DEPARTMENT OF THE ARMY

UNITED STATES ARMY GARRISON ITALY

DARBY MILITARY COMMUNITY

PUBLIC WORKS OFFICE

APO AE 09613

Project

PS1 00313 - 8

UPGRADE ELECTRICAL SYSTEM BLDG 5013, DEPOT

SCOPE OF WORK/PERFORMANCE WORK SCHEDULE

Consisting of 15 pages and 1 enclosure

ING. PAOLO SERRAGLINI

Chief, Engineering Services Branch

Prepared by:

STEPHEN L. DONNELLY, PE

Public Works Manager on 24 January 2019 APPROVAL DATE ________________

SCOPE OF WORK

Project. PS1 00313-8 Upgrade electrical system bldg 5013, Supply & Maintenance Area, Camp Darby, Livorno, Italy.

Basic Project and Options. The project is made of one basic item only. No optional work is included.

Phase 1 (Design) Description:

a. Scope of the work.

The work in this phase consists of designing the details, providing calculations and whatever necessary to define in scale all parts of work required to fulfill the scope of work, consisting of the upgrade of the electrical system of the Fire Department Bldg. 5013. The building has been subject to a recent partial renovation; anyway additional works are necessary to increase the power capability of the building and connect additional Government equipment: the purchase of the equipment is excluded by the scope of the work. The new Government equipment to be connected to the utilities are:

- A 400V washer 5.5kW

- A 400V dryer 8.3 kW

- An air compressor 400V 3 kW

- A hydrocleaner 400V 7.6 kW

- A cylinder recharging station 230V 15 Hp (11.19kW)

b. Existing conditions.

The building is currently fed with 230V 3P+PEN cables from the substation bldg 5511 inside existing cable ducts; cables from the substations are terminated inside an outdoor panel located on the south side of the building; from this panel the cables feed the existing Main Distribution

Panel MDP passing through to the automatic generator back up panel located outdoor on the west wall.

At north of bldg 5013 another existing cable duct with 2 double layer pipes dia. 125mm

(internal diameter 105mm) along Kelly Street connects the substation bldg 5511 to bldg 5019.

Inside the building the panel MDP directly feeds various 230V loads and the following electrical subpanels:

- The 230V three phases panel DP inside the administrative area;

- The 230V three phases telecommunication room panel TP;

- The 230V three phases mechanical room panel BP; in addition to the mechanical equipment, this panel currently feeds 2 resistances 400V through an autotransformer

230V/400V.

- The 400V panel in the garage, through a 30kVA 230/400V autotransformer; this panel currently feeds some equipment, that are:

The heat pump (circuit breaker C25A 4P + GFI)

400V Power outlets kitchen (circuit breaker C25A 4P + GFI)

400V Power outlet Washer (circuit breaker C16A 4P + GFI)

400V Power outlet Dryer (circuit breaker C32A 4P + GFI)

No photovoltaic system is actually present.

c. Available documentation.

The following documentation is available and is provided as supporting material, in the electronic version:

- Plan of the existing outdoor electrical cable ducts.

- Plan of the new cable ducts (minimum requirements).

- Existing power system plan of bldg 5013 with the position of the new equipment.

- Wiring diagrams of the existing electrical panels (to not be considered really “as built”).

- Plan of substation bldg 5511.

- Wiring diagram of the 400V panel in the substation bldg 5511.

d. Works description

The works to be done include, but shall not be necessarily limited to:

- Remove and dispose the existing 400V panel;

- Remove and dispose the existing 230V panel MDP;

- Remove and dispose the existing 230V generator and back up panel;

- Remove and dispose the 230V cables between the outdoor panel at south of the building and the generator and between the generator and the existing 230V panel MDP.

- Remove and dispose the existing 230V outdoor panel; install a new 230V outdoor panel complete with new terminals and Plexiglas screen, reconnecting the existing 230V cables coming from the substation bldg 5511.

- Install a new cable duct and manholes as shown in the plan; pipes shall be double layer, crush resistance 750N, minimum diameter 160mm; number of pipes shall be such to install the new cables leaving one pipe as spare. The manholes shown must be considered as the minimum required; additional manholes shall be installed if necessary to properly allow the installation of the new cables. Restore asphalt as per original conditions.

- Install new 400V cables from the substation 5511 to bldg 5013, connected to an existing

400A spare breaker (with electronic relay) of the existing 400V panel in the substation;

contemporary absorbed power to be considered is 100kW; distribution shall be TN-S;

maximum admitted voltage drop from the substation to the building is 1,5%. Cables shall run partially in the existing cable ducts and partially in the new cable ducts.

- Install a new 400V generator, 125kVA continuous power, complete with automatic back up panel for automatic switch grid-generator in case of grid power shutdown. Demolish the existing concrete slab and install a new concrete slab to support the new generator.

Generator shall be complete with a built-in fuel tank having a capacity of 2500 liters.

- Install a new 400V outdoor panel complete with not automatic breakers in order to manually bypass the generator and feed directly the building in case of generator maintenance or temporary removal.

- Install a new 400V Main Distribution Panel, feeding at least (not exhaustive list):

all the existing 400V loads the new 400V equipment the existing panel BP;

the existing panel TP;

a new 230V Main Distribution Panel through the existing autotransformer 30kVA

230/400V;

The panel shall be complete with a Surge Protection Device, a digital power meter and

LED pilot lights. Provide a dedicated breaker complete with Ground Fault Interrupter for each load. Include 20% of spare breakers. Existing circuits feeding the existing loads shall be reconnected to the new panel: perform splices of the cables if necessary; modify the existing cable trays and conduits as necessary.

- Install a new 230V Main Distribution Panel, feeding at least:

the new 230V cylinder recharging station the existing 230V panel DP all the other existing loads currently connected to the existing 230V Main

Distribution Panel, with the exception of what directly fed by the new 400V Main

Distribution Panel.

The panel shall be complete with a digital power meter and LED pilot lights. The new panel shall be designed redistributing the existing circuits in a more efficient and accurate way; new panel shall be composed at least by all the breakers composing the removed

230V MDP; however the following loads shall have a dedicated circuit breakers complete with dedicated ground fault interrupters:

Fire Alarm Control Panel (FACP)

Emergency lighting

Exhaust fan systems

Heater units; since heater units appear to work not well, verify also if they should be fed at 400V instead of 230V and, if so, connect them to the 400V panel.

Existing circuits feeding the existing loads shall be reconnected to the new panel: perform splices of the cables if necessary; modify the existing cable trays and conduits as necessary.

- Convert the panel BP and the electrical system in the mechanical room from 230V three phases to 400V three phases.

- Convert the panel TP and the electrical system in the telecommunication room from 230V three phases to 400V three phases.

- Check the actual loads and install permanent plastic labels in the existing 230V panel DP.

- Install new industrial IEC 309 power outlets, new cables and new conduits to connect all the new Government furnished equipment. New conduits and boxes shall be galvanized steel type having a minimum ingress degree IP55.

- Provide potable water and sewage connection for the new washer. Perform the necessary civil works.

- Provide potable water connection for the new hydrocleaner in both the location shown in the reference plan (inside the garage area and outdoor on the south wall).

- Provide an air exhaust connection for the new dryer, including the pipe and a proper hole in the wall complete with anti-insect screen.

General Notes:

- Various emergency current trip coils are currently present in the panels to be replaced/modified to allow the emergency shut down in determined conditions; new panels shall therefore be complete with the same current trip coils, to be connected to the existing push buttons or Fire Alarm Control Panel to perform the same shut down criteria.

All the coils shall be current trip type.

e. Interferences with the User Activities

The Fire Station shall remain active during the works, including the presence of the personnel;

during the design phase the Contractor shall submit for approval a works schedule showing how he is going to proceed with the construction works minimizing the voltage interruption in the building.

f. Design

Design analysis and project drawings shall be signed by a registered professional engineer/architect. Design will be in compliance with applicable Italian and U.S. Codes.

g. Required documents

Documents required to accomplish this phase prior to construction are as follows:

- As-built drawings of the existing facilities to be used for design, to be prepared based on the documents which will be provided by the Government and on site investigations and measurements taken in order to ascertain local conditions and extent of required work. Topographic survey of the area will be required.

- Civil/Structural design analysis, extended to the elements of the infrastructures involved in the project. The analysis, in two copies, shall include all loads, computations, assumptions, and codes on which the design is based.

- Verify and prepare documentation for special material disposal per current Italian regulation, if the case occurs. In designing and planning construction and/or demolition activities, waste produced will be identified and waste removal opportunities will be evaluated. The designer shall identify all reusable materials to be turned in and materials to be disposed off in landfill or to be delivered to recycling plant.

- Prepare documentation for hazardous material handling and disposal, for ASL approval, if that kind of material is planned to be removed. To be noted that Asbestos

Containing Material is not expected to be required to be demolished under this project.

- The requirements of Italian Law 81 of 2008 are deemed applicable to this project. The

Government will award a separate contract for Design and Construction Safety

Coordination. During the Design Phase maximum cooperation will be granted to the nominated Safety Coordinator to allow preparation of Safety and Coordination Plan and other documents required by Law.

- Sets of construction drawings on ISO A1 sheets. Drawings, at a minimum, must contain the following, if applicable:

Cover sheet and index of drawings including vicinity map, and a general location plan;

Exterior works;

Existing/Demolition plan;

Future conditions plan;

Elevations/Sections/Details;

All drawings shall be to scale, with graphic scale indicated. Dimensions and material identifications shall be clearly indicated. Drawings shall include all necessary notes and legends. All wording shall be in both English and Italian.

- Detailed technical report (in English and Italian) to include the following:

Detailed description of all works to be accomplished;

Method of accomplishment;

Materials and finishing;

Reference to norms and laws (both US and Italian) in force;

- For any excavations deeper than 6" (15 cm.), the Contractor must request to COR the digging permit. This form will be furnished to the Contractor at the pre-construction conference.

- Construction drawings must be prepared and signed by professional engineers or architects or technicians, within their respective expertise, registered in Italy, who will accept responsibility in accordance with Italian laws in force.

- All documents shall be submitted in paper and electronic format Autocad compatible for drawings, MS Office compatible for documents and in TIFF/PDF format for raster and pictures.

- The final submission shall include Certification of Compliance with Italian Norms. It will consist of the following statement, to be signed and stamped by a professional engineer:

“Having reviewed the definitive and detailed project No. PS1 00313-8, pertaining to

“Upgrade electrical system bldg 5013, Supply & Maintenance Area, Livorno, Italy”, I declare that I have ascertained that the structures and technological system included therein comply with the applicable Italian norms.

DATE SIGNATURE

Esaminato il progetto definitivo e dettagliato No. PS1 00313-8, relativo a

“Miglioramento impianto elettrico edificio 5013, Area Deposito, Livorno, Italia”, dichiaro di aver accertato che strutture ed impianti tecnologici in esso contenuti rispondono alla vigente normativa italiana.

DATA FIRMA

- The final design submittal shall also be accompanied by the following statement, signed by a technically qualified representative of the construction contractor:

“I, undersigned __________, in the vest of __________, have reviewed the final design submittal of project _____________, prepared by __________, with particular reference to the drawings and technical specifications, and I have found it:

- complete;

- constructible;

- fully compliant with the Scope of Work;

- feasible within the terms of the contract.

I understand that the above mentioned design documents, once reviewed and accepted by the Government, will become contract documents. I also understand that if anything of the Scope of Work is missing in the design, my Company will still be obliged to perform.”

h. As-built.

As-built drawings as described a c. above are provided with the purpose of showing the consistency of the area where the work is planned. There is however the possibility that some discrepancy exists between what depicted in the drawings and the existing conditions.

The drawings are provided in pdf format. Additional technical documentation might exist and could be available to the successful bidder in electronic or paper format.

i. Technical Specifications.

Technical Specifications are furnished to the Contractor to be used as the basis for design.

The TS will be able to be modified/expanded/integrated as applicable only upon authorization of the Design COR. Integrations will be however mandatory for sections which are not covered in what provided by the Government.

j. Applicable Codes and Standars

- Italian D.M. 37/08

- All applicable Italian CEI and European CEI EN norms

- NFPA Codes, in particular NFPA 70 (National Electrical Code)

- UFC 4-010-01, Unified Facilities Criteria, Design: DOD Minimum Antiterrorism

Standards for Buildings

- UFC 4-730-10, Fire Stations

- All other applicable Unified Facilities Criteria

- USAG Livorno Installation Design Guide, April 2009

k. Submission Requirements.

(1) Preliminary Submission (35% Design Completion). The preliminary submission will be delivered as per enclosed Progress Plan (enclosure 4) and will consist of the following elements in the quantities specified:

ELEMENT QUANTITY

a. Print copies of proposed Technical Specifications

(additions/modifications will be highlighted)

2 sets (English only)

b. Print copies of drawings 2 sets (English and Italian)

c. Print copies of basis of design including survey report identifying all codes requirements and technical information related to the selected material/techniques.

2 sets (English only)

d. Preliminary Design Analysis 2 sets (Italian only)

e. CD containing PDF copy of the documents listed above

2 copies

(2) Final Design Submission (100% Design Completion). The final design will be delivered as per enclosed Progress Plan and will consist of the following elements in the quantities specified for the project:

ELEMENT QUANTITY

a. Final drawings (English/Italian) including details as necessary to construct all features of the project, signed and stamped

2 set

b. Print copies of technical specifications 2 sets (English and Italian)

c. Final Design Analysis, signed and stamped

(English/Italian)

2 sets

d. Certification of Compliance with Italian norms, signed and stamped

2 originals

e. Contractor’s statement, signed and stamped 2 originals

f. Compact disk, rewritable, containing: 2 copies

The entire technical specifications (English and Italian) in a data format compatible with

Word for Windows Software.

All project drawings in a data format compatible with Autocad Software.

g. Compact disk, rewritable, containing:

The entire technical specifications (English and Italian) in a data format compatible with

Adobe Acrobat Reader.

All project drawings in a data format compatible with Adobe Acrobat Reader

2 copies

(3) Review meetings. The Contractor is expected to attend a pre-design meeting, and review meetings after the preliminary submittal. All meetings will take place at the COR’s office, Bldg 5155, Supply and Maintenance Area, Livorno.

(4) Design Review Comments. In general, design review comments will be returned to designers within 15 calendar days from the date of receipt of design. Every submittal after the preliminary shall be accompanied by an annotated copy of the review comments.

Phase 2 (Construction) Description:

Provide construction of all features of the project as designed in phase 1 and approved, in accordance with proposed and approved design and progress plan. Construction will start upon final approval of design, and will last as per the enclosed progress plan

(enclosure 4).

At the completion of the construction works:

At the completion of the construction works:

Provide an accurate cleaning of the areas involved by the construction works.

At the completion of the work, the following documents will be provided to the COR:

a. Copy of the certification of each item/element/material installed, according to

Italian D.M. 14/1/08 and any other Codes requirements; in addition to paper copy, provide a .pdf file of each certification, created by scanning the original document, stamped and signed, attachments included.

b. Copy of all the official material tests performed in accordance with the above mentioned Code; in addition to paper copy, provide a .pdf file of each test report, created by scanning the original document, stamped and signed.

c. An additional Statement of Conformity (dichiarazione di conformita’) according to the Italian DM 37/08 shall be provided relatively to the electrical system modifications.

d. Copy of the instruction and maintenance manuals of the systems and materials installed.

e. Copy of the As built drawings stamped and signed, in reproducible format; in addition to the reproducible copy provide electronic copies in CAD format (.dwg files) and in ADOBE ACROBAT format (.pdf files); As built drawings will show the final condition of the building (the new installed systems and the existing systems, modified or not)

f. All the other documents required in the Technical Specification

General notes:

a. Compliance with laws, regulations, criteria. All design and construction work shall be performed in full accordance with applicable Italian and United States laws, regulations, codes, whichever is more restrictive at contract award date. Main criteria are listed under 2.e. This includes any required certification by engineers licensed in

Italy.

b. The project is subject to D. Lgs. 81/08. The Safety & Coordination Plan will be prepared during the design phase under a separate contract. The contractor shall provide his/her

Piano Operativo di Sicurezza (safety plan, complementary final plan) and comply with the requirements of above mentioned laws as well as with those all other applicable Italian safety laws.

c. Emergency Situations. Contractor will maintain the following documentation available and usable at the work site, to be provided by the COR:

- A copy of the Camp Darby Emergency Plan, to which contractor will refer in the case of the emergency conditions indicated in the plan itself.

- Base Grid Coordinates layout, with the work site highlighted.

- List of emergency telephone numbers.

d. Project Identification Sign. The contractor shall supply and install a sign identifying the project. The sign shall be of high-resistant plywood for outdoor installation, white painted. The dimensions shall be 1200x2400x12 mm. The letters of the wording shall be uppercase, black color, 5 cm high, except the letters of the project title which shall be

10 cm. The sign shall be fixed to a structure made of any material provided it is lasting and in compliance with all safety requirements. The sign shall be well visible, with the lower side at 1.2 m from ground level.

e. The annexed Technical Specifications general sections Ia, Ib, are ruling, for what attains construction management, quality control, anti-terrorism requirements, and are not allowed to be modified by Contractor.

AT/OPSEC/Environmental requirements:

AT Level I Training. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas will complete

AT Level I awareness training within 30 calendar days after the contract start-date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor will submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, prior to issuance of Installation Access Passes. AT Level I awareness training is available online at https://atlevel1.dtic.mil/at.

According to AR 530-1, new contractor employees must complete Level I OPSEC training within 30 calendar days after they report for duty. All contractor employees must complete annual OPSEC awareness training.

Access and General Protection/Security Policy and Procedures: The Contractor shall obtain entry passes for each employee from the COR. The Contractor shall inform his personnel that they may be subjected to search when entering or leaving the installation at the discretion of the Installation Commander. Upon completion of the contract work or upon employee termination the Contractor shall return all passes to the Contracting Officer or the COR. Contractor and all associated sub-contractors' employees shall comply with applicable installation, facility, and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshall Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

iWATCH Training: The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program. This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 15 calendar days of contract award and within 10 calendar days of new employees commencing performance with the results reported to the COR NLT 10 calendar days after contract award.

ENVIRONMENTAL MANAGEMENT SYSTEM: The USAG Italy implements an

EMS in accordance with EO13693, ISO 14001:2004(E), DoD, and IMCOM requirements.

An EMS is an overall management system that includes organizational structure, planning activities, responsibilities, practices, procedures, processes and resources for developing, implementing, achieving, reviewing and maintaining the environmental policy of an organization. The USAG Italy EMS is designed to ensure that all personnel, including contract personnel, whose work activities can cause real or potential significant environmental impact, are aware of how their work supports the EMS and are competent to perform their roles, responsibilities and authorities while supporting the USAG Italy mission. Contractors and their personnel are required to be aware of, and comply with, the

USAG Italy Environmental policy and legal and other requirements when performing work at an installation.

The contractor will provide the following information semi-annually to be used by the

Government to address environmental performance relative to the goals of the USAG

Italy Environmental Management System. Please note that the amounts reported are those used/generated by the contractor regardless of source (private purchase or government furnished). Reports for January – June will be submitted by 15 July and reports for July-

December will be submitted by 15 January each year.

Media Report Element #1 Report Element #2

Non-Hazardous Solid

Waste

Total Waste

Generated (Kg)

Amount of Waste Diverted from Landfill (Kg)

Construction

Debris/Demolition

Materials

Total Waste

Generated (Kg)

Amount of Waste Diverted from Landfill (Kg)

Compostable/Organic

Material

Total Waste

Generated (Kg)

Amount of Waste Diverted from Landfill (Kg)

Hazardous Materials Total Used (Kg)

Hazardous Waste Total Generated

(Kg)

Total Recycled (Kg)

Energy Consumption -

Electricity

Total Energy

Consumed (MBtu)

Energy Consumption -

Fuel

Total Fuel

Consumed (L)

Renewable/Alternative

Energy

Total Consumed

(MW)

Facility

Construction/Renovation

Number of Buildings

LEED Certified

Silver or Higher

SqFt of buildings LEED

Certified

SECTION END

IMIT-LPW-F 14 January 2019

PERFORMANCE WORK SCHEDULE

1. Project. PS1 00313-8 Upgrade electrical system bldg 5013, Supply & Maintenance Area, Camp Darby, Livorno, Italy.

2. This project is made of one (1) Basic Project Item and no (0) Project Option Items.

3. This project shall be performed in two phases. The contract performance period for the entire contract (Phase 1 plus Phase 2) is as follows:

- Design Phase: 90 calendar days;

- Construction Phase: 75 calendar days.

Individual Notices to Proceed will be released for each of the two phases.

a. Phase 1 (Design): This phase is managed by a Contracting Officer Representative, from the Directorate of Public Works (DPW), Engineering Services Branch. The US

Government should not take longer than 15 days to provide review comments to the contractor for each planned submittal.

b. Phase 2 (Construction): This phase will be controlled by the COR from the DPW

Construction Management Branch, in accordance with documents approved in Phase

1. Normally, construction can begin once the contractor has made all changes identified during the Government design review. However, the contractor may be allowed to proceed with construction while clarification and administrative comments are being incorporated into the design. The revisions can be approved by partial re-submittals.

c. The Notice to Proceed (NTP) date for the Design Phase will be established at the Pre-

Performance Conference. After the final design submittal has been approved and it is time to start construction, the first phase is closed and a new Notice to Proceed is issued by the Contracting Officer to the contractor.

d. Phasing: Project phasing will be in accordance with the Milestones Plan at Enclosure

1, which is a Contract document.

Overall number of Calendar Days allowed will be in accordance with paragraph 3. This will include Government times as listed in the Milestone Plan at Enclosure 1.

e. General Installation Access Information: Once the contractor has been awarded the contract, he must apply for installation passes for each contract personnel requiring access for more than 60 calendar days to perform work. It takes a minimum of 30 working days from the date of application to the Security Office to be issued an installation pass. This strict access requirement will require more attention for scheduling and handling pass applications and shall be considered prior to submission of contractor’s proposal.

f. General Submittal Requirements:

(1) Government approval is required for extensions of design, critical materials, deviations, O&M manuals or those involving equipment whose compatibility with the entire system must be checked, and other items as designated by the

Contracting Officer. Within the terms of the Contract Clause entitled

“Specifications and Drawings for Construction,” they are considered to be “shop drawings.” The Contracting Officer’s approval of submittals shall not be construed as a complete check, but will indicate that the general method of construction, materials, detailing and other information are satisfactory.

Approval will not relieve the Contractor of the responsibility for any error, which may exist, as the contractor is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work.

(2) Shop drawing submittals for Government approval are required for electrical, mechanical and LAN equipment to be installed and shall be made concurrently, and shall include layout drawings showing the equipment proposed to be furnished, including special foundations, duct work, piping and electrical conduit, superimposed on the building plans and elevation. Elevation views of the layout shall be included. The layouts shall be true to scale in both plan and elevation.

The equipment shall be shown in its final position as recommended by the manufacturer and shall contain adequate dimensions to determine the location of all equipment proposed and areas required for maintenance indicated.

(3) Definitions and Examples: The examples provided below are not all-inclusive and are used only for illustration purposes.

(4) Extensions of design examples are fire alarm and sprinkler protection systems, prefabricated buildings, structural steel drawings, standing seam metal roof drawings, coordination studies such as short circuit analysis of contractor selected electrical equipment, etc.

(5) Critical materials are defined as materials, which must meet specific quality performance standards required by design parameters, the failure of which will have a major impact on the operation, maintenance, quality of life or life safety of the system. Examples of critical materials are coatings for cathodic protection of storage tanks, high-pressure piping and controls, acid and hazardous waste systems, or architectural finishes for customer approval.

(6) Deviations are any submittal by the construction contractor that varies from or are omitted from the construction contract specifications.

(7) Examples of equipment which must be checked for compatibility with existing systems or the entire new system are equipment for sewage treatment and water purification plants, energy management control systems, intrusion detection systems, power generation and distribution systems, etc.

SECTION END

Milestones Date Phase duration Progressive

Design Phase

NTP/Start Design 1-Oct-19 0 Submittal Prel Design 31-Oct-19 30 30 Comments 15-Nov-19 15 45

Submittal Prefinal Design and Approval Req 15-Dec-19 30 75 Review/Approval 30-Dec-19 15 90

Construction Phase NTP/Start Construction 14-Jan-20 Completion of construction 14-Mar-20 60 165 Final Inspection/Corrections 29-Mar-20 15 180

Oct 19 is hypothetycal NTP1 date.

Phases with bold durations are contractor's managed

Notes Passes for construction shall be obtained during design phase

Project PS1 00313-8 Upgrade electrical system bldg 5013

ENCLOSURE 1 - MILESTONES PLAN