This document contains an amendment to a federal solicitation for a sand placement contract. The United States Army Corps of Engineers, New Orleans District, is seeking bids for Sand Placement Contract #2 to clear and grub land, place sand fill to elevation +3.0 feet in a marsh area, construct three canal crossings, one pipeline crossing, and perform other incidental work. The base contract scope is 58,505 linear feet with options to add 1550 linear feet and 3289 linear feet. Bids are due by April 26, 2022. The amendment provides responses to contractor questions, revises specifications, and provides call-in information for an audio teleconference bid opening.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912P822B0030_Bid Abstract.pdf | ||
| W912P822B0030 0002 Amendment.pdf | ||
| W912P822B0030 Amendment 0001.pdf | ||
| W912P822B0030 Solicitation Package.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
West Shore Lake Pontchartrain, LA Hurricane and Storm Damage Risk Reduction Project, WSLP-SP2, Site Preparation Contract 2, St. John the Baptist Parish, LA (ED-22-014) has been amended to:
1. Respond to Questions
2. Make Change to Specification
3. Provide Conference Line Information
1. CONTRACT ID CODE PAGE OF PAGES
1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Apr-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P822B0030
X 9B. DATED (SEE ITEM 11)
16-Mar-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Apr-2022
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P822B0030
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0003
Question 1:
Regarding the Gov furnished sand, will any other contractors be working this stockpile concurrently?
Gov’t Response: Another contractor will be working just northeast of the cross hatched area in the same overall stockpile of sand.
Question 2:
How many contractors will be working on Access Road J concurrently (ie. how many contractors will be working the various stockpiles, and contracts at the end of J)(to understand how much truck traffic/congestion will be on this site?
Gov’t Response: Six contractors will be concurrently working with start and completion dates varying.
Question 3:
Does this contractor have any responsibility for roadway maintenance of Access Road J? If so, how will that be measured and paid?
Gov’t Response The contractor does not have responsibility for the grading and potential addition of stone along Road J.
Question 4:
In regards to the clearing and grubbing of the future levee area: Is it the intent to clear from Right of Way to Right of Way or just in the limits of sand placement?
Gov’t Response: Limits of sand placement.
Question 5:
Please consider making all canal crossings part of the base bid. The clearing and grubbing of the base and options is under the base bid. We need to be able to access the optional work across the canals so we can clear.
Gov’t Response: This was considered. Contract remains unchanged.
Question 6:
Specification 32 15 00.00 12 paragraph 3.3 last sentence states that the surfacing will be measured and paid for. There is no bid item in the solicitation that covers the measurement and payment for surfacing.
Gov’t Response: Specification will be revised to no measurement for payment of such surfacing described therein.
Question 7:
Specification Section 01100- General Provisions Part 12 Project Benchmarks : Benchmark And Project Temporary Benchmarks (TBM). Field records of these benchmark verifications shall be submitted to the Contracting Officer's Representative in electronic format via RMS within 7 days after each verification has been completed. The differential levels must be to Second Order Class II closure standards, as defined in Appendix 4 of the afore mentioned Survey Standards, and as follows: closure error (in feet) must be less than or equal to 0.035 x √(distance in miles). Ties between the three “project controls” identified on the drawings and the Contractor utilized temporary benchmarks shall be performed at least every 6 months using differential leveling.
Field notes showing all data and the closure error shall be provided to the Government. Field records of these survey verifications shall be submitted in a survey report, which shall be updated with each periodic verification. A Registered Land Surveyor licensed in any of the 48 contiguous United States shall perform, sign, and seal the benchmark verification survey.
Would the USACE consider allowing us to use RTK GNSS methods to verify the benchmarks?
Gov’t Response: No.
Question 8:
Is the contractor prohibited from hauling sand or accessing the work going northeast from the Sand Stockpile on Access Road J?
Gov’t Response: The Contractor shall not travel further northeastward on J than is shown to access the sand stockpile. The entrance to the stockpile is shown on drawing C-011.
Question 9:
What are the gas main crossing limitations on Access Road J?
Gov’t Response: Refer to Specifications Section 01100 9(d).
Question 10:
Are contractor furnished scales required for the sand delivery from the Government stockpile?
Gov’t Response: Yes.
Question 11:
Are there any additional limitations or restrictions (other than no left turns) on the haul route from the Government stockpile to Frenier Road?
Gov’t Response: All specification requirements shall be followed. In addition, all publicly posted signs and restrictions shall be followed.
Question 12:
In light of continuing COVID concerns, how is the delivery of sand to be checked/assured at the site?
Gov’t Response: See Section 31 24 00.00 12, Paragraph 1.3.1.1
Question 13:
The sand stockpile area provided in Amendment 0002 for WSLP-SP2 as shown on Dwg. C-011 is part of the same sand stockpile area provided for WSLP-SP1 Site Preparation Contract 1. Is this correct as would be a conflict between the two (2) contracts?
Gov’t Response: The two contracts have separate apportions of the stockpile.
Question 14:
As there are multiple contractors hauling in materials to stockpile areas along Access Road J, who will be responsible for maintaining the access road including any cleaning or sweeping of Hwy. 61 at the entrance to the access road?
Gov’t Response: Maintenance of the rock roadway is shared amongst the existing Contractors using Access Road J. Sweeping and cleaning are as required in 01100.
Question 15:
USACE Response to Question 55 states that one Truck Wash Down Rack is sufficient. Is this correct as two (2) Wash Down Racks are shown on Dwg. C-003, one (1) on each side of Frenier Road as the road splits the project?
Gov’t Response: Prior response to question 55 is correct.
Question 16:
Section 01100- General Provisions, Item 4 requires the Contractor to furnish for the exclusive use of the Government employees, a temporary building conveniently located at the site of construction. Since there are inadequate utilities at the site of construction, can the building be located off of the project, but, at an approved location within a reasonable distance from the project?
Gov’t Response: Yes.
Question 17:
Section 31 11 00.00 Grubbing, just to clarify, the removal of sticks, branches and roots is in the Limit of Sand area only?
Gov’t Response: Yes.
Question 18:
Will the fallen debris outside of the Limit of Sand be required to be removed and if so to what extent?
Gov’t Response: No.
Question 19:
What will be required for traffic control plan at the sand stock pile since you are unable to make a left turn into the site and will have to travel to the next light to turn around for a right turn into the site?
Gov’t Response: All vehicles shall follow the requirements of the contract and publicly posted signs and restrictions.
Question 20:
In continuance of Amendment 2, Question 11, the placement of the government’s temporary trailer is to be within the right of way, based on the limits of the right of way, the trailer will need to be placed along Frenier Road, set off to the side. Additional sand fill, mats and gravel will be required to reclaim the marsh for the trailer compound. Will the modifications made for the tailer pad need to be removed once the project is completed?
Gov’t Response: Yes.
Question 21:
Will permits be required from St John Parish to install the subgrade and trailer?
Gov’t Response. The Contractor shall research any necessary permits.
Question 22:
Will the cubic yards of sand calculated by the Corp be furnished in the next Amendment and include the cubic yard to ton mulitplier?
Gov’t Response: No.
Question 23:
Will the Government require a full time superintendent, Safety and QC manager at the sand stockpile
Gov’t Response: No, separate personnel are not required both at the sand stockpile and the project site. The contract as a whole requires a Superintendent, QC Manager, and SSHO assigned to the project.
W912P8-22-B-0030 Project: West Shore Lake Pontchartrain,LA
Hurricane And Storm Damage Risk Reduction Report
WSLP-SP2
Site preparration Contract 2 St. John the Baptist Parish
Unit Estimated Item Description Quantity
0001 JOB N/A
0002 Channel Crossing JOB 1 (Contractor Design)
0004 Truck Wash-Down Rack EA 2
0005 Clearing and Grubbing AC 25.5
0007 Crushed Stone Pipeline Crossings JOB 1 Separtor Geotextile SY 671 Sand TONS 260 Crushed Stone TONS 525 Geogrid SY 607
0010 Channel Crossing JOB 1 (Contractor Design)
0012 Channel Crossing JOB 1 (Contractor Design)
JOB QTO PAGE 1 OF 1
Base Work
Mobilization and Demobilization
Optional 1
Optional 2
During the lifetime of this project, only one mobilization and demobilization will be required.
It is expressly understood that the accuracy of these estimates is in no wise warranted and that the furnishing of this information to a bidder will not relieve him/her of his/hers responsibility to estimate the quantities involved. It is further to be expressly understood in no case will such estimate be used as a basis of a claim against the Government.
W912P822B0030
SECTION 32 15 00.00 12
Page 5, paragraph 3.3. Delete this paragraph in its entirety, and substitute the following therefore:
“3.3 MAINTENANCE
The crushed stone surfacing shall be maintained by such shaping and addition of surfacing material as directed by the Contracting Officer to provide a usable and drivable road under all weather conditions during the construction period. No additional payment will be made for shaping operations. Additional surfacing materials required to repair any damages to the finished surfacing occasioned by the Contractor's construction operations will be at the Contractor’s expense.”
INSTRUCTION TO BIDDERS
Due to the response for COVID-19, most federal employees have been mandated to telework, and currently only authorized personnel are allowed access to the District buildings throughout USACE. As a result, we have implemented the below procedures for all current and future bid openings, until such restrictions have been lifted and normal access has resumed at the MVN HQ Building.
Electronic Submission of Bids:
MVN will utilize mail for receipt of electronic bids under IFB Solicitations. In order to submit an electronic bid please follow these steps:
Send an email containing your name, email address and proposal to BOTH the following Contracting Officer and Contract Specialist associated with the IFB:
Contracting Officer – Ms. Veronica Garner-Flint email: Veronica.Garner-Flint@usace.army.mil Contract Specialist – Ms. Cori Caimi, email: Cori.A.Caimi@usace.army.mil
Once the Contracting Officer or Contract Specialist receives your Proposal, you will then receive a confirmation email stating your Proposal was received.
The Bid Opening is currently scheduled for Tuesday, April 26, 2022 at 11:30 AM CST. The Contracting Officer and Contract Specialist will begin downloading bids at 11:00 AM CST, which is the bid receipt cutoff time. All bids received after 11:00 AM CST on Tuesday, April 26, 2022 will be considered late.
Audio Teleconference Bid Opening Information:
Bid Opening will be held on Tuesday, April 26, 2022 at 11:30 AM CST. Please use the following call-in information to attend the meeting:
1-877-226-8152
Access Code: 4218069
Following the conclusion of the bid opening, the Bid Abstract will be uploaded to SAM website under this solicitation, within 24 hours.