This document is a solicitation for a construction project to repair a navigation channel's west jetty. The solicitation is issued by the U.S. Army Corps of Engineers New Orleans District on behalf of the Department of the Army. The work consists of excavation for site access, placement of new stone to repair the west jetty, and construction of a "bullnose" at the jetty's southern end. Barge-mounted equipment will perform the work.

The bid opening will take place virtually on September 8, 2023 at 11:00 AM local time. Bids are due by 10:00 AM that same day. The base work is to be completed within 300 calendar days of the notice to proceed. Optional additional work may also be ordered. Bids must include pricing for both base work and optional items. Evaluation will consider the total price of all options. Safety standards are defined by EM 385-1-1.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912P823B0023

ED-22-056

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The subject solicitation for Port Fourchon Navigation Channel, East and West Jetty Repair, Lafourche Parish, Louisiana (ED-22-056), is hereby amended as follow s:

1) Provides revisions to the subject requirement as stated on the follow ing continuation pages.

2) The virtual bid opening is scheduled for Friday, September 8, 2023, 11:00AM, local time. The bid submission deadline is Friday, September 8, 2023, 10:00AM, local time.

PLEASE ACKNOWLEDGE AND SUBMIT THIS AMENDMENT WITH YOUR BID PACKAGE.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-Sep-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P823B0023

X 9B. DATED (SEE ITEM 11)

26-Jul-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Sep-2023

CODE

CONTRACTING DIV- CHIEF

7400 LEAKE AVENUE, ROOM 172

NEW ORLEANS LA 70118-3651

W912P8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)

The following items are applicable to this modification:

AMENDMENT 0005

GENERAL

1. In this contract change every occurrence of the contract title “Port Fourchon Navigation Channel, East and West Jetty Repair, Lafourche Parish, Louisiana” to “Port Fourchon Navigation Channel, West Jetty Repair, Lafourche Parish, Louisiana”.

2. In this contract change every occurrence of the term “east and west jetty” to “west jetty”.

COVER SHEET

Delete the Cover Sheet in its entirety and substitute the attached revise Cover Sheet, therefore.

SOLICITATION SHEET

Delete the Solicitation Sheet in its entirety and substitute the attached revise Solicitation Sheet, therefore.

STANDARD FORM 1442

Page 7/253, Block 11. Change “270 calendar days” to “300 calendar days”.

BIDDING SCHEDULE

Pages 11/253 and 12/253. Delete the BIDDING SCHEDULE in its entirety and substitute the attached revised BIDDING SCHEDULE, therefore.

SECTION 00700

1. Page 31/253, clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK.

Delete this clause in its entirety and substitute the following therefore:

“COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(FAR 52.211-10 - 1984 APR)

The Contractor shall be required to

(a) Commence work under this contract within 10 calendar days after the date the

Contractor receives the notice to proceed,

(b) Prosecute the work diligently, and

(c) Complete the entire work not later than 300 calendar days after the date of receipt by the Contractor of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

NOTE1: The term “work” referenced in subparagraph (a) above includes tasks such as submission of submittals, performance of positioning surveys, and/or cross section surveys and does not necessarily have to be excavation or dike construction.

NOTE 2: The Contractor is advised that the time allowed for completion of the Base Work 300 calendar days, and 90 additional calendar days, if Optional Work is exercised, reflects the Government's best estimate of the shortest reasonable performance period.

The Contractor shall be obligated to make any and all arrangements necessary (multiple crews, overtime, concurrent operations, etc.) to complete the work within the available time period – such arrangements shall not constitute grounds for an equitable adjustment.”

2. Page 47/253, clause 252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS, subparagraph (e). Delete this subparagraph in its entirety and substitute the following therefore:

“(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title File Drawing No.

Port Fourchon Navigation Channel, H-16-48613 G-01 thru G-02 West Jetty Repair C-04 thru C-06, Lafourche Parish, Louisiana C-07A, C-10 thru

C-12”

DRAWINGS

SHEET IDENTIFICATION Nos. C-01, C-02, C-03, C-07, C-08, and C-09. Delete these drawings in their entirety.

IFB NO. W912P823B0023

US Army Corps of Engineers

New Orleans District

Port Fourchon Navigation Channel

West Jetty Repair Lafourche Parish, Louisiana

Construction Solicitation And Specifications

July 2023

ED 22-056

DEPARTMENT OF THE ARMY

UNITED STATES ARMY CORPS OF ENGINEERS, NEW ORLEANS DISTRICT

7400 LEAKE AVENUE

NEW ORLEANS, LA 70118-3651

SOLICITATION: W912P823B0023 July 2023

FOR: Port Fourchon Navigation Channel, West Jetty Repair, Lafourche Parish, Louisiana TO OPEN: All bids must be received by 10:00AM (local time) on 8 September 2023.

Bid Opening will be held at 11:00 AM (local time), on 8 September 2023.

I. NOTE THE AFFIRMATIVE ACTION PROGRAM REQUIREMENT OF THE EQUAL OPPORTUNITY

CLAUSE WHICH MAY APPLY TO THE CONTRACT RESULTING FROM THIS SOLICITATION.

II. NOTE THE CERTIFICATION OF NONSEGREGATED FACILITIES IN THIS SOLICITATION.

Bidders, offerors, and applicants are cautioned to note the "Certification of Non-segregated Facilities" in the solicitation. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause.

III. Prospective contractors must register in the System for Award Management (SAM). See FAR Clause

52.204-7 for required information. The website for SAM is https://www.sam.gov. As of April 4, 2022, the Federal Government has stopped using the DUNS Number as a unique identifier for entities and switched to a Unique Entity ID generated by SAM.gov. In addition, entities with DUNS Numbers but no SAM.gov registration have been able to get Unique Entity IDs without registering in SAM.gov since October 2021.

NOTE: The DUNS Number is no longer used in SAM.gov, eSRS, FSRS, FPDS, CPARS, or FAPIIS.

BIDDERS MUST PROVIDE FULL, ACCURATE AND COMPLETE INFORMATION AS REQUIRED BY THIS

SOLICITATION AND ITS ATTACHMENTS. THE PENALTY FOR MAKING FALSE STATEMENTS IN BIDS

IS PRESCRIBED IN 18 U.S.C. 1001. (FAR 52.214-4 APR 1984)

DESCRIPTION AND MAGNITUDE OF WORK: The work consists of excavation of flotation channels as required for site access, placement of new stone for the repair of the west jetty, and construction on both jetties of a “bullnose” by placement of new stone at the southern end of each jetty. Barge mounted excavators and draglines will perform the work with associated attendant plant (tugs, crew boats, etc.) and all associated incidental work thereto and all associated incidental work thereto.

CAUTION TO BIDDERS: In delivery of hand-carried bids, bidders are cautioned to allow sufficient time for delays which may be encountered as a result of frequent trains which are subject to block all access roads to place of bid opening for various lengths of time and for visitor background checks by MVN security when entering the installation at place of bid opening. Such delays DO NOT permit acceptance or consideration of late bids.

VIRTUAL BID OPENING, please read and adhere to all special instructions in reference to subject solicitation and future amendments, including the dial-in information which is annotated in Section #10 of the SF 1442 and in SECTION 00100 - INSTRUCTIONS TO BIDDERS of the solicitation.

NOTE: ALL WORK UNDER THESE SPECIFICATIONS SHALL BE PERFORMED IN ACCORDANCE WITH

THE PROVISIONS OF EM 385-1-1 "CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS

MANUAL", DATED NOVEMBER 2014

ED 22-056

SECTION 00010 – BIDDING SCHEDULE

Port Fourchon Navigation Channel, West Jetty Repair

Lafourche Parish, Louisiana

Item DESCRIPTION Estimated Quantity Unit Unit Price Estimated Amount

BASE WORK

0001 Mobilization and Demobilization 1 JOB

0002 Jetty Stone 23,000 TON

0003 Bullnose Stone 7,000 TON

TOTAL BASE WORK: $

OPTIONAL WORK (OW)

0004 Jetty Stone - OW 18,000 TON

0005 Bullnose Stone - OW 1,000 TON

TOTAL OPTIONAL WORK: $

TOTAL OPTIONAL WORK: + OPTIONAL WORK $

**The unit "JOB" as used in this Bidding Schedule is synonymous with the term "Lump Sum" used elsewhere within these plans and specifications.

Award will be made as a whole to one bidder.

NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED TOTAL

OR ESTIMATED AMOUNT FOR ANY ITEM, ITS BID SHALL BE DECLARED NON-

RESPONSIVE AND THEREFORE INELIGIBLE FOR AWARD.

NOTE 2: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or subline items are materially unbalanced (See FAR 14.404-2, Rejection of Individual Bids).

NOTE 3: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442 after Notice of Award. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within 24 hours after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal

00010-3 ED 22-056

process with the Area or Resident Engineer or his authorized representative.

Physical work cannot start until the Accident Prevention Plan, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.

NOTE 4: OPTIONAL WORK ITEMS (FAR 52.217-5). The Government may require the delivery of the numbered line item identified in the schedule as OPTIONAL WORK Item, in the quantities and prices stated in the schedule. The Contracting Officer may exercise the OPTIONAL WORK Item by written notice to the Contractor within no later than 30 days after the issuance of the NTP.

Bidders shall bid on all items including optional item (see "Evaluation of Options" FAR 52.217-5). Failure to bid on all items will result in a non-responsive bid. If OPTIONAL WORK is exercised, the stone placement shall occur concurrently with the BASE WORK.

NOTE 5: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990) Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for this basic requirement.

Evaluation of options will not obligate the Government to exercise the option(s).

**If an option is to be exercised at the time of contract award FAR17.208 shall be used in place of FAR 52.217-5.

NOTE 6: TIME ADJUSTMENT IN THE EVENT OF THE EXERCISE OF OPTIONAL

WORK. In the event that OPTIONAL WORK items are exercised under the terms of the contract, the time required for completion of the contract shall be extended by 90 calendar days in addition to the original contract duration of 300 calendar days established for the BASE WORK items specified in the Contract Clause entitled “COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK (FAR 52-211-10 – APR 1984)”.

00010-4

Ed 22-056

File details come from the government source that posted it. Updated .