Q A_5-17.pdf

PDF 80 KB Posted

Attached to
Rend Lake - Benton, Illinois - Vegetative Control and Grounds Maintenance
Solicitation number
W912P9-16-B-0002
Issued by

About this file

Q A 5-17

View the file

Other files

File Type Posted
Amendment_0002.pdf PDF
Appendix_A_Updated.pdf PDF
Amendment_1_to_Solic.pdf PDF
Campground__Lake_Maps.pdf PDF
Appendix_I_-_Mowing_Required_Documents.pdf PDF
Site_Visit_Sign_in_Sheet.pdf PDF
Q A_1-4.pdf PDF
Site_Visit.pdf PDF
Appendix_C.pdf PDF
Appendix_B_Maps_24-47.pdf PDF
A20_-_SCA_Wage_Determination.pdf PDF
Solicitation.pdf PDF
Appendix_B_Maps_48-69.pdf PDF
Appendix_B_Maps_1-23.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS & ANWSERS

SOLICITATION W912P9-16-B-0002

REND LAKE MOWING SERVICES

QUESTIONS 5-17

Question 5: Can you describe the ordering process per mow, or the expected schedule of mowing’s?

There are 26 level 1 mowing’s, does that mean we will mow every 10 days or so? Do we make our own mowing schedule? If not how it is done?

Answer 5: Mowing requirements will vary during the Recreation Season. Weather will play a huge factor in how much mowing will be required. Mowing cycles are 10 days long ( no mowing on weekends & holidays unless approved). The quantities given are estimates only as this is an indefinite quantity contract. You may have to mow some level 1 areas 2 times during that cycle. Reference Section C, 1.11 Work Schedule, Section 7.1 General Vegetative Control.

Question 6: Do we make our own mowing schedule?

Answer 6: Mowing items to be completed are provided/assigned for each cycle and then you create your schedule from there to meet the required deadlines.

Question 7: Are 26 level 1 mowing’s and 10 level 2 mowing’s guaranteed per year?

Answer 7: The guaranteed minimum for the base year is $600, each option year is $300. This is an Indefinite Quantity Contract (IDIQ).

Question 8: On Maps 24-47 there are a lot of small level 2 mowing’s. How far apart are they? It is difficult to determine how to get the tractor from one area to another without knowing where they are located?

Answer 8: A detailed map has been provided to the Solicitation just for clarity, see campground map.

Question 9: Can we store tractors and mowers on site, overnight or for multiple days or will equipment need to be removed daily?

Answer 9: No, tractors and mowers can’t be stored on site. Equipment will need to be removed daily.

Question 10: Has the scope and or quantity of work to be performed increased from the existing contract?

Answer 10: The items have changed, more items have been added and the estimated quantities have increased on many items.

Question 11: Can the sign‐in sheet be posted from the site visit on 24 Feb 2016?

Answer 11: Yes. The sign‐in sheet has been posted as part of Amendment 0001.

Question 12: Which wage rate determinations apply?

Answer 12: See Wage Rate No. 05‐2309, Rev 16 as provided in the Solicitation.

Question 13: Where does the Government find wage increase projections: Do they contact Labor board?

Answer 13: No, wage projections are pulled from http://www.dol.gov.

Question 14: Can we tell how many level 1 mowing’s there were over the past 5 years?

Answer 14: There was an average of 16 Level 1 mowing’s executed per year.

Question 15: Can they look at a checklist given to contractor once bid is awarded that summarizes paperwork that needs to be turned into the customer?

Answer 15: Yes. A checklist has been provided as attachment XX to the SOW.

Question 16: Is it practical for a company my size to win a bid of this size. Last year’s receipts were approx. 100,000 Answer 16: This requirement is for a Set‐a‐Side small business under NAICS code 561730 with the size standard of $7.5M.

Question 17: Do we have to bid on the complete job or will you award different areas to different vendors Answer 17: The contract will be awarded as a single IDIQ and every item listed in Schedule B will need to be completed to determine technical capability.