AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

06/02/2014

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 307

0001 Jun 2, 2014 ED-06-098

U.S. Army Corps of Engineer District, New Orleans Attn: CEMVN-CT-E 7400 Leake Avenue, Room 172 New Orleans, LA 70118

W912P8-12-R-0027

May 22, 2014

The above numbered solicitation for Southeast Louisiana Urban Flood Control Project (SELA 20), Widening of Florida Avenue Canal (Phase II), and Widening of Florida Avenue Canal (Phase III), Orleans Parish, LA; ED 06-098 (W912P8-12-R-0027) is hereby amended as follows: (See Continuation Pages)

You are reminded that the deadline to submit questions regarding this solicitation is June 12, 2014, 11:00 AM CST. Any questions submitted after this deadline will not be considered.

THE PROPOSAL DUE DATE OF 24 June 2014, 11:00 AM LOCAL TIME REMAINS UNCHANGED.

Michelle R. Dalmado

SECTION 00010

Delete pages 00010-3 thru 9 in their entirety and substitute the attached revised pages 00010-3 thru 9 therefore.

SECTION 01100

Delete this section in its entirety and substitute the attached revised Section 01100 therefore.

SECTION 02081

Delete this section in its entirety and substitute the attached revised Section 02081 therefore.

SECTION 02252

Add the attached LEGEND AND NOTES FOR LOG OF BORING AND TEST RESULTS to the end of this section.

SECTION 02320

Delete this section in its entirety and substitute the attached revised Section 02320 therefore.

SECTION 02510

Delete this section in its entirety and substitute the attached revised Section 02510 therefore.

SECTION 02531

Delete this section in its entirety and substitute the attached revised Section 02531 therefore.

SECTION 02538

Delete this section in its entirety and substitute the attached revised Section 02538 therefore.

SECTION 02630

Delete this section in its entirety and substitute the attached revised Section 02630 therefore.

SECTION 02845

Delete this section in its entirety and substitute the attached revised Section 02845 therefore.

SECTION 03310

Delete this section in its entirety and substitute the attached revised Section 03310 therefore.

SECTION 09940

Delete this section in its entirety and substitute the attached revised Section 09940 therefore.

00010-3 Ed 06-098

SECTION 00010 – BIDDING SCHEDULE

Southeast Louisiana Urban Flood Control Project, Widening of Florida Avenue Canal, (Phase II), (From Piety Street to Mazant Street), and Widening of Florida Avenue Canal (Phase III) (From St. Ferdinand Street to Piety Street), Orleans Parish, Louisiana

Item DESCRIPTION Estimated Quantity

Unit Unit Price Estimated Amount

BASE

0001 Mobilization and Demobilization 1 JOB

0002 Railroad Insurance 1 JOB

0003 Flagging Service 1 JOB

Entergy Transmission Power Outages

0004AA First 40 Outages 40 EA $2,625.00 $105,000.00

0004AB All Over 40 Outages 40 EA $2,625.00 $105,000.00

0005 Erosion Control 1 JOB

Portland Cement Concrete Pavement (9" Thick)

21,952 SY

Portland Cement Concrete Pavement (8" Thick)

2,200 SY

0008 Concrete Driveway (6" Thick) 1,604 SY

0009 Concrete Driveway (8" Thick) 322 SY

0010 Concrete Sidewalk (4" Thick) 2,600 SY

0011 Sidewalk at Intersection 689 SY

Incidental Concrete Pavement (4" Thick)

50.0 SY

0013 Base Course (8” Thick) 5,697 CY

Integral Concrete Curb (Barrier Type)

7,100 LF

Integral Concrete Curb (Mountable Type)

7,300 LF

Combination Concrete Curb and Gutter Bottom (Barrier Type)

LF

Combination Concrete Curb and Gutter Bottom (Mountable Type)

LF

Asphaltic Concrete – Wearing Course

116 TON

Asphaltic Concrete – Binder Course

290 TON

0020 Geotextile Fabric 24,000 SY

00010-4 Ed 06-098

0021 Geogrid 24,000 SY

Plastic Pavement Striping and Raised Pavement Markers

1 JOB

Removal of Existing Pavement (Concrete with Asphalt Overlay)

24,152 SY

Removal of Existing Sidewalks and Drives

5,000 SY

0025 Removal of Existing Curbing 14,846 LF

Temporary Roadway Patching (Full Depth Asphalt)

2,800 SY

Temporary Traffic Maintenance Aggregate

1,000 CY

Maintenance and Diversion of Storm Water

1 JOB

Temporary Dam Emergency Removal and Reconstruction

0029AA First 30 Occurrences 30 EA

0029AB All Over 30 Occurrences 10 EA

Removal and Disposal of 20” or 30” Diameter Steel Bituminous Asbestos Coated Sewer and Waterline

237 LF

0031 Demolition 1 JOB

0032 Clearing and Grubbing 1 JOB

Construction Dewatering (Florida Ave. Canal)"

1 JOB

Construction Dewatering (48” Dia. Waterline)

1 JOB

Temporary Retaining Structure (Florida Ave. Canal)

1 JOB

Temporary Retaining Structure (48” Water Line)

1 JOB

Retaining Structure (Side Street Drainage Culverts)

1 JOB

Construction Unwatering (Side Streets)

1 JOB

Furnish and Drive Steel H-Piling (HP 14 x 73)

24,440 LF

0040 Structural Excavation and Backfill 1 JOB

0041 Foundation Jet Grouting 1 JOB

0042 Furnish and Drive Timber Piles 411,327 LF

Pre-Cast Concrete Piles (14” X 14”)

526 LF

Cast-in-Place Revetment Concrete

4,950 SY

00010-5 Ed 06-098

8" Diameter Ductile Iron Waterline Crossing

133 LF

0046 30" Diameter Steel Waterline 130 LF

0047 48" Diameter Steel Waterline 2,049 LF

Welded Access Manhole For Steel Pipe

2 EA

Manhole Over Access Portal in Steel Pipe

2 EA

0050 30” Gate Valve and Manhole 1 EA

0051 48” Gate Valve and Manhole 1 EA

Abandon 48” Diameter Steel Waterline

1,978 LF

20" Diameter Ductile Iron Sewer Force Main Crossing

115 LF

0054 20” Gate Valve and Manhole 1 EA

0055 12” Diameter RCP 205 LF

0056 15” Diameter RCP 1,108 LF

0057 18” Diameter RCP 294 LF

0058 24” Diameter RCP 53 LF

0059 30” Diameter RCP 12 LF

0060 36” Diameter RCP 42 LF

0061 42” Diameter RCP 100 LF

0062 48” Diameter RCP 68 LF

0063 54” Diameter RCP 10 LF

0064 60” Diameter RCP 32 LF

0065 18” x 28” RCPA 48 LF

0066 22” x 36” RCPA 151 LF

0067 26” x 43” RCPA 6 LF

0068 31” x 51” RCPA 145 LF

0069 40” x 65” RCPA 51 LF

0070 Single Mountable Catch Basin 12 EA

0071 Double Mountable Catch Basin 2 EA

No. 1 Standard Single CatchBasin

5 EA

0073 15” x 12” RC Wye 20 EA

00010-6 Ed 06-098

0074 18” x 12” RC Wye 2 EA

0075 Drain Manhole (No. 1 Standard) 15 EA

0076 Drain Manhole (No. 2 Standard) 2 EA

0077 Drain Manhole (No. 3 Standard) 5 EA

Standard Manholes For Large Concrete Arch Pipe

5 EA

Standard Manhole For Large Circular Pipe Greater Than 36 Inch

9 EA

24”x30” Clear Opening Drop Inlet Catch Basin

8 EA

Adjusting Existing Manhole (Water, Sewer, or Drain)

0081AA First 12 Adjustments 12 EA

0081AB All Over 12 Adjustments 12 EA

0082 Adjusting Catch Basin/Drop Inlet 30 EA

0083 Blocked Out Guard Rail 3,395 LF

Guard Rail End Treatment (Flared)

4 EA

0085 Chain Link Fence 3,850 LF

0086 Swing Gates 2 EA

0087 Fence Fans 6 EA

0088 Traffic Control 1 JOB

Relocation of Existing Traffic Signals

1 JOB

0090 Fertilizing, Seeding and Mulching 18 AC

0091 Florida Avenue Drainage Canal 3,579 LF

Box Culvert and Tie-In (Florida Avenue Canal)

810 LF

Box Culvert and Tie-In (Desire Street)

945 LF

0094 Box Culvert Tie-In (Alvar Street) 65 LF

Box Culvert and Tie-In (Montegut Street)

582 LF

0096 Box Culvert Tie-In (Louisa Street) 23 LF

0097 Box Culvert Tie-In (Block 4) 1 JOB

Temporary Bypass of S&WB Electrical Feeders #410 & #510

1 JOB

Relocation of S&WB Aerial Electrical Feeder #20

1 JOB

00010-7 Ed 06-098

S&WB Standard Electrical Manhole

11 EA

S&WB Electrical Feeder Duct Bank

1,945 LF

Removal and Replacement of S&WB Power Poles

1 JOB

0103 Street Lighting 1 JOB

TOTAL BASE: $

OPTIONAL WORK

0104 8" Diameter PVC Waterline 5,000 LF

8” Diameter Ductile Iron Waterline

200 LF

12" Diameter Ductile Iron Waterline

100 LF

0107 12" Diameter PVC Waterline 150 LF

0108 Fire Hydrant 18 EA

0109 8” Gate Valve and Manhole 14 EA

Replace 1” and Smaller Water House Connection with 1” Service

141 EA

Replace 1-½” Water House Connection

6 EA

Replace 2” Water House Connection

1 EA

8” Diameter PVC Gravity Sewer Line

2,471 LF

0114 Sewer Manholes 17 EA

Remove and Replace Sewer House Connection

128 EA

TOTAL OPTIONAL WORK: $

TOTAL BASE + OPTIONAL WORK: $

Award will be made as a whole to one bidder.

NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED

TOTAL OR ESTIMATED AMOUNT FOR ANY ITEM, ITS BID SHALL BE

DECLARED NON-RESPONSIVE AND THEREFORE INELIGIBLE FOR

AWARD.

00010-8 Ed 06-098

NOTE 2: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or sub line items are materially unbalanced (See FAR 14.404-2).

NOTE 3: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Program, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.

NOTE 4: OPTIONAL WORK ITEMS. The Government may require the delivery of the numbered line item(s), identified in the schedule as Optional Work items, in the quantities and prices stated in the schedule. The Contracting Officer may exercise the Optional Work by written notice to the Contractor. The Government will exercise the Optional Work no sooner than 300 calendar days and or no later than 550 calendar days after award of this contract. Bidders shall bid on all items including Optional Work items (see “Evaluation of Options” FAR 52.217-5).

Failure to bid on all items will result in a non-responsive bid.

NOTE 5: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). The Government will evaluate offers for award purposes by adding the total price for all options to the total price for this basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

NOTE 6: TIME ADJUSTMENT IN THE EVENT OF THE EXERCISE OF

OPTIONAL WORK. In the event that OPTIONAL WORK items are exercised under the terms of the contract, the time required for completion of the contract will not be adjusted but shall be performed concurrent with original contract duration of 1,900 calendar days established for the BASE WORK items specified in the Contract Clause entitled “COMMENCEMENT, PROSECUTION, AND

COMPLETION OF WORK (FAR 52.211-10 - APR 1984)”.

00010-9 Ed 06-098

EVALUATION OF SUBDIVIDED ITEMS..

Item Nos. 0004, 0029, and 0081 is subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its sub-items.

(End of Clause)

VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS..

The Variations in Estimated Quantities Subdivided Items clause is applicable only in Item Nos. 0004, 0029, and 0081.

a. Variations from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in contract unit price.

b. Where the actual quantity of work performed for Item Nos. 0004, 0029, and 0081 is less than 85% of the quantity of the first sub-item listed under such items, the Contractor will be paid at the contract unit price for that sub-item for the actual quantity of work performed and, in addition, an equitable adjustment in contract price shall be made in accordance with the clause FAR 52.211-18, Variation in Estimated Quantity .

c. If the quantity of work performed under Item Nos. 0004, 0029, and 0081 exceeds 115% or is less than 85% of the total estimated quantity of the sub-items under that item, and/or if the quantity of work performed under the second sub-item or any subsequent sub-item under Item No. NONE exceeds 115% or is less than 85% of the estimated quantity of any such sub-item, and if such variation causes an increase or a decrease in the time required for performance of this contract, the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, Variation in Estimated Quantity.

(End of Clause)

01100-a Ed 06-098

Section Table of Contents

SECTION 01100 - GENERAL PROVISIONS

1. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER 1

2. DAMAGE TO WORK 2

3. SAFETY PROVISIONS 2

4. INSPECTOR'S FIELD OFFICE 6

5. PROJECT SIGN 9

6. RIGHTS-OF-WAY 9

7. CERTIFICATES OF COMPLIANCE 10

8. ENVIRONMENTAL LITIGATION 10

9. UTILITIES AND IMPROVEMENTS 11

10. PERMISSIBLE HOURS OF WORK 11

11. U.S ARMY CORPS OF ENGINEERS CRD-C STANDARDS 12

12. AGGREGATE SOURCES 12

13. STONE SOURCES 14

14. FORMAT OF SURVEYS 16

15. PROJECT BENCHMARKS 17

16. REQUIRED INSURANCE (RAILROADS) 18

17. WORK ON OR ADJACENT TO RAILROAD 19

18. COMMERCIAL WARRANTY 23

19. ACCESS PLAN 23

20. VIBRATION MONITORING 23

21. VIDEO AND PHOTOGRAPHIC DOCUMENTATION 23

22. UNWATERING OF CONSTRUCTION SITE 24

23. COORDINATION OF WORK WITH S&WB FEEDER OUTAGES 24

24. MONITORING BEFORE AND DURING CONSTRUCTION 26

25. ENTERGY OVERHEAD HIGH VOLTAGE TRANSMISSION LINES 28

26. COORDINATION OF WORK 29

27. NORMAL OPERATION OF STORM WATER DRAINAGE SYSTEM 33

28. FLOODING REQUIREMENTS 34

29. EVACUATION REQUIREMENTS 34

30. PUBLIC CONVENIENCE 34

31. GENERAL LIMITATIONS 35

32. SEWER FORCE MAIN CHANGE-OVER 35

33 SERVICE INTERRUPTION TO THE EXISTING WATERLINE SERVICE. 36

34. VERIFICATION OF EXISTING GRADES 37

35. ADVERTISEMENT OF TRAFFIC DETOURING PLAN 37

36. DUST CONTROL 37

37. OPERATIONS AND MATERIAL STORAGE AREA 37

38. SUGGESTED ORDER OF WORK 38

39. OPTIONAL WORK ITEMS 38

01100-1 Ed 06-098

SECTION 01100 - GENERAL PROVISIONS

1. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

(a) This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the Contract Clause in Section 00700, entitled Default (Fixed Price Construction) (FAR 52.249-10). In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied.

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

(b) The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) for temperature, precipitation and wet ground conditions or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities. Also considered in the chart below was wind, fog, high or low tides, etc.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS

BASED ON (5) DAY WORK WEEK

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

14 8 7 4 4 8 7 6 6 4 8 13

(c) Upon receipt of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.

(d) The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), and shall be calculated chronologically from the first to the last day of each month, and shall be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in

01100-2 Ed 06-098 paragraph b, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clause in Section 00700, entitled Default (Fixed Price Construction) (FAR 52.249-10).

2. DAMAGE TO WORK

(a) The responsibility for damage to any part of the permanent work shall be as set forth in the Contract Clause in Section 00700, entitled Permits and Responsibilities (FAR 52.236-7). However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit price or job prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there is no contract unit or job prices applicable to any part of such work, an equitable adjustment shall be made pursuant to the Contract Clause in Section 00700, entitled Changes (FAR 52.243-4). Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

(b) All costs associated with flooding of the dewatered areas, including flooding as directed by the Contracting Officer’s Representative, shall be included in the Contract unit price per each for “Temporary Dam Emergency Removal and Reconstruction” as specified in Section 01568 MAINTENANCE AND

DIVERSION OF STORM WATER.

3. SAFETY PROVISIONS

The safety provisions as specified herein refer to the Sept 2008 edition of EM 385-1-

1. The current document can be found at EM 385-1-1 USACE Safety Manual.

(a) Accident Reporting and Recordkeeping. Refer to EM 385- 1-1, Section 01.D.

Reports shall be submitted on ENG Form 3394. Accidents shall be investigated and reports completed by the immediate supervisor of the employee(s) involved and reported to the Contracting Officer or his/her representative within one working day after the accident occurs. All data reported must be complete, timely and accurate. A follow-up report shall be submitted when the estimated lost time days differs from the actual lost time days.

(b) Accident Prevention Program (APP). (See the Contract Clause in Section 00700, entitled Accident Prevention (FAR 52.236-13).) Within 15 days after receipt of Notice of Award of the contract, and at least 7 days prior to the prework http://publications.usace.army.mil/publications/eng-manuals/EM_385-1-1_languages/EM_385-1-1_English_2008/toc.html

01100-3 Ed 06-098 conference, four copies of the Accident Prevention Program shall be submitted to the Contracting Officer for review and acceptance. The program shall be prepared in the following format:

(1) Executed MVN Form 385-43 (Latest Edition), Accident Prevention Program Administrative Plan (available upon request), see Appendix A of

EM 385-1-1.

(2) Executed MVN 385-43/1 (Latest Edition), Accident Prevention Plan Checklist and MVN Form 385-43/2 (Latest Edition), Activity Hazard Analysis (available upon request), see Figure 1-1 of EM 385-1-1.

(3) A copy of company policy statement regarding accident prevention.

The Contractor shall have on the construction site during working hours a trained Site Safety and Health Officer (SSHO) in accordance with paragraph 01.A.17 of EM 385-1-1. The Contractor’s trained SSHO will be required to have completed a 30 hour OSHA Construction Safety Course or equivalent, within 3 years of his assignment as SSHO on the project, and the SSHO is required to be on-duty at all times when work is being performed. The Contractor shall not commence physical work at the site until his program has been accepted by the Contracting Officer, or his/her authorized representative. At the Contracting Officer's discretion, the Contractor may submit its Activity Hazard Analysis only for the first phase of construction provided that it is accompanied by an outline of the remaining phases of construction. All remaining phases shall be submitted and accepted prior to the beginning of work in each phase. Also refer to Section 1 of

EM 385-1-1.

(c) Comprehensive Hazard Communication Program. The Contractor shall develop, implement, and maintain at the workplace a written, Comprehensive Hazard Communication Program (see Section 06.B.01 of EM 385-1-1) that includes identification of potential hazards as prescribed in 29 CFR Part

1910.1200 and/or 1926.59, effects of exposure and control measures to be used for chemical products and physical agents that may be encountered during the performance of work on this contract, provisions for container labeling, Material Safety Data Sheets, and employee training program, and other criteria in accordance with 29 CFR Part 1910.1200 and/or 1926.59. Training shall include communication methods and systems to be used (i.e., voice, hand signals, radios or other means), and training in the use and understanding of material safety data sheets and chemical product hazard warning labels. Prior to bringing hazardous substances, as defined in 29 CFR 1910.1200 and/or 1926.59, onto the job site, a copy of the Hazard Communication Program and the Material Safety Data Sheets of each substance shall be submitted to the Contracting Officer and made available to the Contractor's employees as part of its Accident Prevention Program. A site map shall be attached to the inventory showing

01100-4 Ed 06-098 where the inventoried hazardous substances are stored. The inventory list and site map shall be updated monthly to assure accuracy.

(d) Daily Inspections. The Contractor shall perform daily safety inspections and record them on the forms approved by the Contracting Officer. Reports of daily inspections shall be maintained at the jobsite in accordance with Section 01451 "CONTRACTOR QUALITY CONTROL". The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:

(1) Phase(s) of construction underway during the inspection.

(2) Locations of areas where inspections were made.

(3) Results of inspections, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.

(e) Weekly Inspections. The Contractor shall also conduct weekly safety inspections in the presence of the onsite quality assurance representative.

Reports, records and information shall be according to the requirements of subparagraph titled “Daily Inspections” above.

(f) Safety Sign. The Contractor shall furnish, erect, and maintain a safety sign at the site where indicated by the Contracting Officer. The sign shall conform to the requirements of this paragraph and the drawing included at the end of this section. The lettering shall be black, the safety circle and cross green, and the background white. When placed on a floating plant, the sign may be half size.

The sign shall be erected as soon as practicable, but not later than 15 calendar days after the date established for commencement of work. The data required shall be current. The sign coordinator is Mary Pizzuto @ 504.862.2000.

(g) Ground Fault Protection. Electrical equipment used on this contract shall be equipped with ground fault circuit interrupters in accordance with EM 385-1-1, Section 11.D.05.

(h) Safety Fence. The Contractor shall provide, erect, and maintain a temporary 6 foot high chain link safety fence around the limits of work extending along the entire length of the south side of the Florida Avenue Canal, and on the north side of the Florida Avenue Canal for a minimum of two hundred feet (200') along the north side of the canal on either side of the Piety Street and Louisa Street crossings, and on any work areas on the south side of the Florida Avenue Canal, including work on the side streets (Desire and Montegut). The fence may be removed during the day as necessary to facilitate construction work, but must be restored by the end of each work day. Fencing shall consist of a 6 foot high chain link fence with three strands of barbed wire supported on angled arms at

01100-5 Ed 06-098 the top for the staging and office trailer area. To provide access, the fence shall have a minimum 16 foot wide gate with keyed lock. The Contractor shall provide and maintain on the fence "DANGER – CONSTRUCTION AREA – NO TRESPASSING" signs every 100 feet facing out from the enclosed area. Details for the staging and office trailer area shall be submitted to the Contracting Officer for approval. The Contractor shall cut any grass or vegetation within the construction limits and along both sides of the safety fence whenever the height exceeds 6 inches, at which time it shall be cut to a height of approximately 2 inches. At other work locations along the railroad tracks on the north of Florida Avenue, the fabric for the safety fence may be four foot (4’) high zinc coated hog wire mesh. No separate measurement or payment will be made for this work.

Payment for all work associated with the safety fence shall be distributed amongst the existing bid items.

(i) Hurricane Plan. The Contractor shall provide a detailed Hurricane Plan covering protection and evacuation of Contractor’s personnel, equipment and materials from the Florida Avenue Canal, in the event of an impending hurricane or storm. The Hurricane plan is required as a submittal attachment to the Contractor's Accident Prevention Program and shall be submitted to the Contracting Officer, his/her representative, for review prior to the pre-construction conference. No separate measurement or payment will be made for the Hurricane Plan. Payment for all work associated with each implementation of the Hurricane Plan, including providing all equipment required to implement the plan for the duration of any hurricane event(s), shall be considered incidental to the project and be distributed amongst the existing bid items. The Hurricane Plan shall include at least the following:

(1) The time each phase of the plan will be put in effect. The time shall be the number of hours remaining for the storm to reach the worksite if it continues at the predicted speed and direction.

(2) The estimated time necessary to secure and evacuate the site. If the Contractor has any existing drain lines cut off and bypass pumping in place, an emergency operator will be required to remain onsite 24 hours per day during any hurricane event to ensure proper operation of all pumping systems.

(3) The safe harbor for personnel and plant specifically identified.

(j) Hazardous Energy Protection. The Contractor shall develop, implement and maintain at the workplace, a written Control of Hazardous Energy (Lockout/Tagout) System. Refer to Section 12 of EM 385-1-1.

(k) Handling Sheet Piling: The Contractor’s personnel shall not sit or place themselves on top of the sheet piling during the handling, installation, and removal of the piling.

01100-6 Ed 06-098

(l) Cranes. The Contractor (including subcontractors) shall have cage boom guards, insulating links, or proximity warning devices on cranes that will be working adjacent to power lines. These devices shall not alter the requirements of any other regulation of this part - even if such device is required by law or other regulation. Insulating links shall be capable of withstanding a 1-minute dry low frequency dielectric test of 50,000 volts, alternating current (EM 385-1-1, Section 11.F.08). Calibration records or stamped date of required manufacturer inspection of proximity warning devices shall be kept on the crane. EM 385-1-1, Section 11.A.02, 11.F.03, 11.F.04, 11.F.05, and Table 11-1 requirements shall be submitted to and accepted by the Contracting Officer.

(m) Contractor shall employ a competent person at each project to function as the Site Safety and Health Office (SSHO). The SSHO will manage the Contractor’s APP. (This may be a collateral duty responsibility unless specified differently in the contract.) See EM 385-1-1 Appendix A. paragraphs 4 and 7.

The person(s), as a minimum, must have completed the 30-hour OSHA Construction safety class or an equivalent course applicable to the work to be performed and given by qualified instructors. Such training shall have been within the last four (4) years. An SSHO shall be on-duty at all times when work is being performed and shall be responsible for enforcing and implementing the Contractor’s Safety and Health Program in accordance with the accepted APP.

(n) Fall Protection. The Contractor shall comply with fall protection requirements as specified in EMS 385 – for all cofferdam/retaining structures or excavations for utilities.

(o) Metal Work Fabrication, Machine Work and Miscellaneous Provisions:

Welding rod material safety data sheets shall be reviewed for their toxicity with the MSDS kept onsite. Section 10.B of AWS D1.1 shall be applied as required.

(p) In locations where trucks and other equipment will be passing beneath overhead power lines, the contractor shall install at least two (2) signs on either side of the crossings warning drivers of the overhead lines. The signs shall face both directions of travel. The signs shall have arrows pointing upward and state “Overhead Electric”.

(q) All excavations and trenches shall be excavated and protected with sheeting and bracing or other requirements in accordance with U.S. Army Corps of Engineers EM 385-1-1.

4. INSPECTOR'S FIELD OFFICE

(a) The Contractor shall furnish, throughout the contract period, for the exclusive use of the Government employees, two (2) temporary, waterproof buildings or trailers. One to be utilized as an Inspector’s Field Office, and one capable of holding at least 20 people to be utilized as a Field Meeting Room. Both the

01100-7 Ed 06-098

Inspector’s Field Office and Field Meeting Room shall be mobilized to the work site and fully functional, including electric, water, telephone, and sewerage within thirty (30) days of NTP, or prior to start of work at the site.

(b) Both the Inspector’s Field Office and Field Meeting Room shall be conveniently located at the site of construction and shall be independent of any building, or trailer, used by the Contractor. Both the Inspector’s Field Office and Field Meeting Room shall be equipped, as a minimum, with the following:

1. Potable water toilet facilities and lavatory.

2. Bottled water and water cooler.

3. Private telephone service and telephone answering machine.

4. Fax/Scanner/Copier/Printer machine.

5. At least three (3) ceiling lamp receptacles.

6. At least three (3) duplex convenience outlets.

7. Air conditioning unit(s) to provide cooling in warm or hot weather, and a heater, properly installed and vented in accordance with the National Fire Protection Association Code, for heating in cold weather, as required.

8. A drafting table providing a flat work surface, having dimensions of at least 4-feet by 6-feet (which may consist of a piece of plywood, at least 3/4-inch thick, hinged to a wall of the building with hinged legs).

9. One (1) draftsman's stool, two (2) strong chairs and two (2) desks.

10. A built-in locker, extending from the floor to the ceiling, having dimensions of at least 2 feet by 5 feet, with a shelf twelve (12”) inches from the top, and one door equipped with two hinges, a hasp and a padlock.

11. Approved service disconnect, fuse panel, electrical wiring, of sufficient rated capacity to provide 110-volt, 60 Hz power required to operate the air conditioning unit, lights, and laptop computer and printer. The Contractor shall make the necessary arrangements to obtain or to generate the power required to operate all electrical equipment, and the power or fuel required for the heater, and shall bear the cost thereof.

12. All exterior doors and window frames of the building shall be equipped with iron security guards. The door shall also be equipped with butt hinges and a cylinder lock.

01100-8 Ed 06-098

13. Screens shall be installed over all windows; walls and ceilings shall be insulated; and interior walls shall be finished.

14. Each building or trailer shall conform to the following minimum dimensions and capacity requirements:

Ceiling height, not less than 6-feet 9-inches Floor space, no less than 480 square feet Windows, not less than 4 Doors, exterior 2 Rooms 3

(c) The Inspector’s Field Office shall be removed by the Contractor after completion of all work under this contract and before final acceptance thereof.

No separate payment will be made for furnishing, maintaining, providing the prescribed utilities, and removing the inspector's field office, but the cost of the same shall be distributed throughout the existing bid items. In the event the Contractor fails to furnish the required facilities, the Government may elect to procure the required facilities and deduct all costs from amounts due or to become due under this contract.

(d) The Contractor shall provide daily janitorial services for this and other buildings at the site throughout the life of the contract. The cost of this service shall be distributed throughout the existing bid items and there shall be no separate payment.

(e) The Contractor shall provide the inspector’s field office with a hard line broadband high speed internet service and associated equipment for the exclusive use of the Government. If this service is not practical at the jobsite, the Contractor may instead provide the inspector’s field office with a cellular wireless Broadband / WiFi 802.11n capable router that accepts cellular data signals through Express Card / Air Card or USB modems. This service must be capable of providing adequate connection to allow the inspectors to import/export files through RMS. The Contractor must field verify that the service provider chosen has adequate continuous coverage at the construction site. This service shall provide a minimum download speed of 10 Mbps and a minimum upload speed of

1.5 Mbps. The Contractor shall be responsible for the installation, the maintenance of, and the monthly service fees necessary to provide continuous high speed internet service for the duration of the contract.

(f) The Contractor shall provide facilities for a meeting room capable of accommodating a minimum of 25 people.

01100-9 Ed 06-098

5. PROJECT SIGN

Prior to commencement of work, the Contractor shall construct a project sign at the site of the work at a location directed by the Contracting Officer. The sign, which will identify the work with the Corps of Engineers shall be 4 feet by 6 feet in size and shall conform to the requirements of the PROJECT SIGN drawing and installation instructions attached at the end of this section. The lettering for the 2 feet by 4 feet section of the sign with the Corps logo shall be white; all other lettering shall be black.

Lettering for the project name shall be Helvetica Bold, all other lettering shall be Helvetica Regular. The sign coordinator is Mary Pizzuto @ 504.862.2000. No separate payment will be made for construction and erection of the project sign and all costs in connection therewith will be considered an incidental obligation of the Contractor. Upon completion of the work, the sign shall become the property of the Contractor and shall be removed from the job site.

6. RIGHTS-OF-WAY

a. The rights of entry required for the work to be constructed under this contract, within the rights-of-way limits indicated on the drawings, have been obtained by the Government and are provided without cost to the Contractor. The Contractor shall make its own investigations to determine the conditions, restrictions, and difficulties that may be encountered in the transportation of equipment and material to and from the work site. The proposed work, including rights-of-way, as defined by these specifications and as shown on the drawings, is in compliance with all applicable Federal and state environmental laws and regulations. Upon completion of the Contractor’s work, rights-of-way furnished by the Government shall be returned to its original condition prior to construction unless otherwise noted.

b. If the Contractor proposes a deviation from the Government furnished rights-of-way for his convenience, the Contractor shall notify the Contracting Officer or its representative in writing. Contractor shall not provide any permanent rights-of-way for the project. The Contractor is cautioned that any deviation to the Government furnished rights-of-way is subject to all applicable Federal and state environmental laws and regulations. Compliance with these environmental laws and regulations may require additional National Environmental Policy Act (NEPA) documents, cultural resources surveys, coordination with the Louisiana State Historical Preservation Officer, water quality certification, modification of the Federal consistency determination, etc. The Government is ultimately responsible for environmental compliance; therefore, the Government will determine the additional environmental coordination and documentation necessary for a proposed deviation to the Government furnished rights-of-way.

For any environmental investigations the Government is to perform on areas outside of Government furnished rights-of-way, the Contractor shall provide sufficient rights of entry to the Government. The Contracting Officer will advise the Contractor of the additional environmental coordination and documentation

01100-10 Ed 06-098 that must be completed. The Government shall be responsible for any additional environmental compliance; however, the Contractor may conduct specific tasks identified by the Government. The Government will offer advice and assistance to the Contractor in conducting these tasks. Depending on the environmental impact of the proposed deviation, obtaining the coordination and documentation may not be approved or could take as much as 180 days for approval by the Government. The Government must review, approve and ensure distribution of all environmental compliance documentation and ensure all comments on the same have been resolved before any utilization of any areas outside of the Government furnished rights-of-way. The Contractor shall reimburse the Government for actual expenses incurred for assistance in completing or attempting to complete additional environmental coordination and documentation, which expenses will not exceed one hundred thousand ($100,000.) dollars. There is no guarantee that environmental compliance will be obtained; therefore, the Contractor shall assume all risks and liabilities associated with pursuing a deviation. Any delays resulting from the deviation and/or the environmental coordination and documentation shall not be made the basis of any Contractor claim for increase in the contract cost and/or increase in contract time. Deviations will be at Contractor’s sole risk and liability, including, but not limited to, such liabilities associated with items such as hazardous substances regulated under the Comprehensive Environmental Response, Compensation, and Liability Act (42 U.S.C. 9601 et. seq.), and at no cost to the Government. Government assistance in obtaining additional environmental clearances does not relieve the Contractor of responsibility for complying with other Federal, state or local licenses and permits.

7. CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in three (3) copies. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet specified requirements.

8. ENVIRONMENTAL LITIGATION

(a) The term "environmental litigation", as used herein, means a lawsuit alleging that the work has an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.

01100-11 Ed 06-098

(b) If the performance of all or any part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If the order is not due in any part to acts or omissions of the Contractor (or a Subcontractor at any tier) other than as required by this contract, such suspension, delay, or interruption shall be as if ordered by the Contracting Officer under the Contract Clause in Section 00700, entitled Suspension of Work (FAR 52.242-14). The period of such suspension, delay or interruption shall be considered unreasonable, and an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof.

9. UTILITIES AND IMPROVEMENTS

(a) All known utilities within the limits of the work, such as pipes, communication lines, power lines, etc., that would interfere with construction work will be removed, modified or relocated by local interests or utility companies at no cost to the Contractor unless otherwise noted in the plans and/or specifications. The Contractor, however, shall cooperate with the authorities or company representatives and shall conduct his/her operations in such manner as to result in a minimum of inconveniences to the owners of said utilities. The Contractor shall notify each utility owner by certified mail 45 days, 15 days, and again 72 hours prior to the date utilities must be moved and provide a copy of these notifications to the Contracting Officer. Contact points for utilities companies are located in paragraph “COORDINATION OF WORK”.

(b) Any unidentified pipes or structures which may be found within the limits of the work during the course of construction shall not be disturbed nor shall construction or excavation be performed at these locations unless and until approved by the Contracting Officer. Payment for ordered excavation, if any, will be made in accordance with the Contract Clause in Section 00700, entitled Differing Site Conditions (FAR 52.236.2).

10. PERMISSIBLE HOURS OF WORK

No work shall be done at the jobsite between 7:00 p.m. and 7:00 a.m.. The Contractor will be allowed to work on Saturdays, Sundays and Holidays. Prior to 7:00 a.m. the Contractor shall not start up any equipment nor have any trucks for delivery, service, hauling, etc. arrive at the jobsite. Trucks shall remain on designated truck routes until 7:00 a.m. When the Contractor elects to work weekends and holidays, notice shall be given to the Contracting Officer, in writing, 36 hours in advance of commencement of such operations to permit suitable arrangements for inspections to be made. Adequate lighting for thorough inspection of night operations conducted within the permissible hours of work shall be provided by the Contractor at his/her

01100-12 Ed 06-098 own expense. The Contractor shall also maintain noise levels at the jobsite at all times below 75 dB. The Contractor shall coordinate the requirements of this paragraph with all affected utility companies and/or agencies as identified in paragraph “COORDINATION OF WORK”.

11. U.S ARMY CORPS OF ENGINEERS CRD-C STANDARDS

CRD-C standards can be found at the following case sensitive address:

http://gsl.erdc.usace.army.mil/SL/MTC/handbook/handbook.htm

12. AGGREGATE SOURCES

(a) Concrete aggregates meeting the quality requirements of these specifications have been produced from the sources listed below:

3 December 2012

PRODUCER NEAREST TOWN TO PIT* TYPE PIT DESIGNATION

B. & M. B., Inc. Jackson, LA S, G Dudley Pit

B. & M. B., Inc. Wakefield, LA S, G Island Pit

B. & M. B., Inc. Jackson, LA S, G Thompson Pit

Barriere’s Construction Co., LLC Arcola, LA S, G Ponder Pit

Bayou Sand and Gravel, LLC Amite, LA S, G Bayou Sand and Gravel

Blain Sand & Gravel, Inc. Georgetown, MS S, G Bailey Pit

Bunch Gravel Co. Clinton, LA G Bunch Gravel Plant #1

Bunch Gravel Co. Darlington, LA S, G Bunch Gravel Plant #2

DK Aggregates, LLC Nicholson, MS S, G DK Aggregates Pit

Fleniken Sand & Gravel Co. Grangeville, LA S, G Flen-Rock Pit (Spears Lease)

Irv Daniel Wakefield, LA S, G Island Pit

Lafarge North America Pearl River, LA S, G Honey Island Operation

Lafarge North America Sun, LA S, G Isabel Plant

Martin Marietta Aggregates Smithland, KY LS Three Rivers Quarry

Mears Sand & Gravel Co. Watson, LA S, G Penny & Easterly Lease

Norris Springs Gravel Sicily Island, LA S, G Norris Springs Gravel Pit

Pine Bluff Sand & Gravel Co. Delaware, AR SS River Mountain Quarry

Southern Aggregates, LLC Watson, LA S, G Glaciel Lease

Southern Aggregates, LLC Watson, LA S, G Mullins Lease

Southern Aggregates, LLC Watson, LA S, G Weyerhauser Lease

Southern Aggregates Watson, LA S, G Clemons Plant

Standard Gravel Co., Inc. Hattiesburg, MS S Plant 63

Standard Gravel Co., Inc. Hattiesburg, MS S Plant 80

Standard Gravel Co. Enon, LA S, G Enon Pit (C-10 & CZ-30 leases)

Standard Gravel Co. Franklinton, LA G Green Lakes Plant http://gsl.erdc.usace.army.mil/SL/MTC/handbook/handbook.htm

01100-13 Ed 06-098

Standard Gravel Co. Pearl River, LA S, G Mitchell - 11 Plant

Standard Gravel Co. Pearl River, LA S, G Nicholson Plant (Nic-9)

Texas Industries, Inc. Perryville, LA S, G Perryville Plant

Texas Industries, Inc. Woodworth, LA S, G Woodworth Plant

Tower Rock Stone Co. Scott City, MO LS Grays Point Quarry

Trinity Materials, Inc DeRidder, LA S, G Anacoco Creek Plant

Vulcan Materials Co. Lake City, KY LS Grand Rivers Quarry

Warren Paving Co. Salem, KY LS Slats Lucas Quarry

Type:

G = Gravel LS = Limestone S = Sand SS = Sandstone

*“Nearest Town to Pit” according to LDOTD Official State Highway Map and Rand McNally Road Atlas copyrighted 2010.

(b) Concrete aggregates may be furnished from any of the above listed sources or at the option of the Contractor may be furnished from any other source designated by the Contractor and approved by the Contracting Officer, subject to the conditions hereinafter stated and as specified in Section 03301.

(c) After the award of the contract, the…