Sacramento RFI Q-A_23 May 2025.pdf
PDF 119 KB Posted
- Attached to
- Sacramento River DWSC Dredging FY25
- Solicitation number
- W912P725BA011
About this file
This document is a Questions & Responses (RFI) file for the Sacramento Deepwater Ship Channel (DWSC) Dredging project, Solicitation Number W912P725BA011. The document captures six specific questions and corresponding government responses related to the upcoming dredging project, including anticipated award date (2 June 2025), notice to proceed timeline (5-7 days after award), water quality management requirements, and environmental compliance details. Key highlights include a requirement for third-party water quality monitoring at both dredge material placement sites (DMPS) and in-water dredge sites, and specific environmental protocols such as stopping work and notifying authorities if more than 5 Delta Smelt are encountered during the project. The contract involves annual maintenance dredging of the Sacramento DWSC to -30-ft depth, with an estimated contract value between $1-3 million, and will be conducted as a full and open competition under NAICS Code 237990.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sacramento Deepwater Ship Channel (DWSC) Dredging
FY25 AS OF: May 23, 2025
QUESTIONS & RESPONSES
SOLICITATION NUMBER W912P725BA011
The intent of this section is to provide questions & comments received from interested parties on the above solicitation, and our responses to those questions and comments. It is possible that the information below does not reflect 100% of the questions and responses. The questions and comments do not necessarily represent questions received from any particular contractor.
Questions and responses are provided for information only and are not made part of the solicitation. Only a formal amendment
(SF30) to the solicitation changes the solicitation.
Changes to any previous responses in this document will be struck-through and new, updated responses will be provided appropriate
RFI # SPEC SECTION/DRAWING RFI QUESTION RESPONSES
1 Topic:
N/A
Would the government be able to specify the anticipated date of award?
The award is anticipated to be executed 2 June 2025
2 Topic: Would the government be able to specify the anticipated date of notice to proceed?
NTP is usually 5-7 days after award
(Pending Bond receipt and validation or other unforeseen issues)
3 Topic: Can the government specify if the water quality management is required to be done by a 3rd party?
See specs section 1.11 Operations and Water Quality Monitoring Plan
SECTION 01 57 19. IT IS required to be done by a 3rd party.
4 Topic: Can the government specify the consequences of taking more than 5 Delta Smelt during the duration of the contract?
Stop work, notify KO and environmental manager immediately. USACE will contact
FWS on path forward.
5 Topic:
6 Topic:
Section:
Can a Dredging Plant & Equipment Schedule be updated from Richmond Inner Harbor Dredging Project Sacramento DWSC Dredging
Strike though the Richmond Inner Harbor Dredging Project-replace with Sacramento DWSC Dredging
After reviewing the updated RFI responses, could you please clarify if third party WQM is required at the DMPS AND the Dredge Site (In water), or is the third party requirement just at the DMPS?
Yes it is required by 3rd party at both locations.
Water Quality Monitoring Plan
SECTION 01 57 19
Water Quality Monitoring Plan
SECTION 01 57 19
Water Quality Monitoring Plan