SEE SCHEDULE
HOLLEY (DANIELLE) MCNEELY (314) 633-8363
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
09-Aug-2018
(RFP)
(IFB)
X
CALL:
REPAIR HVAC SYSTEMS BLDGS 901, 3041, 3050, 4013
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________350 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Section F
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________0 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________14 Sep 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
414TH CSB RCO ITALY SUBOFFICE LIVORNO
VIA AURELIA, EDIFICIO 5131
ZONA DEPOSITO
56128 TIRRENIA (PISA)
W912PF
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
12:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
AA1 00233-5
8. ADDRESS OFFER TO (If Other Than Item 7)
39-050-54-8289FAX:TEL: 39-050-54-8365/4 TEL: FAX:
W912PF18R0021 82
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912PF18R0021
Section A - Solicitation/Contract Form
SECTION A
A. The magnitude of this project is between $250,000 (€233,225) and $500,000 (€466,450) (Rate used is $1 = €0.9329).
B. To be awarded a Government contract, you MUST have a DUNS (Dun & Bradstreet) (https://fedgov.dnb.com/webform/) and NCAGE (www.dlis.dla.mil/Forms/Form_AC135.asp) number and to be registered in the System for Award Management (SAM) website (https://www.sam.go/portalpublic/sam)
C. See clause 52.236-27 ALT I for site visit information.
D. Request for Information (RFI) will be accepted until seven working days before the closing date as identified on page 1, block 13A.
E. For this project, the U.S. Government intends to combine the design and construction into a single contract with one contractor. The U.S. Government has developed in-house a scope of work that defines the project and provides prospective offerors with sufficient information regarding the requirements to enable offerors to submit proposals which meets the U.S. Government’s needs. The statement of work, technical specifications, and drawings are included in the attachments to this solicitation in Section J.
F. Offerors are required to indicate the cost for the design in strict accordance with all terms and conditions of the work described in the Scope of Work.
G. NON AVAILABILITY OF FUNDS. In accordance with FAR 52.232-18, Subject to the Availability of Funds, funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Repair HVAC Systems Bldgs 901
FFP
The contractor shall furnish all labor, equipment, material and transportation necessary for the accomplishment of the work in strict accordance with the Technical Specifications Project AA1 00233-5 "Repair HVAC Systems Bldgs 901, 3041, 3050, 4013" consisting of 35 pages dated 18 July 2018, technical specifications consisting of 136 pages, and drawing sheets consisting of 6 sheets.
Offerors are required to indicate the cost of design for building 901 in strict accordance with all terms and conditions of the work described in the Scope of Work. FOR INFORMATION ONLY: Please indicate the cost of design
EURO ________________
FOB: Destination
PURCHASE REQUEST NUMBER: 0011224894
PSC CD: Z1EB
NET AMT
0002 1 Job Repair HVAC Systems Bldgs 3041
FFP
The contractor shall furnish all labor, equipment, material and transportation necessary for the accomplishment of the work in strict accordance with the Technical Specifications Project AA1 00233-5 "Repair HVAC Systems Bldgs 901, 3041, 3050, 4013" consisting of 35 pages dated 18 July 2018, technical specifications consisting of 136 pages, and drawing sheets consisting of 11 sheets.
Offerors are required to indicate the cost of design for building 3041 in strict accordance with all terms and conditions of the work described in the Scope of Work. FOR INFORMATION ONLY: Please indicate the cost of design
EURO ________________
FOB: Destination
0003 1 Job Repair HVAC Systems Bldgs 3050
FFP
The contractor shall furnish all labor, equipment, material and transportation necessary for the accomplishment of the work in strict accordance with the Technical Specifications Project AA1 00233-5 "Repair HVAC Systems Bldgs 901, 3041, 3050, 4013" consisting of 35 pages dated 18 July 2018, technical specifications consisting of 136 pages, and drawing sheets consisting of 12 sheets.
Offerors are required to indicate the cost of design for building 3050 in strict accordance with all terms and conditions of the work described in the Scope of Work. FOR INFORMATION ONLY: Please indicate the cost of design
EURO ________________
FOB: Destination
0004 1 Job Repair HVAC Systems Bldgs 4013
FFP
The contractor shall furnish all labor, equipment, material and transportation necessary for the accomplishment of the work in strict accordance with the Technical Specifications Project AA1 00233-5 "Repair HVAC Systems Bldgs 901, 3041, 3050, 4013" consisting of 35 pages dated 18 July 2018, technical specifications consisting of 136 pages, and drawing sheets consisting of 12 sheets.
Offerors are required to indicate the cost of design for building 4013 in strict accordance with all terms and conditions of the work described in the Scope of Work. FOR INFORMATION ONLY: Please indicate the cost of design
EURO ________________
FOB: Destination
7500 1 Job Contractor Manpower Reporting (CMR)
FFP
THe contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the subject contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address:
http://www.ecmra.mil/ Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2018.
Contractors may direct questions to the help desk by clicking on “Send an email” which is located under the Help Resources ribbon on the right side of the login page.
FOB: Destination
PURCHASE REQUEST NUMBER: 0011224894-0001
Section C - Descriptions and Specifications
SECTION C
Section J for the list of the attached documents.
Section D - Packaging and Marking
SECTION D
Not applicable.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 7500 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-12 Inspection of Construction AUG 1996
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 350 dys. ADC 1 W582RR USAG ITALY
N/A
USAG ITALY, DARBY MILITARY
COMMUNITY VIA AUR
TIRRENIA (PISA)
N/A FOB: Destination
W582RR
0002 350 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0003 350 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0004 350 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
7500 350 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
52.211-13 Time Extensions SEP 2000
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 (ten) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 350 (three hundred and fifty) calendar days after the issuance of the notice to proceed.
* The time stated for completion shall include final cleanup of the premises.
Note:
- The Government intends to issue two separate notice to proceed letters. The first notice to proceed letter will be issued for the design phase and the second letter will be issued for the construction phase.
- The number of days for the design phase (which includes 30 days to obtain passes and the time required for the Government to provide review comments to the contractor for each planned submittal) is 150 (one hundred and fifty) calendar days.
- The number of days for the construction phase is 200 (two hundred) calendar days
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of €167 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
Section H - Special Contract Requirements
SECTION H
CONTRACTING OFFICER AUTHORITY
1. In no event shall any understanding or agreement between the Contractor and any Government employee, other than the Contracting Officer on any contract, modification, change order, letter of verbal direction to the Contractor be effective or binding upon the Government. All such actions must be formalized by a proper contractual document executed by an appointed Contracting Officer.
2. The Contractor is hereby put on notice that in the event a Government employee, other than the Contracting
Officer, directs a change in the work to be performed, or increases the scope of work to be performed, it is the Contractor's responsibility to make inquiry of the Contracting Officer before making the deviation. Payments will not be made without being authorized by an appointed Contracting Officer with the legal authority to bind the Government.
CONTRACT MANAGER
1. The contractor shall provide a contract manager who shall be responsible for the performance of work. The name of this person and an alternate(s) who shall act for the contractor when the manager is absent shall be designated in writing to the Contracting Officer or designee prior to start performance.
2. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract.
3. The contract manager or alternate shall be available during normal duty hours within sixty (60) minutes to meet at the job site with the Contracting Officer or designee to discuss problem areas. The contractor shall provide to the Contracting Officer or designee the telephone number of the person(s) to call should the need arise.
4. The contract manager or alternate shall be capable of explaining the work operations and receiving instructions in the English language. The Contracting Officer shall have the right to determine without appeal of such decision, whether the proposed representative has sufficient technical and lingual capabilities and the Contractor shall immediately replace any individual not acceptable to the Contracting Officer.
5. Before starting performance, the Contractor SHALL coordinate the operation with the COR.
SUBSTITUTION OF PROPOSED FIRM(S)
If the award is made to a Permanent Pool of Firms (Consorzio Stabile), the Contractor shall make no substitution of the firm(s) that it has proposed to perform the work during the evaluation phase unless the firm(s) goes/go out of business. In this case, the Permanent Pool of Firms shall provide to the Contracting Officer the names of at least five (5) proposed substitutions with comparable or better qualification, past performance, and technical competence to the firm being replaced, and any additional information requested by the Contracting Officer. The Contracting Officer will notify the Contractor within ten (10) calendar days after receipt of all required information of the decision on substitution.
SUBCONTRACTING
The Contractor shall submit requests to subcontract any portion of work to be performed under this contract to the Contracting Officer for approval. The following documents shall be submitted for subcontract consent.
1. Description of Work to be subcontracted
2. Name(s) of the Subcontractor(s)
TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1. This requirement specifies the procedure for determining time extensions for unusually severe weather, in accordance with FAR Clause FAR 52.249-10 “DEFAULT (FIXED PRICE CONSTRUCTION (APR 1984)”. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control, and without the fault and negligence, of the Contractor.
2. The following schedule of monthly anticipated adverse weather delays for the project location is based on the Italian Weather Agency (Bollettino Meteorologico) and will constitute the base line for monthly weather time evaluations. The Contractor’s progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
Monthly Anticipated Adverse Weather (Calendar Days)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 8 7 10 8 5 3 3 3 5 10 10 8
3. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily Contractor Quality Control (CQC) report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor’s scheduled work day.
4. The number of actual adverse weather delay days shall include days impacted by actual adverse weather, even if the adverse weather occurred in the previous month, be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 2 above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification for time, in accordance with the FAR Clause 52.249-10 “DEFAULT (FIXED PRICE
CONSTRUCTION) (APR 1984).
PRE FINAL AND FINAL INSPECTION
1.Prior to the final inspection, the Contracting Officer has the right to schedule one, or more than one, prefinal inspection if he/she determines it necessary. The pre-final inspection(s) will be conducted jointly among the Contractor, the COR, and appropriate Government personnel. Any discrepancies noted shall be corrected prior to any final inspection.
2.When the project is ready for final inspection, the Contractor shall request final inspection in writing to the Contracting Officer at least two (2) calendar days before the desired date of inspection.
U.S. AND HOST NATION HOLIDAYS
U.S. Holidays: Work shall not be performed on U.S. holidays occurring during the normal work week unless otherwise directed by the Contracting Officer. When a U.S. Holiday occurs on a Saturday or a Sunday, the Holiday is observed on the preceding Friday or following Monday, respectively.
Host Nation Holidays: Work shall not be performed on local Host Nation* Holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer.
* Local Host Nation Holidays occur in the Provence (Provincia) or Region (Regione) where contract performance takes place.
U.S. Holidays:
Name of U.S. Holiday Date
New Year’s Day January 1
Martin Luther King, Jr. Day 3rd Monday of January
Washington’s Birthday / President’s Day 3rd Monday of February
Memorial Day Last Monday of May
Independence Day July 4
Labor Day 1st Monday of September
Columbus Day 2nd Monday of October
Veterans’ Day November 11
Thanksgiving 4th Thursday of November
Christmas Day December 25
Host Nation Holidays:
English Name of Host Nation Holiday Italian Name Holiday Date
New Year’s Day Capodanno January 1
Epiphany Day Epifania January 6
Easter Monday Pasquetta Monday after Easter
Liberation Day Festa della Liberazione April 25
Labor Day Festa del Lavoro May 1
Local Public Holiday* Saint Giulia May 22
Republic Day Festa della Repubblica June 2
Local Public Holiday* Saint Ranieri June 17
Ferragosto / Assumption Day Ferragosto and Assunta August 15
All Saints’ Day Tutti i santi (or Ognissanti) November 1
Immaculate Conception Day Immacolata Concezione December 8
Christmas Day Natale December 25
Saint Stephen’s Day Santo Stefano December 26
CONTRACTOR IDENTIFICATION REQUIREMENTS
All contractor personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious are required to identify themselves as such to avoid being mistaken for Government officials. Contractors performing work at Government workplaces will provide their employees with an easily readable identification (ID) badge indicating the employee’s name, the contractor’s name, the functional area of assignment, and a recent color photograph of the employee. Contractors shall require their employees wear the ID badges visibly when performing work at Government workplaces. Contractor personnel must also ensure that all emails, documents or reports they produce are suitably marked as contractor products or that contractor participation is appropriately disclosed.”
INSTALLATION CLEARENCE REQUIREMENTS
(a) Access to U.S. installations and controlled areas is limited to personnel who meet security criteria and authorized by Host Nation law to work in that country. Failure to submit required information/data and obtain required documentation or clearances in accordance with AE Regulation 190-16, Installation Access Control, will be grounds for denying access to U.S. installations and controlled areas. The Contractor is responsible to ensure that any Subcontractor used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any Subcontractor utilized by the contractor, are made aware of and comply with these requirements.
(b) The Contractor is responsible for being aware of and complying with the requirements associated with Installation Access Control. The Government is not liable for any costs associated with performance delays due solely to a firm’s failure to comply with Installation Access Control (IAC) processing requirements.
(c) The Contractor is responsible for returning installation passes to the issuing Installation Access Control Office (IACO) when the contract is completed or when a contractor employee no longer requires access.
(d) Should the force protection condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
(e) Below is the responsible Organizational Sponsor & Installation Access Control Office for this contract:
Organizational Sponsor: _______DPW – Mr. Giuseppe Spanu______________________ Location: __Depot Area_______________________Building No: ____5155_______ DSN Phone No: _633-7442________ Commercial Phone No: ___050-547442____ Installation Access Control Office: Installation Pass & Badge Office Location: _Camp Darby______________________Building No: ____302_________ DSN Phone No: ___633-7369___________ Commercial Phone No: _050-547369___
INSTRUCTIONS FOR CONTRACTOR'S QUALITY CONTROL PLAN
The contractor will coordinate with the COR (or receiving activity, if no COR has been appointed) to establish a Contractor's Quality Control Plan (CQCP).
The contractor will provide a copy of the CQCP annotated with the contract number to the COR at the preperformance conference. The COR will submit an approved copy to the Contracting Officer.
In addition to any requirements in the specification or statement of work, the contractor's quality control plan must have as a minimum:
- Identification and clearly defined authority of key personnel under the contractor's organization.
- A quality inspection system covering all general and specific tasks included in the contract scope of work. It should specify tasks or areas to be inspected on either a scheduled or unscheduled basis, and the manner in which inspections are to be conducted.
- The names of firms or individuals tasked to perform inspections and the extent of their authority. This may be in the form of an organization chart or other form approved by the contracting officer's representative (COR).
- Proposed test methods, including names of technicians or qualified testing laboratories to be used, if applicable.
Tests must be specified.
- A method of identifying deficiencies in the quality of services or construction performed before the level of performance becomes unacceptable.
- A method of documenting and enforcing quality control operations of both prime and subcontractor work, including inspection and testing.
- Key control, internal control or security procedures, if applicable.
- Any winterization plans and procedures for outdoor and exposed contractor and Government furnished equipment, if applicable.
- A method of identifying deficiencies in the quality of manufacturing, services, or construction performed before the level of performance becomes unacceptable.
- Detailed information specifying the types of action the contractor will take to correct deficiencies and prevent their recurrence.
- Detailed information on the inspection methods used and proposed test methods, including names of technicians or qualified testing laboratories to be used, if applicable. Tests must be specified.
Section I - Contract Clauses
52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
APR 2014
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2016
52.204-13 System for Award Management Maintenance OCT 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.222-50 Alt I Combating Trafficking in Persons (MAR 2015) Alternate I MAR 2015 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-14 Inconsistency Between English Version And Translation Of
Contract
FEB 2000
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-4 Workers' Compensation and War-Hazard Insurance Overseas APR 1984 52.229-6 Taxes--Foreign Fixed-Price Contracts FEB 2013 52.232-17 Interest MAY 2014 52.232-18 Availability Of Funds APR 1984 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984
52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) -
Alternate I
APR 1984
52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.244-6 Subcontracts for Commercial Items JUL 2018 52.248-3 Value Engineering-Construction OCT 2015 52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984
52.228-15 PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION (OCT 2010)
(a) Definitions. As used in this clause--
Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25-A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection. (i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the U.S. Department of the Treasury, Financial Management Service, Surety Bond Branch, 3700 East West Highway, Room 6F01, Hyattsville, MD 20782. Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.
(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
(1) The Contractor's request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract.
(iii) A listing of the total amount of each subcontract under the contract.
(iv) A listing of the amounts previously paid to each such subcontractor under the contract.
(v) Additional supporting data in a form and detail required by the Contracting Officer.
(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if--
(i) Consideration is specifically authorized by this contract; and
(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that--
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
(Name)
(Title)
(Date)
(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall--
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until--
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as--
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.
(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(h) Final payment. The Government shall pay the amount due the Contractor under this contract after--
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of 1940 (31 U.S.C. 3727 and 41 U.S.C. 6305).
(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR Subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(j) Interest computation on unearned amounts. In accordance with 31 U.S.C. 3903(c)(1), the amount payable under subparagraph (d)(2) of this clause shall be--
(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and
(2) Deducted from the next available payment to the Contractor.
52.233-1 DISPUTES. (MAY 2014)
(a) This contract is subject to 41 U.S.C. chapter 71, Contract Disputes.
(b) Except as provided in 41 U.S.C. chapter 71, all disputes arising under or relating to this contract shall be resolved under this clause.
(c) “Claim,” as used in this clause, means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to this contract. However, a written demand or written assertion by the Contractor seeking the payment of money exceeding $100,000 is not a claim under the Act until certified. A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim under 41 U.S.C. chapter 71. The submission may be converted to a claim under the Act, by complying with the submission and certification requirements of this clause, if it is disputed either as to liability or amount or is not acted upon in a reasonable time.
(d)(1) A claim by the Contractor shall be made in writing and, unless otherwise stated in this contract, submitted within 6 years after accrual of the claim to the Contracting Officer for a written decision. A claim by the Government against the Contractor shall be subject to a written decision by the Contracting Officer.
(2)(i) The Contractor shall provide the certification specified in paragraph (d)(2)(iii) of this clause when submitting any claim exceeding $100,000.
(ii) The certification requirement does not apply to issues in controversy that have not been submitted as all or part of a claim.
(iii) The certification shall state as follows: “I certify that the claim is made in good faith; that the supporting data are accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the Contractor believes the Government is liable; and that I am authorized to certify the claim on behalf of the Contractor.”
(3) The certification may be executed by any person authorized to bind the Contractor with respect to the claim.
(e) For Contractor claims of $100,000 or less, the Contracting Officer must, if requested in writing by the Contractor, render a decision within 60 days of the request. For Contractor-certified claims over $100,000, the Contracting Officer must, within 60 days, decide the claim or notify the Contractor of the date by which the decision will be made.
(f) The Contracting Officer’s decision shall be final unless the Contractor appeals or files a suit as provided in 41 U.S.C. chapter 71.
(g) If the claim by the Contractor is submitted to the Contracting Officer or a claim by the Government is presented to the Contractor, the parties, by mutual consent, may agree to use alternative dispute resolution (ADR). If the Contractor refuses an offer for ADR, the Contractor shall inform the Contracting Officer, in writing, of the Contractor’s specific reasons for rejecting the offer.
(h) The Government shall pay interest on the amount found due and unpaid from (1) the date that the Contracting Officer receives the claim (certified, if required); or (2) the date that payment otherwise would be due, if that date is later, until the date of payment. With regard to claims having defective certifications, as defined in FAR 33.201, interest shall be paid from the date that the Contracting Officer initially receives the claim. Simple interest on claims shall be paid at the rate, fixed by the Secretary of the Treasury as provided in the Act, which is applicable to the period during which the Contracting Officer receives the claim and then at the rate applicable for each 6-month period as fixed by the Treasury Secretary during the pendency of the claim.
(i) The Contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, appeal, or action arising under the contract, and comply with any decision of the Contracting Officer.
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)
(a) The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates determined by the Contracting Officer. The Contractor shall carefully conserve any utilities furnished without charge.
(b) The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
(b) This warranty shall continue for a period of 2 (two) years from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 2 (two) years from the date the Government takes possession.
(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of--
(1) The Contractor's failure to conform to contract requirements; or
(2) Any defect of equipment, material, workmanship, or design furnished.
(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 2 (two) years from the date of repair or replacement.
(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.
(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall--
(1) Obtain all warranties that would be given in normal commercial practice;
(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and
(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.
(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.
(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.
(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://farsite.hill.af.mil
252.201-7000 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 1991)
(a) "Definition. Contracting officer's representative" means an individual designated in accordance with subsection 201.602-2 of the Defense Federal Acquisition Regulation Supplement and authorized in writing by the contracting officer to perform specific technical or administrative functions.
(b) If the Contracting Officer designates a contracting officer's representative (COR), the Contractor will receive a copy of the written designation. It will specify the extent of the COR's authority to act on behalf of the contracting officer. The COR is not authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the contract.
252.203-7000 REQUIREMENTS RELATING TO COMPENSATION OF FORMER DOD OFFICIALS (SEP
2011)
(a) Definition. Covered DoD official, as used in this clause, means an individual that--
(1) Leaves or left DoD service on or after January 28, 2008; and
(2)(i) Participated personally and substantially in an acquisition as defined in 41 U.S.C. 131 with a value in excess of $10 million, and serves or served--
(A) In an Executive Schedule position under subchapter II of chapter 53 of Title 5, United States Code;
(B) In a position in the Senior Executive Service under subchapter VIII of chapter 53 of Title 5, United States Code;
or
(C) In a general or flag officer position compensated at a rate of pay for grade O-7 or above under section 201 of Title 37, United States Code; or
(ii) Serves or served in DoD in one of the following positions: Program manager, deputy program manager, procuring contracting officer, administrative contracting officer, source selection authority, member of the source selection evaluation board, or chief of a financial or technical evaluation team for a contract in an amount in excess of $10 million.
(b) The Contractor shall not knowingly provide compensation to a covered DoD official within 2 years after the official leaves DoD service, without first determining that the official has sought and received, or has not received after 30 days of seeking, a written opinion from the appropriate…