This abstract of bids summarizes three offers received in response to Solicitation Number W912P924B0003 for the Belleville East Creek Sewer Separation project. The U.S. Army Corps of Engineers, St. Louis District and the City of Belleville, Illinois are seeking a contractor to complete construction of approximately 13,100 feet of 15-inch to 72-inch storm sewer, 2,000 feet of 12-inch and 18-inch sanitary sewer, 153 storm and sanitary structures, two detention ponds, and related work including tree removal, pavement removal, concrete and asphalt patching, sidewalks and ADA ramps, pavement marking, fencing, site restoration, seeding, traffic control, and material testing. The bids were opened on March 8, 2024 with DMS Contracting, Inc. providing the lowest total price of $10,108,563.89, followed by Haier Plumbing & Heating Inc. at $11,210,697.57, and Baxmeyer Construction Inc. at $11,035,656.03. The abstract provides unit pricing and extended costs for over 50 line items to allow for evaluation of the offers.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No: W912P924B0003 Date Issued: 03/08/2024 Amendments: 0005 Bids Due: 03/08/2024 10:00am CST Public Bid Opening: 03/08/2024 2:00pm CST

Bid received by due date/time? Yes Yes Yes Amendments Acknowledged? Yes Yes Yes Bid Security (Type and amount) Yes Bid Bond-$3M/20% Yes Bid Bond-$3M/20% Yes Bid Bond-$3M/20% Grand Total Prices $10,108,563.89 $11,210,697.57 $11,035,656.03

CLIN Description Quantity U/M Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount

A001 Mobilization and Demobilization Phase 1 1 JB $246,500.00 $246,500.00 $386,540.00 $386,540.00 325,000.00$ $325,000.00 $270,245.23 $270,245.23

A002 Temporary Traffic Control 1 JB $17,900.00 $17,900.00 $17,140.00 $17,140.00 47,500.00$ $47,500.00 $20,636.07 $20,636.07

A003 Tree Removal (6 to 15 Inches Diameter) 146 IN $44.90 $6,555.40 $139.50 $20,367.00 91.50$ $13,359.00 $61.39 $8,962.94

A004 Tree Removal (Over 15 Inches Diameter) 538 IN $29.80 $16,032.40 $145.50 $78,279.00 37.25$ $20,040.50 $79.54 $42,792.52

A005 Tree Removal (Acre) 1.7 AC $7,060.00 $12,002.00 $38,730.00 $65,841.00 19,650.00$ $33,405.00 $18,690.22 $31,773.37 A006 Erosion & Sedimentation Control 1 JB $30,100.00 $30,100.00 $12,318.00 $12,318.00 12,550.00$ $12,550.00 $25,971.49 $25,971.49 A007 Stabilized Construction Entrance 1 EA $3,870.00 $3,870.00 $16,137.00 $16,137.00 4,000.00$ $4,000.00 $3,084.18 $3,084.18 A008 Temporary Erosion Control Blanket 5026 SY $3.20 $16,083.20 $1.40 $7,036.40 2.80$ $14,072.80 $2.81 $14,123.06 A009 Erosion Control Blanket 5026 SY $6.20 $31,161.20 $1.40 $7,036.40 2.80$ $14,072.80 $2.81 $14,123.06

A010 Temporary Erosion Control Seeding & Mulching 2.5 AC $3,800.00 $9,500.00 $11,585.00 $28,962.50 3,000.00$ $7,500.00 $6,243.66 $15,609.15

A011 Detention Pond Seeding & Mulching 2.5 AC $4,580.00 $11,450.00 $20,762.00 $51,905.00 10,000.00$ $25,000.00 $4,952.05 $12,380.13 A012 Curb Removal 890 LF $14.60 $12,994.00 $6.50 $5,785.00 9.50$ $8,455.00 $12.51 $11,133.90 A013 Pavement Removal, Concrete 0.0 SY $54.40 $0.00 $500.00 $0.00 $0.00 $1,000.00 $0.00 A014 Pavement Removal, Bituminous 1469.9 SY $17.00 $24,988.30 $6.10 $8,966.39 9.15$ $13,449.59 $22.26 $32,719.97

A015 Driveway Pavement Removal, Concrete 0 SY $142.00 $0.00 $500.00 $0.00 $0.00 $1,000.00 $0.00

A016 Driveway Pavement Removal, Bituminous 26 SY $86.80 $2,256.80 $70.90 $1,843.40 63.00$ $1,638.00 $33.74 $877.24

A017 Remove Fence 360 LF $27.10 $9,756.00 $10.10 $3,636.00 9.50$ $3,420.00 $7.99 $2,876.40 A018 Sidewalk Removal 0 SF $3.80 $0.00 $500.00 $0.00 $0.00 $100.00 $0.00

A019 Sanitary Sewer Abandonment or Removal, 10" to 15" 50 LF $83.00 $4,150.00 $515.00 $25,750.00 95.00$ $4,750.00 $456.48 $22,824.00

A020 Storm Sewer Removal, 48" 1580 LF $41.50 $65,570.00 $19.90 $31,442.00 32.75$ $51,745.00 $25.94 $40,985.20 A021 Manhole/Inlet Removal 19 EA $812.00 $15,428.00 $434.50 $8,255.50 346.00$ $6,574.00 $393.65 $7,479.35 A022 Remove Retaining Wall 50 LF $49.20 $2,460.00 $65.40 $3,270.00 96.00$ $4,800.00 $17.24 $862.00 A023 Earth Excavation 7077 CY $7.10 $50,246.70 $0.01 $70.77 1.00$ $7,077.00 $0.01 $70.77

Belleville East Creek Sewer Separation Bid Abstract - Construction

Government Estimate

Offeror 1 DMS Contracting, Inc Mascoutah, IL 62256

UEI: R7TACFLXH3G1

CAGE: 37TQ2

Offeror 3 Baxmeyer Construction Inc

Waterloo, IL 62298

UEI: D3WNJHNFERL8

CAGE: 1BSR9

Offeror 2 Haier Plumbing&Heating Inc Okawville, IL 62271

UEI: L5XLSFMD1JF3

CAGE: 0EJV5

Tracy N. Tenholder Contracting Officer

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

BASE CONTRACT - EXHIBIT A (PHASE 1)

A024 Aggregate Base Course, Type A 6-inch 2095.0 SY $8.40 $17,598.00 $8.00 $16,760.00 13.00$ $27,235.00 $16.71 $35,007.45

A025 Aggregate Surface Course, Type B 6-inch 30 SY $74.50 $2,235.00 $78.30 $2,349.00 16.50$ $495.00 $18.22 $546.60

A026 Asphalt Roadway Pavement, 6-inch 1469.9 SY $67.10 $98,630.29 $65.80 $96,719.42 72.00$ $105,832.80 $85.50 $125,676.45 A027 Asphalt Driveway Replacement 26 SY $126.00 $3,276.00 $135.20 $3,515.20 104.00$ $2,704.00 $68.55 $1,782.30 A028 Concrete Driveway Replacement 0 SY $214.00 $0.00 $1,200.00 $0.00 $0.00 $1,000.00 $0.00 A029 15" Storm Sewer, Class B 11 LF $97.50 $1,072.50 $280.75 $3,088.25 147.00$ $1,617.00 $76.58 $842.38 A030 24" Storm Sewer, Class B 30 LF $122.00 $3,660.00 $215.00 $6,450.00 168.00$ $5,040.00 $86.45 $2,593.50 A031 48" Storm Sewer, Class A 20 LF $499.00 $9,980.00 $293.90 $5,878.00 480.00$ $9,600.00 $485.64 $9,712.80 A032 48" Storm Sewer, Class B 471 LF $189.00 $89,019.00 $198.25 $93,375.75 175.00$ $82,425.00 $248.41 $117,001.11 A033 72" Storm Sewer, Class A 793 LF $823.00 $652,639.00 $552.60 $438,211.80 502.00$ $398,086.00 $592.58 $469,915.94 A034 72" Storm Sewer, Class B 321 LF $777.00 $249,417.00 $584.15 $187,512.15 817.00$ $262,257.00 $768.52 $246,694.92 A035 12" PVC Sanitary Sewer, SDR-26 1983 LF $48.80 $96,770.40 $237.25 $470,466.75 156.00$ $309,348.00 $179.22 $355,393.26

A036 Connection of Existing Pipe to Manhole 22 EA $1,700.00 $37,400.00 $1,035.00 $22,770.00 2,193.00$ $48,246.00 $4,077.36 $89,701.92

A037 Reconnect Sanitary Sewer Lateral 10 EA $452.00 $4,520.00 $858.45 $8,584.50 2,745.00$ $27,450.00 $5,515.20 $55,152.00 A038 72" FES 1 EA $8,860.00 $8,860.00 $14,567.00 $14,567.00 12,473.00$ $12,473.00 $13,831.36 $13,831.36 A039 Control Structure, CS-1 1 EA $38,600.00 $38,600.00 $28,460.00 $28,460.00 31,268.00$ $31,268.00 $51,629.21 $51,629.21

A040 Concrete Junction Box, 48x96, Type 1 Frame & Lid 5 EA $6,560.00 $32,800.00 $18,875.00 $94,375.00 15,420.00$ $77,100.00 $14,385.71 $71,928.55

A041 Concrete Junction Box, 48x96, Type 8 Frame & Grate 2 EA $7,960.00 $15,920.00 $15,228.00 $30,456.00 13,720.00$ $27,440.00 $14,100.90 $28,201.80

A042 Concrete Junction Box, 72x72, Type 1 Frame & Lid 5 EA $11,300.00 $56,500.00 $22,907.00 $114,535.00 14,050.00$ $70,250.00 $15,749.19 $78,745.95

A043 Concrete Junction Box, 72x96, Type 1 Frame & Lid 1 EA $13,500.00 $13,500.00 $17,310.00 $17,310.00 15,900.00$ $15,900.00 $16,374.99 $16,374.99

A044 Manholes, Type A 4-ft. Diameter, Type 1 Frame & Lid 13 EA $10,600.00 $137,800.00 $8,490.00 $110,370.00 5,676.00$ $73,788.00 $5,604.14 $72,853.82

A045 Concrete Channel, 8-ft Wide 508 LF $217.00 $110,236.00 $106.65 $54,178.20 110.00$ $55,880.00 $101.82 $51,724.56 A046 Concrete Curb, 6-inch 890 LF $41.50 $36,935.00 $33.25 $29,592.50 70.00$ $62,300.00 $33.38 $29,708.20 A047 Site Restoration 1 JB $106,800.00 $106,800.00 $52,500.00 $52,500.00 27,145.00$ $27,145.00 $219,660.56 $219,660.56

A048 B Street Detention Pond - Chain Link Fence, 6' 1130 LF $71.40 $80,682.00 $36.85 $41,640.50 44.00$ $49,720.00 $38.78 $43,821.40

A049 B Street Detention Pond - Chain Link Gate, 6' x 12' Single 1 EA $4,840.00 $4,840.00 $3,234.00 $3,234.00 3,872.00$ $3,872.00 $2,035.00 $2,035.00

A050 B Street Detention Pond - Chain Link Gate, 6' x 18' Double 1 EA $8,490.00 $8,490.00 $3,935.00 $3,935.00 4,711.00$ $4,711.00 $2,200.00 $2,200.00

A051 B Street Detention Pond - Flared End Section Grate 2 EA $2,470.00 $4,940.00 $4,202.00 $8,404.00 3,900.00$ $7,800.00 $2,252.70 $4,505.40

A052 B Street Detention Pond - Earth Excavation 24880 CY $7.10 $176,648.00 $22.25 $553,580.00 9.87$ $245,565.60 $3.14 $78,123.20

A053 B Street Detention Pond - Hauling Off Spoils 18660 CY $16.30 $304,158.00 $0.01 $186.60 11.43$ $213,283.80 $18.29 $341,291.40

BASE CONTRACT - EXHIBIT A (PHASE 1) TOTAL $2,992,930.19 $3,293,585.98 $2,877,240.89 $3,196,186.06

B001 Mobilization and Demobilization Phase 2 1 JB $124,700.00 $124,700.00 $347,450.00 $347,450.00 375,000.00$ $375,000.00 $187,949.00 $187,949.00

B002 Temporary Traffic Control 1 JB $17,900.00 $17,900.00 $21,589.00 $21,589.00 15,360.00$ $15,360.00 $54,629.65 $54,629.65

B003 Tree Removal (6 to 15 Inches Diameter) 34.5 IN $47.50 $1,638.75 $109.25 $3,769.13 57.25$ $1,975.13 $61.38 $2,117.61

B004 Tree Removal (Over 15 Inches Diameter) 368 IN $29.70 $10,929.60 $159.70 $58,769.60 50.00$ $18,400.00 $102.53 $37,731.04

B005 Tree Removal (Acre) 0.1 AC $17,600.00 $1,760.00 $124,346.00 $12,434.60 39,500.00$ $3,950.00 $21,971.20 $2,197.12 B006 Erosion & Sedimentation Control 1 JB $32,900.00 $32,900.00 $4,775.00 $4,775.00 12,500.00$ $12,500.00 $15,917.85 $15,917.85

BASE CONTRACT -EXHIBIT B (PHASE-2)

B007 Stabilized Construction Entrance 1 EA $3,870.00 $3,870.00 $16,416.00 $16,416.00 7,030.00$ $7,030.00 $6,013.95 $6,013.95 B008 Temporary Erosion Control Blanket 5562 SY $3.20 $17,798.40 $1.35 $7,508.70 2.90$ $16,129.80 $3.15 $17,520.30 B009 Erosion Control Blanket 5562 SY $6.20 $34,484.40 $1.35 $7,508.70 2.90$ $16,129.80 $3.63 $20,190.06

B010 Temporary Erosion Control Seeding & Mulching 2.6 AC $3,800.00 $9,880.00 $11,170.85 $29,044.21 2,873.00$ $7,469.80 $0.01 $0.03

B011 Detention Pond Seeding & Mulching 2.6 AC $4,580.00 $11,908.00 $19,575.75 $50,896.95 10,000.00$ $26,000.00 $4,819.45 $12,530.57 B012 Curb Removal 3880 LF $14.60 $56,648.00 $3.85 $14,938.00 10.00$ $38,800.00 $17.13 $66,464.40 B013 Pavement Removal, Concrete 1924 SY $54.40 $104,665.60 $11.20 $21,548.80 18.70$ $35,978.80 $44.53 $85,675.72 B014 Pavement Removal, Bituminous 4686 SY $16.30 $76,381.80 $3.06 $14,339.16 17.10$ $80,130.60 $20.90 $97,937.40

B015 Driveway Pavement Removal, Concrete 0 SY $142.00 $0.00 $500.00 $0.00 $0.00 $1,000.00 $0.00

B016 Sidewalk Removal 10427 SF $3.80 $39,622.60 $0.90 $9,384.30 3.00$ $31,281.00 $0.88 $9,175.76 B017 Remove Fence 260 LF $27.10 $7,046.00 $14.00 $3,640.00 16.00$ $4,160.00 $8.42 $2,189.20 B018 Manhole/Inlet Removal 14 EA $812.00 $11,368.00 $259.15 $3,628.10 580.00$ $8,120.00 $596.04 $8,344.56 B019 Earth Excavation 4125 CY $7.10 $29,287.50 $0.01 $41.25 1.00$ $4,125.00 $0.01 $41.25

B020 Aggregate Base Course, Type A 6-inch 3365 SY $8.40 $28,266.00 $10.85 $36,510.25 10.00$ $33,650.00 $15.80 $53,167.00

B021 Aggregate Surface Course, Type B 6-inch 350 SY $39.00 $13,650.00 $22.75 $7,962.50 13.30$ $4,655.00 $16.36 $5,726.00

B022 Asphalt Roadway Pavement, 6-inch 4686 SY $64.60 $302,715.60 $16.36 $76,662.96 103.00$ $482,658.00 $85.71 $401,637.06

B023 Concrete Roadway Pavement, 7-inch 1924 SY $53.40 $102,741.60 $55.10 $106,012.40 103.00$ $198,172.00 $76.33 $146,858.92 B024 Concrete Driveway Replacement 0 SY $214.00 $0.00 $1,200.00 $0.00 $0.00 $1,000.00 $0.00

B025 Portland Cement Concrete Sidewalk, 4-inch 10427 SF $9.70 $101,141.90 $4.25 $44,314.75 11.00$ $114,697.00 $15.31 $159,637.37

B026 Remove and Restore Trail 150 SF $24.30 $3,645.00 $22.15 $3,322.50 40.00$ $6,000.00 $22.71 $3,406.50 B027 Detectable Warnings 310 SF $63.00 $19,530.00 $82.50 $25,575.00 30.00$ $9,300.00 $37.92 $11,755.20 B028 15" Storm Sewer, Class B 531 LF $63.40 $33,665.40 $101.75 $54,029.25 120.00$ $63,720.00 $159.09 $84,476.79 B029 18" Storm Sewer, Class B 347 LF $84.00 $29,148.00 $134.45 $46,654.15 149.00$ $51,703.00 $208.88 $72,481.36 B030 36" Storm Sewer, Class B 1151 LF $153.00 $176,103.00 $290.85 $334,768.35 325.00$ $374,075.00 $442.47 $509,282.97 B031 42" Storm Sewer, Class B 313 LF $187.00 $58,531.00 $307.90 $96,372.70 362.00$ $113,306.00 $393.78 $123,253.14 B032 36" FES 1 EA $1,850.00 $1,850.00 $4,875.00 $4,875.00 3,180.00$ $3,180.00 $3,792.63 $3,792.63 B033 42" FES 1 EA $2,870.00 $2,870.00 $5,720.00 $5,720.00 3,800.00$ $3,800.00 $4,889.02 $4,889.02 B034 Control Structure, CS-2 1 EA $38,600.00 $38,600.00 $35,185.00 $35,185.00 8,225.00$ $8,225.00 $39,797.86 $39,797.86 B035 Curb Inlet, Set Back 1 EA $3,950.00 $3,950.00 $5,695.00 $5,695.00 4,200.00$ $4,200.00 $5,411.25 $5,411.25 B036 Double Curb Inlet, Set Back 1 EA $7,890.00 $7,890.00 $8,260.00 $8,260.00 6,800.00$ $6,800.00 $8,014.18 $8,014.18

B037 Manholes, Type A 4-ft. Diameter, Type 3 Frame & Grate 4 EA $8,160.00 $32,640.00 $5,010.00 $20,040.00 5,000.00$ $20,000.00 $5,393.75 $21,575.00

B038 Manholes, Type A 4-ft. Diameter, Type 3V Frame & Grate 1 EA $5,160.00 $5,160.00 $3,250.00 $3,250.00 4,263.00$ $4,263.00 $5,393.74 $5,393.74

B039 Manholes, Type A 5-ft. Diameter, Type 1 Frame & Lid 5 EA $19,700.00 $98,500.00 $7,855.00 $39,275.00 7,585.00$ $37,925.00 $7,564.48 $37,822.40

B040 Manholes, Type A 5-ft. Diameter, Type 3V Frame & Grate 1 EA $19,300.00 $19,300.00 $9,235.00 $9,235.00 9,300.00$ $9,300.00 $7,742.62 $7,742.62

B041 Manholes, Type A 6-ft. Diameter, Type 1 Frame & Lid 1 EA $24,800.00 $24,800.00 $9,965.00 $9,965.00 10,900.00$ $10,900.00 $8,482.14 $8,482.14

B042 Inlet, Type A, Type 3 Frame & Grate 1 EA $3,450.00 $3,450.00 $2,090.00 $2,090.00 8,144.00$ $8,144.00 $2,837.87 $2,837.87

B043 Inlet, Type A, Type 3V Frame & Grate 1 EA $3,720.00 $3,720.00 $2,765.00 $2,765.00 2,637.53$ $2,637.53 $3,045.10 $3,045.10 B044 Concrete Channel, 8-ft Wide 432 LF $217.00 $93,744.00 $121.15 $52,336.80 94.00$ $40,608.00 $103.92 $44,893.44 B045 Concrete Curb, 6-inch 3880 LF $41.50 $161,020.00 $16.60 $64,408.00 70.00$ $271,600.00 $52.81 $204,902.80

B046 Relocate Chain Link Gate, 6'x18', Double 1 EA $4,970.00 $4,970.00 $3,938.00 $3,938.00 4,700.00$ $4,700.00 $2,200.00 $2,200.00

B047 Paint Pavement Marking - Line 4" 10 LF $67.40 $674.00 $12.80 $128.00 13.80$ $138.00 $14.55 $145.50 B048 Paint Pavement Marking - Line 12" 245 LF $21.00 $5,145.00 $14.40 $3,528.00 16.10$ $3,944.50 $16.45 $4,030.25 B049 Paint Pavement Marking - Line 24" 40 LF $51.90 $2,076.00 $21.65 $866.00 24.15$ $966.00 $24.04 $961.60

B050 Site Restoration 1 JB $89,400.00 $89,400.00 $50,030.00 $50,030.00 88,759.00$ $88,759.00 $111,427.98 $111,427.98

B051 Orbon Place Detention Pond - Chain Link Fence, 6' 1302 LF $71.40 $92,962.80 $36.85 $47,978.70 44.00$ $57,288.00 $38.50 $50,127.00

B052 Orbon Place Detention Pond - Chain Link Gate, 6' x 18' Double 1 EA $8,490.00 $8,490.00 $4,000.00 $4,000.00 4,700.00$ $4,700.00 $2,200.00 $2,200.00

B053 Orbon Place Detention Pond - Flared End Section Grate 2 EA $2,470.00 $4,940.00 $2,000.00 $4,000.00 5,750.00$ $11,500.00 $1,832.26 $3,664.52

B054 Orbon Place Detention Pond - Earth Excavation 20985 CY $7.10 $148,993.50 $23.10 $484,753.50 9.18$ $192,642.30 $3.26 $68,411.10

B055 Orbon Place Detention Pond - Hauling Off Spoils 15739 CY $16.30 $256,545.70 $0.01 $157.39 11.22$ $176,591.58 $18.94 $298,096.66

BASE CONTRACT - EXHIBIT A (PHASE 2) TOTAL $2,573,617.15 $2,322,345.70 $3,127,287.84 $3,138,172.44

BASE SCHEDULE SUBTOTAL $5,566,547.34 $5,615,931.68 $6,004,528.72 $6,334,358.50

C001 Mobilization and Demobilization Phase 3 1 JB $260,800.00 $260,800.00 $540,000.00 $540,000.00 482,000.00$ 482,000.00$ $255,215.68 $255,215.68

C002 Temporary Traffic Control 1 JB $17,900.00 $17,900.00 $75,892.00 $75,892.00 30,000.00$ 30,000.00$ $89,148.16 $89,148.16 C003 Erosion & Sedimentation Control 1 JB $32,900.00 $32,900.00 $31,440.00 $31,440.00 9,700.00$ 9,700.00$ $23,596.30 $23,596.30 C004 Temporary Erosion Control Blanket 112 SY $3.20 $358.40 $3.40 $380.80 8.40$ 940.80$ $4.34 $486.08 C005 Erosion Control Blanket 112 SY $6.20 $694.40 $3.40 $380.80 8.40$ 940.80$ $4.34 $486.08

C006 Temporary Erosion Control Seeding & Mulching 0.8 AC $3,800.00 $3,040.00 $17,161.50 $13,729.20 4,500.00$ 3,600.00$ $0.01 $0.01

C007 Permanent Seeding & Mulching 1 AC $11,600.00 $11,600.00 $28,385.20 $28,385.20 5,500.00$ 5,500.00$ $25,399.27 $25,399.27 C008 Tree Removal (Acre) 1.7 AC $7,060.00 $12,002.00 $0.01 $0.02 19,650.00$ 33,405.00$ $19,492.66 $33,137.52 C009 Curb Removal 3994 LF $14.60 $58,312.40 $12.70 $50,723.80 10.00$ 39,940.00$ $13.15 $52,521.10 C010 Pavement Removal, Concrete 2072 SY $54.30 $112,509.60 $26.70 $55,322.40 21.00$ 43,512.00$ $26.31 $54,514.32 C011 Pavement Removal, Bituminous 2503 SY $16.70 $41,800.10 $17.30 $43,301.90 18.00$ 45,054.00$ $16.76 $41,950.28

C012 Driveway Pavement Removal, Concrete 10 SY $142.00 $1,420.00 $196.20 $1,962.00 100.00$ 1,000.00$ $35.17 $351.70

C013 Driveway Pavement Removal, Bituminous 0 SY $86.80 $0.00 $500.00 $0.00 -$ $1,000.00 $0.00

C014 Sidewalk Removal 9370 SF $3.80 $35,606.00 $0.95 $8,901.50 3.10$ 29,047.00$ $3.38 $31,670.60

C015 Lebanon Avenue Pavement Removal 390 SY $44.50 $17,355.00 $38.75 $15,112.50 30.00$ 11,700.00$ $33.02 $12,877.80

C016 Sanitary Sewer Abandonment or Removal, 10" to 15" 50 LF $83.00 $4,150.00 $515.00 $25,750.00 200.00$ 10,000.00$ $484.02 $24,201.00

C017 Manhole/Inlet Removal 72 EA $812.00 $58,464.00 $608.60 $43,819.20 1,150.00$ 82,800.00$ $539.90 $38,872.80 C018 Earth Excavation 14845 CY $7.10 $105,399.50 $0.01 $148.45 1.00$ 14,845.00$ $0.01 $148.45

C019 Aggregate Base Course, Type A 6-inch 13245 SY $8.40 $111,258.00 $9.35 $123,840.75 14.35$ 190,065.75$ $15.15 $200,661.75

C020 Aggregate Surface Course, Type B 6-inch 50 SY $46.20 $2,310.00 $52.60 $2,630.00 18.00$ 900.00$ $23.77 $1,188.50

C021 Asphalt Roadway Pavement, 6-inch 2503 SY $64.10 $160,442.30 $65.80 $164,697.40 103.00$ 257,809.00$ $86.09 $215,483.27 C022 Asphalt Driveway Replacement 0 SY $126.00 $0.00 $1,350.00 $0.00 -$ $1,000.00 $0.00

C023 Concrete Roadway Pavement, 7-inch 2072 SY $53.50 $110,852.00 $102.25 $211,862.00 98.00$ 203,056.00$ $108.67 $225,164.24 C024 Concrete Driveway Pavement 10 SY $214.00 $2,140.00 $237.10 $2,371.00 320.00$ 3,200.00$ $125.42 $1,254.20

C025 Portland Cement Concrete Sidewalk, 4-inch 9370 SF $9.70 $90,889.00 $10.19 $95,480.30 12.00$ 112,440.00$ $17.92 $167,910.40

C026 Lebanon Avenue Pavement Patch 390 SY $53.40 $20,826.00 $157.80 $61,542.00 315.00$ 122,850.00$ $185.89 $72,497.10 C027 Detectable Warnings 880 SF $62.80 $55,264.00 $67.65 $59,532.00 35.00$ 30,800.00$ $37.63 $33,114.40 C028 12" Storm Sewer, Class B 23 LF $73.70 $1,695.10 $97.20 $2,235.60 165.00$ 3,795.00$ $145.63 $3,349.49 C029 15" Storm Sewer, Class B 1605 LF $77.50 $124,387.50 $128.35 $206,001.75 184.00$ 295,320.00$ $147.17 $236,207.85

OPTIONS SCHEDULE - EXHIBIT C (PHASE 3)

C030 18" Storm Sewer, Class A 155 LF $106.00 $16,430.00 $151.95 $23,552.25 355.00$ 55,025.00$ $182.07 $28,220.85 C031 18" Storm Sewer, Class B 2452 LF $84.00 $205,968.00 $124.65 $305,641.80 200.00$ 490,400.00$ $127.77 $313,292.04 C032 24" Storm Sewer, Class B 2446 LF $87.00 $212,802.00 $142.15 $347,698.90 186.00$ 454,956.00$ $163.20 $399,187.20 C033 30" Storm Sewer, Class B 362 LF $125.00 $45,250.00 $184.55 $66,807.10 274.00$ 99,188.00$ $205.55 $74,409.10 C034 36" Storm Sewer, Class B 818 LF $153.00 $125,154.00 $197.95 $161,923.10 346.00$ 283,028.00$ $288.53 $236,017.54 C035 42" Storm Sewer, Class B 681 LF $187.00 $127,347.00 $348.65 $237,430.65 400.00$ 272,400.00$ $468.87 $319,300.47 C036 48" Storm Sewer, Class B 318 LF $211.00 $67,098.00 $309.35 $98,373.30 400.00$ 127,200.00$ $398.07 $126,586.26 C037 12" PVC Sanitary Sewer, SDR-26 46 LF $80.10 $3,684.60 $249.40 $11,472.40 268.00$ 12,328.00$ $285.39 $13,127.94 C038 18" PVC Sanitary Sewer, SDR-26 839 LF $120.00 $100,680.00 $376.65 $316,009.35 280.00$ 234,920.00$ $341.76 $286,736.64

C039 Connection of Existing Pipe to Structure 7 EA $1,700.00 $11,900.00 $2,984.35 $20,890.45 2,200.00$ 15,400.00$ $4,166.67 $29,166.69

C040 Reconnect Sanitary Sewer Lateral 19 EA $452.00 $8,588.00 $3,686.65 $70,046.35 2,200.00$ 41,800.00$ $10,080.63 $191,531.97 C041 24" FES 1 EA $1,120.00 $1,120.00 $3,028.75 $3,028.75 2,775.00$ 2,775.00$ $3,175.10 $3,175.10 C042 48" FES 1 EA $3,330.00 $3,330.00 $6,334.85 $6,334.85 4,375.00$ 4,375.00$ $5,373.09 $5,373.09 C043 Curb Inlet, Set Back 20 EA $3,940.00 $78,800.00 $6,087.45 $121,749.00 5,275.00$ 105,500.00$ $5,578.36 $111,567.20 C044 Double Curb Inlet, Set Back 2 EA $7,890.00 $15,780.00 $9,885.55 $19,771.10 8,450.00$ 16,900.00$ $8,473.19 $16,946.38

C045 Concrete Junction Box, 72x72, Type 1 Frame & Grate 2 EA $11,100.00 $22,200.00 $16,447.00 $32,894.00 16,775.00$ 33,550.00$ $16,298.67 $32,597.34

C046 Manholes, Type A 4-ft. Diameter, Type 1 Frame & Lid 13 EA $9,900.00 $128,700.00 $7,098.00 $92,274.00 6,360.00$ 82,680.00$ $5,377.00 $69,901.00

C047 Manholes, Type A 4-ft. Diameter, Type 3 Frame & Grate 21 EA $8,000.00 $168,000.00 $5,336.00 $112,056.00 6,100.00$ 128,100.00$ $5,560.49 $116,770.29

C048 Manholes, Type A 4-ft. Diameter, Type 3V Frame & Grate 17 EA $8,080.00 $137,360.00 $4,544.00 $77,248.00 5,780.00$ 98,260.00$ $5,560.49 $94,528.33

C049 Manholes, Type A 4-ft. Diameter, Type 4 Frame & Grate 2 EA $5,070.00 $10,140.00 $4,931.00 $9,862.00 4,600.00$ 9,200.00$ $5,762.32 $11,524.64

C050 Manholes, Type A 5-ft. Diameter, Type 3 Frame & Grate 2 EA $9,960.00 $19,920.00 $6,372.00 $12,744.00 7,200.00$ 14,400.00$ $7,982.11 $15,964.22

C051 Manholes, Type A 5-ft. Diameter, Type 3V Frame & Grate 1 EA $7,580.00 $7,580.00 $6,372.00 $6,372.00 7,700.00$ 7,700.00$ $7,982.12 $7,982.12

C052 Manholes, Type A 6-ft. Diameter, Type 1 Frame & Lid 2 EA $23,300.00 $46,600.00 $10,251.00 $20,502.00 10,500.00$ 21,000.00$ $8,743.69 $17,487.38

C053 Manholes, Type A 6-ft. Diameter, Type 3 Frame & Grate 2 EA $22,500.00 $45,000.00 $9,050.00 $18,100.00 10,600.00$ 21,200.00$ $8,927.17 $17,854.34

C054 Manholes, Type A 7-ft. Diameter, Type 1 Frame & Grate 1 EA $28,700.00 $28,700.00 $16,902.00 $16,902.00 16,000.00$ 16,000.00$ $16,601.48 $16,601.48

C055 Inlet, Type A, Type 3 Frame & Grate 6 EA $3,450.00 $20,700.00 $1,780.00 $10,680.00 3,900.00$ 23,400.00$ $2,940.34 $17,642.04

C056 Inlet, Type A, Type 3V Frame & Grate 6 EA $3,720.00 $22,320.00 $1,778.00 $10,668.00 3,600.00$ 21,600.00$ $3,154.14 $18,924.84

C057 Inlet, Type A, Type 4 Frame & Grate 1 EA $3,450.00 $3,450.00 $2,322.00 $2,322.00 4,250.00$ 4,250.00$ $3,142.20 $3,142.20

C058 Inlet, Type B, Type 3 Frame & Grate 2 EA $4,750.00 $9,500.00 $2,581.00 $5,162.00 4,575.00$ 9,150.00$ $3,466.33 $6,932.66

C059 Inlet, Type B, Type 3V Frame & Grate 5 EA $5,030.00 $25,150.00 $2,636.00 $13,180.00 5,000.00$ 25,000.00$ $3,680.13 $18,400.65 C060 Concrete Curb, 6-inch 3994 LF $41.50 $165,751.00 $64.20 $256,414.80 78.50$ 313,529.00$ $36.62 $146,260.28 C061 Paint Pavement Marking - Line 4" 30 LF $67.40 $2,022.00 $17.50 $525.00 13.80$ 414.00$ $19.92 $597.60 C062 Paint Pavement Marking - Line 12" 315 LF $29.60 $9,324.00 $26.10 $8,221.50 16.10$ 5,071.50$ $29.73 $9,364.95 C063 Paint Pavement Marking - Line 24" 60 LF $102.00 $6,120.00 $30.55 $1,833.00 24.15$ 1,449.00$ $34.79 $2,087.40 C064 Site Restoration 1 JB $112,900.00 $112,900.00 $108,500.00 $108,500.00 89,800.00$ 89,800.00$ $80,686.95 $80,686.95

OPTIONS SCHEDULE SUBTOTAL $3,469,743.90 $4,492,632.22 $5,206,168.85 $4,701,297.53

$9,036,291.24 $10,108,563.89 $11,210,697.57 $11,035,656.03TOTAL BASE SCHEDULE AND OPTIONS SCHEDULE