LRN Crane MATOC and Seed Project (Old Intake Crane) Site Visit Overview.pptx
PPTX presentation 8 MB Posted
- Attached to
- Replace, Rehab, Repair (R3) Crane MATOC
- Solicitation number
- W912P523R0004
About this file
This document provides an overview of a pre-bid site visit for a Multiple Award Task Order Contract (MATOC) for crane replacement, rehabilitation, and repair services. The solicitation seeks proposals for an initial seed project to replace the 75-ton intake gantry crane at Old Hickory Dam with a new 105-ton crane, with a value between $10-25 million. The MATOC has a total ceiling value of $95 million shared across multiple awardees over a five-year period. Offerors must submit proposals for both the seed project and MATOC evaluation factors to be considered for award. Evaluation will be based on past performance, technical approach, small business participation, and price. The Department of the Army Corps of Engineers will issue task order requests on a competitive or sole-source basis under the MATOC.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Site Visit 18 July 2023 LRN Crane (Replace, Rehab, Repair) MATOC Seed Project:
Task Order 0001 - “Old Hickory Intake Crane” File Name
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
.59
Gov’t Team Introductions File Name JW Purcell – LRN Contracting Officer
Cierra Vega / Dani Bautch – LRN Contract Specialists
Omar Acevedo – LRN Project Manager
Jason Bedard – Design Technical Lead – HDC Mechanical Engineer
Lionel Fox – LRN Electrical Engineer
Keith Ward – LRN – Mechanical Engineer
Wyatt Sherry – LRN – Structural Engineer
Chris Campbell – Old Hickory Power Plant Maintenance Supervisor
Have all attendees sign in.
Have all contractors introduce themselves and their firm.
Topics of Discussion Overall MATOC:
Basic Scope Types of Cranes and Tonnage
Seed Project- Task Order 0001: Old Hickory Intake Crane:
Scope
Subsequent Task Orders Under MATOC Subsequent to the seed project task order- Task orders under this MATOC may be evaluated using either Best-value Lowest Price Technically Acceptable (LPTA) OR Best-Value Trade Off (BVTO) methods in accordance with FAR 15.101. Task order proposal requests (TOPR) will be sent electronically to the MATOC contractors to provide a fair opportunity in accordance with FAR 16.505(b)(1). Single or Multiple awards may be made on any TOPR and will be stated in the TOPR letter.
Overview of MATOC Project Description: The Nashville District U.S. Army Corps of Engineers (USACE) anticipates a requirement for a firm fixed-price Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) for civil works construction services including crane replacement, rehabilitation, and repairs within the Nashville District Mission Boundaries. This MATOC will also be available for use at Government Facilities and installations located anywhere within the geographical boundaries of the Great Lakes and Ohio River Division if MATOC capacity allows.
Type of Set-Aside: This procurement is an unrestricted MATOC with a target of six (6) sources, which includes a small business set-aside reserve with a target of three (3) sources.
The magnitude of the resulting award(s) will be a shared Not-to-Exceed capacity of $95,000,000.
The MATOCs will be awarded for a three (3) year base period and two (2), one (1) year option periods.
The minimum and maximum values for a single Task Order are $100,000 and $25,000,000 dollars, respectively.
Great Lakes and Ohio River Division Mission Boundaries
Basic MATOC General Scope of Work and typical equipment/tonnage :
The general scope of work to be performed by the Crane IDIQ MATOC will typically include repairs, rehabilitation, and replacements of existing cranes and hoist equipment at USACE projects. The primary types of various cranes and equipment with large tonnage capacities are at USACE operated hydropower, navigation, and flood risk management facilities. Most of the work includes, but is not limited to, the following equipment:
• Bridge Cranes (typical capacity may range from 75 tons to 600 tons)
• Overhead Gantry Cranes (typical capacity may range from 15 tons to 480 tons)
• Underhung Monorail Cranes (typical capacity may range from 5 tons to 25 tons)
• Below-the-hook lifting devices Other types of cranes and equipment may include, but not limited to:
• Navigation Facility Cranes
• Floating and Floating Derrick Cranes (typical capacity may range from 10 tons to 550 tons)
• Base/Wall Mounted Jib Hoists/Booms
Seed Project (Task Order 0001) Old Hickory Intake Crane:
Old Hickory Intake Crane (September 2022) SEED PROJECT MAGNITUDE: Disclosure of magnitude of the seed project “Task Order 0001 – Old Hickory Intake Crane” is between $10,000,000.00 and $25,000,000.00.
**Offerors are required to submit a proposal for all evaluation factors for the seed project in order to be considered for the MATOC pool.
SCOPE: Replace existing 75 Ton Intake Gantry Crane with a new 105 Ton Intake Gantry Crane at Old Hickory Dam. The Contractor is to design, manufacture, install, test, and commission the new intake crane on both primary shore power and emergency diesel generator power. The new crane must be fully commissioned and operational prior to demolition of the existing crane (Option). Existing intake crane is known to have asbestos containing material and lead based paint.
Old Hickory Intake Crane Project background File Name The existing Intake crane was manufactured by MOFFETT ENG CO. and was completed around 1956, with an original design capacity of 75 tons. The crane was installed to provide the closure of the three intake gates of a unit against unbalanced head in case of runaway turbine, and to handle intake gates as required for unit maintenance. Only one intake gate can be lowered at a time. The crane was also designed to perform gate cracking to re-water generating units with unbalanced head across the gate. Below are the current hoist functions:
Main Hoist - 75 tons Deploy the intake gates for maintenance.
Deploy intake gates for emergency closure.
Perform gate cracking to re-water unit.
Deploy the spillway bulkheads Used for various maintenance lifts, removing hatch covers, deploying floating work platform.
Trash Hoist – 10 tons Remove and install the intake trash racks.
Various maintenance lifts.
Old Hickory Intake Crane Project Crane Functions File Name A new intake crane will be designed to replace the function of the original crane and restore reliability of the plant. The list below describes the function of each hoist.
Main Hoist - 105 tons Deploy the intake gates for maintenance.
Deploy intake gates for emergency closure.
Perform gate cracking to re-water unit.
Deploy the spillway bulkheads
Auxiliary Hoist (new) – 10 tons Handle intake and spillway hatch covers.
Deploy floating work platform.
Various maintenance lifts.
Handle mechanical and electrical equipment on the intake and spillway deck
Trash Hoist – 10 tons Remove and install the intake trash racks.
Plans and Specifications for Seed Project – Task Order 0001 – Old Hickory Intake Crane Specifications:
Division 01 - General Requirements Division 02 - Existing Conditions Division 03 - Concrete Division 05 - Metals Division 09 - Finishes Division 13 - Special Construction Division 25 - Integrated Automation Division 26 - Electrical Division 41 - Material Processing and Handling Equipment
Plans and Specifications for Seed Project – Task Order 0001 – Old Hickory Intake Crane Contract Drawings:
General: location, index, and staging area Mechanical Crane diagram Walkways and stairways Trolley layout Lifting beam details Operator cab Intake gate and spillway bulkhead lifting lug details Electrical Operator chair layout Radio control details AC auxiliary power one line diagram
Basis for award for MATOC and SEEd The statement of work and plans/specifications for the seed project, “Task Order 0001, Old Hickory Intake Crane”, will be included in this single-phase solicitation. Offerors are required to submit a proposal for all evaluation factors for the seed project in order to be considered for the MATOC pool.
Following the evaluation of proposals, the MATOC awards and seed project “Task order 0001 Old Hickory Intake Crane” will be made based on the best value to the Government using the Best Value Trade-Off source selection process in FAR Part 15.
Offerors are cautioned that the award may not necessarily be made to the lowest priced offerors. Any deficiency found in source selection could render the proposal unawardable both for the seed project and the overall MATOC.
The government may award the MATOCs and seed project (Task Order 0001) on the basis of initial offers received without discussions; therefore, an offeror’s proposal should contain the offeror’s best terms from a technical and price standpoint.
Submission requirements to be eligible for the MATOC pool and to be eligible for the seed project can be found in the RFP.
Factors to be Evaluated Factor I: Past Performance Confidence: Each Offeror’s past performance will be evaluated to determine the level of confidence the Government has in the Offeror successfully completing the solicited work. There are three aspects to the past performance evaluation: Recency, Relevancy (including context of data) and Quality (including general trends in contractor performance and source of information).
IMPORTANT: a stand-alone proposal whose past performance projects submitted are as JV’s, are not always available to be evaluated appropriately through CPARS.
Factor II: Technical Approach: Each Offeror’s proposal shall demonstrate the offeror’s approach to performing the required work as outlined in the scope of work and associated references.
Factor III: Small Business Participation Proposal: All Offerors shall submit a Small Business Participation Proposal (SBPP) in accordance with Defense Federal Acquisition Supplement (DFARS) 215.304. The SBPP will be incorporated into any resultant prime contract as the basis for a formal Small Business Subcontracting Plan the successful Offeror (if Other-Than-Small) will be required to submit upon contract award.
Factor IV: Price: Price proposals will be evaluated by a cost engineer (separate from the SSEB) for fairness, reasonableness, price realism and for material unbalancing through the use of price analysis in accordance with FAR 15.404-1. Should certified cost and pricing data be required, then cost analysis may be performed to determine realism and reasonableness. Pricing of the seed project will be used as the total evaluated price for purposes of the best value trade-off.
Task Order procedures
Future Projects: When work under this MATOC arises, a Task Order Proposal Request (TOPR) letter will be issued to all participants in the MATOC pool that have maintained satisfactory performance.
The TOPR will specify construction performance requirements, the schedule for a site visit, and requirements for proposal submission. The TOPR will include such documents as technical specifications, drawings, data, attachments, DOL Wage Determinations, and a statement of work.
Task orders will be competed among the MATOC pool or negotiated on a sole source basis. The circumstances justifying a sole source procurement are stated in W912P523R0004 Solicitation.
Competed task orders will generally be awarded based on the lowest, responsive price received. The Government reserves the right to award task orders based on the best value trade off process, where price may be more important, equal, or less important than past performance or technical factors when combined. The basis of award for task orders will be stated in the individual Task Order Proposal Request (TOPR) letter.
Whenever possible, task order awards will be made without discussions.
Contracting Comments
Questions: I will hand out note cards for your use. You may ask questions here today, especially to our technical experts and they can answer them but know that nothing is “official” unless it is submitted via our Bidder Inquiry system – ProjNet. ProjNet will be discussed more in depth in the Solicitation, as well as have the “Bidder Inquiry Key” which is like your password to getting into the system for this project. Please use these notecards to take notes on any questions or comments you may think of as we walk the site today.
Things to be proactive on:
-SAM.gov: Please have your SAM account active and up to date.
-ProjNet: please log into ProjNet and make sure you can access the Bidder Inquiry page.
-Procurement Integrated Enterprise Environment (PIEE) Account: The Solicitation will have links for how to do that and to make sure you have the proper Role. Proposals shall be submitted via PIEE, and they will only be accepted when they are sent via PIEE.
- Any agreements or commitments for proposal submission (JV, subcontractors, supervisor/managerial commitments)
Questions and Comments
All formal questions must be uploaded to Projnet.
Proposals are currently due by 31 July 2023 at 1:00 PM Central Time, pending any amendments including proposal extensions.