RWC RFIs.pdf
PDF 76 KB Posted
- Attached to
- REDWOOD CITY MAINTENANCE DREDGING FY 24
- Solicitation number
- W912P724B0008
About this file
This document contains Requests for Information (RFIs) related to a federal contract opportunity for the REDWOOD CITY MAINTENANCE DREDGING FY 24 project.
The key details are:
- The contract opportunity is a Firm Fixed Price (FFP) contract for annual maintenance dredging of the Redwood City channel to -30 ft (MLLW) plus 1 ft of paid over-depth, and transporting the dredged material to various upland disposal sites.
- The total estimated cost range is between $5,000,000 - $10,000,000.
- All bids are due on/about August 1, 2024 at 12:00 PM PDT.
- The RFIs address requests for higher resolution dredging survey data and a potential contract duration extension, which the government has responded to.
- This is a full and open competition solicitation issued by the U.S. Army Corps of Engineers, San Francisco District.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SPN REDWOOD CITY Bid Abstract- OF 1419-signed.pdf | ||
| RFI RedwoodCityDrdg 30 July 2024.xlsx | XLSX spreadsheet | |
| W912P724B0008 002.pdf | ||
| W912P724B0008 - 001.pdf | ||
| W912P724B0008_REDWOOD_CITY_O_M_FY24_SPECS.pdf | ||
| W912P724B0008_REDWOOD CITY_O-M_FY24_PLANS.pdf | ||
| Davis-Bacon Act-WD-CA20240018.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFIs
1. Can USACE please provide the full sounding density multibeam survey data in an XYZ point file for the survey conducted on June 17th, 2024 in Redwood City? The posted survey data is lower resolution as it is sorted and only on 100 ft line spacing.
a. Yes- See amendment 1 which provides the condition survey.
2. Disposal of all dredge material can occur at a Contractor furnished beneficial reuse site.
Will the Government consider extending the contract duration by approximately 31 days or until December 31, 2024, to allow Contractor’s greater flexibility in meeting the schedule requirements?
a. No, the period of performance is appropriate for the quantities for dredging and the Environmental Window.
File details come from the government source that posted it. Updated .