Sacramento RFI Q-A_23 May 2025.pdf

PDF 119 KB Posted

Attached to
Sacramento River DWSC Dredging FY25
Solicitation number
W912P725BA011
Issued by

About this file

This document is a Questions & Responses (RFI) file for the Sacramento Deepwater Ship Channel (DWSC) Dredging project, Solicitation Number W912P725BA011. The document captures six specific questions and corresponding government responses related to the upcoming dredging project, including anticipated award date (2 June 2025), notice to proceed timeline (5-7 days after award), water quality management requirements, and environmental compliance details. Key highlights include a requirement for third-party water quality monitoring at both dredge material placement sites (DMPS) and in-water dredge sites, and specific environmental protocols such as stopping work and notifying authorities if more than 5 Delta Smelt are encountered during the project. The contract involves annual maintenance dredging of the Sacramento DWSC to -30-ft depth, with an estimated contract value between $1-3 million, and will be conducted as a full and open competition under NAICS Code 237990.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sacramento Deepwater Ship Channel (DWSC) Dredging

FY25 AS OF: May 23, 2025

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P725BA011

The intent of this section is to provide questions & comments received from interested parties on the above solicitation, and our responses to those questions and comments. It is possible that the information below does not reflect 100% of the questions and responses. The questions and comments do not necessarily represent questions received from any particular contractor.

Questions and responses are provided for information only and are not made part of the solicitation. Only a formal amendment

(SF30) to the solicitation changes the solicitation.

Changes to any previous responses in this document will be struck-through and new, updated responses will be provided appropriate

RFI # SPEC SECTION/DRAWING RFI QUESTION RESPONSES

1 Topic:

N/A

Would the government be able to specify the anticipated date of award?

The award is anticipated to be executed 2 June 2025

2 Topic: Would the government be able to specify the anticipated date of notice to proceed?

NTP is usually 5-7 days after award

(Pending Bond receipt and validation or other unforeseen issues)

3 Topic: Can the government specify if the water quality management is required to be done by a 3rd party?

See specs section 1.11 Operations and Water Quality Monitoring Plan

SECTION 01 57 19. IT IS required to be done by a 3rd party.

4 Topic: Can the government specify the consequences of taking more than 5 Delta Smelt during the duration of the contract?

Stop work, notify KO and environmental manager immediately. USACE will contact

FWS on path forward.

5 Topic:

6 Topic:

Section:

Can a Dredging Plant & Equipment Schedule be updated from Richmond Inner Harbor Dredging Project Sacramento DWSC Dredging

Strike though the Richmond Inner Harbor Dredging Project-replace with Sacramento DWSC Dredging

After reviewing the updated RFI responses, could you please clarify if third party WQM is required at the DMPS AND the Dredge Site (In water), or is the third party requirement just at the DMPS?

Yes it is required by 3rd party at both locations.

Water Quality Monitoring Plan

SECTION 01 57 19

Water Quality Monitoring Plan

SECTION 01 57 19

Water Quality Monitoring Plan

SECTION 01 57 19

l3ct9jn9 Highlight

File details come from the government source that posted it. Updated .