GEOTECH-AMENDMENT 0004.pdf

PDF 767 KB Posted

Attached to
A-E GEOTECHNICAL ENGINEERING IDC/IDIQ Federal contract opportunity
Solicitation number
W912P721R0006
Issued by
Department of the Army Corps of Engineers Engineering District San Francisco

View the file

Other files for this federal contract opportunity

Other files attached to A-E GEOTECHNICAL ENGINEERING IDC/IDIQ, newest first.
File Type Posted
DPM 2020-02.pdf PDF
6. PAST PERFORMANCE QUESTIONNAIR.pdf PDF
GEOTECH PRE-PROPOSAL.pdf PDF
GEOTECH - AMENDMENT 0003-1.pdf PDF
PRE PROPOSAL CONFERENCE ATTENDEES.xlsx XLSX spreadsheet
AMENDMENT 0002.pdf PDF
AMENDMENT 0001.pdf PDF
Geotech IDIQ_Synopsis .pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

A-E GEOTECHNICAL ENGINEERING IDC/IDQ

See Continuation page of SF-30 Summary of changes for Amendment 0004

CONTRACTING DIVISION

450 GOLDEN GATE AVE., 4TH FLOOR

SAN FRANCISCO, CA 94102

SEE ITEM 6

W912P721R0006

W912P721R0006

1 3

04/01/2021

04/01/2021

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

Continuation page of SF 30 – Summary of changes for Amendment 0004

This amendment answers RFIs 19 -25

RFI 19: Assuming there are 3 to 5 highly-qualified firms in the MATOC pool, will Task Orders be issued on a rotational basis or will there be a request for additional qualifications before a Task Order is assigned?

ANSWER: The government will follow the procedures in DPM #2020-02, using the Task Order Requirement Notice (TORN) process. Please see attached.

RFI 20: If there is an additional round of “competition”, can price ever play a factor in the assignment?

ANSWER: The government will follow the procedures in DPM #2020-02, using the Task Order Requirement Notice (TORN) process. Price becomes a factor when your firm is selected as the most qualified, then your firm submit a proposal. Please see attached.

RFI 21: Is this Solicitation governed by USACE DPM 2020-02, dated 03 Mar 20, Subject, Procedures for the Selection of Task Orders on A-E IDC Contracts?

ANSWER: Yes, this synopsis is governed by DPM 2020-02.

RFI 22: USACE is asking that “For all relevant projects include the percentage of work self-performed by the prime offeror and subcontractors for each contract and/or task order.” If our engineering services were a just percentage of the total contract value of a comprehensive A/E design contract, do we base the percentages on the specific services or the total contract value?

For example, if we were responsible for 100% of the geotechnical scope on a project and present the project description with only the geotechnical scope, could we state that 100% of the work was self-performed?

ANSWER: Please provide the total percentage of your effort under the total design and then the effort specifically under Geotechnical Engineering.

RFI 23: Regarding PPQ and ACASS ratings: Should we have our project clients send the PPQ directly to USACE procurement?

ANSWER: Please have your clients provide the PPQ directly to USACE procurement.

RFI 24: Should we include the PPQ and ACASS ratings in our solicitation response?

ANSWER: Please just provide your ACASS/CPARS rating only, USACE procurement will distribute the PPQ’s

RFI 25: If so, where in our solicitation response should the PPQ and ACASS ratings be placed?

W912P721R0006-0004

Answer: Past Performance on DoD and other contracts with respect to cost control, quality of work and compliance with performance schedules, and customers addressing your firm's cost control, quality of work and schedule compliance capabilities may be included in Section H of the SF 330.

RFI 26: And, are PPQs and ACASS ratings included in the page count?

ANSWER: Yes.