W912P6-14-R-0019-0002.pdf

PDF 25 KB Posted

Attached to
Ecosystem Restoration of Nippersink Creek Section 206
Solicitation number
W912P6-14-R-0019
Issued by

About this file

Amendment 0002 to Solicitation W912P6-14-R-0019.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W81G6633025705

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SUBJECT: W912P6-14-R-0019, "Nippersink Creek Ecosystem Restoration Section 206"

CONTINUED ON NEXT PAGE

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Sep-2014

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P6-14-R-0019

X 9B. DATED (SEE ITEM 11)

14-Aug-2014

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Sep-2014

CODE

U. S. ARMY ENGINEER DISTRICT, CHICAGO

231 SOUTH LASALLE STREET SUITE 1500

CHICAGO IL 60604-1437

W912P6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P6-14-R-0019

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMMARY OF CHANGES

1. AMENDED PROJECT SPECIFICATION SECTIONS: The following specification sections have been amended based on Contractor’s Inquiries:

a. Section 01 45 00.00 – language added about the SSHO requirement.

2. CONTRACTOR INQUIRIES: USACE responses to Contractor Inquiries are included with this amendment.

3. POINT OF CONTACT: The POC for this amendment is Alex Heinzel at (312) 846-5368 or alex.heinzel@usace.army.mil.

(End of Summary of Changes)

W912P6-14-R-0019

W912P6-14-R-0019 AMD 0002

Contractor Inquiries

Question #1: Would it be possible to add section 3.4.3.1 from the Portage Lakefront Park Ecosystem Restoration project into the Nippersink Creek Section 206 documents? The section reads as follows:

“3.4.3.1 Safety Requirement for Establishment of Native Landscape During the establishment period for the native plantings (Years 2-5) only, the superintendent or foreman can have an additional role as the Site Safety and Health Officer (SSHO). The Contractor may designate the superintendent or foreman as the SSHO during the establishment period. Submit, for approval, documentation the superintendent has the following qualifications:

a. A minimum of 30 hours Occupational Safety and Health Administration (OSHA) Construction or General Industry training for approval.

b. Meets the requirements of EM 385-1-1, Section 1 and 29 CFR 1926.16 for the project.”

Answer: Specification Section 01 45 00.00 has been modified by this amendment. Please see Specification Section 01 45 00.00 for revisions.

Question #2: Barring any potential changes in the QAQC team as they relate to the above question, we would like to know if it is the government’s intent to have the full QAQC / Safety team as outlined in the documents (including the SSHO, the CQC System Manager, and the submittals clerk) for the full five year duration of the project. If so, was this included in the owners construction cost estimate?

Answer: By this amendment, changes have been made to Specifications Section 01 45 00.00. Please bid accordingly.

Question #3: Per section 01 45 00.00 – “3.4.4 Organizational Changes” it appears that we can make changes in the CQC staff as the work dictates. Can we designate an individual who meets all the necessary requirements as both the foreman of the native landscape management activities and as the SSHO?

Answer: Based on the changes made to Section 01 45 00.00 in this amendment, the superintendent or foreman during Year 2-5 activities can act as the Site Safety and Health Officer(SSHO).

Question #4: Can we designate an individual who meets all the necessary requirements as both the foreman of the native landscape management activities and as the CQC systems manager?

Answer: Based on the changes made to Section 01 45 00.00 by this amendment, the CQC System Manager must be assigned as System Manager and have no other duties.

Question #5: Can we designate one individual who meets all the necessary requirements as the foreman of the native landscape management activities, the CQC systems manager, and the SSHO?

Answer: Please see the response to Question #4.

Question #6: Would the owner consider alternate stockpile locations to help reduce the long haul distances involved in the excavation?

Answer: No alternate stockpile locations will be allowed.