W912PF-17-R-0002-0001.pdf
PDF 78 KB Posted
- Attached to
- Furnish and Install New Electrical Transformer Station in the DOL area, Caserma Ederle, Vicenza, Italy.
- Solicitation number
- W912PF-17-R-0002
About this file
AMENDMENT 0001
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0010943589 E8-41188-5J
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The intent of this amendment is the follow ing:
1. Change the requierd response date/time;
2. Add SOA Category OG10, Classification II;
3. Delete the Statement of Work provided w ith the solicitation in its entirety and replace it w ith the attached Revised Statement of Work;
4. Provide the offerors w ith the Cable Distribution Standards (CDS) Construction Standards, ATTACHMENT #5 and the Technical Criteria for the Installation Information Infrastructure Architecture, ATTACHMENT #6;
5. Provide answ ers to the questions posed by the offerors;
6. Provide the List of Work Features, ATTACHMENT #1, in excel format text.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Dec-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PF-17-R-0002
X 9B. DATED (SEE ITEM 11)
18-Nov-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Dec-2016
CODE
414TH CSB - PARC AFRICA
ATTN: PATRIZIA MELONI
VIA DELLA PACE #197
36100 VICENZA (VI)
ITALY
W912PF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912PF-17-R-0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 19-Dec-2016 03:00 PM to 10-Jan-2017 03:00 PM.
(End of Summary of Changes)
The following items are applicable to this modification:
AMENDMENT
1. SOA Category OG10, Classification II is hereby added. To be eligible for an award offerors shall have SOA OG11, Classification II, required by the solicitation, OR SOA OG10, Classification II.
2. The Statement of Work, ATTACHMENT #2, provided with the solicitation is deleted in its entirety and replace with the Revised Statement of Work, dated 1 December 2016, ATTACHMENT #2.
3. Offerors are provided with the Cable Distribution System (CDS) Construction Standards , ATTACHMENT #5 and the Technical Criteria for the Installation Information Infrastructure Architecture (ATTACHMENT #6)
4. THE FOLLOWING ARE THE ANSWERS TO THE QUESTIONS POSED BY THE OFFERORS:
Question 1.
Size of the ductbank (see quantity of conduits and size of conduits) are OK, or does the contractor need to verify and eventually modify the layout?
Answer 1.
Sse the Revised Statement of Work dated 1 Dec 2016, Paragraph 4.3.13 (cables size and P.V.C. pipes shall be calculated by Contractor).
Question 2.
Does the contractor need to install a new Rack in Bldg#204 ?
Answer 2.
No, we don't need a new cabinet inside B204, we will use the existing cabinet "I3MP Cabinet 3".
Question 3.
In the new rack in Bldg#204, does the contractor need to consider one F.O. patch panel dedicated per each building that needs to be connected to?
Answer 3.
Inside B204, I3MP Cabinet 3, in order to save space, the contractor can consolidate fibers coming from the buildings with a 48 port patch panels with SC ports instead to have one dedicated patch panels for each building. By doing this, we will need only two patch panels instead of five.
Question 4.
Which is the cos δ that the contractor needs to consider in order to develop the Electrical load analysis (Low Voltage Panelboard 400V) ?
Answer 4.
In order to develop the electrical load analysis assume a cos δ 0,8.
Question 5.
In the SOW is not clear which loads are required to be connected to the new Low Voltage Panelboard 230 V.
Please, clarify.
Answer 5.
See the Revised Statemen of Work dated 1 Dec 2016, Parapgrah 4.3.10 (The new LV column for 230V section shall be furnished and installed of the same material, color and dimension of the new 400V column with a 1250A, 4 ph motorized circuit breaker and accessories as described above).
Question 6.
Does the contractor need to pull the new power cable / Optical Fiber cable to the new manholes close out to the new Paint Booth area? Or predispose the electrical CB in the Low Voltage Panel 400 V is sufficient?
Answer 6.
See the Revised Statement of Work dated 1 Dec 2016, Parapgarph 4.3.13 (4.3.13 Provide L.V.
cables type FG7R 0.6/1 kV (three phases + neutral + ground) to connect the four buildings 266, 263E, 238, 210A and future Paint Booth (cables with 15m of spare shall be left in place in the new final manhole of the future Paint Booth to the new Transformer Station).
The same solution shall be considered for the Optical Fiber.
Question 7.
Is it required the registration process (to the Municipality “ACCATASTAMENTO”/ SCIA etc.) for the new ESS, or is the USAG in charge for this process?
Answer 7.
These processes are not needed.
5. The List of Work Features, ATTACHMENT #1, is provided in excel format text.
All the other terms and conditions of the solicitation remain the same.
File details come from the government source that posted it. Updated .