Solicitation Amendment W912P826BA0440003 SF 30.pdf
PDF 4 MB Posted
- Attached to
- Mississippi River, Baton Rouge to Gulf, Southwest Pass Hopper Dredge Contract No. 1-2026 (OM26001)
- Solicitation number
- W912P826BA044
About this file
This is Amendment 0003 to a solicitation for the Mississippi River Baton Rouge to the Gulf Southwest Pass Hopper Dredge Contract No. 1-2026 (OM26001), issued by the USACE New Orleans District on June 5, 2026. The amendment is not extended and requires offerors to acknowledge receipt prior to the offer deadline specified in the original solicitation. Offerors may acknowledge receipt by completing and returning the amendment, acknowledging receipt on each copy of their offer, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt may result in offer rejection.
The amendment makes two substantive changes: (1) deletion of the Construction of Magnitude requirement that was removed under the Revolutionary FAR Overhaul (RFO), and (2) a response to questions regarding Section 00 10 00, Paragraph 1.5 (Bidder Qualifications). Regarding bidder qualifications, the USACE declined a request to remove documentation requirements proving that proposed dredges and attendant plants are available and not obligated for other work that would delay dredging commencement. The government determined that such documentation remains necessary to establish whether bidders meet definitive responsibility criteria for bidder qualifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
1. 1.5 BIDDER QUALIFICATIONS... "(b) Documentation to prove that the dredge and attendant plant are available and not already obligated for the performance of other work which would delay commencement of dredging. If the proposed dredge and attendant plant are not currently performing work or obligated under a contract, the bidder must submit a statement that the dredge and attendant plant can commence dredging within the time required in the specifications. If the proposed dredge and attendant plant are currently performing work or obligated under a contract, the bidder must submit approved release documentation along with a statement that the dredge and attendant plant can commence dredging within the time required in the specifications. The approved release documentation must be issued by the entity currently utilizing the dredge and attendant plant, and the documentation must clearly indicate the approved release date of the dredge and attendant plant from its current work commitment.
Contractors typically have multiple contracts in place that have varying performance windows. These performance windows often overlap and the contractor is responsible for managing the performance and completion of their contracts. The below requirement seems unreasonable to request as the other entity is not privy to the New Orleans District contract requirements and do not have a responsibility to the New Orleans District. The Contractor is the sole entity responsible for meeting the contractual requirements and are subject to the repercussions if the contractual terms are not met. While the below may be warranted on a rapid response contract the early award nature of the subject contract does not warrant this level of documentation.
Can the USACE please remove the requirement to provide documentation as the submittal of a bid acknowledges the availability and expectation that the Contractor will meet the contractual requirements?
Response: No, the documentation requirement will not be removed as it is necessary for a determination of whether the bidder meets the definitive responsibility criteria stated in Section 00 10 00, Paragraph 1.5 entitled "Bidder Qualifications".
| IDCode: J |
| Page: 1 |
| Pages: 2 |
| AmendNo: 0003 |
| EffDate: 05 JUN 2026 |
| ReqNo: |
| ProjNo: OM26001 |
| IssCode: W912P8 |
| AdmCode: |
| IssuedBy: W07V ENDIST N ORLEANS |
KO CONTRACTING DIVISION, 7400 LEAKE AVE
NEW ORLEANS, LA 70118-3651
UNITED STATES
CORI CAIMI, EMAIL: CORI.A.CAIMI@USACE.ARMY.MIL TELEPHONE: 504-862-1352
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W912P826BA044 |
| SolDate: 08 MAY 2026 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: The above numbered Solicitation for Mississippi River Baton Rouge to the Gulf Southwest Pass Hopper Dredge Contract No. 1-2026 (OM26001) is hereby amended to: |
1. Delete the Construction of Magnitude as it has been removed with the Revolutionary FAR Overhaul (RFO)
2. Respond to questions
| ContNameTitle: |
| CoNameTitle: VERONICA GARNER-FLINT |
| ContDate: |
| CODate: 05 JUN 2026 |