W912P820B0060-P00003.pdf
PDF 560 KB Posted
- Attached to
- Westshore Lake Pontchartrain Sand Stockpile
- Solicitation number
- W912P820B0060
About this file
This document provides details on a federal contract solicitation for sand stockpiling services. The United States Army Corps of Engineers, New Orleans District is soliciting bids to excavate approximately 750,000 cubic yards of sand material from the Bonnet Carre spillway, haul and stockpile the sand in the Highway 61 stockpile area. Additional requirements include clearing and grubbing vegetation from the stockpile area, constructing and maintaining crushed stone access roads, and other incidental work. Bids are due virtually with amendments providing clarification on questions from industry and adjusting the bid opening date. Pricing will be on a unit price basis for line items such as mobilization, borrow pit development, clearing and grubbing, silt fencing, sand stockpiling, culverts, and crushed stone surfacing, with optional items for additional surfacing and geotextile. The magnitude of work is estimated between $10-25 million.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912P820B0060 Bid Abstract SIGNED.pdf | ||
| W912P820B0060-P00005.pdf | ||
| W912P820B0060-P00004.pdf | ||
| W912P820B0060 Solicitation.pdf | ||
| W912P820B0060-P00002.pdf | ||
| W912P820B0060-P00001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
West Shore Lake Pontchartrain, Louisiana, Hurricane and Storm Damage Risk Reduction Project, Sand Stockpile Contract 1, St. Charles and St. John the Baptist Parishes, Louisiana (ED 20-028) has been amended to:
1. Provide the Government Response to Industry Questions.
2. Set date for submission of questions. Submit questions no later than 1 DEC 2020 at 5:00PM (CST), to the contract specialist, Cori A. Caimi, at Cori.A.Caimi@usace.army.mil.
3. A subsequent amendment w ill be forthcoming extending the bid opening date.
4. Engineering Changes
1. CONTRACT ID CODE PAGE OF PAGES
1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Nov-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P820B0060
X 9B. DATED (SEE ITEM 11)
14-Oct-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Nov-2020
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P820B0060
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00100 - INSTRUCTIONS TO BIDDERS
The following have been added by full text:
AMENDMENT 0003
Industry Question and Government Response for West Shore Lake Pontchartrain, Louisiana, Hurricane and Storm Damage Risk Reduction Project, Sand Stockpile Contract 1, St. Charles and St. John the Baptist Parishes, Louisiana (ED 20-028)
Q.1 The Quality Control section below states that this course is given by the USACE from time to time. Can you please provide a list of dates for the next scheduled classes?
3.4.4 Additional Requirement
In addition to the above experience and educational requirements, the CQC System Manager, and his/her alternate, shall have completed the course entitled "Construction Quality Management For Contractors" within the last 3 years. This course is periodically offered at the New Orleans District and other Corps of Engineers districts.
A.1 Government Response: A class is planned for the last week of February 2021, which already has a waiting list over 40 people. Email David.J.Martinez@usace.army.mil to add the names to the waiting list. Here is the link for classes.
https://www.mvd.usace.army.mil/Missions/Engineering-and-Construction-E- C/Construction-Quality-Management-CQM/
Q.2 Can the Government provide the approximate amount of sand available in each borrow pit?
A.2 Government Response: BP 1 = approx. 386,000 CY, BP 2 = approx. 40,000 CY, BP 3‐A =approx. 270,000 CY, BP 3‐B = approx. 333,000 CY, BP 6 = approx. 498,000 CY, and BP 7 =approx. 65,000 CY.
Q.3 Is it intended to utilize all 6 borrow pits provided?
A.3 Government Response: No.
Q.4 Is there an order of precedence in which the pits are to be utilized?
A.4 Government Response: Yes. See drawing C‐01, Note 2. Utilize Pit 7 last. In addition, each borrow pit that the contractor chooses to excavate must be fully excavated of sand as stated in the specifications. The contractor is not allowed to randomly remove a smaller quantity of sand from each of the available pits. The sum of all pits chosen by the contractor to excavate shall yield approximately 750,000 cubic yards of sand.
Q.5 At the stockpile location will any other contractors be utilizing this haul road?
A.5 Government Response: Yes.
Q.6 Please clarify‐ Spec Section 31 23 00; 3.1.1 states “All excavations shall be performed in an unwatered borrow pit”, and Spec Section 31 23 00; 3.1.2 states “The borrow area shall be drained and kept dry during excavation. Excavation will not be permitted in water nor shall excavated material be scraped, dragged or otherwise moved through water.”
A.6 Government Response: Excavation shall be performed in the dry, as described in the referenced specification sections.
Q.7 What are the current USACE estimated quantities for available sand in each of the pits, 1, 2, 3A, 3B, 6, and 7?
A.7 Government Response: See answers to question 1.
Q.8 Will the cane be harvested and roots burned by others at the stockpile site?
A.8 Government Response: The cane has been harvested. The roots will not be burned.
Q.9 There is no pay item for the base bid separator fabric and crushed stone for the Northeast and Southwest Entrances: will these be added?
A.9 Government Response: The separator fabric is included in the unit price for Bid Item 0006. An amendment will address the crushed stone.
Q.10 How wide is the Access Road easement on section A‐3 on sheet C‐06?
A.10 Government Response: About 40 feet wide at that section.
Q.11 Silt Fence will very likely not contain the stockpiled sand over time and rain events:
has the USACE considered concrete barrier? When will this contract no longer be responsible for the stockpile erosion control?
A.11 Government Response: No. We have not considered concrete barrier. The contractor will be responsible for silt fence maintenance until final acceptance of the project.
Q.12 General Note 14 on sheet G‐03 provides that the Contractor clean and remove all trash from ROW limits prior to contract completion: is this only the job limits, or does it include Airline Highway ROW?
A.12 Government Response: The contractor is required to clean all areas within the right‐of‐ way limits including Airline Highway (HWY 61). The truck wash‐down rack is an important feature that the contractor shall utilize for maintaining the cleanliness of the highway.
Q.13 General Note 16 on sheet G‐03 requires cleaning all drainage structures in ROW limits after completion: does this include Airline Highway?
A.13 Government Response: Yes.
Q.14 A note requires removing and stockpiling field culverts in the staging area: is this only cul‐ 07A?
A.14 Government Response: There is another culvert next to cul‐07A, and any other culverts found but not shown in the drawings.
Q.15 Since you have you to turn right off Hwy 628 onto Hwy 61, what will be the route, and what is the mileage to the stockpile?
A.15 Government Response: You are not allowed to turn right off of Hwy 628 onto Hwy
61. As shown on drawing C‐01, egress from the Bonnet Carre spillway onto Hwy 61 is from the levee ramp shown on the northeast side of the drawing. You will be making a right turn from the lower guide levee onto Hwy 61. The access routes outside of the spillway are further restricted to right turns only when entering and exiting the stockpile location off of Hwy 61. The routes and mileage shall be determined by consulting with your Traffic Engineer who will be developing your traffic control plan.
Q.16 Will there be another company using the stockpile road at the same time as the sand contractor?
A.16 Government Response: Yes
Q.17 Is there an area that power, water, and sewage will be available for the construction site trailer? If not, how would this be handled?
A.17 Government Response: The contractor shall visit the site and speak to the utility companies to determine the availability of power, water, sewage and internet. If these utilities are unavailable, a contractor supplied generator, water tank, sewage holding tank and cellular internet data will be necessary to comply with the specification requirements.
Q.18 Can all excavated material generated from item 0003 Clearing and Grubbing Stockpile Area 1 remain on site or will the contractor have to get dispose offsite?
A.18 Government Response: There is no excavation called for within specification section 31 11 00.00 12, Clearing and Grubbing. Disposal of cleared and grubbed materials is as prescribed within paragraph 3.4 of the same specification section.
Q.19 Plan sheet C‐01 is showing that ingress from 628 is apparently from Highway 61. Are we allowed left hand turns onto Highway 61 from the stockpile which contradicts specifications of previous project of clay stockpile
A.19 Government Response: No. Left hand turns are not allowed onto Hwy 61 from the stockpile.
ENGINEERING CHANGES
SPECIFICATIONS:
SECTION 00010
Page 00010-3 thru 5. Delete the Bidding Schedule in its entirety and substitute the attached revised Bidding Schedule, page 00010-3 thru 5.
SECTION 32 15 00.00 12
Page 3, paragraph 1.4 PAYMENT. Delete the 1st sentence in its entirety and substitute the revised sentence as follows:
“Payment for the surfacing material required for the access roads, including their maintenance with the limitations specified in paragraph “MAINTENANCE” will be made at the applicable contract unit price per cubic yard for “Surfacing” or “Surfacing-OW”, if Optional Work is exercised.”
SECTION 00010 – BIDDING SCHEDULE
West Shore Lake Pontchartrain, Louisiana, Hurricane and Storm Damage Risk Reduction Project, Sand Stockpile Contract 1, St. Charles & St. John the Baptist Parishes, Louisiana
Item DESCRIPTION Estimated Quantity
Unit Unit Price Estimated Amount
BASE WORK
0001 Mobilization and Demobilization 1 JOB
0002 Borrow Pit Development 1 JOB
Clearing and Grubbing Stockpile Area 1
1 JOB
0004 Silt Fence
0004AA First 4,450 LF 4,450 LF
0004AB All Over 4,450 LF 800 LF
0005 Sand Stockpile 750,000 CY
Corrugated Metal Pipe Culvert 12’’ Diameter
80 LF
*0007 Surfacing 53 CY
TOTAL BASE WORK: $
OPTIONAL WORK (OW)
0008 Surfacing-OW 8,000 CY
0009 Separator Geotextile-OW 23,000 SY
TOTAL OPTIONAL WORK $
TOTAL BASE WORK + OPTIONAL WORK $
* Denoted change from previous Bidding Schedule.
**The unit "JOB" as used in this Bidding Schedule is synonymous with the term "Lump Sum" used elsewhere within these plans and specifications.
Award will be made as a whole to one bidder.
NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A
BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED TOTAL OR ESTIMATED AMOUNT
FOR ANY ITEM, ITS BID SHALL BE DECLARED NON-RESPONSIVE AND THEREFORE
INELIGIBLE FOR AWARD.
NOTE 2: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or sub line items are materially unbalanced (See FAR 14.404-2, Rejection of Individual Bids).
NOTE 3: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442.
The NTP will be issued immediately after verification of acceptable performance and payment bonds.
Within ten (10) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Plan, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.
NOTE 4: RAPID VENDOR PAYMENT: Web based instructions for the submission of invoices;
http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx
NOTE 5: OPTIONAL WORK ITEMS. The Government may require the delivery of the numbered line item(s), identified in the schedule as OPTIONAL WORK Items, in the quantities and prices stated in the schedule. The Contracting Officer may exercise the OPTIONAL WORK Items by written notice to the Contractor. Bidders shall bid on all items including optional items (see “Evaluation of Options” FAR 52.217-5). Failure to bid on all items will result in a non-responsive bid.
NOTE 6: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for this basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
NOTE 7: TIME ADJUSTMENT IN THE EVENT OF THE EXERCISE OF OPTIONAL WORK. In the event that CLINS 0008 and 0009 are exercised under the terms of the contract, no additional calendar days shall be added to the time required for completion of the contract original duration of 400 calendar days established for the BASE WORK items specified in the Contract Clause entitled
“COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52-211-10 – APR
1984)”.
NOTE 8: The Government will determine the total quantity to be acquired for any unit priced item under either the base or option CLINs.
EVALUATION OF SUBLINE ITEMS (Dec 2019 - AFARS 5152.211-9000).
Item No. 0004 is subdivided into two or more estimated quantities and is to be separately priced. The Government will evaluate the item on the basis of total price of its subline items.
(End of Clause)
VARIATIONS IN ESTIMATED QUANTITIES - SUBLINE ITEMS (Dec 2019 –
AFARS 5152.211-9001).
This variation in estimated quantities clause is applicable only to item No. 0004.
(a) Variation from the estimated quantity in the actual work performed under any second or subsequent subline item or elimination of all work under such a second or subsequent subline item will not be the basis for an adjustment in contract unit price.
(b) Where the actual quantity of work performed for item No. 0004 is less than 85% of the quantity of the first subline item listed under such item, the Contractor will be paid at the contract unit price for that subline item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the clause at Federal Acquisition Regulation (FAR) 52.211-18, VARIATION IN ESTIMATED QUANTITY.
(c) If the actual quantity of work performed under item No. 0004 exceeds 115% or is less than 85% of the total estimated quantity of the subline item under that item and/or if the quantity of the work performed under the second subline item or any subsequent subline item under item Nos. NONE exceeds 115% or is less than 85% of the estimated quantity of any such subline item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, VARIATION
IN ESTIMATED QUANTITY.
(End of Clause)
SECTION SF 30 - SF 30 CONTINUATION
The following have been deleted:
SUMMARY OF CHANGES
(End of Summary of Changes)