. yds., M.R.C.)
GROUP 9: Crane operator (over 25 tons and up to and including 50 tons mrc); Derrick barge operator (over 25 tons up to and including 50 tons mrc); Highline cableway operator;
Hoist operator, stiff legs, Guy derrick or similar type (over 25 tons up to and including 50 tons mrc); K-crane operator; Polar crane operator; Self erecting tower crane operator maximum lifting capacity ten tons
GROUP 10: Crane operator (over 50 tons and up to and including 100 tons mrc); Derrick barge operator (over 50 tons up to and including 100 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 50 tons up to and including 100 tons mrc), Mobile tower crane operator (over 50 tons, up to and including 100 tons M.R.C.); Tower crane operator and tower gantry
GROUP 11: Crane operator (over 100 tons and up to and including 200 tons mrc); Derrick barge operator (over 100 tons up to and including 200 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 100 tons up to and including 200 tons mrc); Mobile tower crane operator (over 100 tons up to and including 200 tons mrc)
GROUP 12: Crane operator (over 200 tons up to and including 300 tons mrc); Derrick barge operator (over 200 tons up to and including 300 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 200 tons, up to and including 300 tons mrc); Mobile tower crane operator (over 200 tons, up to and including 300 tons mrc)
GROUP 13: Crane operator (over 300 tons); Derrick barge operator (over 300 tons); Helicopter pilot; Hoist operator, stiff legs, Guy derrick or similar type (over 300 tons);
Mobile tower crane operator (over 300 tons)
TUNNEL CLASSIFICATIONS
GROUP 1: Skiploader (wheel type up to 3/4 yd. without attachment)
GROUP 2: Power-driven jumbo form setter operator
GROUP 3: Dinkey locomotive or motorperson (up to and including 10 tons)
Lower Santa Ana River Channel Reach 9 – Phase 3 W912PL-13-B-0004
00850-14 Amendment 1
GROUP 4: Bit sharpener; Equipment greaser (grease truck);
Slip form pump operator (power-driven hydraulic lifting device for concrete forms); Tugger hoist operator (1 drum);
Tunnel locomotive operator (over 10 and up to and including 30 tons)
GROUP 5: Backhoe operator (up to and including 3/4 yd.);
Small Ford, Case or similar; Drill doctor; Grouting machine operator; Heading shield operator; Heavy-duty repairperson;
Loader operator (Athey, Euclid, Sierra and similar types);
Mucking machine operator (1/4 yd., rubber-tired, rail or track type); Pneumatic concrete placing machine operator (Hackley-Presswell or similar type); Pneumatic heading shield (tunnel); Pumpcrete gun operator; Tractor compressor drill combination operator; Tugger hoist operator (2 drum);
Tunnel locomotive operator (over 30 tons)
GROUP 6: Heavy Duty Repairman
GROUP 7: Tunnel mole boring machine operator
ENGINEERS ZONES
$1.00 additional per hour for all of IMPERIAL County and the portions of KERN, RIVERSIDE & SAN BERNARDINO Counties as defined below:
That area within the following Boundary: Begin in San Bernardino County, approximately 3 miles NE of the intersection of I-15 and the California State line at that point which is the NW corner of Section 1,…