W912P622B0014-0001.pdf

PDF 11 MB Posted

Attached to
Indiana Shoreline Erosion Project: Beach Nourishment Services
Solicitation number
W912P622B0014
Issued by

View the file

Other files

File Type Posted
Bid Opening Results.docx DOCX document
W912P622B0014-0002.pdf PDF
Attachment I (For AMDT 0002).pdf PDF
Attachment B (For AMDT 0002).pdf PDF
Attachment H (For AMDT 0002).pdf PDF
Attachment F (For AMDT 0001).pdf PDF
Attachment G (For AMDT 0001).pdf PDF
Attachment C (For AMDT 0001).pdf PDF
Attachment E.pdf PDF
Attachment B (For AMDT 0001) Performance of Work Statement.pdf PDF
Attachment C.pdf PDF
Attachment B.pdf PDF
Attachment E.pdf PDF
Attachment D.pdf PDF
Attachment A.pdf PDF
W912P622B0014 - 16SEPT22.pdf PDF
Attachment F.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation W912P622B0014 for the Indiana Shoreline Erosion Project is hereby modified as follows:

SEE CONTINUATION PAGE: Reference "AMDT 0001 - Summary of Changes"

1. CONTRACT ID CODE PAGE OF PAGES

1 135

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P622B0014

X 9B. DATED (SEE ITEM 11)

16-Sep-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Oct-2022

CODE

U.S. ARMY ENGINEER DISTRICT, CHICAGO

231 SOUTH LASALLE STREET SUITE 1500

CHICAGO IL 60604-1437

W912P6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P622B0014

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMDT 0001 - SUMMARY OF CHANGES

A. PROCUREMENT INFORMATION: The following Sections have been revised. The revised sections are enclosed hereunder and replace the previously furnished sections.

1) DUE DATE AND TIME: BIDS WILL BE REQUIRED NO LATER THAN October 26, 2022, AT 12:00 P.M. (Central Time). Submission requirements and Bid Opening procedures are specified in the “E- Submission Instructions.”

B. PERFORMANCE WORK STATEMENT (Attachment B): The Performance Work Statement (PWS) has been revised and is hereby replaced in its entirety. The table enclosed hereunder depicts the changes made to the

PWS.

SECTION NUMBER AND

TITLE

PARAGRAPH AND DESCRIPTION OF CHANGE

Section 1 – 6.1 Contractor Site Visit

Added Time/Date and Location for Contractor Site Visit

Subsection 3.1 Relabeled Section 4 to Subsection 3.1 Subsection 3.2 Relabeled Section 5 to Subsection 3.1

Section 9 Relabeled Section 6 to Section 9

Section 10 Relabeled Section 7 to Section 10

Subsection 10.1 Relabeled Section 8 to Subsection 10.1

Section 4 New Section – General Provisions

Section 5 New Section – Submittal Provisions

Section 6 New Section – Government Safety Requirements

Subsection 6.1 New Subsection – Government Safety Requirements – Execution

Section 8 New Section – Quality Control

Section 10 Updated Section with definitions and references

Section 11 New Section – Project Identification

Section 12 New Section – Contract Requirements Package Security Review -Clauses from OPSEC Form 6055

Exhibit E - Attachment C Fully Executed Real Estate Access Agreement and Original Real Estate Access Agreement

Exhibit I – Attachment G New Project Identification Sign

Exhibit A, B, C, D NOT USED

Exhibit H – Attachment F Removed Note 6 from R-001 referencing old specifications.

C. Modified Contract Solicitation Drawings: The table enclosed hereunder depicts the changes made to the Drawings.

SHEET REF. NO. TITLE AND DESCRIPTION

R-001 Removed Note 6

D. ATTACHMENTS LIST: The following Attachments have been revised and/or added; revised attachments are hereby replaced in their entirety.

1) Attachment B – Performance Work Statement: This attachment has been revised.

2) Attachment C – Exhibit E: This attachment has been revised.

3) Attachment F – Exhibit H: This attachment has been revised.

4) Attachment G – Exhibit I: This attachment has been added.

E. PROVISIONS AND CLAUSES: The following FAR clause and provision is hereby incorporated.

1) FAR 52.237-1 – Site Visit (APR 1984)

F. AMENDMENT ACKNOWLEDGMENT: Please note that ALL amendments must be acknowledged.

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 17-Oct-2022 12:00 PM to 26-Oct-2022 12:00 PM.

The following have been added by reference:

52.237-1 Site Visit APR 1984

The following have been added by full text:

SITE VISIT

Indiana Shoreline Erosion Protection

A Site Visit/ Pre-Proposal Meeting is scheduled for 19 October 2022.

All attendees are required to meet NIPSCO West Gate in Michigan City, Indiana 46360.

The coordinates for Google Maps are 41.706784, -86.924970 (input this into Google Maps to get exact location of west gate. Inputting NIPSCO West Gate into google maps will direct you to the wrong location).

Schedule:

10:00 AM CENTRAL TIME

No inquiries will be allowed during the site visit. All inquiries must be submitted via the Projnet Bidder Inquiry site.

A Bidder Key is provided with the solicitation information.

Please RSVP the following information:

1. Name of Attendee

2. Company

3. Phone Number

4. Email Address

Please remember to bring a State Issued ID in order to attend the site visit.

Send RSVP to Samir Abu-Ali at samir.abu-ali@usace.army.mil. USACE must receive the email by 10:00 AM Central Time on 18 October 2022. No additional attendees will be registered after this date or time.

(End of Summary of Changes)

Indiana Shoreline Erosion Protection

ATTACHMENT B

PERFORMANCE WORK STATEMENT

August 12, 2022

U.S. Army Corps of Engineers Chicago District

PERFORMANCE OF WORK STATEMENT

SECTION 1

SUMMARY

1.1) GENERAL: The purpose of this contract is to provide beach nourishment services for the Indiana

Dunes National Lakeshore through the award of an Indefinite Delivery/Indefinite Quantity (ID/IQ) contract, administered by the U.S. Army Corps of Engineers (USACE), Chicago District. The scope of services that this contract will generally consist of are detailed below. The contract will be awarded not to exceed a five (5) year base period and a $15,00,000.00 ($15 million) capacity. Firm fixed price task orders will be issued against this contract. The period of performance for task orders awarded under the ID/IQ contract will be determined based upon the work requirements and will be included in the task order solicitation and award documents.

2.1) PROJECT INFORMATION. Indiana Dunes National Lakeshore is located in Michigan City in LaPorte

County. Indiana Shoreline Erosion Protection, authorized in Section 501(a) of the Water Resources

Development Act of 1986, provides for mitigation of loss of sand caused by the Federal harbor structures at Michigan City and restoration of natural littoral processes at the eastern end of the

Indiana Dunes National Lakeshore at Mount Baldy. The authorized project consists of the placement of approximately 264,500 cubic yards of sand at five-year intervals over 50 years and monitoring of subsequent sand movement. Actual quantities of sand placed are dependent on funding availability.

3.1) SCOPE OF PERFORMANCE. The beach nourishment project consists of rebuilding approximately

1,500 feet along the beach by placing new sand. National Park Services (NPS) provides the specific location of sand placement depending on their regular site inspections. The condition at Indiana

Shoreline is very dynamic and changes drastically after every storm. A pre- and post-placement survey will be conducted by the Army Corp of Engineers to evaluate sand placement. The post-placement survey data will be used as a base map for the next sand placement.

This project will also include silt fencing installation along the southern boundary of the site to protect local vegetation and potentially a geocell road repair dependent on the conditions of the site after winter. The Contractor shall furnish all necessary management, personnel, materials, supplies, tools, equipment, fuel, and vehicles, except as otherwise provided herein, required to perform sand placement, temporary silt fencing installation and access road maintenance when necessary at the eastern end of the Indiana Dunes National Lakeshore, as specified and in strict accordance with all Terms, Conditions, General, Specific and Technical Provisions, Drawings, Attachments, Exhibits, etc., contained herein or incorporated by reference. The contractor performance and responsibility shall include all planning, programming, administration, management, supervision, communications, and inspections necessary to assure that all services are conducted in accordance with the contract requirements and all applicable Federal, State, and local laws and regulations. The Contractor is required to attend a pre-performance meeting to be scheduled by the Contracting Officer Representative (COR). The quantities listed in the price breakout schedule are approximate and are provided as information only to assist in preparations of proposed pricing. They are not guaranteed, and the actual quantities may be more or less than shown. Variations in these estimated quantities shall not be justification for modification of the contract or request for additional payment.

It is emphasized that the services described in this contract is a critical part of the Corps mission. The services described will be performed in a public recreation area. The Corps is committed to

“Customer Care” and providing quality professional service. The following is listed as the Contractor

Office Representative:

Samir Abu-Ali Contracting Officer Representative , Army Corp of Engineers

Email: samir.abu-ali@usace.army.mil Phone: (219) 923-1763

The following are points of contact that may require coordination with, Adam Fauth Environmental Engineer Supervisor, NIPSCO Point of Contact

Email: AFauth@nisource.com Phone: (219)647-5990

Charles Morris Environmental Protection Specialist, National Park Services Point of Contact

Phone: (219) 983-1352

4.1) TASK ORDERS. All performance under this contract will be ordered by issuance of individual Task

Orders. Tasks Orders may include options for additional sand. No performance shall be performed under this contract before an individual Task Order has been issued by the Contracting Officer (KO).

Only the KO, by issuance of a modification, may make any change to a Task Order. The Task Order will list those items from the price breakout schedule that are to be performed.

Fixed Price. Under this procedure the Government requires definite quantities of items from the price breakout schedule for routine work. The Contractor furnishes the services in accordance with the technical provision of the contract at the quoted price in the Price Breakout Schedule. The

Contractor furnishes all plant, labor, equipment, and materials for fixed price work unless otherwise specified.

5.1) WORKING HOURS.

a) NORMAL WORKING HOURS - Normal working hours, except as otherwise specified herein, shall be Monday through Friday, 7:00 a.m. to 4:00 p.m Central Time. Performance inside secured areas shall be performed during the above referenced work hours. Performance that interferes with other ongoing functions at the project shall be scheduled around normal working hours.

b) HOLIDAY WORK – The eleven Federal holidays observed are:

New Year’s Day (January 1st) Martin Luther King Day (3rd Monday in January)

President’s Day (3rd Monday in February) Memorial Day (Last Monday in May)

Juneteenth Independence Day ( June 19th) Independence Day (July 4th)

Labor Day (1st Monday of September) Columbus Day (2nd Monday in October)

Veterans Day (November 11th) Thanksgiving Day (4th Thursday in November)

Christmas Day (December 25th)

When one of the above designated holidays falls on a Sunday, the following Monday is observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday. Services shall be scheduled around the above listed Federal holidays except as specified herein or as stated within each Task Order.

c) INCLEMENT WEATHER WORK – The Contractor shall maintain the schedule of services regardless of inclement weather. Exceptions may be approved by the COR when severe conditions make services impractical or dangerous. The COR will notify the Contractor, by modification to the Task Order, of any change that extends the performance period due to unusually severe weather.

6.1) CONTRACTOR SITE VISIT. The following is the date and time for contractors to visit the site. Please notify COR at least 24 hours before site visit if you would like to be part of site visit.

NIPSCO WEST GATE

MICHIGAN CITY, INDIANA 46360

TIME/DATE: 10:00 CENTRAL TIME - OCTOBER 19TH

41.706784, -86.924970– input this into google maps to get exact location of west gate. Inputting

NIPSCO West Gate into google maps will direct to the wrong location.

-END OF SECTION 1-

SECTION 2

SAND PLACEMENT AND MAINTANCE OF ACCESS ROAD

1.1) SCOPE OF PERFORMANCE. The Contractor is allowed to transport sand material to the site land based by trucks or water based by barges. From previous projects, the most effective and economical method was found to be a vehicular transportation. The quantity for sand placement was determined based the funds available for the project. The COR will provide the exact location of sand placement. From previous years, sand has been placed either at Crescent Beach and/or Central

Beach. See Drawings or Plans.

Before sand placement is started, the Army Corp of Engineer will conduct a pre-placement survey to obtain current conditions. Temporary silt fencing will be installed on south side of beach to protect vegetation during sand placement. Contractor will maintain access road to ensure the road remains accessible and in good condition, this includes protection geo-web with sand cover, and depending on the condition of geo-web, replacement of geo-web sections. After the Task Order is awarded, the

COR will notify the Contractor of when and where to being placing sand.

2.1) GENERAL. During the pre-performance conference the COR will point out the sand placement limits. Contractor shall strictly place sand to these limits, without exceeding them. Before sand is delivered onto site, temporary silt fencing will be installed on the south end of the beach to protect local vegetation. Once erected, depending on the delivery method and the location of sand placement, sand will be unloaded onto the beach and spread as noted on drawings. See B1 –

Typical Section – Beach Fill Berm on CS-501.

Sand being brought into site must comply with the following. All tests referenced are designed to ensure the permanence and quality of the material placed at the project site. See Section 4 for Test

Description.

Petrographic Analysis

Sodium Sulfate Soundness Test

Freezing and Thawing Test

As equipment moves through the access road, geo-web will begin to be exposed, it is recommended that before end of day exposed geo-web be covered with the same sand being used in the beach. This is to protect from any overnight water level changes and to prepare for the next day’s activities. Once all sand has been utilized and spread throughout the beach the contractor will notify the COR. The Army

Corp of Engineers will conduct a post-placement survey to evaluate the sand placement. Temporary silt fencing will be removed before completion of yearly duties.

-END OF SECTION 2-

SECTION 3

EROSION PROTECTION – SAND FILL PLACEMENT

1.1) SCOPE OF PERFORMACE. The work covered by this Section consists of furnishing all plant, labor, equipment and materials and performing all operations in connection with the placement of the beach fill project.

2.1) SUBMITTALS. Government approval is required for submittal with a “G” designation; submittal not having a “G” designation are for information only. When used, a designation following the “G” designation identifies the office that will review the submittal for the Government. Submit the following:

SD-01 Preplacement Submittals

Sand Source G ECE-G

Work Plan G ECE-C

In addition to ECE-C, ECE-H will approve the work plan if barge will be used by the Contractor

Sand Placement Equipment Lists

Traffic Control Plan G ECE- C

Sampling Plan for Contractor- Furnished Borrow Source

G ECE-H ECE-G

Analytical Test Report for Contractor Furnished Borrow Source

G ECE-H ECE-G

SD-03 Product Data

Displacement Gauge Installation Data G ECE-C

SD-05 Design Data

Gauging Table Data G ECE-C

SD-06 Test Report

Independent Testing Laboratory Qualifications

G ECE-G

Moisture Sample Test Results G ECE-G

Gradation Sample Test Results G ECE-G

Daily Log Sheets of Shipment G ECE-C

Weight Bills G ECE-C

SD-07 Certificates

Weigh Scale Certification G ECE-C

a) WORK PLAN. Submit a plan of operations for obtaining, delivering, and placing sand at site. This work plan must be approved by the Contracting Officer's Representative (COR) prior to the commencement of placement activities at the site. If a barge will be used to transport sand to the site, the Contractor's work plan must include the methodology of getting sand from the barge to the dry beach in accordance with the environmental permits in Exhibit “J”. The work plan shall include measures for controlling pedestrian and sand placement equipment traffic, along with security and safety measures at the project site in a Traffic Control Plan.

b) SAND PLACEMENT EQUIPMENT LIST. Submit a list of all equipment, tools, and machines, including their size, capacities, and operating speeds, to be used in the performance of the work. Maintain all equipment, tools, and machines in satisfactory working conditions at all times.

c) SAND SOURCE. At least thirty (30) calendar days prior to use of the material in Beach Fill placement activities, submit the name(s) and location(s), description of the geologic origin of the sand (s) and gradation (s) of the sand material.

d) DISPLACEMENT GAUGE INSTALLATION DATA. Submit complete information on the sand hauling vessel gauge installation if vessel is used for transportation or placement of sand.

e) GAUGING TABLE DATA. Provide certified sand hauling vessel gauging tables and a copy of the data and calculations used for the preparation of the tables.

f) INDEPENDENT TESTING LABORATORY QUALIFICATIONS. Use only USACE Validated laboratories for testing associated with this Contract. Laboratories must be validated for the specific tests submitted. USACE Validated Laboratories may be located via the website:

https://mtc.erdc.dren.mil/searchvalidation.aspx.

g) WORK AND STORAGE AREAS. Prior to utilizing the work and storage areas, submit a drawing indicating location and all legal documents or leases permitting the use of private or other properties.

h) MOISTURE SAMPLE TEST RESULTS. On the workday following the day that sample testing occurs, submit moisture test results.

i) GRADATION SAMPLE TEST RESULTS. On the workday following the day that sample testing occurs, submit gradation test results.

j) WEIGHT SCALE CERTIFICATION. Prior to the use of any scale under this contract, submit details on the location of the scale and a copy of the certification of the scale’s accuracy from the local weights and measures regulating agency.

k) DAILY LOG SHEETS OF SHIPMENTS. On the workday following shipment, submit a copy of the daily log of all shipments from the sand source(s). The log sheets must include information regarding placement or stockpiling of the shipments, and shipments sampled. The Daily Log sheet and its format must be approved by the Government prior to the shipment of any sand materials.

l) WEIGH BILLS. Provide certified weigh bills to the COR at the time the weighted material is delivered. Certified weigh bills for each load of sand materials delivered to the project site must include certification of weight, the time of weighing, and the time of delivery.

3.1) METHOD OF SAND MEASUREMENT.

a) MEASUREMENT. Acceptable delivered and placed sand will be measured for acceptance by the ton or 2,000 pounds, dry weight. Determination of tonnage of sand must be by actual weight as determined by certified weigh bills or carrier displacement and adjusted by the Government for the moisture content of the sand as described in Paragraph "Adjustment for Moisture Content" of this Section. Determination of the dry weight quantities of material delivered will be made by the Contractor and agreed upon by the Contracting Officer and once agreement has been made, will not be reopened, except on evidence of collusion, fraud, or obvious error. Prior to performing any work under this Section, coordinate all operations with the COR so that necessary sampling of sand materials for quantity determinations will be made at the https://mtc.erdc.dren.mil/searchvalidation.aspx appropriate time. The quantity of dry weight sand material delivered and placed, which is within the specified gradation and contains less than the maximum allowable percent of deleterious materials, must be equal to the total awarded amount stated in the contract.

b) METHOD OF DETERMINING WEIGHT WITH DELIVERY BY TRUCK. The method of measurement for determining the weight of sand materials delivered and placed by truck must be public weight master certified weigh bills provided by the Contractor at the job site. A weighing record must accompany each delivery. The weighing record must indicate the name of the shipper, date, trailer, number, gross, tare and net weights. The weigher must sign each weight record.

The weight delivery ticket and weigh records must be submitted to the COR at the placement site prior to unloading. The COR reserves the right to reject delivery if any required information is missing or incomplete from the delivery tickets. Other methods of establishing weights, if used for determination of weights for payment purposes, must be subject to the approval of the

COR. Weigh bills and the scales used for weighing of trucks and materials must conform to the following requirements.

i) Scales - Scales must conform to NIST HB 44. The tolerance applications of the Handbook, as applicable to under-registration and over-registration and to tests involving digital indications or representations, must apply. A scale must not be used for weighing a load totaling more than the natural capacity marked on the scale by the manufacturer. Any portion of the load in excess of the nominal scale capacity will not be considered for payment.

ii) Accuracy of Scales - The accuracy of the scale must be checked. When a state scale inspector is not immediately available for checking the scale, the Contractor may, at his own expense, secure a check from a local official sealer of weights and measures. The COR may give tentative approval based on check truckloads weighed on other scales which bear an official seal placed in the current calendar year.

iii) Weigh of Vehicle - The total weight of a single highway vehicle must be weighed as a single draft and must not be determined by adding together the results obtained by separately weighing each end of such vehicle except that weighing of a coupled combination may be determined without uncoupling under the following conditions:

(1) The brakes are released.

(2) The is no tension or compression of the drawbar.

(3) The approaches are straight and in the same level plane as the scale platform.

(4) The approached are paved at least 50 feet in each direction with a seal coat of higher type surfacing.

(5) The approaches are of sufficient width and length to ensure level positioning of vehicles during the weighing operation.

iv) Print-Out Weigh Tickets – When a print-out system is employed on a platform or surge bin scale, it must be equipped with a printer which must print out the following information on a triplicate ticket for each truckload. The system must be so interlocked as to allow printing only when the scale has come to a complete rest.

(1) Time,

(2) Date,

(3) Sequential ticket number (may be pre-printed on ticket,)

(4) Gross Weight,

(5) Tare Weigh (trucks must be tare weighted at least twice daily),

(6) Net Weight, and

(7) Truck identification number (or license plate number).

v) Weigh Bills - Scales not equipped with a print-out system, weight bills must contain the same or equivalent data as specified for the print-out system. Weigh bills, including print-outs, must be certified by the signature of the scale operator. The scale operator must attest that the information shown on the weigh bill and the weight(s) observed on the scale at the time the weigh bill was signed are correct. Each truck must be plainly marked by a distinctive number, letter, or name, which must not be changed or given to any other truck during the contract period. The Government reserves the right to periodically inspect the weighing operations at the scales.

vi) Verification of Weighs – The Government reserves the right to have loaded and unloaded trucks re-weighted at another certified weigh scale.

c) METHOD OF DETERMINING WEIGHT WITH DELIVERY BY VESSEL OR BARGE.

i) Gauges - If sand is delivered by vessel or barge, the carrier must, prior to use in connection with this work, be fitted by the Contractor at its own expense with gauges or such other facilities for determining displacement as may be required by, or be satisfactory to, the COR.

Carriers which, owing to their model or other cause, cannot be accurately gauged for displacement, must not be used on this work. Gauges must be graduated to the tenth of a foot, or to another suitable unit approved by the COR. They must be six in number and must be located as follows: two near each end on opposite sides, and two amidships on opposite sides. The gauges must be attached solidly to the hull itself, and wherever practicable, must be located inside the hull. If located inside the hull, provisions must be made for the free passage of the outside water to a vertical tube and for the ready measurement of the depth of the water within the tube. If located outside on wood hulls, the gauges must be protected by solid fenders or be recessed into the planking, or if on steel hulls, the gauge marks may be placed directly on the plates and identified by punch marks. Gauges must be so placed that their zeros are below water when the carrier is in its normal trim, light and free from water. The installation of the gauges must be subject to the approval of the COR. The COR must be notified a minimum of five (5) calendar days prior to installation of gauges.

ii) Gauging Tables - To facilitate the determination of the weight of each load, a gauging table for each carrier employed must be prepared by an accredited agent satisfactory to the COR.

The gauging table must show the cargo weight, in tons of 2,000 pounds, for each unit of measurement of the draft. If the lines of the carrier are such that the cubic feet of displacement for each measured unit of draft can be accurately calculated, the gauging table must be based upon the data, using 62.4 pounds as the weight of one cubic foot of water. If the lines of the carrier to be gauged are such as to render impracticable the preparation of the gauging table by the above-described method, the weight for each unit of draft must be determined by measurement of displacement by actually loading sand of known weight and the weight thus obtained must be entered in the table for use in subsequent gauging’s. If alterations are made in any carrier which affect the accuracy of the gauging table, after it has been prepared, or if otherwise deemed necessary at any time by the COR, the carrier must be remeasured, and a new gauging table prepared.

iii) Reading of Draft Gauges - Readings to determine the draft must be taken before and after unloading, and the difference in tonnage thus found, that is, the difference between displacements loaded and light, will be used to determine the net weight to be paid for. The draft must be determined from the average of all six readings, weighting the readings of the middle gauges at double those of the end gauges. The Contracting Officer or the designated

Contracting Officer's Representative (COR) will be present at all draft gauge readings.

iv) Uniform Loading - The carrier must be so loaded as to cause uniform submergence. The increase in draft on the middle gauges, as a result of the load, must not differ by more than

0.5 feet from each other. The increase in draft between any bow gauges and any stern gauges must not differ more than 1.5 feet from each other. If such is not the case, the

Contractor must trim the carrier by shifting the sand until this limit is reached, before the sand will be accepted. If, however, the carriers proposed to be used by the Contractor are so built that they cannot be loaded as prescribed, and yet can be calibrated accurately for displacement under varying loads, such other method of determination of displacement as may be approved by the COR may be used.

v) Reading in Still Water - All measurements for determining gauging table data and for load depths must be made in still water as close to the work as is possible. The Contractor is required to place the carriers where such measurements can be accurately made.

vi) Leaks - All carriers used in transporting sand must be free of leaks such as would render accurate gauging difficult. Facilities for inspecting the hold of each carrier to determine whether leakage is occurring must be provided. Each carrier must also be provided with adequate pumping facilities, and if water is found to be accumulating in the hold, the carrier must be pumped dry before each gauging, both before and after unloading.

vii) Variations During Unloading Operations - Lightening, by pumping or by transfer of crews or supplies, will not be permitted while sand is being discharged. Should any lightening become necessary, the unloading of sand must be suspended and the load marks must be taken in such manner as to ensure the Government against loss from the cause.

viii) Carrier Designations - Each carrier must be plainly marked by a distinctive number, letter, or name, which must not be changed or given to any other carrier during the contract period.

ix) Variation of Measurements – The readings, other data, and calculations from which the gauging table and the tonnage are determined will be open to verification by the Contractor and must be subject to the approval of the COR. The Contractor is invited to be present in person or to be represented by an authorized agent during the measuring of carriers. When the displacements of the carriers are determined or re-determined, a record of allowed displacement for quantity determination will be sent to the Contractor. If the Contractor protests within five (5) calendar days, the carrier must be re-measured and the Contractor must be present in person or be represented by an accredited agent so that correct measurements can be agreed upon. The Contractor will be given the weight of each load as it is determined. Failure to protest within five (5) calendar days will be taken as equivalent to expressing acceptance of the measurements and weight of sand determined by the COR.

x) Carriers Not Measured - In case any sand is delivered by carriers not measured for displacement and marked as described herein, the Contractor must, at its own expense, furnish means for properly and conveniently weighing such sand at the work site.

4.1) ADJUSTMENT FOR MOISTURE CONTENT - The weights of the sand materials delivered and placed at the project site must be adjusted for moisture content. Moisture content must be determined in the laboratory in accordance with ASTM D2216 or moisture content of materials must be determined in the field in accordance with ASTM D 3017. All moisture content testing must be by the Contractor's hired Independent Laboratory and the test results must be reported to the

Government at the time they become available to the Contractor. The Contractor must take a representative sample of the sand materials in the delivered material for laboratory determination of moisture content. A minimum of one sample must be collected and tested for every 500 tons of material, or portion thereof, delivered and placed from each source, each day. The moisture contents determined by each test will be averaged separately for each source and for each day's deliveries. The total dry weight tons of sand materials delivered each day, from each source, will be determined in accordance with the formula below, using the average moisture content for each day's deliveries from each source.

Total dry weight tons = TW X (1.0 – Percent Moisture) / 2000 pounds

TW = total weight of materials delivered from each respective source for the day, in pounds (sand plus moisture)

2,000 pounds = one ton

Percent Moisture = Average moisture content for each respective source, and each day’s delivered material

5.1) ADJUSTMENT FOR OUT-OF-GRADATION QUANTITIES – Use the following procedure for the adjustment for out-of-gradation sand quantities. For any sieve size, determine the percentage retained on the sieve (R%) from gradation tests on specimens representing a certain tonnage of out-of-gradation material placed on the beach. For any sieve size n, if tests on out-of-gradation materials indicate percentage retained as Rn1, Rn2, Rn3…, corresponding to tonnage of materials placed Wn1, Wn2, Wn3 …., then weighted average of percentage retained for the total out-of-gradation material

(Wn = Wn1 + Wn2 + Wn3+….) for sieve size n can be given by Equation 1:

Rnav = Wn1. Rn1 + Wn2. Rn2 + Wn3. Rn3 + …

Wn1 + Wn2 + Wn3 + ….

The following table (Table 1) will be used to determine the percentage deficient for each sieve size:

Sieve Size n= #8 #16 #30 #50

15 20 16 28

“A” is the minimum percentage required to be retained on a particular size sieve using the series of sieve given in the specifications. Thus, For size #8, A = (100-85) = 15 For size #6, A = (100 -65) – 15 = 20

For size #30, A = (100-49) – 20 - 15 = 16

For size #50, A = (100-21) – 16 -20 – 15 = 28

“B” is Rnav which is the weighted average of percentage retained for the total out-of-gradation material for a particular size.

% Deficiency, Dn = A - B

Subtract the weighted average Rnav from the Minimum Required Percent Retained from Table 1 for each sieve size. This will give a value of Deficiency, Dn in percent for each sieve size. Then use Equation 2

(below) to calculate total tons of in-gradation material to be placed for each sieve size.

Tn= Dn * Wn * SFn

Where:

Tn = Total weight in tons of in-gradation material required to make up for the deficiency of sieve size n

Dn = Deficiency in percent from Table 1

Wn = Total weight in tons of out-of-grade material associated with failed sieve tests size n, placed on the site

SFn = Scale Factor, a constant of proportionality which is equal to 100 divided by the Minimum Required

Percentage Retained given in Table 1 for specific sieve size n

Where:

Sieve Size n= #8 #16 #30 #50

SF= 6.7 5.0 6.3 3.6

Equation 2 will give the minimum tons of in-grade material required to make up for the deficit for each sieve size. Compare the tonnage for each sieve size and determine which sieve size gives the maximum tonnage. This maximum tonnage is the acceptable adjustment for Out-of-Gradation Quantities which is to be provided by the Contractor without additional cost to the Government.

6.1) DELETERIOUS MATERIAL TESTING. No measurement or payment for Petrographic Tests ASTM

C295/C295M, Sodium/Magnesium Sulfate Soundness Tests ASMT C88, and Freezing and Thawing

Tests AASHTO T 130 performed on the initial 50% stockpiles from each Source will be made.

Subsequent performance of these tests, made at the Government’s request, will be measured and paid on a per test basis.

7.1) DEFINITIONS.

Acceptance Reach: segment of the beach fill berm used for inspection and acceptance of work. An acceptance reach is placed to the full design section, and is measured an arbitrary length, up to 300 feet, along the placement baseline. The acceptance reach length must be determined in the field by the COR.

NIPSCO : Northern Indiana Public Service Company

NPS : National Park Service

Deleterious Materials: Components of sand that are deemed less than adequately durable or environmentally unsuitable for the purposes of this work by virtue of their composition, including, but not limited to shale, mica or micaceous minerals, weathered rock fragments, lignite, coal, clay, organic materials, lightweight or other non-durable components.

-END OF SECTION 3-

SUBSECTION 3.1

EROSION PROTECTION – PRODUCTS

1.1) SOURCE OF MATERIAL.

a) CONTRACTOR FURNISHED SOURCES - Provided the materials meet the quality criteria contained within this Performance Work Statement and are approved by the COR, the Contractor may obtain the required beach fill materials from a Contractor-furnished source. A written notice must be provided by the Contractor to the COR fifteen (15) calendar days in advance of the time the material will be used in the work. This notification must include a clear description of the areas, stockpiles, lifts, pits, and geological units in the source to be utilized. Stockpile 50 percent of the sand material to be obtained from a particular source, at the source site. Upon completing the stockpiling at the source site(s), the Government will make an inspection of the source(s) and stockpile(s); and, if material is not from a previously-used, listed and verified source at which testing was performed in the past five (5) years as detailed below in the section title "Material Quality Testing", will witness and direct the gathering of a representative sample from the stockpile(s)for testing. Perform the Petrographic Analysis test(s), Sodium/Magnesium

Sulfate Soundness test(s), and Freezing and Thawing test(s), as described in Paragraph "Material

Quality Testing" on samples collected from the stockpile(s) and furnish the test results to the

Government. Additionally, perform environmental testing of the borrow material as described in

Paragraph "Environmental Testing of Contractor-Furnished Borrow Source". Based on the source and stockpile inspection(s), and the Petrographic Analysis, Sodium/Magnesium Sulfate

Soundness, Freezing and Thawing test(s) results, and environmental testing, a written notice of approval, approval with limitations, or disapproval will be furnished to the Contractor within thirty (30) calendar days after Government receipt of the submitted test results. Petrographic

Analysis, Sodium/Magnesium Sulfate Soundness, and Freezing and Thawing test results which exceed the maximum limits allowable as stated in Paragraph "Material Quality Testing" will result in disapproval of the stockpiled material. The Contractor must begin hauling and storing the approved stockpiled material once written approval is received, and immediately begin a second, separate stockpile of the remaining 50 percent of the material to be used from that particular source. After completing the second stockpile, the Contractor must provide a written notice to the COR thirty (30) calendar days in advance of the time that the Contractor expects to use the material in the work.

b) LISTED SOURCE OF AGGREGATES – The following Government-Listed sources of aggregate material have recently been inspected and reviewed as possible suppliers. Use of these or any other sources must be approved prior to delivery on site. This list of potential sources is being provided for information only and in no particular order. The Government does not guarantee the availability of sufficient quality or quantities from the listed sources. The Contractor is responsible for coordinating with the listed source.

Thelen Materials LLC Aggregate Industries / LafargeHolcim

28957 IL-173 3203 US-12

Antioch, IL 60002 Niles, MI 49120

(847) 395-3313 (743) 216-0841

Beverly Materials LLC Purdy Materials

1100 Brandt Dr 1505 E 510 S Hoffmen Estates, IL 60192 Lafayette, IN 47909

(847) 628-6074 (765) 474-9611

Carri Scharf Materials Co Phend-Brown Inc.

12581 E 200 N Rd 76 W 600 N Heyworth, IL 61745 Leesburg, IN 46538

(309) 473-3555 (574) 453-4354

Ozinga (Moose Lake) Nugent Sand and Gravel 1886 Barron Lake Dr 5205 Indianapolis Rd

Niles, MI 49120 Columbus, IN 47203

(219) 405-5382 (812)372-7508

American Aggregate Inc. Hill Top Basic Resources

2041 M-140 14208 IN-156

Niles, MI 49120 Patriot, IN 47038

(269) 683-6160 (812) 594-2293

2.1) BEACH FILL MATERIAL REQUIREMENTS.

a) GENERAL - Beach fill materials must meet all requirements as specified elsewhere in this document. The COR may, at any time during the contract, at the sand source or at the job site, reject material not meeting the specified requirements. The COR inspection of materials at the sand source and at the job site will be made as part of the government's Quality Assurance

Program. Inspection and testing of materials by the Contractor must be as stated in Paragraphs

"Material Quality Testing" and "Gradation Testing" of this Section. Materials which have been delivered to the project site and are rejected, whether in a stockpile or in place in the beach fill structure, must be removed from the project site at the Contractor's expense.

b) MATERIAL QUALITY - Beach fill material must consist of clean, hard, durable, uncoated, un-weathered particles of natural sand within the limits of the grading as defined under the

Paragraph Gradation. Fine aggregates for use in beach nourishment must consist of natural sand. Manufactured sand consisting of crushed rock, fly ash, or slag will not be permitted as

Beach Fill material. Amounts of organic impurities, light weight and deleterious materials in the beach fill material must be determined by petrographic analyses and limited as specified in paragraph "Material Quality Testing". Deleterious materials include, but are not limited to shale, alkali, chert, weathered carbonates, mica, coated grains of soft and flaky particles, clay lumps, coal, or lignite. The beach fill material must not be obtained from sanitary landfill areas or areas exposed to contaminated ground water or other contaminated materials. In addition, the sand materials must be clean and free of sod, roots, brush, wood, plant residue, seeds of any kind, rubbish, oil, metal, chemical contaminants and other waste materials. The material must not contain organic or non-organic substances which may be leached from the sand in amounts sufficient to be deleterious or harmful or in any way interfere with the designated uses of the lake. Material must also meet all environmental testing requirements.

i) Material Quality Testing - Existing Test results from USACE Validated Laboratories for the corresponding tests may be acceptable to the COR provided they are representative and less than five (5) years from the time of source designation. Arrange for a USACE-Validated

Laboratory, from those listed in Paragraph “USACE-Validated Laboratories ", to perform one

Petrographic Analysis test, one sodium/magnesium sulfate soundness test, and one freeze thaw test, as necessary, as described below, on the material from the initial 50 percent stockpile from each proposed source. Beyond the initial source testing required above, the

Government may require the Contractor to perform additional quality testing, as described below, throughout the contract period to verify material quality.

(1) Petrographic Analysis Test ASTM C295/C295M. The petrographic analysis must be performed and constituents identified such that the criteria below may be readily evaluated. The Beach Fill material must have not more than 15 percent total deleterious materials, and not more than 5 percent of organic impurities determined by the petrographic analyses.

(2) Sodium/Magnesium Sulfate Soundness Test ASTM C88. When the sand is subjected to five cycles of the sodium/magnesium sulfate soundness test, the weighted loss must not exceed 10 percent by weight.

(3) Freezing and Thawing Test AASHTO T 103. Fine aggregates must be subjected to 50 cycles of freezing and thawing in accordance with AASHTO T 103, Procedure A, and may be accepted provided they do not have a loss greater than 10 percent by weight. This test is not required if the Sodium/Magnesium Sulfate Soundness test results in a weighted loss of eight percent or less.

ii) USACE-Validated Laboratories – List of USACE Validating labs at:

https://mtc.erdc.dren.mil/index.aspx

c) GRADATION - The sand materials furnished by the Contractor must have a final composite gradation curve which fits within the band expressed in the table in paragraph "Gradation

Testing" below. Materials which have gradation characteristics which will cause the composite gradation to not comply with the required gradation band must require delivery of an additional dry-weight quantity of in-gradation material as determined by the Government in accordance with the Paragraph "Adjustment for Out-of-Gradation Quantities" of this Section.

i) Gradation Testing - The gradation of materials must be determined in accordance with

ASTM C136. One gradation sample must be taken and tested from each 500 tons of materials per source delivered to the job site. A minimum of two (2) samples must be taken and tested on any day in which delivery of more than 5 truckloads or 100-tons occurs. On days where less than 5 truckloads or 100 tons are delivered and placed, take one sample and perform a gradation test on it. The gradation test samples must be periodically taken at uniform intervals throughout the workday as materials are delivered to the site. In addition to the percentage passing, the test results must also include percentage retained on each sieve. The gradation test on a sample collected at the job site must be completed by next day of sample collection. Test results must be submitted to the Government on the workday following the day of the test.

REQUIRED GRADATION FOR BEACH FILL MATERIALS

Sieve Designation U.S. Standard Square Mesh Percentage by Weight Passing

3/8 inch 100 https://mtc.erdc.dren.mil/index.aspx

No. 4 40-100 No. 8 20-85

No. 16 8-65 No. 30 2-49 No. 50 0-21

No. 100 0-6 No. 200 0-4

3.1) MATERIAL QUALITY ASSURANCE - During the contract period, both prior to and after materials are delivered, visual inspections of the beach fill materials may be performed by the COR. If, due to these inspections, the COR suspects that the material quality or gradation is not as specified herein, the COR may require supplemental testing by the Contractor's hired laboratory or laboratories for tests or a series of tests as described in Paragraph "Material Quality Testing". Samples of the delivered sand for testing and the manner in which the test is to be performed must be as approved by the COR. When test results indicate that the materials do not meet specified requirements the

Contractor must be subject to the adjustments as described in Paragraphs "Adjustment for Out-of-

Gradation Quantities" and "Deleterious Material Testing" of this section.

4.1) ENVIRONMENTAL TESTING OF CONTRACTING-FURNISHED BORROW SOURCE - Material obtained from any Contractor-furnished borrow source will be considered acceptable under this part if the values obtained by the analysis of all parameters specified in Paragraph "Sampling Plan for

Contractor-furnished Borrow Source". If the values obtained by the analysis of one or more of the parameters set forth in Parameter Table below are exceeded, the material from that source will be deemed unsatisfactory and may not be used for this contract. Analytical results must not be averaged for purposes of determining compliance with the requirements set forth.

Parameter Table

Parameter Total Concentration (mg/kg)

Barium 21000 Cadmium 98 Chromium 100000

Copper 4300 Cyanide 0.94

Iron 77000 Lead 400

Manganese 1.9 Mercury 3.1

Nickel 2100 Selenium 550

Zinc 32000 Nitrogen, as nitrate + nitrite 0.6

Nitrogen, as ammonia 4.6 Total kjeldahl Nitrogen 6

Total Phosphorus 2.25

a) SAMPLING PLAN FOR CONTRACTOR-FURNISHED BORROW SOURCE - The Contractor must receive written Government approval of the sampling plan prior to conducting sampling of any

Contractor-furnished borrow source. Address the following, at a minimum, in the sampling plan for any given Contractor-furnished source of material: location of the material source, proposed sample locations (including a map), volume of borrow material, sample collection and handling procedures, laboratory selected, laboratory certifications, parameters to be…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .