ABSTRACT OF BIDS - CONSTRUCTION CEMVN-ED-C page 1 of 1 BID NO. 1 of 4 BID NO. 2 of 4 BID NO. 3 of 4 BID NO. 4 of 4 For: Maintenance Dredging FY18, Mile 5.0 to

Mile 17.0, Including Beneficial Use within Sabine Date Opened: 11-Sep-18 National Wildlife Refuge and Devil's Elbow Calcasieu and Cameron Parishes, LA

Item Description of Bid Item Estimated Unit Unit Price Estimated Unit Price Estimated Unit Price Estimated Unit Price Estimated Unit Price Estimated No. Quantity Cost Cost Cost Cost Cost

Number of Amendments: 0003 0001 Mobilization and Demobilization 1 JOB $1,916,000.00 $1,916,000.00 $800,000.00 $800,000.00 $5,750,000.00 $5,750,000.00 $3,750,000.00 $3,750,000.00 $4,650,000.00 $4,650,000.00

0002 Dredging - Mile 14.0 to Mile 17.0 0002AA First 830,000 Cubic Yards 830,000 CY $2.92 $2,423,600.00 $2.50 $2,075,000.00 $4.25 $3,527,500.00 $4.15 $3,444,500.00 $2.50 $2,075,000.00 0002AB All Over 830,000 Cubic Yards 120,000 CY $2.66 $319,200.00 $2.50 $300,000.00 $3.25 $390,000.00 $4.15 $498,000.00 $1.00 $120,000.00

0003 Dredging - Mile 5.5 to Mile 6.5 0003AA First 110,000 Cubic Yards 110,000 CY $6.07 $667,700.00 $3.90 $429,000.00 $7.25 $797,500.00 $5.50 $605,000.00 $7.00 $770,000.00 0003AB All Over 110,000 Cubic Yards 30,000 CY $4.50 $135,000.00 $4.00 $120,000.00 $6.00 $180,000.00 $5.50 $165,000.00 $1.00 $30,000.00

0004 Dike Construction - Mile 5.5 to 6.5 1 JOB $991,000.00 $991,000.00 $700,000.00 $700,000.00 $500,000.00 $500,000.00 $1,300,000.00 $1,300,000.00 $1,000,000.00 $1,000,000.00 Mile 14.0 to Mile 17.0

0005 Dredging - Devil's Elbow 0005AA First 800,000 Cubic Yards 800,000 CY $3.40 $2,720,000.00 $2.70 $2,160,000.00 $3.50 $2,800,000.00 $2.90 $2,320,000.00 $5.00 $4,000,000.00 0005AB All Over 800,000 Cubic Yards 300,000 CY $2.58 $774,000.00 $2.70 $810,000.00 $3.25 $975,000.00 $2.90 $870,000.00 $5.00 $1,500,000.00

0006 Dike Construction - Devil's Elbow 1 JOB $554,000.00 $554,000.00 $425,000.00 $425,000.00 $950,000.00 $950,000.00 $1,075,000.00 $1,075,000.00 $1,000,000.00 $1,000,000.00

0007 Aerial Photography Documentation 1 JOB $5,800.00 $5,800.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $50,000.00 $50,000.00 $32,000.00 $32,000.00

0011 Dredging - Mile 6.5 to Mile 14.0 0011AA First 1,300,000 Cubic Yards 1,300,000 CY $5.07 $6,591,000.00 $2.80 $3,640,000.00 $5.50 $7,150,000.00 $3.90 $5,070,000.00 $3.50 $4,550,000.00 0011AB All Over 1,300,000 Cubic Yards 210,000 CY $4.54 $953,400.00 $2.80 $588,000.00 $4.00 $840,000.00 $3.90 $819,000.00 $1.00 $210,000.00

0012 Dike Construction - Mile 6.5 to Mile 14.0 1 JOB $824,000.00 $824,000.00 $400,000.00 $400,000.00 $225,000.00 $225,000.00 $460,000.00 $460,000.00 $375,000.00 $375,000.00

Dredging - Calcasieu River Mile 5.0 - Mile 17.0

Contract Specialist: Jenifer Bordelon

Mike Hooks, Inc., 409 Mike Hooks Rd

Westlake, LA

Weeks Marine Innwoods Business Park

304 Gaille Drive Covington, LA 70433

Manson Constuction, 5985 Richard Street,Suite 1

Jacksonville, FL 32216

Orion Marine 1112 Broadway St, Port Lavaca, TX 77979

W912P8-18-B-0022

$15,177,000.00

GOVERNMENT ESTIMATE

Alternative 2

TOTAL BASE WORK: $10,506,300.00 $7,829,000.00 $15,880,000.00 $14,077,500.00

ALTERNATIVE 2 - PLACEMENT OF MATERIAL WITHIN CDF'S

TOTAL ALTERNATIVE 2: $8,368,400.00 $4,628,000.00 $8,215,000.00 $6,349,000.00 $5,135,000.00

Signature Melissa K. Koehn

ABSTRACT OF BIDS - CONSTRUCTION CEMVN-ED-C page 1 of 1 BID NO. 1 of 4 BID NO. 2 of 4 BID NO. 3 of 4 BID NO. 4 of 4 For: Maintenance Dredging FY18, Mile 5.0 to

Mile 17.0, Including Beneficial Use within Sabine Date Opened:

National Wildlife Refuge and Devil's Elbow Calcasieu and Cameron Parishes, LA

Item Description of Bid Item Estimated Unit Unit Price Estimated Unit Price Estimated Unit Price Estimated Unit Price Estimated Unit Price Estimated No. Quantity Cost Cost Cost Cost Cost

0013 Bird Nesting Prevention and 80 DAYS $1,562.00 $124,960.00 $100.00 $8,000.00 $100.00 $8,000.00 $850.00 $68,000.00 $400.00 $32,000.00 Avoidance Measures - OW

0014 Spill Box Removal and Replacement - OW 4 EACH $441,000.00 $1,764,000.00 $400,000.00 $1,600,000.00 $600,000.00 $2,400,000.00 $660,000.00 $2,640,000.00 $700,000.00 $2,800,000.00

0015 Ditching/Drainging CDF - 12B - OW 26,439 LF $35.00 $925,365.00 $30.00 $793,170.00 $35.00 $925,365.00 $44.00 $1,163,316.00 $55.00 $1,454,145.00

0016 Ditching/Drainging CDF - 13 - OW 33,716 LF $35.00 $1,180,060.00 $26.00 $876,616.00 $35.00 $1,180,060.00 $34.50 $1,163,202.00 $45.00 $1,517,220.00

0017 Ditching/Drainging CD F- 17 - OW 22,121 LF $35.00 $774,235.00 $18.00 $398,178.00 $25.00 $553,025.00 $26.00 $575,146.00 $27.00 $597,267.00

0018 Ditching/Drainging CDF - 22 - OW 19,400 LF $35.00 $679,000.00 $30.00 $582,000.00 $25.00 $485,000.00 $65.25 $1,265,850.00 $69.00 $1,338,600.00

0019 Ditching/Drainging CDF- H - OW 13,978 LF $35.00 $489,230.00 $18.00 $251,604.00 $25.00 $349,450.00 $26.00 $363,428.00 $27.00 $377,406.00

TOTAL $24,811,550.00 $16,966,568.00 $29,995,900.00 $27,665,442.00 $28,428,638.00

Dredging - Calcasieu River Mile 5.0 - Mile 17.0 MAXIMUM $31,014,437.50 -31.62% 20.89% 11.50% 14.58%

Mike Hooks Weeks Marine Manson Constuction Orion Marine Westlake, LA Covington, LA Jacksonville, FL Port Lavaca, TX

OPTION WORK

TOTAL OPTION WORK: $5,936,850.00 $4,509,568.00 $5,900,900.00 $7,238,942.00 $8,116,638.00

GOVERNMENT ESTIMATE

Alternative 2

2018-09-14T13:27:34-0500
KOEHN.MELISSA.KEELER.1243845870