This document is an Amendment to Solicitation for the Calcasieu River and Pass, Dredged Material Management Plan (DMMP), CDF-H Degrading and Dike Construction project in Cameron Parish, Louisiana. The solicitation (W912P825BA021) involves degrading an existing dike and constructing a new dike within a Confined Disposal Facility (CDF), with an estimated 520,000 cubic yards of material to be excavated and approximately 360,000 cubic yards used for new dike construction. Key details include a project duration of 365 calendar days, with work to commence within 10 calendar days of receiving notice to proceed, and a bid opening scheduled for Thursday, 14 August 2025 at 11:00 AM local time.
The amendment includes significant contractor questions and responses addressing site-specific challenges, such as material moisture content, drainage requirements, and site preparation. Notable responses include permission to use degraded dike material for construction, a requirement to naturally dry borrow materials without chemical treatments, and clarification on extending existing discharge pipes by 225 feet each. The U.S. Army Corps of Engineers New Orleans District will manage the project, with bids to be submitted electronically via email to specified contract personnel or physically delivered to their contracting office, with strict submission guidelines and a 35MB email size limit.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract W912P825BA021.pdf | ||
| W912P825BA021.pdf | ||
| Attachment 0002 - 250611 CDF-H Plans.pdf | ||
| Attachment 0001 - Specs CDF-H.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section 00 01 15 - List of Drawing Sheets
The attachments table has changed from:
Identifier Document Name Document Description Reference Identifier
Date Line Item Page Numbers
Document Type
Provided Under Separate Cover
Advertise Specs_CDF-H Degrading and Dike Construction, LA
(ED 23-022)
Specification 12 Jun 2025 Attachment No
250611 CDF-H
Plans
Plans 12 Jun 2025 Attachment No
To:
Identifier Document Name Document Description Reference Identifier
Date Line Item Page Numbers
Document Type
Provided Under Separate Cover
Advertise Specs_CDF-H Degrading and Dike Construction, LA
(ED 23-022)
Specification 12 Jun 2025 Attachment No
250611 CDF-H
Plans
Plans 12 Jun 2025 Attachment No
Contractor Questions Government Responses
Contractor Questions Government Response
07 Aug 2025 Attachment No
Detailed Changes Amendment 0001
W912P825BA021
CDF-H Degrading Dike Construction Ed 23-022
Specification 07 Aug 2025 Attachment No
Instructions to Bidders
Instructions to Bidders 07 Aug 2025 Attachment No
The following contract documents were added:
Contractor Questions Government Responses Detailed Changes Amendment 0001 W912P825BA021 CDF-H Degrading Dike Construction Ed 23-022 Instructions to Bidders
Section 00 21 00 - Instructions
The following clauses were modified:
52.236-27 Site Visit (Construction). Feb 1995 hereby reads as follows:
Site Visit (Construction) (Feb 1995)
The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions(a) Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
Site visits may be arranged during normal duty hours by contacting:(b)
Name: James LaFleur
Telephone: 337-529-7510
Email: James.W.Lafleur@usace.army.mil
(End of Provision)
Section 00 72 00 - General Conditions
The following clauses were modified:
52.211-10 Commencement, Prosecution, and Completion of Work. Apr 1984 hereby reads as follows:
Commencement, Prosecution, and Completion of Work (Apr 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 365 calendar days after the date of receipt by him of notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
SECTION 31 23 00.00 20
Page 4, paragraph 3.4.2. Delete this paragraph in its entirety and substitute the following, therefore:
“3.4.2 Drainage Ditches
Prior to grading, the Contractor shall dewater the site by excavating drainage ditches across the entire site footprint to assist in control of soil moisture content of borrow material, dike foundation, and rainwater runoff. Excavation for the purpose of ditching and draining shall be conducted through the existing perimeter dike. Dewatering shall be utilized by the Contractor in order to meet the required moisture control of the embankment material in accordance with the requirements of Section 31 24 00.00 12 EMBANKMENT. Bottom width of the drainage ditches shall be approximately 5 foot wide with 1V:2H side slopes, as shown in the contract drawings. Ditches shall be dug every 500 feet, covering the entire site, including intercepting the existing retention dikes. The Contractor may field fit the location of the ditches to allow adequate drainage. Ditches shall be dug to an elevation of +15.0 feet NAVD88 at their center point as viewed along their length, with a minimum 1% slope to either side of their center point, as viewed along their length. Ditch shall extend through the original borrow site used to construct the existing perimeter dike. Concern for excessive moisture within these old borrow pits shall be alleviated by draining excess water within those pits. In the event that the drainage ditches are required below elevation +10.0 feet NAVD88, the Contractor shall obtain approval from the Government for such drainage operations. No additional payment will be made for any drainage ditches constructed for moisture control and site drainage.
Backfilling of the drainage ditches to elevation +15.0 feet NAVD88 shall be in accordance with density and moisture contents for dike construction.”
SECTION 31 24 00.00 12
1. Page 5, paragraph 1.3.1.1. Delete this paragraph in its entirety and substitute the following, therefore:
“1.3.1.1. Reserved”
2. Page 11, paragraph 3.1, subparagraph d. Delete this paragraph in its entirety and substitute the following, therefore:
“d. Reserved”
Calcasieu River and Pass, Dredged Material Management Plan (DMMP), CDF-H Degrading and Dike ConstrucƟon, Cameron Parish, LA - W912P824BA021 Contractor QuesƟons
QUESTION 1: “In regards to the CDF-H Degrading and Dike project, there appears to be approximately 520,000 cy of material excavated and only 360,000 cy of material being used for the dike construcƟon.
Can you advise of where the addiƟonal material is to be placed?”
RESPONSE 1: The new dike is being built on exisƟng borrow ditches which are currently saturated. The material will compress when required moisture parameters are met (drainage) to construct the new dike and will be lower than the required (+)15.0 feet (NAVD88) when the construcƟon of the dike commences. The extra excavated material will be used to fill in the exisƟng borrow ditch areas which compress below the required (+)15.0 feet (NAVD88) aŌer draining is completed as well as those areas of the ditches that were previously excavated below (+)15.0 feet (NAVD88). If there is sƟll excess material aŌer placement within the borrow ditches, the material shall be Ɵed into the interior slope of the dike, with a maximum height of five (5) feet and a maximum width of 35 feet.
QUESTION 2: With regard to the above SolicitaƟon, in the specificaƟon under disposiƟon of materials, it states the following: “All wasted materials shall be disposed of within the interior dike toe limits, shown in the contract drawings, or removed from the site. A tolerance for Ɵmber/wood and stones/rocks within the embankment will be permiƩed as follows: a. Timber/wood - Timber and wood greater in length of 12 inches and/or greater than three (3) inches in diameter shall not be placed within the embankment secƟon. b. Stones/rocks - Stones and rocks greater than three (3) inches in diameter shall not be placed within the embankment secƟon.” Can it be deduced that if woody debris from clearing and grubbing is chipped or ground to less than 3” long and less than 3” in diameter that it may be disposed of within the interior dike toe limits?
RESPONSE 2: It is the intent of the specificaƟon to minimize placement of vegetaƟve debris within the dike and berm secƟon. VegetaƟve debris can be stockpiled away from embankment materials and leŌ within the CDF upon compleƟon of construcƟon. Any material stockpiled on site that needs to be moved during construcƟon, shall be moved by the Contractor at the contractor’s expense.
QUESTION 3: Also, in the specificaƟon for Spillbox relocaƟon and Culvert installaƟon it states, “The new dike footprint would require an addiƟonal five (5) culvert pipes of 225 feet in length each to be welded onto the exisƟng pipes.” Alternately, under the steel culvert installaƟon spec, it states “Contractor shall remove the exisƟng spill boxes and culvert pipe and dispose offsite at an approved disposal area.” So do we remove and dispose of the exisƟng pipe or do we weld new pipe to old?”
RESPONSE 3: The spillbox was installed in new condiƟon on June 12, 2019. Contractor shall have to add 225-Ō to the exisƟng five (5) discharge pipes to accommodate the 140-Ō dike shiŌ to the inside.
QUESTION 4: Regarding SECTION 31 11 00.00 12 Clearing and Grubbing Paragraph 3.4.3 Disposal LocaƟon, the specificaƟon states “If debris from clearing operaƟons is placed on adjacent property, the Contractor shall obtain, without cost to the Government, addiƟonal right-of-way for such purposes.” Can you please provide details on the adjacent property that is available for disposal? Who do we obtain the addiƟonal right-of-way from?
RESPONSE 4: VegetaƟve debris can remain on site. Non-vegetaƟve debris shall be hauled off-site at no addiƟonal cost to the Government.
QUESTION 5: Would the government consider allowing the contractor to bury debris from clearing and grubbing in a designated locaƟon on-site?
RESPONSE 5: No. VegetaƟve debris can be stockpiled away from embankment materials and leŌ within the CDF upon compleƟon of construcƟon. Buried debris becomes an issue on future contracts.
QUESTION 6: Where exactly will the borrow material for the dike be obtained if we are unable to excavate below elevaƟon 15’? Can the Deconstructed dike be set aside and be used as fill material?
RESPONSE 6: Borrow material is considered any material on the site that is currently above elevaƟon 15- Ō. This quanƟty includes degraded dike. This material will be degraded and used to build the “New Dike Alignment”.
QUESTION 7: Will the USACE consider adding more days to the contract? With a wait period of 3 months aŌer drainage ditching and the iniƟal wait Ɵme before MobilizaƟon, the contract days will be extremely difficult to meet especially with a Compacted Dike and a large amount of CY quanƟƟes.
RESPONSE 7: An extension of the duraƟon to 365 calendar days is approved.
QUESTION 8: What locaƟon is the degrade material intended to be brought to?
RESPONSE 8: The degrade material will be first used to construct the new dike, and therefore will be placed on the new dike and berm footprint. AŌer compleƟon of the new dike, any excess material will be used to fill in any exisƟng ditches (below elevaƟon +15) within the site. If there is sƟll excess material aŌer filling in the ditches, material shall be Ɵed into the interior slope of the dike, at a maximum height of 5 feet and a maximum width of 35 feet.
QUESTION 9: Does the degraded material have to be placed in liŌs and tested?
RESPONSE 9: Yes, material must be placed in liŌs and tested to make sure it meets the moisture parameters. See Paragraph 3.5.2 Placement, Spreading, and CompacƟon in Spec secƟon 31 24 00.00 12.
QUESTION 10: Is there a maximum equipment weight limit or pressure restricƟon for working over the 36-inch brine pipeline?
RESPONSE 10: The 36” pipeline is abandoned in place and has not been an issue in the past during dike construcƟon projects within CDF “H”.
QUESTION 11: Can the USACE provide the date of when the disposal area was last dredged into?
RESPONSE 11: The last dredged material placement within CDF “H” was completed June 24th, 2025.
QUESTION 12: During our site visit it appeared the CDF had recently had dredge spoils deposited into the area. These soils are very wet, accordingly we took soil samples from two locaƟons within the area and have sent these samples to TSI Materials TesƟng in Victoria, TX to have moisture contents and aƩerburg limits run on this material. The results of the moisture content of the samples and communicaƟons with TSI are as follows. The samples show in-situ moisture contents over 100% with opƟmum moisture content in the 21% range. TSI informs us that shrinkage of this material will be in excess of 50% not including subsidence or compacƟon. The excavaƟon quanƟty of CDF-H under CLIN 2 is 520,000 CY. Per TSI's results we should expect shrinkage of 50% resulƟng in a net dike construcƟon material of 260,000 CY for construcƟon of the new levee. This is short of the 360,000 CY shown for Dike ConstrucƟon under CLIN 3. We request lowering the boƩom elevaƟon of the ditches to +10' from the +14' shown on the plans to allow for addiƟonal borrow for the required construcƟon of the dike. Lowering the ditches is necessary because of the amount of shrinkage expected from the results of TSI's tesƟng of the material.
RESPONSE 12: The quanƟƟes on the bid sheet were determined using the design survey data collected in October 2022. This determinaƟon was made prior to the latest disposal event which concluded in June 2025. There is a sufficient amount of material on site to construct the dikes.
QUESTION 13: As stated above the borrow material for this project is extremely wet and will require substanƟal drying Ɵme to meet the +10% of opƟmum moisture content to be placed in the levee template per the specificaƟons. The specificaƟons only allow 330 calendar days to complete this project.
With historic rainfall of Southern Louisiana, the only way to achieve this Ɵme of compleƟon is to chemically dry the borrow with a drying agent (quick lime). Should you elect to use a chemical drying agent (quick lime) a new bid item will need to be added so the contractor can be paid as this work progresses.
RESPONSE 13: Chemical drying of the borrow material was considered and will not be permiƩed.
Requirement is to ditch and drain the disposal site to allow the material to dry naturally, with the intent to use on site material for dike construcƟon.
QUESTION 14: If chemical treatment of the soil is not allowed we anƟcipate this project will require an addiƟonal calendar days to naturally dry the borrow materials with the weather anƟcipated for Southern Louisiana. This will raise the contractual compleƟon Ɵme for the project to 930 calendar days. Please understand that if you elect to naturally dry the borrow, the contractor will have no control over the weather and while the contractor will make every aƩempt to dry the borrow it will ulƟmately be up to how much drying Ɵme is available during the contract Ɵme. The anƟcipated weather delays shown in the specificaƟons show 1/3 of the contract Ɵme to anƟcipated weather delays. This does not include the addiƟonal Ɵme to process the material again aŌer a weather event. We highly recommend chemically drying the borrow area so the contractor can have some control over the drying process and Ɵme of compleƟon.
If chemically drying the borrow materiel is not allowed, or addiƟonal contract days are not added, then weather delay days must also include days in which the available borrow does not meet the +/-10% of opƟmum moisture content required in the specificaƟons.
RESPONSE 14: Chemical drying of the borrow material was considered and will not be permiƩed.
Requirement is to ditch and drain the disposal site to allow the material to dry naturally, with the intent to use on site material for dike construcƟon. Time between compleƟon of dredge fill to esƟmated start of ditching coupled with the extension on quesƟon seven (7) is adequate Ɵme for preparaƟon of the site, degrading, and dike construcƟon.
QUESTION 15: There are no plan sheets showing the relocaƟon of the spill box or the new spill box to be constructed. Please incorporate the needed plans per addendum.
RESPONSE 15: The spill-box will remain in the same general area that it is currently located, which is shown on plan sheet C-01. It will need to be set approximately 140-feet inward from its exisƟng locaƟon to accommodate for the dike shiŌ from the exisƟng locaƟon to the new design locaƟon. Although a new spill-box is not needed, the discharge pipes will need to be extended to accommodate new dike and berm secƟon. The exisƟng five (5) discharge pipes shall be extended approximately 225 feet each (approximately 1,125 feet total) of 500 wall.
INSTRUCTIONS TO BIDDERS
SOLICITATION NUMBER: W912P825BA021
NOTE: BIDDERS MAY SUBMIT BIDS BY ONLY ONE METHOD: A) ELECTRONIC COMMERCE (EMAIL) OR BY
2) PHYSICAL SUBMISSION. BIDDERS SHALL LIMIT THE BID SUBMITTAL TO ONE OPTION OR THE OTHER, NOT BOTH.
Electronic Submission of Bids (Email):
The New Orleans District utilizes electronic commerce (Email) for receipt of electronic bids under this IFB solicitation. To submit an electronic commerce (Email) bid please follow these steps:
1. Send an email containing your name, email address and bid/proposal to the following emails associated with the IFB (MUST include all emails):
taylor.h.brandon@usace.army.mil
AND
Christopher.Nuccio@usace.army.mil
2. ALL BIDS SUBMITTED BY EMAIL MUST CONTAIN THE SOLICITATION NUMBER IN THE SUBJECT LINE.
3. Once the agency receives your bid/proposal at the above email addresses, you will then receive a confirmation email stating your bid/proposal was received. If a bidder does not receive a reply acknowledging receipt electronically from the New Orleans District, it is incumbent upon the bidder to seek confirmation from the issuing Contracting office by phone.
NOTE: The size limit for incoming emails is 35MB. Any bid/proposal over this size may not be accepted by the server and will constitute the bid not being received timely. Please note that embedded links, URLs, and other html language included may interfere with the USACE server security, which may cause emails to be removed prior to being received by the contracting office. Bidders are advised to refrain from including external links, embedded links, URLs, and other html language not germane to the proposal/bid. Please note it is a bidder’s responsibility, when transmitting its bid electronically, to ensure the receipt of its bid to the proper designee at the proper time. See FAR 14.304(b)(1)(i) regarding untimely electronic bids. Please note, MVN’s computer system firewall may cause a delay in receipt of emails, so be sure to allow ample time for possible delay. If your email would exceed 35MB you can use one of the following methods as a work-around:
- Use .zip files as attachments. Combine multiple files into a .zip file to compress file size prior to adding as an email attachment.
- Send multiple emails. Label each email with same subject line and indicate number of emails.
For example: Smith Construction W912P825BA025 (1 of 2) Smith Construction W912P825BA025 (2 of 2).
mailto:Angela.C.Day@usace.army.mil mailto:Christopher.M.Nuccio@usace.army.mil
Physical Submission of Bids:
Bidders may submit their bids by hand carrying or express mail to the New Orleans District Contracting Office in Room 172. Bidders are advised to allow adequate time to ensure timely submission of its bid.
Traffic onto the New Orleans District campus may be delayed by trains blocking the entrance or security either at the gate and/or inside of the building. Express delivery may be utilized but it is incumbent upon the bidder to ensure bid delivery time and date is before the receipt of bid cutoff time. See FAR 14.304(b)(1)(ii) and (c).
In accordance with current Security procedures at the District, any bidder hand carrying bids MUST notify the contract specialist and contracting officer no later than the day before the bid opening via email that they intend to submit their bid in person. Security will be notified of the expected time of the visit. For this bid opening, please notify:
taylor.h.brandon@usace.army.mil
AND
Christopher.Nuccio@usace.army.mil
BID OPENING:
The Bid Opening is currently scheduled for THURSDAY, 14 AUGUST 2025 at 11:00 AM local time. The Contracting Officer and Contract Specialist will begin downloading bids at 10:00 AM local time, which is the bid submission receipt cutoff time. All bids received after 10:00 AM local time on THURSDAY, 14 AUGUST 2025, will be considered late.
Audio Teleconference Bid Opening Information:
The audio teleconference number for the bid opening at 11:00 AM local time is: Dial in by phone +1 601-262-2433
Phone conference ID: 690 495 004# https://dod.teams.microsoft.us/l/meetup-join/19%3adod% 3ameeting_bf1bef5be9104c94b8c67a1e2bc90ee4%40thread.v2/0?context=%7b%22Tid%22%3a% 22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22df68d226-f594-4b15-a055-0aa9ffa0c19c%22%7d
Following the conclusion of the bid opening, in accordance with FAR 14.403(b), abstracts of offers for unclassified acquisitions shall be available for public inspection via SAM.GOV.
mailto:Angela.C.Day@usace.army.mil mailto:Christopher.M.Nuccio@usace.army.mil https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_4690410be17e419abf45e2502155912f%40thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22bca6cd27-53d7-49be-9571-7584b0883693%22%7d https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_4690410be17e419abf45e2502155912f%40thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22bca6cd27-53d7-49be-9571-7584b0883693%22%7d https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_4690410be17e419abf45e2502155912f%40thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22bca6cd27-53d7-49be-9571-7584b0883693%22%7d https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_4690410be17e419abf45e2502155912f%40thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22bca6cd27-53d7-49be-9571-7584b0883693%22%7d
| A21. W912P8-25-B-A021_AM0001.pdf |
| Rev 1 Amendment 0001 W912P825BA021 CDF-H Degrading Dike Construction Ed 23-022.pdf |
| Contractor Questions Government Responses.pdf |
Instructions to Bidders (003).pdf
| IDCode: J |
| Page: 1 |
| Pages: 10 |
| AmendNo: 0001 |
| EffDate: 08 AUG 2025 |
| ReqNo: |
| ProjNo: ED 23-022 |
| IssCode: W912P8 |
| AdmCode: |
| IssuedBy: W07V ENDIST N ORLEANS |
KO CONTRACTING DIVISION, 7400 LEAKE AVE
NEW ORLEANS, LA 70118-3651
UNITED STATES
TAYLOR BRANDON, EMAIL: TAYLOR.H.BRANDON@USACE.ARMY.MIL TELEPHONE: (504) 862-1009
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| SolNo: W912P825BA021 |
| SolChg: 1 |
| SolDate: 15 JUL 2025 |
| AwardChg: Off |
| AwardNo: |
| Code: |
| FacCode: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: THE ABOVE NUMBERED SOLICITATION IS HERE BY AMENDED TO: |
1. RESPOND TO QUESTIONS.
2. INCORPORATE SITE VISIT DETAILS.
3. INCORPORATE INSTRUCTIONS TO BIDDERS.
4. NO FURTHER QUESTIONS WILL BE ANSWERED.