W42HEM60958961
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The above numbered solicitation for Electricial Equipment and Repair Maintenance for the Dredge Wheeler, New Orleans, Louisiana is hereby amended as follow s:
1. Delete Initial Section B in its entirety - Supplies or Services and Prices, items nos. 1000-1009, 2000-2009, 3000-3009, 4000-4009, and 5000-5009
2. Replace w ith attached Section B - Suppies or Services and Prices, item nos. 1000-1009, 2000-2009, 3000-3009, 4000-4009, and 5000-5009.
3. All others remains unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Jun-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P8-16-R-0038
X 9B. DATED (SEE ITEM 11)
15-Jun-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Jun-2016
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1000 1
FFP - BASE YEAR
SEE ATTACHED SOW
FOB: Destination
1001 120 Hours
FFP - FOREMAN, ELECTRICAL; S.T.
1002 30 Hours
FOREMAN, ELECTRICAL; O.T.
1003 120 Hours
FFP - ENGINEER, ELECTRICAL; S.T.
1004 30 Hours
FFP - ENGINEER, ELECTRICAL; O.T.
1005 6480 Hours
FFP - ELECTRICIAN; S.T.
1006 1620 Hours
FFP - ELECTRICIAN; O.T.
1007 1 Lot $100,000.00
FFP - MATERIALS/PARTS/CONSUMABLES
SUB CONTRACTORS & SUPPLIES,
INSERT % MARK-UP ON ESTIMATED
UNIT PRICE OF $100,000 AND EXTEND TOTAL
1008 10000 Miles
FFP - TRANSPORTATION OF PERSONNEL
1009 1 Lot $5,000.00
FFP - MEALS AND LODGING
NOTE: THIS LINE ITEM IS NON-COMPETITIVE
INSERT THE GIVEN AMOUNT ON THE
BLANK BID SCHEDULE
BASE YEAR GRAND TOTAL: ________________________
OPTION FFP - OPTION YEAR ONE (1)
2001 120 Hours
OPTION
2002 30 Hours
FFP - FOREMAN, ELECTRICAL; O.T.
2003 120 Hours
2004 30 Hours
2005 6480 Hours
2006 1620 Hours
2007 1 Lot $100,000.00
OPTION
FFP - MATERIALS/PARTS/CONSUMABLES
SUB CONTRACTORS & SUPPLIES,
INSERT % MARK-UP ON ESTIMATED
2008 10000 Miles
OPTION
2009 1 Lot $5,000.00
OPTION
FFP - MEALS AND LODGING
NOTE: THIS LINE ITEM IS NON-COMPETITIVE
INSERT THE GIVEN AMOUNT ON THE
OPTION YEAR 1 GRAND TOTAL: ________________________
OPTION FFP - OPTION YEAR TWO (2)
3001 120 Hours
FFP – FOREMAN, ELECTRICAL; S.T.
3002 30 Hours
3003 120 Hours
3004 30 Hours
3005 6480 Hours
3006 1620 Hours
1 Lot
$100,000.00
FFP - MATERIALS/PARTS/CONSUMABLES
SUB CONTRACTORS & SUPPLIES,
INSERT % MARK-UP ON ESTIMATED
3008 10000 Miles
3009 1 Lot $5,000.00
FFP - MEALS AND LODGING
INSERT THE GIVEN AMOUNT ON THE
OPTION YEAR 2 GRAND TOTAL: ________________________
OPTION FFP - OPTION YEAR THREE (3)
4001 120 Hours
4002 30 Hours
4003 120 Hours
4004 30 Hours
4005 6480 Hours
FFP – ELECTRICIAN; S.T.
4006 1620 Hours
1 Lot $100,000.00
OPTION FFP - MATERIALS/PARTS/CONSUMABLES
SUB CONTRACTORS & SUPPLIES,
INSERT % MARK-UP ON ESTIMATED
4008 10000 Miles
FFP – TRANSPORTATION OF PERSONNEL
1 Lot $5,000.00
OPTION FFP - MEALS AND LODGING
NOTE: THIS LINE ITEM IS NON-COMPETITIVE
INSERT THE GIVEN AMOUNT ON THE
OPTION YEAR 3 GRAND TOTAL: ________________________
OPTION FFP - OPTION YEAR FOUR (4)
5001 120 Hours
5002 30 Hours
5003 120 Hours
5004 30 Hours
5005 6480 Hours
5006 1620 Hours
5007 1 Lot $100,000.00
FFP - MATERIALS/PARTS/CONSUMABLES
SUB CONTRACTORS & SUPPLIES,
INSERT % MARK-UP ON ESTIMATED
5008 10000 Miles
FFP – TRANSPORTATION OF PERSONNEL
5009 1 Lot $5,000.00
FFP – MEALS AND LODGING
INSERT THE GIVEN AMOUNT ON THE
OPTION YEAR 4 GRAND TOTAL: ________________________
| Bid Schedule W912P8-16-R-0038.pdf |
| C-1. GENERAL INFORMATION |
| C-2. SPECIFIC TASKS |
| C-3. REQUIREMENTS/PERFORMANCE STANDARDS |
| C-4. CONTRACTOR FURNISHED PROPERTY |
| C-5. GOVERNMENT FURNISHED PROPERTY AND SERVICES |
| SAFE CLEARANCE LOG |
| HAZARDOUS ENERGY CONTROL PROGRAM, US DREDGE WHEELER |