W912P524R0004 A0003 Revised Plans and Specifications.pdf

PDF 389 KB Posted

Attached to
Wolf Creek GSU Replacement Federal contract opportunity
Solicitation number
W912P524R0004
Issued by
Department of the Army Corps of Engineers Engineering District Nashville

About this file

This document is an amendment to a solicitation for the Wolf Creek GSU Transformer Replacement Project (Solicitation No. W912P524R0004). The purpose of this amendment is to: 1) Provide updated technical plans and specifications, the physical site visit sign-in sheet, and revise the fill-in information for FAR Clause 52.228-1 Bid Guarantee to be consistent with the Instructions to Offerors; 2) Provide government answers to questions received from industry; and 3) Update FAR Provision 52.252-3 Alterations in Solicitation.

The amendment revises several technical specifications, drawings, and FAR clauses. The bid guarantee requirement is for the construction portion of the contract only, up to 20% of the bid price or $3 million, whichever is less. This amendment is issued by the U.S. Army Corps of Engineers Engineering District Nashville for the Wolf Creek GSU Transformer Replacement Project.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT: Wolf Creek GSU Transformer Replacement Project PURPOSE: the purpose of this Amendment is to:

1.) Provide updated Technical Plans and Specifications, the physical site visit sign-in sheet, and revise the fill-in information for FAR Clause 52.228-1 to be consistent w ith the Instructions to Offerors.

2.) Provide Government answ ers to questions received from Industry.

3.) Update FAR Provision 52.252-3, Alterations in Solicitation.

1. CONTRACT ID CODE PAGE OF PAGES

K 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-Oct-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P524R0004

X 9B. DATED (SEE ITEM 11)

06-Aug-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-Oct-2024

CODE

CONTRACTING DIVISION

110 9TH AVE N

NASHVILLE TN 37203

W912P5 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P524R0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The following have been added by full text:

AMENDMENT 0003 CHANGES

AMENDMENT 0003

Wolf Creek GSU Transformer Replacement Project

DESCRIPTION OF CHANGES

SPECIFICATIONS

1. Specification 26 08 01.00 26

a. Paragraph 3.2 Operational Test Phase has been revised.

2. Specification 48 19 23.04 26

a. Paragraph 2.11.7 On-Line Dissolved Gas and Moisture Content Monitor Operational has been revised.

b. Paragraph 2.11.7.1 General has been revised.

c. Paragraph 2.11.7.2 Features has been revised.

d. Paragraph 2.11.7.3 Communications and Data has been revised.

e. Paragraph 2.11.7.4 Accessories and Features to be included has been revised.

3. Specification 48 20 00.04

a. Paragraph 1.8.4 Specialized Equipment Installation Services has been revised.

CONTRACT DRAWINGS

1. The following Contract Drawing sheets have been revised.

a. E-301, Transformer Requirements Summary Sheet

b. E-303, Transformer Layout and Limiting Dimensions Sheet1

c. E-306, Transformer Layour and Limiting Dimensions Sheet4

d. E-307, Transformer Layout and Limiting Dimensions Sheet5

e. E-311, Transformer Mounted Devices Layout and Detail

FAR CLAUSES

1. FAR Clause 52.228-1, Bid Guarantee

a. FAR Clause 52.228-1 has been revised to reflect the bid guarantee is for the construction portion only of the requirement.

SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR QUOTERS

The following have been modified:

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be twenty (20) percent of the bid price for the construction portion of the contract price or $3 Million, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of provision)

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 0001:

PROJECT: Wolf Creek GSU Transformer Replacement PURPOSE: the purpose of this Amendment is to:

1) Provide updated Technical Specifications.

2) Provide the Pre-Proposal Teleconference Slides.

3) Update the Instructions, Paragraph 2.0, Bonds and Insurance, to include Bid Guarantee.

4) Incorporate FAR Provision 52.228-1, Bid Guarantee, by full text.

5) Update FAR Clause 52.211-12, Liquidated Damages - Construction.

6) Update FAR Clause 52.217-7, Options for Increased Quantity - Separately Priced Line Item.

7) Provide updated Construction Wage Determinations.

8) Update FAR Provision 52.252-3, Alterations in Solicitation.

Amendment 0002:

PROJECT: Wolf Creek GSU Replacement PURPOSE: the purpose of this Amendment is to:

1) Provide Site Visit Information. A site walk will occur on Wednesday, 9 October 2024 at 10:00AM Central Time.

2) Incorporate FAR 52.236-27 Alternate I, Site Visit (Construction) - Alternate I by Full Text.

3) The deadline for receipt of questions in Projnet Bidder Inquiry has been extended to 11 October 2024.

4) Update FAR Provision 52.252-3, Alterations in Solicitation.

Amendment 0003:

PROJECT: Wolf Creek GSU Transformer Replacement Project PURPOSE: the purpose of this Amendment is to:

1.) Provide updated Technical Plans and Specifications, the physical site visit sign-in sheet, and revise the fill-in information for FAR Clause 52.228-1 to be consistent with the Instructions to Offerors.

2.) Provide Government answers to questions received from Industry.

3.) Update FAR Provision 52.252-3, Alterations in Solicitation.

(end of provision)

(End of Summary of Changes)

File details come from the government source that posted it. Updated .