AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to add the Questions & Answ ers, remove language pertaining to RMS, add the Financial Form and add the Additional Location Maps for the task order. The response date remains 19 September 2022 at 10 AM CST. There are no other changes. All other conditions remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 11

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P922B0031

X 9B. DATED (SEE ITEM 11)

21-Aug-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0002

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

12-Sep-2022

CODE

CONTRACTING DIVISION

US ARMY ENGR DIST ST LOUIS

1222 SPRUCE STREET, RM 4.207

ST LOUIS MO 63103-2833

W912P9 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P922B0031

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

QUESTIONS AND ANSWERS

Lake Shelbyville Shoreline Protection W912P922B0031 Solicitation Questions and Answers

Question 1: Do you anticipate two mobilizations and demobilizations per year or one mobilization and one demobilization equaling the quantity of 2?

Answer: The project office is anticipating 1 mobilization/demobilization per ordering period and will try to maximize the work to be completed while the contractor is onsite.

Question 2: Can mobilization be set as a non pre priced item to allow the negotiation of mobilization each year?

Answer: The mobilization/demobilization line item is priced as "each" item. The line item reflects the contractors cost to mobilize to the lake project and establish sites to conduct work at any or all of the three defined locations per task order. The three areas identified should allow the contract the ability to reach any area of the lake to complete work. If the contractor chooses to operate out of only one location and transport the material by boat to areas farther away, they can choose to as part of their execution plan, but no additional time will be given to the schedule or period of performance for not moving operations to another approved mobilization site. As listed in the contract specification the contractor can also propose to use an alternative site for operation pending the Contracting Officers approval. Reference Section 01 22 00 Measurement and Payment, Par 1.1.

Question 3: With two different bid schedules being submitted — Contract Bidding Schedule, Task Order Bid Schedule — what is the basis of selection? Does the awardee need to be low on both schedules?

Answer: The contractor should bid the base contract line items for each ordering period. Additionally, the task order will use the same contract pricing for ordering period 1, for each job on the task order, except for the jobs that use the alternative stone structure line item. Those “jobs” are reviewed as individual proposals and evaluated by the government.

Question 4: During the winter will park roads be open and maintained ( e.g. snow removal) for contractor’s access to the work areas?

Answer: The park access roads remain open year-round to the public unless there is a safety hazard or flooding on the roadways. Basic snow removal from the roadways, accomplished by truck and plow during regular business hours. This does not include salt or spreading of sand.

Question 5: During the period of performance will there be work by others at the boat ramps that contractor will need to schedule around?

Answer: There is no other work scheduled to be accomplished at the identified highwater boat ramp mobilization/demobilization sites listed in the contract specs and drawings. Once the contractor has mobilized to that site it will be considered their jobsite and will be their responsibility until work is complete. The regular boat ramps will be operational for the public year-round.

Question 6: At the site walk it was stated that contractors could request alternate staging or access points to the work areas subject to KO approval. What is the approval criteria that the Gov’t will be looking at to approval an alternate staging area?

Answer: Correct, as listed in the contract under the mobilization/demobilization site specifications, an alternative site can be proposed and accepted, pending the Contracting Officers approval. The three sites that are preselected are the Opossum Creek high water ramp, Bo Wood high water ramp, and Wilborn Creek high water ramp. These locations were chosen to control haul route access roads to highway and county roads to minimize roadway damage and allow access to each section of the lake with relationship to the potential work sites identified in the drawings and are cleared of any cultural or environmental concerns. Any alternative site proposed should meet or exceed what the preselected sites currently offer. No sites can be located on a cultural sites, environmentally sensitive area, or state park managed area. Reference Sec 02 01 00 Performance Work Requirement, Par 2.

Question 7: Task Order Bid Schedule — CLIN 002. How will pricing be evaluated between bidders if there are different assumptions made on the quantity of tons required per subitem (i.e. Lineal Feet —> Volume —> Tons)

Answer: CLIN 002 “Breakwater Structure” will be evaluated on pricing for tons placed at the identified location listed on the task orders as a “Job”. Each Job on a task order may have a single site or multiple sites. The shape of the breakwater structure listed in the drawings is representative of the amount of stone needed to create that profile and will only vary a little. There is a tolerance +/- for height and width listed in the specification. All other assumptions for the contractor’s approach and execution cost should be represented in the type, amount, size of equipment and execution strategy to meet the period of performance and satisfactory level of quality.

Question 8: Task Order Bid Schedule. How will CLIN 002 be awarded? Unit Price or Job Price?

Answer: CLIN 002 “Breakwater Structure” will be awarded based on unit price of Tons placed. The “Job” represents a group of locations that will equal a total amount of tonnage to complete the work listed.

Question 9: Are the forms for the Equipment List, Financial, & Subcontractor Agreements available or do we make up the form ourselves? What information should be included?

Answer: The contractor will submit the information requested along with the contract bid schedule and the task order bid schedule. There is no special format or document to be submitted pertaining to the Equipment List and the Subcontractor Agreements. The Financial Form is attached to be completed and submitted with your bid.

End of Questions & Answers

The following have been modified:

TASK ORDER BID SCHEDULE & SOW

REVISED TASK ORDER BID SCHEDULE

Lake Shelbyville Shoreline Protection Contract Task Order TBD

Item Unit No. Description Quantity Unit Price Amount

ORDERING PERIOD 1

0001. Mobilization and Demobilization 1 EA _ _____

0002. Breakwater Structures Job 1 TN _ ____ 0002. Breakwater Structures Jobs 2-4(Optional) TN _

0003. Alt. Stone Structure Job 5 TBD Job TBD TBD 0003. Alt. Stone Structure Job 5-9(Optional)TBD Job TBD TBD

Job 1 Shoreline protection work shall be completed at multiple location identified in the “Job 1 Location and Detail Table” and as shown in the drawings. Items 2-17 will be installed in accordance with the drawings and specifications.

Mobilization and Demobilization will be issued once for this Order to mobilize and demobilize the contractor to the Lake Shelbyville Project Office to complete all awarded work. No additional mobilization and demobilization will be used to move the contractor to additional sites within the lake project property boundaries.

Job 1 Location and Detail Table

Job 1 Cost:

Job 2 (Optional) Shoreline protection work shall be completed at multiple location identified in the “Job 2 Location and Detail Table” and as shown in the drawings. Items

Item Line Item Type Location UOM Quantity Item Cost

1 Mob and Demob See Specification for

Sites EA 1

Item Line Item Type Location Linear Feet Tons Item Cost 2 Breakwater Structure Dam East A 1000 3 Breakwater Structure Dam East B 200 4 Breakwater Structure Dam West High Water 700 5 Breakwater Structure Lithia A-Leg 1000 6 Breakwater Structure Lithia D-Leg 1000 7 Breakwater Structure Country Club Cove 200 8 Breakwater Structure Opossum Creek South 1A 1000 9 Breakwater Structure Opossum Creek South 1B 200 10 Breakwater Structure Coon Creek A-Leg 1 600 11 Breakwater Structure Coon Creek A-Leg 2 1000 12 Breakwater Structure Coon Creek D-Leg 500 13 Breakwater Structure Coon Creek E-Leg 350 14 Breakwater Structure Lone Point 1 600 15 Breakwater Structure Lone Point 2 500 16 Breakwater Structure Wolf Creek Cemetery North 400 17 Breakwater Structure Wolf Creek Cemetery South 150

18-33 will be installed in accordance with the drawings and specifications.

Job 2 Location and Detail Table

Job 2 Cost:________ Job 3 (Optional) Shoreline protection work shall be completed at multiple location identified in the “Job 3 Location and Detail Table” and as shown in the drawings. Items 34-46 will be installed in accordance with the drawings and specifications.

Job 3 Location and Detail Table

Job 3 Cost:________ Job 4 (Optional) Shoreline protection work shall be completed at multiple location identified in the “Job 4 Location and Detail Table” and as shown in the drawings. Items 47-57 will be installed in accordance with the drawings and specifications.

Job 4 Location and Detail Table

Item Line Item Type Location Linear Feet Tons Item Cost 18 Breakwater Structure Coalshaft North 1 1000 19 Breakwater Structure Coalshaft North 2 1000 20 Breakwater Structure Coalshaft North 3 200 21 Breakwater Structure Liberty Point Prairie 1A 1000 21 Breakwater Structure Liberty Point Prairie 1B 400 23 Breakwater Structure Area F 1A 1000 24 Breakwater Structure Area F 1A 200 25 Breakwater Structure Camp Camfield 1 600 26 Breakwater Structure Camp Camfield 1B 1000 27 Breakwater Structure Camp Camfield 2A 1000 28 Breakwater Structure Camp Camfield 2B 1000 29 Breakwater Structure Camp Camfield 2C 700 30 Breakwater Structure Bo Wood 1A 1000 31 Breakwater Structure Bo Wood 1B 500 32 Breakwater Structure Bo Wood Area 5A 1000 33 Breakwater Structure Bo Wood Area 5B 300

Item Line Item Type Location Linear Feet Tons Cost 34 Breakwater Structure West Slaughter House A 1000 35 Breakwater Structure West Slaughter House B 1000 36 Breakwater Structure West Slaughter House C 400 37 Breakwater Structure Fin and Feather 1A 1000 38 Breakwater Structure Fin and Feather 1B 200 39 Breakwater Structure Fin and Feather 2 640 40 Breakwater Structure Sullivan Marina 1 750 41 Breakwater Structure Sullivan Marina 2A 1000 42 Breakwater Structure Sullivan Marina 2B 200 43 Breakwater Structure Okaw Bluff 1A 1000 44 Breakwater Structure Okaw Bluff 1B 1000 45 Breakwater Structure Okaw Bluff 1C 1000 46 Breakwater Structure Okaw Bluff 1D 500

Job 4 Cost:________

Jobs 5-9 Shoreline protection using the “Alternate Stone Structure” Line Item shall be completed at multiple locations. Locations are found in the contract drawings. Jobs 5-9 will be installed in accordance with the drawings and specifications and will be bid as “Job”

Additional Details for Alternate Stone Structures

Job 5 Dam West Boat Ramp 1. The breakwater structure rock profile for this segment will be placed in a manor to allow for both shoreline protection and foot traffic along approximately 325 linear feet of shoreline. RR4 stone shall be placed on top of any existing stone at this location and match the contour of the existing shoreline. The elevation of protection shall start at a bottom elevation of 596 to a top elevation of 601.5. The top of this structure will be a level 5’ wide path. All stone used for this structure will be RR4. Geotextile shall be placed on the lower 15’and under the 5’ wide walkway path and tapered under to lake side slope. See drawings and map for additional information. Job 5 will be bid as a “Job”.

Job 5 Cost:________

Job 6 (Optional) Lithia Springs Beach Breakwater. There is currently a

300’ long curved breakwater structure located on the North side of the Lithia Springs Beach. The current breakwater structure is composed of RR4 and RR5 stone. This work will involve raising the height of the existing breakwater structure to a top elevation of 605 and will utilize RR5 stone. The current breakwater height ranges between 600.9 and 601.5 with an average of 601.17.

These elevations are approximate and are for reference only, it will be the contractor’s responsibility to verify current elevation. The final profile of the structure shall be the “standard offshore breakwater profile”. No geotextile will be applied to this structure. Job 6 will be bid as a “Job”.

Job 6 Cost:________

Job 7 (Optional) Lone Point Hill Prairie. There is currently 325 linear feet of RR4 stone placed at this location. Work at this location will include raising the top of the existing breakwater structure from 601.5 to an elevation of 603. RR4 stone will be used for this work. All stone will be

Item Line Item Type Location Linear Feet

Tons

Cost 47 Breakwater Structure Refuge Point 1800 48 Breakwater Structure Bruce Findlay Bridge East 700 49 Breakwater Structure Wilborn Creek South 3500 50 Breakwater Structure Wilborn Creek 1 450 51 Breakwater Structure Wilborn Creek Shelf 2 1000 52 Breakwater Structure Wilborn Creek Shelf 3 1000 53 Breakwater Structure Wilborn Creek Shelf 4 100 54 Breakwater Structure Wilborn Creek South 1 1000 55 Breakwater Structure Wilborn Creek South 2 1000 56 Breakwater Structure Wilborn Creek South 3 1000 57 Breakwater Structure Wilborn Creek South 4 500 placed on the inside or land side, and be at least 4 feet in width, matching the profile of the current breakwater structure until the new elevation is met. No geotextile will be applied to this structure. Job 7 will be bid as a “Job”.

Job 7 Cost:________

Job 8 (Optional) Coalshaft South. The breakwater structure rock profile for this segment will be placed in a manor to allow for both shoreline protection and foot traffic along approximately 1000 linear feet of shoreline. RR4 stone shall be placed on top of any existing stone at this location and match the contour of the existing shoreline. The elevation of protection shall start at a bottom elevation of 596 to a top elevation of

601.5. The top of this structure will be a level 5’ wide path. All stone used for this structure will be RR4. Geotextile shall be placed on the lower 15’and under the 5’ wide walkway path and tapered under to lake side slope.

See drawings and map for additional information. Job 8 will be bid as a “Job”.

Job 8 Cost:________

Job 9 (Optional) Sullivan Beach Breakwater. There is currently a 400’ long breakwater structure located on the North side of the Sullivan Beach that extends from the shoreline into the water. The current breakwater structure is composed of RR4 and RR5 stone. This work will involve raising the height of the existing breakwater structure to a top elevation of 605 and will utilize RR5 stone. The estimated current elevation ranges from 601.3 to

603.2 with an average height of 602.5. These elevations are approximate and are for reference only, it will be the contractor’s responsibility to verify current elevation. The final profile of the structure shall match the existing breakwater profile. Stone will be placed on the West side of the existing structure to support the new elevation. No geotextile will be applied to this structure. Access by land to this site is available at the Sullivan Beach Recreation Area by means of a utility road on the West end of the South parking lot. Job 9 will be bid as a “Job”.

Job 9 Cost:________

Notes:

All Lake Pool Elevations listed are in National Geodetic Vertical Datum 29

(NGVA29)

SECTION 00 10 00 - SOLICITATION

The following have been deleted:

SCR-203-11

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been modified:

LOCAL CLAUSES

LOCAL CLAUSES:

52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (SEP 2021)

252.204-7007 ALTERNATE A, ANNUAL REPRESENTATION & CERTIFICATIONS (MAY 2021)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.

(2) The small business size standard is $36.5M.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

[X ] (i) Paragraph (e) applies.

[ ] (ii) Paragraph (e) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(iv) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(v) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation. This provision applies to solicitations using funds appropriated in fiscal years 2008, 2009, 2010, or 2012.

(vi) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(vii) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(viii) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(ix) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(x) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xi) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xii) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xiii) 52.222-38, Compliance with Veterans’ Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xiv) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA–designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xv) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA–designated items.

(xvi) 52.225-2, Buy American Act Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xvii) 52.225-4, Buy American Act—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $79,507, the provision with its Alternate II applies.

(D) If the acquisition value is $79,507 or more but is less than $100,000, the provision with its Alternate III applies.

(xviii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xix) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.

(xx) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications. This provision applies to all solicitations.

(xxi) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to—

(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and

(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.

(2) The following certifications are applicable as indicated by the Contracting Officer:

[Contracting Officer check as appropriate.] __ (i) 52.219-22, Small Disadvantaged Business Status.

__ (A) Basic.

__ (B) Alternate I.

__ (ii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

__ (iii) 52.222-48, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment Certification.

__ (iv) 52.222-52, Exemption from Application of the Service Contract Act to Contracts for Certain Services– Certification.

_x_ (v) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA– Designated Products (Alternate I only).

__ (vi) 52.227-6, Royalty Information.

__ (A) Basic.

__(B) Alternate I.

__ (vii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d)(1) The following representations or certifications in the System for Award Management (SAM) database are applicable to this solicitation as indicated:

(i) 252.209-7003, Reserve Officer Training Corps and Military Recruiting on Campus—Representation. Applies to all solicitations with institutions of higher education.

(ii) 252.216-7008, Economic Price Adjustment—Wage Rates or Material Prices Controlled by a Foreign Government. Applies to solicitations for fixed-price supply and service contracts when the contract is to be performed wholly or in part in a foreign country, and a foreign government controls wage rates or material prices and may during contract performance impose a mandatory change in wages or prices of materials.

(iii) 252.225-7042, Authorization to Perform. Applies to all solicitations when performance will be wholly or in part in a foreign country.

(iv) 252.225-7049, Prohibition on Acquisition of Certain Foreign Commercial Satellite Services— Representations. Applies to solicitations for the acquisition of commercial satellite services.

(v) 252.225-7050, Disclosure of Ownership or Control by the Government of a Country that is a State Sponsor of Terrorism. Applies to all solicitations expected to result in contracts of $150,000 or more.

(vi) 252.229-7012, Tax Exemptions (Italy)—Representation. Applies to solicitations and contracts when contract performance will be in Italy.

(vii) 252.229-7013, Tax Exemptions (Spain)—Representation. Applies to solicitations and contracts when contract performance will be in Spain.

(viii) 252.247-7022, Representation of Extent of Transportation by Sea. Applies to all solicitations except those for direct purchase of ocean transportation services or those with an anticipated value at or below the simplified acquisition threshold.

(2) The following representations or certifications in SAM are applicable to this solicitation as indicated by the Contracting Officer: [Contracting Officer check as appropriate.] ___ (i) 252.209-7002, Disclosure of Ownership or Control by a Foreign Government.

___ (ii) 252.225-7000, Buy American—Balance of Payments Program Certificate.

___ (iii) 252.225-7020, Trade Agreements Certificate.

___ Use with Alternate I.

_x__ (iv) 252.225-7031, Secondary Arab Boycott of Israel.

___ (v) 252.225-7035, Buy American—Free Trade Agreements—Balance of Payments Program Certificate.

___ Use with Alternate I.

___ Use with Alternate II.

___ Use with Alternate III.

___Use with Alternate IV.

___ Use with Alternate V.

(e) The offeror has completed the annual representations and certifications electronically via the SAM website at https://www.acquisition.gov/. After reviewing the SAM database information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in FAR 52.204-8(c) and paragraph (d) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer, and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by provision number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR/DFARS Provision # Title Date Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications located in the SAM database.

(End of provision)

SUSTAINABILITY

SUSTAINABILITY GUIDANCE:

Bio-Preferred Program:

The United States Department of Agriculture (USDA) designates certain biobased products for federal procurement and specifies minimum biobased content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA Bio Preferred’s minimum biobased content level. Visit the Bio Preferred web site (https://www.biopreferred/faces/pages/ProductCategories.xhtml) for the complete list of designated products and the associated mininimum biobased content level requirements.

EPA-Designated:

Under the Comprehensive Procuremnt Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials, and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit http://www.epa.gov/epawaste/conserv/tools/cpg/products for a complete list of designated products and the associated recommended content levels. Offererors must be able to demonstrate that eah offered product meets minimum content levels upon request.

(End of Summary of Changes)