US Army Corps of Engineers St. Louis District

LAKE SHELBYVILLE SHORELINE

PROTECTION CONTRACT

LAKE SHELBYVILLE

SHELBYVILLE, IL

PERFORMANCE WORK STATEMENT

AND SPECIFICATIONS

SOLICITATION NUMBER: W912P922B0031

JUNE 2022

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 00 10 BIDDING SCHEDULE

00 08 00 SPECIAL CONTRACT REQUIREMENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 30 ENVIRONMENTAL PROTECTION

01 13 20 PROJECT SCHEDULE

01 15 00 TEMPORARY CONSTRUCTION FACILITIES

01 22 00 MEASUREMENT AND PAYMENT

01 33 00 SUBMITTAL PROCEDURES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

DIVISION 02 – PERFORMANCE WORK REQUIREMENTS

02 01 00 PERFORMANCE WORK REQUIREMENTS

02 37 00 STONE SPECIFICATIONS

-- End of Project Table of Contents --

00 00 10-1

00 00 10 BIDDING SCHEDULE

Item Estimated Unit Estimated No. Description Quantity Unit Price Amount _

ORDERING PERIOD 1

0001. Mobilization and Demobilization 2 EA _

0002. Breakwater Structures 30,000 TN _

0003. Alt. Stone Structure TBD TBD TBD TBD

ORDERING PERIOD 2

1001. Mobilization and Demobilization 2 EA _

1002. Breakwater Structures 20,000 TN _

1003. Alt. Stone Structure TBD TBD TBD TBD

ORDERING PERIOD 3

2001. Mobilization and Demobilization 2 EA _

2002. Breakwater Structures 20,000 TN _

2003. Alt. Stone Structure TBD TBD TBD TBD

ORDERING PERIOD 4

3001. Mobilization and Demobilization 2 EA _

3002. Breakwater Structures 20,000 TN _

3003. Alt. Stone Structure TBD TBD TBD TBD

ORDERING PERIOD 5

4001. Mobilization and Demobilization 2 EA _

4002. Breakwater Structures 20,000 TN _

4003. Alt. Stone Structure TBD TBD TBD TBD

00 00 10-2

ORDER PERIOD 1 TOTAL

ORDER PERIOD 2 TOTAL

ORDER PERIOD 3 TOTAL

ORDER PERIOD 4 TOTAL

ORDER PERIOD 5 TOTAL

TOTAL $

(See BIDDING SCHEDULE NOTES)

00 00 10-3

BIDDING SCHEDULE NOTES

1. Legend for Unit of Measurement

EA = Each TN = Ton TBD = To Be Determined

2. All quantities shown on the BIDDING SCHEDULE are estimated quantities. All Estimated quantities are to be used for bid evaluations only. The government is not restricted to these quantities and quantities issued over the duration of the contract are subject only to the following parameters:

Minimum Order Per Task Order: $2,500.00

Cumulative Guaranteed Minimum (Overall Contract): $2,500.00

Cumulative Guaranteed Maximum (Overall Contract): $24,000,000.00

3. TBD items shall be defined and negotiated at the Task Order Level via supplemental specifications or statements of work issued via Request for Proposal.

4. When bids are solicited on a unit price basis, bidders shall insert in the spaces provided therefore in the SCHEDULE both the "unit price" and the "estimated amount" resulting from applying the said unit price to the estimated quantity shown. In event the bidder quotes only a total price ("estimated amount") in its bid and fails to quote the unit price, the Government will determine such unit price by dividing the total price quoted by the quantity of the item set out in the SCHEDULE. The bidder agrees that the unit price so determined shall be used for the purpose of bid evaluation, award and all payments to the Contractor including final payment.

5. All Prices are on a Firm Fixed Price Basis.

6. All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the bid and the extension will be corrected accordingly.

7. If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.

8. Bidders are required to bid on all items listed on the Bidding Schedule in addition to inserting a total quoted bid in the appropriate space provided with the exception of items marked as TBD, “To Be Determined”. Failure to do so will be considered good cause to disqualify the bid.

9. Information concerning Indefinite Quantity Contracts, as well as the issuance and limitation of deliver orders may be found in Section 0700, Contract Clauses.

SECTION 00 08 00 Page 1

SECTION 00 08 00

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 PAY REQUESTS

Billing Procedures. Payment will be made by EFT. The Contractor shall supply 2 copies of invoices for equipment, materials, and supplies within three working days of Government request. No additional payments will be made for incidental supplies, materials, and equipment furnished by the Contractor. The invoice shall include the line item number, item description, unit of measurement, unit price and total amount. The invoice shall include the contract number, contract name and invoice number. The Contractor shall provide with the invoice, daily reports, payroll documentation, certified weight and load certificates, and if requested, documentation showing the catalog sheets for materials or products furnished. Payment for placed stone will be verified by certified load tickets delivered from an approved Quarry and shall be submitted with invoices.

1.2 WORK AREAS

In accordance with the Contract Clause entitled, "Operations and Storage Areas", and subject to the approval of the Contracting Officer and the restrictions imposed by SECTION 01 11 30 - ENVIRONMENTAL PROTECTION, of the Technical Provisions, the Contractor will be allowed use of Government-controlled land within the construction limits shown on the drawings or as specified herein.

1.4 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS

a. Unless otherwise specified, shown on the drawings, or stated in writing by the Contracting Officer, the Contractor shall not move or disturb any public utilities or private improvements. Such removals, alterations, and/or relocations, where necessary, will be made by others. The locations shown on the drawings for underground utilities are approximate only. The exact locations of such utilities shall be determined by the Contractor in the field prior to commencing construction operations in their vicinity.

b. The attention of the Contractor is directed to the possibility that public utilities or private improvements may be encountered within the construction limits, some of which may be buried, and the existence of which is presently not known. Should any such utilities or improvements be encountered, the Contractor shall immediately notify the Contracting Officer so that a determination may be made as to whether they shall be removed, relocated, or altered. After such determination is made, the Contractor shall, if so directed by the Contracting Officer, remove, relocate, or alter them as required and an equitable adjustment will be made. In the event the Contracting Officer arranges for such removals, alterations, or relocations to be performed by others, the Contractor shall cooperate with such others during the latters' removal, alteration, or relocation operations.

SECTION 00 08 00 Page 2

c. Protection of Facilities and Underground Utilities. All known facilities and utilities shall be protected during the term of this Contract and any damages shall be the responsibility of the Contractor.

The Contractor shall contact the Julie “811” Call Line for location of all public utilities and contact the COR representative to locate Corps of Engineers owned secondary utilities prior to commencement of work.

Any damages to know utilities or facilities caused by the Contractor’s operations shall be repaired or replaced by the Contractor to the satisfaction of the Contracting Officer.

1.5 DAMAGE TO WORK.

The responsibility for damage to any part of the permanent work shall be as set forth in the Contract Clause entitled "Permits and Responsibilities."

However, if in the judgment of the Contracting Officer any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or job prices as fixed and established in the contract. If in the opinion of the Contracting Officer there are no contract unit or lump sum prices applicable to any part of such work, an equitable adjustment pursuant to the Contract Clause entitled, "Changes," of the contract will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment, and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

1.6 PARTIAL PAYMENT

At the discretion of the Contracting Officer, partial payment will be made for equipment or material delivered and stored on site or off site providing such storage is in accordance with the provisions of these specifications and the Contractor furnishes satisfactory evidence that title to such equipment has been acquired and that it will be utilized on the work covered by these specifications. Partial payment is defined as the invoice amount plus shipping costs. If the equipment or materials are stored off site, the Government shall have the right to inspect the equipment.

1.7 CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall include the signature and title of an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies.

Certification shall not be construed as relieving the Contractor from responsibility for furnishing satisfactory material if, after tests are

SECTION 00 08 00 Page 3 performed on selected samples, the material is found not to meet the specific requirements.

1.8 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1

The Safety and Health Requirements Manual EM 385-1-1 forms a part of these specifications. EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil/USACEPublications/Engineer-Manuals/.

Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation,

1.10 ACCIDENT INVESTIGATIONS AND REPORTING

Refer to EM 385-1-1, Paragraph 01.D. Accidents, involving contractor and/or subcontractor employees performing any work or related work on a USACE project, shall be investigated and reported immediately to the Contracting Officer or authorized Contracting Officer's representative. This reporting requirement applies to on-site or off-site accidents. Upon receipt of the initial accident report notification, the Contracting Officer shall issue additional guidance concerning continuing project operations which may include a "cease work" directive. If a cease work directive is issued, the Contractor will not be allowed to resume work related to the accident until all conditions of the "cease work" directive are met. After the initial notification, the Contractor shall ensure a formal investigation is conducted and reports are completed by the immediate supervisor of the employee(s) involved and reported to the Contracting Officer or an authorized representative within one working day after the accident occurs.

The accident Investigation report shall be made on ENG Form 3394.

1.11 ACCIDENT PREVENTION PROGRAM

Refer to Contract Clause FAR 52.236-13 entitled, "Accident Prevention".

Within 5 days after receipt of Notice to Proceed of the contract, and at least 7 days prior to the prework conference, the original and one copy of the Accident Prevention Program shall be submitted to the Contracting Officer for review. See EM 385-1-1 Appendix A (2020 Edition) and checklist included at the end of this section for guidance in creating the Accident Prevention Plan.

The program shall also include a copy of company policy statement of accident prevention and any other guidance statements normally provided new employees. Each company employee shall be required to sign the company policy statement of accident prevention to verify that all employees have been informed of the safety program, and such signed statements shall be maintained at the project site.

When marine plant and equipment are in use under this contract, the requirements of EM 385-1-1, Section 19 shall be met.

The Contractor shall not commence physical work at the site until the program has been reviewed and found acceptable by the Contracting Officer, or an authorized representative. The Contractor shall submit for approval the Activity Hazard Analysis for each phase of construction prior to the beginning of work in each phase. Also refer to Section 1 of EM 385-1-1.

The Contractor shall include a COVID 19 Plan as part of their APP and include an AHA addressing COVID.

http://www.publications.usace.army.mil/USACEPublications/Engineer-Manuals/

SECTION 00 08 00 Page 4

1.12 DAILY INSPECTIONS

The Contractor shall perform daily safety inspections, record them and email them to the Lake Project POC as part of the daily report. Reports of daily inspections shall be maintained at the job site. The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:

a. Phase(s) of construction underway during the inspection.

b. Locations of areas inspections were made.

c. Results of inspection, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.

1.13 ENVIRONMENTAL LITIGATION

a. If the performance of all or any part of the work is ordered by a court of competent jurisdiction to be suspended, delayed, or interrupted as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a Subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the Contract Clause entitled "Suspension of Work".

b. The term "environmental litigation", as used herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.

1.14 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled, "Default (Fixed-Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

b. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent

SECTION 00 08 00 Page 5 work on critical activities for 50 percent or more of the Contractor's scheduled workday. The delay must be beyond the control and without the fault or negligence of the Contractor. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous day), be calculated chronologically from the first to the last day of each month and be recorded as full days. The Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather workdays, and issue a time extension modification in accordance with the FAR Clause 52.249-10 entitled "Default (Fixed Price Construction)".

1.15 WATER LEVEL LIMITATIONS

The Contractor should be aware that lake level changes are possible from rain events, and high water may cause work delays and/or damage existing conditions. The Contractor is responsible for becoming familiar with expected lake level changes and should monitor lake forecasts and weather forecasts. It may become necessary to delay the Contractor's work due to flood control activities. If pool conditions or emergency operations warrant, the Government may direct the stoppage of work. For such occurrences, an equitable adjustment to the contract will be made in accordance with the Contract Clause entitled "Suspension of Work" as determined by the Contracting Officer. In the event of a significant rise or decrease in lake stages, the Contractor should do all they can to protect completed works and prevent damage. The Contracting Officer's Representative will determine the extent of the delay to the work due to these limitations, and the time fixed for completion of the contract will be extended for the period of the time delay.

1.15.1 For additional information about Lake Shelbyville water levels refer to https://www.mvs-wc.usace.army.mil/ or call (800) 432-1208.

1.16 SUBCONTRACTS

In accordance with the Contract Clause entitled "Subcontracts", the Contractor shall, within seven days after the award of any subcontract by the Contractor or a Subcontractor, deliver to the Contracting Officer an electronic copy of a completed Standard Form 1413 with the original signatures of both parties.

1.17 REQUIRED INSURANCE

a. As required by the Contract Clause entitled "Insurance-Work on a Government Installation", the Contractor shall within 15 days after receipt of Notice of Award and prior to the commencement of work, furnish to the Contracting Officer, a written statement of required insurance as evidence of the following minimum insurance:

(1) Workmen's Compensation. Amounts required by applicable jurisdictional statutes.

(2) Employer's Liability Insurance. $100,000

(3) Comprehensive General Liability Insurance.

https://www.mvs-wc.usace.army.mil/

SECTION 00 08 00 Page 6

Bodily Injury - $500,000 per occurrence

(4) Comprehensive Automobile Insurance.

Bodily Injury - $200,000 each person $500,000 each accident Property Damage - $ 20,000 each accident

b. Statements of required insurance shall be submitted to the following address:

U.S. Army Corps of Engineers Lake Shelbyville Project Office 1989 State Highway 16 Shelbyville, IL 62565

1.18 PROTECTION OF MATERIAL AND WORK

The Contractor shall at all times protect and preserve all materials, supplies, and equipment of every description (including property which may be Government-furnished or owned) and all work performed. All reasonable requests of the Contracting Officer to enclose or specially protect such property shall be complied with. If, as determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payments due to the Contractor.

1.19 CONTAMINATION OF WATER

In addition to the requirements set forth in SECTION 01 11 30, paragraph Protection of Water Resources, the Contractor shall take positive protective measures to prevent spillage of potential pollutant materials such as fuel, emulsion materials, chemicals etc., from storage containers or equipment, into lakes or tributary waters. Such positive protective measures may include, but are not limited to, the following:

(1) A berm enclosure of sufficient capacity to contain such materials.

(2) Security measures to prevent acts of vandalism which could result in spillage of such materials (fences, guards, etc.).

(3) Storage of such materials in an area where the terrain would preclude leakage into lake or tributary waters.

(4) Utilization of secure Government storage areas if the Contracting Officer indicates such space is available. No storage past immediate needs (2 days) without the consent of the Contracting Officer.

The Contractor shall submit its proposals for implementing the above provisions in accordance with SECTION 01 11 30, paragraph Environmental Protection Plan.

1.20 ORDER AND COORDINATION OF WORK

SECTION 00 08 00 Page 7

The Contractor may start and complete the work in such order and sequence as desired subject to compliance with the following paragraphs:

A. PERIOD OF PERFORMANCE.

(1) Period of Performance for installation of stone revetment shall be restricted to achieving required lake elevations to permit access via floating plant. Lake elevations are anticipated to be achieved between the months of May 1st through December 15th. The contractor shall mobilize to complete work outside this date range if elevations and conditions permit. Lake elevations may vary between elevations 596 NGVD and 599.7 NGVD during the performance period. Minor fluctuations may result from lake operational requirements during the contract period of performance. High pool levels do occur and may halt work for extended periods. A Chart of the Water Control Schedule is included in the drawings.

(2) Contractor shall have 30 Calendar Days from Notice to Proceed with mobilization work and establishment of the Floating Plant and establish the loading area in the designated areas during the performance period. Mobilization work may be completed within these days and shall be in accordance with schedule requirements specified herein.

(3) Construction and installation locations shall be identified in the issued task order.

(4) All work shall be completed by the date identified in the issued task order.

B. SPECIAL CONSIDERATIONS.

(1) Contractor shall be required to coordinate all activities and schedule with the Authorized Representative of the Contracting Officer.

(2) Underwater construction will require floating plant.

Floating Plant shall be required to be trucked or hauled to the site and launched onsite.

(3) Floating Plant shall be required to be transported to the lake via roadway and launched and assembled onsite. The Contractor may utilize the designated mobilization high water boat launch ramps at Opossum Creek, Bo Wood, or Wilborn Creek Recreation Areas for launching of the floating plant. All equipment to be loaded on floating plant shall be loaded from the mobilization sites as indicated in the drawings. Tracked equipment shall only be permitted inside the designated construction zone and not be permitted over or on the Boat Ramp parking lot and paved access roads to minimize damage. The contractor shall take all necessary precautions if utilizing the boat ramp and roads to ensure that ramp and road surfaces are not damaged. At the highwater ramp, the contractor shall

SECTION 00 08 00 Page 8 utilize crane mats to preserve the end of the highwater ramp from cracking or damage from unloading stone. Damages that result to government property shall be repaired as specified by the Contracting Officer at no additional cost to the government. During launching and removal of floating plant the designated mobilization sites shall be closed to the public.

The contractor shall submit a schedule identifying durations associated with launching and setup of plant.

(4) Zebra Mussels. Zebra mussels have infested many bodies of water in the United States and can be unknowingly transported by vessels (barges, boats, tugs, etc.), boat trailers, and other equipment that is used in zebra mussel areas. To assist in the prevention of introduction and spread of this aquatic nuisance species in Illinois streams and lakes, the contractor shall follow all precautions as described in SECTION 02 01 00

(5) The Contractor should be aware that work will be highly dependent on lake elevations. The Contractor shall monitor daily lake levels and forecasts so that work schedules can be adjusted accordingly. The Contractor shall maintain close communication with the Government to identify an acceptable window for initiation of work associated with floating plant.

This information will be discussed in detail prior to construction. The Contractor shall not be allowed to begin work associated with floating plant until lake elevations and forecasts are indicating a prolonged condition favorable to utilizing floating plant for placement of stone over the protection site.

(6) To permit installation of stone via floating plant, lake elevations are anticipated to range between 594 to 626 NGVD.

The performance schedule for accomplishing work shall be dependent on capability to achieve required elevations to permit access via floating plant to the island. The contractor may submit request to the Contracting Officer for approval to work outside the lake elevation range of 596 to 615 NGVD if equipment is capable. Approval for working outside these limits shall be based on the Contracting Officer approval and review of effects on items of work. Within 30 calendar days from issuance and award of the task order, the contractor shall submit a schedule identifying sequence of work, durations, and minimum lake elevations required and associated durations in which each lake elevation will need to be maintained in order to accomplish work.

(7) At all times when Contractor’s floating plant is moored or tied off on the lake, the Contractor shall be completely responsible for monitoring and adjusting tie off lines and anchors. The Contractor shall develop a floating plant plan to enable 24 hours a day, 7 days a week monitoring of floating plant. At least 14 days prior to mobilization, the Contractor’s plan shall be submitted to the Contracting Officer for approval.

SECTION 00 08 00 Page 9

(8) During hauling operations, the haul roads and adjacent facilities to the mobilizations site shall remain open to the public for recreational usage. The contractor shall be required to provide traffic control signage in accordance with Manual of Uniform Traffic Control Devices and provide signal personnel during hauling operations near utilized mobilization sites to ensure safety of the public. The Contractor shall maintain the road surface in a condition to permit safe passage for conventional motor vehicles and trailers.

1.21 SUBMITTALS

Additional submittals for this contract that are not listed within individual technical provisions are listed below. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section

01 33 00 - SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Accident Prevention Program; G Statements of Required Insurance; G Waterway Construction Safety Plan; G Floating Plant Plan; G

SD-06 Test Reports

Ledge Testing; G

1.22 MEANS OF ESCAPE FOR PERSONNEL QUARTERED OR WORKING ON FLOATING PLANT

Two means of escape shall be provided for assembly, sleeping, and messing areas on floating plants. For areas involving 10 or more persons, both means of egress shall be through standard size doors opening to different exit routes. Where 9 or fewer persons are involved, one of the means of escape may be a window (minimum dimensions 24-inch by 36-inch) which leads to a different exit route. Refer to Section 19 of EM 385-1-1.

1.23 EMERGENCY ALARMS AND SIGNALS

a. Alarms. Emergency alarms shall be installed and maintained on all floating plant requiring a crew where it is possible for either a passenger or crewman to be out of sight or hearing from any other person. The alarm system shall be operated from the primary electrical system with standby batteries on trickle charge that will automatically furnish the required energy during an electrical-system failure. A sufficient number of signaling devices shall be placed on each deck so that the sound can be heard distinctly at any point above the usual background noise. All signaling devices shall be so interconnected that actuation can occur from at least one strategic point on each deck.

b. Signals.

SECTION 00 08 00 Page 10

(1) Fire Alarm Signals. The general fire alarm signal shall be in accordance with para 97.13-15b of the Coast Guard Rules and Regulations for Cargo and Miscellaneous Vessels, Subchapter I, 1 Sep 77 (CG 257).

(2) Abandon Ship Signals. The signal for abandon ship shall be in accordance with paragraph 97.13-15c of reference cited in (1) above.

(3) Man-Overboard Signal. Hail and pass the word to the bridge.

All personnel and vessels capable of rendering assistance shall respond.

c. Mooring Lines. Eye loops on mooring lines will be equipped with beckets or handling ropes to protect the hands of deckhands.

1.24 USE OF MECHANIZED EQUIPMENT ON FLOATING PLANT

When mechanized equipment is operated on floating plant the Contractor shall provide positive and acceptable means of preventing this equipment from moving or falling into the water. The type of equipment addressed by this clause includes front-end loaders, bulldozers, trucks (both on- and off-road), backhoes, track hoes, and similar equipment. If the Contractor plans to use such equipment on floating plant, an Activity Hazardous Analysis must be developed for this feature of work. The plan must include a detailed explanation of the type or types of physical barriers, curbs, structures, etc., which will be incorporated to protect the operator and prevent the equipment from entering the water. Nonstructural warning devices may be considered for situations where the use of structural barriers is determined to be impracticable. The Activity Hazard Analysis must thoroughly address the procedure and shall be submitted to the Contracting Officer for review and acceptance prior to start of this feature of work.

1.25 OBSTRUCTION OF NAVIGABLE WATERWAYS (DEC 1991) DFARS 252.236-7002

a. The Contractor shall--

(1) Promptly recover and remove any material, plant, machinery, or appliance which the contractor loses, dumps, throws overboard, sinks, or misplaces, and which, in the opinion of the Contracting Officer, may be dangerous to or obstruct navigation;

(2) Give immediate notice, with description and locations of any such obstructions, to the Contracting Officer, and

(3) When required by the Contracting Officer, mark or buoy such obstructions until the same are removed.

b. The Contracting Officer may--

(1) Remove the obstructions by contract or otherwise should the Contractor refuse, neglect, or delay compliance with paragraph (a) of this clause; and

(2) Deduct the cost of removal from any monies due or to become due to the Contractor, or

SECTION 00 08 00 Page 11

(3) Recover the cost of removal under the Contractor's bond.

c. The Contractor's liability for the removal of a vessel wrecked or sunk without fault or negligence is limited to that provided in Sections 15, 19, and 20 of the River and Harbor Act of March 3, 1899 (33 U.S.C. 410 et.seq.).

1.26 SIGNAL LIGHTS

The Contractor shall display signal lights and conduct its operations in accordance with the General Regulations of the Department of the Army, Illinois Department of Transportation, and of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules: International-Inland (Comdtinst M16672.2) or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable.

1.27 WATERWAY CONSTRUCTION SAFETY PLAN

Waterway Construction Safety. The contractor shall provide for installation of buoys, signage, warning lights or systems around floating plant loading and placement construction zones to provide awareness, direction, and warnings of floating plant construction operations to protect and ensure safety for other navigational and waterway activities involving the public.

Systems shall be in accordance with and approved by the Missouri State Highway Patrol. The contractor shall be responsible for obtaining all required permits for waterway warning systems from the Missouri State Highway Patrol. Copies of any required permits shall be provided to the government for record. The contractor shall submit a waterway construction safety plan for government approval indicating systems to be utilized and locations to be placed during daylight operations and at night to protect and warn the public of waterway hazards and construction zones. Plan shall address nighttime staging locations and warning systems.

1.29 STONE SOURCES

a. On the basis of information and data available to the Contracting Officer, stone meeting the quality requirements of these specifications has been produced from the sources listed at the end of these Special Clauses.

b. Stone may be furnished from any of the currently listed sources or, at the option of the Contractor, may be furnished from any other source designated by the Contractor and accepted by the Contracting Officer, subject to the conditions hereinafter stated.

c. It is the Contractor's responsibility to determine that the stone source or combination of sources selected are capable of supplying the quantities and gradation needed and at the rate needed to maintain the scheduled progress of the work.

SECTION 00 08 00 Page 12

d. After the award of the contract, the Contractor shall designate in writing only one source or one combination of sources from which stone will be furnished. If the Contractor proposes to furnish stone from a source not currently listed, only a single additional source for stone may be designated. Samples for acceptance testing shall be provided as required by SECTION 02 37 00. If a source for stone so designated by the Contractor is not accepted for use by the Contracting Officer, the Contractor may not propose other sources but shall furnish the stone from a source listed at no additional cost to the Government.

e. Acceptance of a source of stone is not to be construed as acceptance of all material from that source. The right is reserved to reject materials from certain localized areas, zones, strata, or channels when such materials are unsuitable for stone as determined by the Contracting Officer. Materials produced from a listed or unlisted source shall meet all the requirements of SECTION 02 37 00, of the Technical Provisions of these specifications.

f. If the Contractor proposes to furnish stone from a source or sources listed, he shall submit Department of transportation ledge testing information from within the past 12 months. Selected ledge or ledges for producing crushed stone shall meet the following MINIMUM requirements: Stone shall weigh more than 155 lbs/cubic foot. The stone shall also have an absorption less than 2 percent. The Contractor shall also schedule a site visit to the quarry to inspect the proposed ledge(s) that stone will be produced. The Government shall be included in the scheduling of the site visit and a minimum 72-hour notice shall be given.

1.31 CONTRACTOR PERFORMANCE EVALUATIONS

In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor's performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $100,000.00, the USACE will evaluate contractor's performance and prepare a performance report using the Contractor Performance Assessment Reporting System (CPARS), which is a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period of 30 days. Accessing and using CPARS requires specific software, called PKI certification, which is installed on the user's computer. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and is purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and for contacting vendors can be found on the web site:

http://www.cpars.navy.mil/. If the Contractor wishes to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.

1.32 ENVIRONMENTAL LIMITATIONS

SECTION 00 08 00 Page 13

BALD EAGLE NESTS. Should any bald eagle nest be noted in the project area, the contractor shall immediately contact the contracting officer to determine if any eagle nest buffer zone restrictions will be required for construction operations. Approval by the contracting officer may be granted after appropriate coordination by the St. Louis district with the U.S. Fish and Wildlife Service has been conducted, and it is determined whether an eagle take permit and/or nest buffer zone restrictions are required. If it is determined that an eagle take permit and/or nest buffer zone restrictions are required, an equitable adjustment in contractor performance time will be made for any increase in the time required for performance of any part of the work impacted by such restrictions.

BAT HABITAT. All tree clearing must be coordinated with the USACE environmental compliance section in advance. All tree clearing must be completed from 1 October thru 31 March. No tree clearing is permitted from 1 April thru 30 September unless otherwise approved by the contracting officer. Approval by the contracting officer may be granted after appropriate coordination by the St. Louis district with the U.S. Fish and Wildlife Service has been conducted, and it is determined that clearing can be performed without impacting trees suitable for Indiana, gray, or northern long-eared bat habitat. In the event bats or habitat could be impacted, an equitable adjustment in contractor performance time will be made for any increase in the time required for performance of any part of the work arising from implementation of government mitigation for the presence of Indiana bats, gray, northern long-eared bats, or Indiana, gray, and/or northern long-eared bat habitat.

1.33 SECURITY REQUIREMENTS

A. The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

B. All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

C. The Contractor must pre-screen Candidates using the E-verify Program

(http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

http://www.uscis.gov/e-verify

SECTION 00 08 00 Page 14

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

-- End of Document --

Section 01 11 30 Page 1

SECTION 01 11 30

ENVIRONMENTAL PROTECTION

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2020) Safety and Health Requirements Manual

ER 385-1-80 (2010) Ionizing Radiation Protection

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 261 Identification and Listing of Hazardous Waste

1.2 DEFINITIONS

Environmental pollution and damage is defined as the presence of chemical, physical, or biological elements or agents that adversely affect human health or welfare; unfavorably alter ecological balances of plant or animal communities; or degrade the environment from an aesthetic, cultural or historic perspective. Environmental protection is the prevention/control of pollution and habitat disruption that may occur during construction. The control of environmental pollution and damage requires consideration of air, water, land, biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste;

radiant energy and radioactive materials; and other pollutants.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 - SUBMITTAL PROCEDURES:

Environmental Protection Plan; G

Submit plan detailing Contractor's procedures for complying with all applicable environmental protection regulations and the special requirements of this contract.

1.4 ENVIRONMENTAL PROTECTION REQUIREMENTS

The Contractor shall comply with all applicable Federal, State, and local laws and regulations. The Contractor shall provide environmental protective

Section 01 11 30 Page 2 measures and procedures to prevent and control pollution, limit habitat disruption, and correct environmental damage that occurs during construction.

1.4.1 Protection of Features

This section supplements the Contract Clause PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS. The Contractor shall prepare a list of features requiring protection under the provisions of the contract clause, which are not specially identified on the drawings as environmental features requiring protection. The Contractor shall protect those environmental features shown specially on the drawings, even if such preservation interferes with the Contractor's work under this contract.

1.4.2 Permits and Special Environmental Requirements

This section supplements the Contractor's responsibility under the contract clause PERMITS AND RESPONSIBILITIES. The Contractor shall comply with the terms and conditions of any environmental permits or special environmental requirements which are an outgrowth of environmental commitments made by the Government during the project development. IDNR-Office of Water Resources (OWR) may require a Statewide Permit #09 for this project. This Statewide Permit covers “Minor shoreline, stream bank, and channel protection activities” The contractor should contact Jesse Tinch of IDNR-OWR to verify if the statewide permit or any other permits are required under their State Regulations. Jesse can be reached at 217-782-4545 or Jesse.Tinch@Illinois.Gov Any special environmental requirements, if applicable, can be found at the end of this section.

1.4.3 Environmental Assessment of Contract Deviations

The Contract specifications have been prepared to comply with the special conditions and mitigation measures of an environmental nature which were established during the planning and development of this project. The Contractor is advised that deviations from the drawings or specifications (e.g., disposal areas, staging areas, alternate access routes, etc.) could result in the requirement for the Government to reanalyze the project from an environmental and cultural resources standpoint. The Contractor must obtain, at his expense, all necessary permits to use alternate sites including, but not limited to, Section 401 and Section 404 of the Clean Water Act, and coordination with the State Historic Preservation Officer regarding Section 106 of the National Historic Preservation Act, compliance with the National Environmental Policy Act (NEPA), and the Endangered Species Act. Deviations from the construction methods and procedures indicated by the plans and specifications which may have an environmental impact will require an extended review, processing, and approval time by the Government. The Contracting Officer reserves the right to disapprove alternate methods, even if they are more cost effective, if the Contracting Officer determines that the proposed alternate method will have an adverse environmental impact.

1.5 ENVIRONMENTAL PROTECTION PLAN

Within 15 calendar days of Notice to Proceed, the Contractor shall submit an Environmental Protection Plan for review and acceptance by the Contracting Officer. The Government will consider an interim plan for the first 15 days mailto:Jesse.Tinch@Illinois.Gov

Section 01 11 30 Page 3 of operations. However, the Contractor shall furnish an acceptable final plan not later than 30 calendar days after receipt of Notice to Proceed.

The Contractor shall meet with representatives of the Contracting Officer to develop a mutual understanding relative to compliance with this section and administration of the environmental pollution control program. Acceptance is conditional and is predicated upon satisfactory performance during construction. The Government reserves the right to require the Contractor to make changes in the Environmental Protection Plan or operations if the Contracting Officer determines that environmental protection requirements are not being met. The plan shall detail the actions that the Contractor shall take to comply with all applicable Federal, State, and local laws and regulations concerning environmental protection and pollution control and abatement, as well as the additional specific requirements of this contract.

No physical work at the site shall begin prior to acceptance of the Contractor's plan or an interim plan covering the work to be performed. The environmental protection plan shall include, but not be limited to, the following:

1.5.1 List of State and Local Laws and Regulations

The Contractor shall provide as part of the Environmental Protection Plan a list of all State and local environmental laws and regulations, which apply to the construction operations under the Contract.

1.5.2 Spill Control Plan

The Contractor shall include as part of the environmental protection plan, a Spill Control Plan. The plan shall include the procedures, instructions, and reports to be used in the event of an unforeseen spill of a substance regulated by the Emergency Response and Community Right to Know Act or regulated under State or local laws or regulations. The Spill Control Plan supplements the requirements of EM 385-1-1. This plan shall include as a minimum:

a. The name of the individual who will be responsible for implementing and supervising the containment and cleanup.

b. Training requirements for Contractor's personnel and methods of accomplishing the training.

c. A list of materials and equipment to be immediately available at the job site, tailored to cleanup work of the potential hazard(s) identified.

d. The names and locations of suppliers of containment materials and locations of additional fuel oil recovery, cleanup, restoration, and material placement equipment available in case of an unforeseen spill emergency.

e. The methods and procedures to be used for expeditious contaminant cleanup.

f. The name of the individual who will report any spills or hazardous substance releases and who will follow up with complete documentation.

This individual shall immediately notify the Contracting Officer in addition to the legally required Federal, State, and local reporting channels (including the National Response Center 1-801-424-8802) if a

Section 01 11 30 Page 4 reportable quantity spill occurs. The plan shall contain a list of the required reporting channels and telephone numbers.

1.5.4 Contaminant Prevention Plan

As a part of the Environmental Protection Plan, the Contractor shall prepare a contaminant prevention statement identifying potentially hazardous substances to be used on the job site and intended actions to prevent accidental or intentional introduction of such materials into the air, water, or ground.