W81G6690724940
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
REFERENCE INVITATION FOR BIDS NO. W912P619B0006, "VILLAGE OF GLENVIEW, GLEN OAK ACRES STORM SEWER IMPROVEMENTS -
SECTION 219, COOK COUNTY, IL (USACE-CHICAGO DISTRICT ACQUISITION)"
-- THE DESCRIPTION OF THIS AMENDMENT FOLLOWS ON THE NEXT PAGES --
1. CONTRACT ID CODE PAGE OF PAGES
1 48
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Aug-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P619B0006
X 9B. DATED (SEE ITEM 11)
15-Jul-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Aug-2019
CODE
U.S. ARMY ENGINEER DISTRICT, CHICAGO
231 SOUTH LASALLE STREET SUITE 1500
CHICAGO IL 60604-1437
W912P6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P619B0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
A. BID OPENING DATE AND TIME:
The Bid Opening Date is EXTENDED to August 16, 2019; the bid opening time is not changed.
Therefore, bids shall be delivered to the Chicago District prior to 2:00 p.m. (Central Time) on August 16, 2019. Detailed information regarding the submission of bids is located at section 00 22 13 of the Solicitation document – See “IMPORTANT BID NOTES.”
B. Bidders may email an acknowledged copy of this particular Amendment No. 0004 to Ericka Hillard at ericka.d.hillard@usace.army.mil with a copy furnished to Regina Blair at regina.g.blair@usace.army.mil. All bids must be mailed to hand‐carried per the provisions set forth in the Solicitation document.
C. BID SCHEDULE:
The government is providing a revised bid schedule (Section 00 10 00 – Solicitation Contract Form). Therefore, Bidders shall remove and replace the previously issued respective Section with the Revised Section 00 10 00 enclosed hereunder. Bidders shall provide their prices on the Revised Bidding Schedule. THE FOLLOWING REVISIONS WERE MADE TO THE BID SCHEDULE:
(1) SUBCLIN 0001BD
The pricing detail quantity has increased by 63.00 from 436.00 to 499.00.
(2) SUBCLIN 0001BE
The CLIN extended description has changed from:
SEWER PIPE INSTALLATION, JACKED & BORED, STORM, 48" DIP
To:
SEWER PIPE INSTALLATION, JACKED & BORED, STORM, 48" RCP
The pricing detail quantity has decreased by 63.00 from 144.00 to 81.00.
D. AMENDED SPECIFICATION SECTION: SECTION 01 22 00.00 10 PRICE AND PAYMENT PROCEDURES under sub‐paragraph 1.2.18 OF THE SPECIFICATION SECTION HAS BEEN AMENDED AS FOLLOWS:
The section of ST‐P‐300‐1‐1 between the Jacking Pit and Receiving Pit, crossing under Wagner Road, has changed to read: “SEWER PIPE INSTALLED, JACKED & BORED, STORM, 48” RCP” and the remainder of ST‐P‐300‐1‐1 through the jacking pit and on to ST‐MH‐300‐2‐1 has changed to read: “SEWER PIPE INSTALLED, STORM, 48” RCP”.
--BY THIS AMENDMENT, BIDDERS ARE NOTIFIED THAT THE USACE WILL BE REFLECTING
THE AFORMENTIONED CHANGE VIA THE CONFORMED COPY OF THE CONTRACT. THUS,
THIS AMENDMENT WILL NOT CONTAIN A REVISED SPECIFICATION SHEET; THE REVISED
PAGE WILL BE INCLUDED IN THE CONFORMED CONTRACT. NONETHELESS, THIS
PARTICULAR REVISION/CHANGE IS HEREBY FORMALIZED VIA THIS AMENDMENT AND
THE BIDDER SHALL INCORPORATE THIS CHANGE BY WAY OF ITS BID.
E. CONTRACTOR’S INQUIRIES: By this Amendment, the Chicago District, USACE responds to Contractor’s inquiries (SEE THE FOLLOWING).
Q1. According to the new Bid Schedule issue as a part of Amendment 1, CLIN 0001BE's description is "SEWER PIPE INSTALLATION, JACKED & BORED, STORM, 48" DIP". However both Amendment 2 and Amendment 3 indicate there is no 48" DIP on this project. Please clarify or change the description of CLIN 0001BE to reflect the proper description.
USACE Response Q1: The contractor shall refer to the above Paragraph D, wherein the USACE has made the applicable revision to its Specifications.
Q2. Drawing C‐300 shows pipe ST‐P‐300‐1‐1 to be 48" RCP and a total of 144 lf long between structures ST‐MH‐300‐1‐1 and ST‐MH‐300‐2‐1. CLIN 0001BE shows "SEWER PIPE INSTALLATION, JACKED & BORED, STORM, 48" DIP" to be 144 lf long. Drawing C‐300 also shows a 15' x 40' jacking pit clearly BETWEEN the 2 structures just referenced. This would indicate that the jacked pipe is substantially less length than 144', probably more like 80'. This is would mean that the balance would likely be paid as part of CLIN 0001BD.
With the method of installation described by Amendment 2 and reinforced by Amendment 3, and that this item is a very significant cost item, we recommend revising the bid schedule with more accurate quantities.
USACE Response Q2: The contractor shall refer to the above Paragraph D, wherein the USACE has made the applicable revision to its BID SCHEDULE.
F. POINT OF CONTACT: The Point of Contact (POC) for this Amendment is Ericka Hillard at (312) 846‐5378; email: ericka.d.hillard@usace.army.mil.
(The aforementioned Revised Bid Schedule follows)
REVISED BID SCHEDULE
AMENDMENT 0004
THE BELOW BID FORM SERVES AS THE BID SCHEDULE AND SHALL BE USED BY THE BIDDER
TO ENTER ITS BID PRICING
IMPORTANT NOTE - DISTINCTION OF LINE ITEMS:
The below Bid Schedule contains a combination of Firm Fixed Price (FFP) and cost reimbursable line items. Although “FFP” is shown in the description of the cost reimbursable line items, it is not to be construed as a Firm Fixed Price line item. In this case, the FFP represents the Contract Type, which is firm fixed price. Therefore, the contractor will be reimbursed as stated within the extended description of the cost reimbursable line items.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
DRAINAGE IMPROVEMENTS - BASE WORK
FFP
Bidders shall provide their pricing at sub-items 0001AA through 0001CL, as this Item 0001 identifies the information that relates directly to sub-items 0001AA through 0001CL. Therefore, this Item 0001 is not to be scheduled separately for delivery, nor is it to be identified separately for shipment or performance. Further, Item 0001 is not to be separately priced for payment purposes.
PURCHASE REQUEST NUMBER: W81G6690724940
NET AMT
0001AA 1 Job
MOBILIZATION
FFP
Under this line item, the contractor is required to perform mobilization activities.
The contractor will be compensated for the totality of its activities needed to mobilize its equipment and labor force to the project site.
Payment Provisions: The Government will pay all costs for the mobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment determined by the Contracting Officer of the actual costs, which is not subject to appeal.
0001AB 1 Job
DEMOBILIZATION
FFP
Under this line item, the contractor is required to perform demobilization activities.
The contractor will be compensated for the totality of its activities needed to demobilize its equipment and labor force from the project site.
Payment Provisions: The Government will pay all costs for the demobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment determined by the Contracting Officer of the actual costs, which is not subject to appeal.
0001AC 149 Square
Yard
CLASS D PATCHING, 12" W/AGGREGATE BASE
FFP
CLASS D PATCHING, 12" W/AGGREGATE BASE COURSE, TYPE B, 12"
0001AD 74 Square
AGGREGATE SHOULDERS, 6"
0001AE 628 Linear
Foot
TRENCH PAVING, 4"
0001AF 153 Net Ton
(2,000
LB).
HOT-MIX ASPHALT SURFACE COURSE, MIX "D"
HOT-MIX ASPHALT SURFACE COURSE, MIX "D", N50 - 2 INCH
0001AG 19 Square
HOT-MIX ASPHALT DRIVEWAY REMOVAL
HOT-MIX ASPHALT DRIVEWAY REMOVAL AND REPLACEMENT
0001AH 100 Linear
CONCRETE CURB AND GUTTER REMOVAL
CONCRETE CURB AND GUTTER REMOVAL AND REPLACEMENT, M-3.12
0001AJ 17 Square
CONCRETE DRIVEWAY REMOVAL & REPLACEMENT
0001AK 1,469 Square
CONCRETE SIDEWALK REMOVAL & REPLACEMENT
0001AL 2,237 Square
HMA SURFACE REMOVAL, 2"
0001AM 1 Job
TRAFFIC CONTROL AND PROTECTION
0001AN 79 Linear
THERMOPLASTIC PAVEMENT MARKING - LINE 4"
0001AP 160 Linear
THERMOPLASTIC PAVEMENT MARKING - LINE 6"
0001AQ 44 Linear
THERMOPLASTIC PAVEMENT MARKING- LINE 24"
0001AR 6 Each
EXISTING SIGN REMOVAL AND REINSTALLATION
0001AS 2 Each
EXISTING MAILBOX REMOVAL& REINSTALLATION
0001AT 12 Each
EXPLORATORY EXCAVATION (STORM,SAN,WATER)
0001AU 6 Each
STRUCTURE REMOVAL, STORM
0001AV 24 Linear
STORM SEWER PIPE REMOVAL, 6"
0001AW 77 Linear
STORM SEWER PIPE REMOVAL, 10"
0001AX 212 Linear
STORM SEWER PIPE REMOVAL, 12"
0001AY 24 Linear
SEWER PIPE INSTALLATION, STORM, 6" PVC
0001AZ 2 Linear
SEWER PIPE INSTALLATION, STORM, 10" PVC
0001BA 271 Linear
SEWER PIPE INSTALLATION, STORM, 12" RCP
0001BB 66 Linear
SEWER PIPE INSTALLATION, STORM, 24" RCP
0001BC 437 Linear
SEWER PIPE INSTALLATION, STORM, 36" RCP
0001BD 499 Linear
SEWER PIPE INSTALLATION, STORM, 48" RCP
0001BE 81 Linear
SEWER PIPE INSTALLATION, JACKED & BORED
SEWER PIPE INSTALLATION, JACKED & BORED, STORM, 48" RCP
0001BF 3 Each
STORM SEWER INLET CONSTRUCTION, TYPE A
0001BG 1 Each
STORM CATCH BASINS CONSTRUCTION, TYPE A
STORM CATCH BASINS CONSTRUCTION, TYPE A, 4' DIAMETER
0001BH 7 Each
STORM CATCH BASINS CONSTRUCTION, TYPE C
STORM CATCH BASINS CONSTRUCTION, TYPE C, 2' DIAMETER
0001BJ 1 Each
STORM MANHOLE, TYPE A, 4' DIAMETER
0001BK 3 Each
STORM MANHOLE, TYPE A, 6' DIAMETER
0001BL 1 Each
STORM MANHOLE, TYPE A, 7' DIAMETER
0001BM 2 Each
STORM CONFLICT MANHOLE, TYPE A
STORM CONFLICT MANHOLE, TYPE A, 6' DIAMETER
0001BN 2 Each
SPECIAL RESTRICTOR STORM STRUCTURE, 6'
SPECIAL RESTRICTOR STORM STRUCTURE, 6' DIAMETER
0001BP 1 Each
SPECIAL RESTRICTOR STORM STRUCTURE, 7'
SPECIAL RESTRICTOR STORM STRUCTURE, 7' DIAMETER
0001BQ 1 Each
SPECIAL RESTRICTOR STORM STRUCTURE, 8'
SPECIAL RESTRICTOR STORM STRUCTURE, 8' DIAMETER
0001BR 6 Each
LOWERING OF SANITARY SEWER SERVICE
0001BS 4 Each
SANITARY SERVICE PROTECTION
0001BT 6 Each
WATER SERVICE REPLACEMENT, 1.5"
0001BU 1 Each
WATER MAIN RELOCATION, 6"
0001BV 1 Each
WATER MAIN RELOCATION, 8"
0001BW 145 Linear
SILT FENCE
0001BX 230 Linear
GRADING AND SHAPING OF DITCHES
0001BY 3 Each
INLET PROTECTION FILTER
0001BZ 9 Each
ABOVE GRADE INLET FILTER
0001CA 1,076 Linear
SEWER CONDITION EVALUATION, STORM, PRIOR
SEWER CONDITION EVALUATION, STORM, PRIOR TO CONSTRUCTION
0001CB 1,076 Linear
SEWER CONDITION EVALUATION, STORM, POST
SEWER CONDITION EVALUATION, STORM, POST CONSTRUCTION
0001CC 1,031 Linear
SEWER CONDITION EVALUATION,SANITARY,PRIO
SEWER CONDITION EVALUATION, SANITARY, PRIOR TO
CONSTRUCTION
0001CD 1,031 Linear
SEWER CONDITION EVALUATION,SANITARY,POST
SEWER CONDITION EVALUATION, SANITARY, POST CONSTRUCTION
0001CE 12 Each
TREE ROOT PRUNING
0001CF 12 Each
TREE TRUNK PROTECTION
0001CG 24 Each
TREE REMOVAL (6" TO 15" IN DIAMETER)
0001CH 22 Each
TREE REMOVAL (OVER 15" IN DIAMETER)
0001CJ 48 Square
DETECTABLE WARNING
0001CK 127 Square
PARKWAY RESTORATION
0001CL 1 Lot
PERFORMANCE AND PAYMENT BONDS
FFP
THIS IS A REIMBURSABLE LINE ITEM FOR BOND COVERAGE FOR LINE
ITEMS 0001AA THROUGH 0001CK.
The Government will reimburse the Contractor for the actual cost of acceptable bonds upon receiving evidence of payment (i.e. paid invoice) from the bonding company or agency, not to exceed the total amount of this contract line item. The Government will not pay more than the amount bid for this item. If the actual bond costs are less than the line item amount, the contract will be modified to adjust the line item accordingly. Adjustment(s) to the line item will also be made for any revisions associated with contract price changes.
OPTION DRAINAGE IMPROVEMENTS - OPTION 1 ITEMS
FFP
Bidders shall provide their pricing at sub-items 0002AA through 0002BF, as this Item 0002 identifies the information that relates directly to sub-items 0002AA through 0002BF. Therefore, this Item 0002 is not to be scheduled separately for delivery, nor is it to be identified separately for shipment or performance. Further, Item 0002 is not to be separately priced for payment purposes.
0002AA 260 Linear
OPTION TRENCH PAVING, 4"
0002AB 28 Net Ton
(2,000
LB).
OPTION HOT-MIX ASPHALT SURFACE COURSE, MIX "D"
HOT-MIX ASPHALT SURFACE COURSE, MIX "D", N50 - 2 INCH
0002AC 19 Square
OPTION HOT-MIX ASPHALT SURFACE DRIVEWAY REMOVAL
HOT-MIX ASPHALT SURFACE DRIVEWAY REMOVAL AND
REPLACEMENT
0002AD 505 Square
OPTION HMA SURFACE REMOVAL, 2"
0002AE 1 Job
OPTION TRAFFIC CONTROL AND PROTECTION
0002AF 3 Each
OPTION EXPLORATORY EXCAVATION (STORM,SAN,WATER)
0002AG 3 Each
OPTION STRUCTURE REMOVAL, STORM
0002AH 35 Linear
OPTION STORM SEWER PIPE REMOVAL, 8"
0002AJ 10 Linear
OPTION STORM SEWER PIPE REMOVAL, 12"
0002AK 50 Linear
OPTION ABANDON EXISTING STORM SEWER, 12"
0002AL 83 Linear
OPTION SEWER PIPE INSTALLATION, STORM, 12" RCP
0002AM 249 Linear
OPTION SEWER PIPE INSTALLATION , STORM, 48" RCP
0002AN 2 Each
OPTION STORM SEWER INLET CONSTRUCTION, TYPE A
0002AP 2 Each
OPTION STORM CATCH BASINS CONSTRUCTION, TYPE A
0002AQ 2 Each
OPTION STORM CATCH BASINS CONSTRUCTION, TYPE C
0002AR 2 Each
OPTION STORM MANHOLE, TYPE A, 6' DIAMETER
0002AS 2 Each
OPTION LOWERING OF SANITARY SEWER SERVICE
0002AT 2 Each
OPTION WATER SERVICE REPLACEMENT, 1.5"
0002AU 2 Each
OPTION WATER MAIN RELOCATION, 6"
0002AV 135 Linear
OPTION SILT FENCE
0002AW 105 Linear
OPTION GRADING AND SHAPING OF DITCHES
0002AX 6 Each
OPTION ABOVE GRADE INLET FILTER
0002AY 185 Linear
OPTION SEWER CONDITION EVALUATION, STORM, PRIOR
0002AZ 185 Linear
OPTION SEWER CONDITION EVALUATION, STORM, POST
0002BA 185 Linear
OPTION SEWER CONDITION EVALUATION, SANITARY
0002BB 185 Linear
OPTION SEWER CONDITION EVALUATION,SANITARY,POST
0002BC 3 Each
OPTION TREE ROOT PRUNING
0002BD 3 Each
OPTION TREE TRUNK PROTECTION
0002BE 103 Square
OPTION PARKWAY RESTORATION
0002BF 1 Lot
OPTION PERFORMANCE AND PAYMENT BONDS
FFP
THIS IS A REIMBURSABLE LINE ITEM FOR BOND COVERAGE FOR LINE
ITEMS 0002AA THROUGH 0002BE.
The Government will reimburse the Contractor for the actual cost of acceptable bonds upon receiving evidence of payment (i.e. paid invoice) from the bonding company or agency, not to exceed the total amount of this contract line item. The Government will not pay more than the amount bid for this item. If the actual bond costs are less than the line item amount, the contract will be modified to adjust the
OPTION DRAINAGE IMPROVEMENTS - OPTION 2 ITEMS
FFP
Bidders shall provide their pricing at sub-items 0003AA through 0003BK, as this Item 0003 identifies the information that relates directly to sub-items 0003AA through 0003BK. Therefore, this Item 0002 is not to be scheduled separately for delivery, nor is it to be identified separately for shipment or performance. Further, Item 0003 is not to be separately priced for payment purposes.
0003AA 64 Square
OPTION CLASS D PATCHING, 12" W/AGGREGATE BASE
CLASS D PATCHING, 12" W/AGGREGATE BASE COURSE, TYPE B, 12"
0003AB 86 Square
OPTION AGGREGATE SHOULDERS, 6"
0003AC 19 Square
OPTION HOT-MIX ASPHALT DRIVEWAY REMOVAL
HOT-MIX ASPHALT DRIVEWAY REMOVAL AND REPLACEMENT
0003AD 1,398 Square
OPTION CONCRETE SIDEWALK REMOVAL & REPLACEMENT
CONCRETE SIDEWALK REMOVAL AND REPLACEMENT
0003AE 64 Square
OPTION HMA SURFACE REMOVAL, 2"
0003AF 1 Job
OPTION TRAFFIC CONTROL AND PROTECTION
0003AG 40 Linear
OPTION THERMOPLASTIC PAVEMENT MARKING - LINE 4"
0003AH 109 Linear
OPTION THERMOPLASTIC PAVEMENT MARKING - LINE 6"
0003AJ 18 Linear
OPTION THERMOPLASTIC PAVEMENT MARKING- LINE 24"
0003AK 2 Each
OPTION EXISTING SIGN REMOVAL AND REINSTALLATION
0003AL 2 Each
OPTION EXISTING MAILBOX REMOVAL AND REINSTALL
EXISTING MAILBOX REMOVAL AND REINSTALLATION
0003AM 5 Each
OPTION EXPLORATORY EXCAVATION (STORM,SAN,WATER)
0003AN 4 Each
OPTION STRUCTURE REMOVAL, STORM
0003AP 192 Linear
OPTION STORM SEWER PIPE REMOVAL, 12"
0003AQ 192 Linear
OPTION SEWER PIPE INSTALLATION, STORM, 12" RCP
0003AR 340 Linear
OPTION SEWER PIPE INSTALLATION, STORM, 30" RCP
0003AS 1 Each
OPTION STORM SEWER INLET CONSTRUCTION, TYPE A
0003AT 1 Each
OPTION STORM CATCH BASINS CONSTRUCTION,TYPE A,4
0003AU 1 Each
OPTION STORM CATCH BASINS CONSTRUCTION,TYPE C,2
0003AV 1 Each
OPTION STORM MANHOLE, TYPE A, 4' DIAMETER
0003AW 1 Each
OPTION STORM MANHOLE, TYPE A, 6' DIAMETER
0003AX 1 Each
OPTION SPECIAL RESTRICTOR STORM STRUCTURE, 5'
SPECIAL RESTRICTOR STORM STRUCTURE, 5' DIAMETER
0003AY 1 Each
OPTION WATER SERVICE REPLACEMENT, 1.5"
0003AZ 245 Linear
OPTION GRADING AND SHAPING OF DITCHES
0003BA 3 Each
OPTION ABOVE GRADE INLET FILTER
0003BB 330 Linear
OPTION SEWER CONDITION EVALUATION, STORM, PRIOR
0003BC 330 Linear
OPTION SEWER CONDITION EVALUATION, STORM, POST
0003BD 330 Linear
OPTION SEWER CONDITION EVALUATION, SANITARY
0003BE 330 Linear
OPTION SEWER CONDITION EVALUATION,SANITARY,POST
0003BF 5 Each
OPTION TREE ROOT PRUNING
0003BG 5 Each
OPTION TREE TRUNK PROTECTION
0003BH 8 Square
OPTION DETECTABLE WARNING
0003BJ 137 Square
OPTION PARKWAY RESTORATION
0003BK 1 Lot
OPTION PERFORMANCE AND PAYMENT BONDS
FFP
THIS IS A REIMBURSABLE LINE ITEM FOR BOND COVERAGE FOR LINE
ITEMS 0003AA THROUGH 0003BJ.
The Government will reimburse the Contractor for the actual cost of acceptable bonds upon receiving evidence of payment (i.e. paid invoice) from the bonding company or agency, not to exceed the total amount of this contract line item. The Government will not pay more than the amount bid for this item. If the actual bond costs are less than the line item amount, the contract will be modified to adjust the
SUMMATION OF BID PRICES
BASE WORK (ITEMS 0001 THROUGH 0001CL): $_____________________
OPTION 1 ITEMS (ITEMS 0002 THROUGH 0002BF): $____________________
OPTION 2 ITEMS (ITEMS 0003 THROUGH 0003BK): $____________________
OVERALL BID PRICE (ITEMS 0001 THROUGH 0003BK (INCLUDES ALL RESPECTIVE SUBITEMS):
END OF REVISED BID SCHEDULE