W912P518B0006_TSpecs_RTA-certified_final.pdf
PDF 3 MB Posted
- Attached to
- Barkley Lock - Electrical Operating System Replacement Federal contract opportunity
- Solicitation number
- W912P518B0006
About this file
W912P518B0006 Technical Specs
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.pdf | ||
| Site_Visit_Attendees.pdf | ||
| W912P518B0006_TSpecs_Am2pgs.pdf | ||
| W912P518B0006_TPlans_Am2Sheets.pdf | ||
| W912P518B0006_Amend_0002_BAR_Electrical_Operating_System_Replacement.pdf | ||
| W912P518B0006_Amend_0001_BAR_Electrical_Operating_System_Replacement.pdf | ||
| Foreign_National_Site_Visit_Request_Form.pdf | ||
| W912P518B0006_Final.pdf | ||
| Site_Visit_Request_Form.pdf | ||
| TPLANS_BAR_LockElectOpSystReplace_RTA_Certified_Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. W912P518B0006
US Army Corps Of Engineers
Nashville District
LOCK ELECTRICAL OPERATING
SYSTEM REPLACEMENT
Barkley Lock and Dam Cumberland River Grand Rivers, Livingston County, Kentucky
Technical Specifications RTA – Certified Final
April 2018
THIS PAGE INTENTIONALLY LEFT BLANK
FOR DUPLEX PRINTING
Lock Electrical Operating System Replacement Barkley Lock and Dam W912P518B0006 RTA-Certified Final Livingston County, Kentucky
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 22 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 50 PROJECT SITE SECURITY AND AT/OPSEC PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 95 00 FORMS AND ATTACHMENTS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND DECONSTRUCTION OF EXISTING CONTROL PANELS,
CONTROL CONSOLES, MOTOR CONTROL CENTERS AND
INTERCONNECTING CABLES AND WIRING
DIVISION 26 - ELECTRICAL
26 28 00 MOTOR CONTROL CENTERS AND PANELBOARDS
26 60 13 LOW-VOLTAGE MOTORS (460 VAC)
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 01 45 BARKLEY LOCK CONTROL SYSTEM REHABILITATION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
1.2 CONTRACTOR'S STAGING AREA
1.3 SITE WORKING HOURS
1.3.1 Government Project Personnel Working Hours
1.3.2 Contractor's Working Hours
1.3.3 Lock Outage Plan
1.4 COORDINATION CONFERENCES
1.5 PARTNERING
1.6 REFERENCES
1.7 SUBMITTALS
1.8 PROJECT SIGNS
1.8.1 General
1.8.2 Materials
1.8.3 Painting
1.8.4 Erection and Maintenance
1.9 CONTRACTOR'S STAGING AREA
1.10 SAFE CLEARANCE PROCEDURES
1.11 DAILY CLEANUP AND DISPOSAL
1.12 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.13 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK
1.14 ON-SITE EQUIPMENT AND MATERIAL APPROVAL
1.15 EVALUATION OF CONTRACTOR PERFORMANCE
1.16 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.17 MEASUREMENT AND PAYMENT
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 AVAILABILITY AND USE OF UTILITY SERVICES
3.1.1 Contractor Responsibilities
3.1.2 Interruptions of Utilities
-- End of Section Table of Contents --
SECTION 01 00 00 Page 1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
This section comprises an explanation of the general contract requirements needed to accomplish the work. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and drawings.
The scope of this project is to furnishing all plant, equipment, supplies, and labor to design and install a new relay based controls system for the Barkley Lock. The Contractor shall remove existing equipment. This upgrade shall also include two new motor control centers, new tow haulage controls, and new emergency gate controls. The new controls system design shall be based on contract plans and specifications. The Contractor shall remove all existing equipment to be upgraded. The Contractor is responsible for commissioning the entire lock controls system. A detailed scope of work is located in Section 35 01 45 BARKLEY LOCK CONTROL SYSTEM
REHABILITATION.
1.2 CONTRACTOR'S STAGING AREA
The Contractor will be assigned an area within or near the project site for use as a staging area. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner. Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.
1.3 SITE WORKING HOURS
1.3.1 Government Project Personnel Working Hours
Barkley Lock is operational 24 hours a day, 7 days a week. The scheduled working hours of the Project maintenance staff are Mondays through Thursdays from 6:00 a.m. until 4:30 p.m. Fridays, Saturdays and Sundays are non-work days. All Project maintenance support required by the Contractor shall be scheduled during the Project staff working hours.
1.3.2 Contractor's Working Hours
The Contractor's schedule of work hours, shifts and days of the week shall be coordinated with the COR. Notification of any proposed changes of the schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site shall be coordinated with the COR. The Contractor shall comply with the requirements of EM 385-1-1 Section 01.A.20 Fatigue Management Plan (FMP).
SECTION 01 00 00 Page 2
1.3.3 Lock Outage Plan
The Contractor shall provide a lock outage plan in order to determine the amount of time the lock will be inoperable to lock watercraft. The lock outage plan shall be submitted as specified in Section 35 01 45 BARKLEY
LOCK CONTROL SYSTEM REHABILITATION.
1.4 COORDINATION CONFERENCES
Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this project. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to this installation. The Corps of Engineers and the Contractor will be represented at each of these meetings. Coordination conferences will be scheduled to occur when notified by the Contracting Officer.
1.5 PARTNERING
In order to most effectively accomplish this contract, the Government urges the contractor to join the Government in establishing a cohesive and professional project management team. Through this "partnering" relationship both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project’s intended results are achieved, within budget and on schedule. This endeavor seeks an environment that nurtures team building, cooperation and trust between the Government and the Contractor. The partnering relationship would be bilateral in make-up, and participation will be totally voluntary.
The first step in initiating the concept would be a joint project management team "partnering" conference attended by multiple officers from each organization representing management and the key jobsite staff of each entity. The initial conference would be held within the first thirty
(30) days following contract award. The Resident Engineer would chair the conference, establish its agenda and distribute minutes of the meeting. A professional facilitator acceptable to both parties would lead the participants of the session, through the steps of team building and the formation of a problem solving mechanism within the group. The conference duration would be no more than one day. Location of the conference would be offsite within a 60 mile radius of the jobsite at a facility which offers conference rooms and food service. All costs in connection with rented facilities and the facilitator would be shared equally by the Government and the Contractor. Each organization would pay other costs of its respective employees attending the conference.
Additional partnering sessions would be held no less than biannually.
Implementation of the partnering concept and philosophy would be an on-going process.
1.6 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
SECTION 01 00 00 Page 3
EP 310-1-6a (2006) Sign Standards Manual, VOL 1
EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices
ER 385-1-31 (2009) The Control of Hazardous Energy
1.7 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Lock Outage Plan
1.8 PROJECT SIGNS
1.8.1 General
Furnish and erect, within 15 days after issuance of the Notice to Proceed, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN at the location directed by the Contracting Officer. Letter signs on one side only and conform to EP 310-1-6a (Section 16), EP 310-1-6b , and to the details and colors shown on the sketches attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS. Name the project as follows:
BARKLEY LOCK ELECTRICAL OPERATING SYSTEM REPLACEMENT
1.8.2 Materials
Construct the sign with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material.
Screws shall be commercial quality and of sizes shown.
1.8.3 Painting
Apply one prime coat and two finish coats of exterior oil paint to signs and post before lettering. Apply letters and trim to one side only using one coat of enamel of color, style, and size shown.
1.8.4 Erection and Maintenance
Erect signs at the locations designated by the Contracting Officer. Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs throughout the life of the contract. Maintain signs in good condition until completion of the contract. Remove signs from the site upon final acceptance of the contract work.
1.9 CONTRACTOR'S STAGING AREA
The Contractor will be assigned a portion of the locks land side storage yard for use as a staging area. The yard is located adjacent to the lock with gated access. All materials and electrical/mechanical equipment for this project shall be staged and/or stored in a fenced-in area.
SECTION 01 00 00 Page 4
Contractor shall contact the lockmaster for the exact staging location.
The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government approves, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner.
Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.
Storage of equipment and materials will be permitted only in designated staging areas. A minimum access space of three feet shall be maintained between the Contractor's stored items and existing facility equipment.
1.10 SAFE CLEARANCE PROCEDURES
Project personnel use A Safe Clearance System, as stated in ER 385-1-31 and amended by the Nashville District to ensure continuity of service and safety to personnel and equipment. Any work performed which requires taking the Project's operating equipment out of service will be done only after a formal clearance is obtained by the Contracting Officer with 48-hour minimum notice. Contractor personnel shall not violate clearance. Any violation of Safe Clearance Procedures will be grounds for removal of the offender(s). Up to five copies of the Nashville District Safe Clearance Procedure will be supplied to the Contractor upon request.
1.11 DAILY CLEANUP AND DISPOSAL
Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.
1.12 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.
1.13 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK
The Government will limit interference with the Contractor's work to the maximum reasonable extent and the Government and Contractor shall coordinate as necessary.
1.14 ON-SITE EQUIPMENT AND MATERIAL APPROVAL
The Contractor shall deliver all required equipment and materials to the project site and obtain on-site approval from the Contracting Officer Representative prior to the start of any physical work.
1.15 EVALUATION OF CONTRACTOR PERFORMANCE
The Contractor's performance will be evaluated in accordance with FAR Part
SECTION 01 00 00 Page 5
42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum.
The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section
01 95 00 FORMS AND ATTACHMENTS.
The Contractor's review of the evaluation shall be completed electronically at the CPARS website, http://www.cpars.gov . This website also includes guidance and the user's manual.
Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.
1.16 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
a. U.S. Department of Labor Veterans employment: www.vets.gov/
b. Federal veteran employment information: www.fedshirevets.gov/index.aspx
c. Veterans’ Employment and Training Service (VETS):
http://www.dol.gov/vets/
d. Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/
e. U.S. Army Warrior Transition Command Employment Index:
http://www.wct.army.mil/modules/employers/index.html
f. Hiring Our Heroes initiative:
www.uschamberfoundation.org/hiring-our-heroes
1.17 MEASUREMENT AND PAYMENT
No separate payment will be made for the work covered under this section.
The costs thereof shall be included in the item to which the work pertains.
SECTION 01 00 00 Page 6
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 AVAILABILITY AND USE OF UTILITY SERVICES
3.1.1 Contractor Responsibilities
a. The Contractor shall be responsible for the availability of utilities for use on the project. Raw water is available with no charge at the site. The contractor shall supply any other utilities needed at his cost. The Contractor shall carefully conserve any utilities furnished without charge.
b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia.
c. The Contractor is responsible for providing drinking water facilities for all personnel associated with this contract.
3.1.2 Interruptions of Utilities
a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.
b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) days prior to date of proposed interruption. The request shall give the following information:
(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)
(2) Size of line and location of shutoff.
(3) Buildings and services affected.
(4) Hours and date of shutoff.
(5) Estimated length of time services will be interrupted.
c. Services shall not be shutoff until receipt of approval of the proposed hours and date from the Contracting Officer.
d. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency.
e. Operation of valves on water mains will be by Government personnel.
Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay or to restore service without delay in event of emergency.
-- End of Section --
SECTION 01 00 00 Page 7
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 PAYMENT ITEMS
1.1.1 Performance and Payment Bonds
1.1.1.1 Payment
1.1.1.2 Unit of Measure
1.1.2 Demolition of Existing Control Systems
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.3 Upstream and Downstream Control Consoles for Control Shelters
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.4 New Relay Control Panels
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.5 Operations Building Operator's Panel
1.1.5.1 Payment
1.1.5.2 Unit of Measure
1.1.6 Hydraulic Local Control Panels
1.1.6.1 Payment
1.1.6.2 Unit of Measure
1.1.7 Operations Building Interface Panel Modifications
1.1.7.1 Payment
1.1.7.2 Unit of Measure
1.1.8 Emergency Gate Control
1.1.8.1 Payment
1.1.8.2 Unit of Measure
1.1.9 Motor Control Centers (MCC's)
1.1.9.1 Payment
1.1.9.2 Unit of Measure
1.1.10 Tow Haulage Control
1.1.10.1 Payment
1.1.10.2 Unit of Measure
1.1.11 Field Device Installation
1.1.11.1 Payment
1.1.11.2 Unit of Measure
1.1.12 Installation and Wiring of the New Control Systems
1.1.12.1 Payment
1.1.12.2 Unit of Measure
1.1.13 Factory Acceptance Tests
1.1.13.1 Payment
1.1.13.2 Unit of Measure
1.1.14 Start-up and Commissioning Services
1.1.14.1 Payment
1.1.14.2 Unit of Measure
1.1.15 Operation and Maintenance Manuals
SECTION 01 22 00 Page 1
1.1.15.1 Payment
1.1.15.2 Unit of Measure
1.1.16 Training Services
1.1.16.1 Payment
1.1.16.2 Unit of Measure
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 CONTRACT COST BREAKDOWN
SECTION 01 22 00 Page 2
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 PAYMENT ITEMS
Payment items for the work required under this contract are listed in the BIDDING SCHEDULE and described below for Barkley Lock Control Rehab. All costs for items of work, which are not specifically mentioned to be included in a particular payment item, shall be included in the listed item most closely associated with the work involved. Payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, equipment, tools, supplies, and incidentals necessary to complete the work, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Performance and Payment Bonds
1.1.1.1 Payment
Payment will be made for the performance and payment bonds that are required as part of this contract. The Government will pay the actual cost of acceptable performance and payment bonds or the Contractor's bid price, whichever is less. The Contractor shall provide evidence of payment (paid invoice) from the bonding company or agency. If the actual cost of the bonds is less than the line item amount, the contract will be modified to adjust the line item accordingly. Adjustment(s) to the line item will also be made for any revisions to the actual bond costs associated with contract changes.
1.1.1.2 Unit of Measure
Unit of measure: Job.
1.1.2 Demolition of Existing Control Systems
1.1.2.1 Payment
Payment for performing all demolition work, as specified in Section 02 41 00 DEMOLITION and shown in the contract drawings, will be made at the contract price per Job for "Demolition of Existing Control Systems".
1.1.2.2 Unit of Measure
Unit of measure: Job.
1.1.3 Upstream and Downstream Control Consoles for Control Shelters
1.1.3.1 Payment
Payment will be made for costs associated with Upstream and Downstream
SECTION 01 22 00 Page 3 control consoles for control shelters. Payment will be made at the single job pay item for "Upstream and Downstream Control Consoles for Control Shelters" in accordance with contract plans and specifications Section
35 01 45 BARKLEY LOCK CONTROL SYSTEM REHABILITATION.
1.1.3.2 Unit of Measure
Unit of measure: Job.
1.1.4 New Relay Control Panels
1.1.4.1 Payment
Payment will be made for costs associated with New relay control panels.
Payment will be made at the single job pay item for "New Relay Control Panels" in accordance with contract plans and specifications Section
35 01 45 BARKLEY LOCK CONTROL SYSTEM REHABILITATION.
1.1.4.2 Unit of Measure
Unit of measure: Job.
1.1.5 Operations Building Operator's Panel
1.1.5.1 Payment
Payment will be made for costs associated with the Operation Building Operator's Panel and the Small Craft Annunciation System. Payment will be made at the single job pay item for "Operations Building Operator's Panel" in accordance with contract plans and specifications Section 35 01 45
BARKLEY LOCK CONTROL SYSTEM REHABILITATION.
1.1.5.2 Unit of Measure
Unit of measure: Job.
1.1.6 Hydraulic Local Control Panels
1.1.6.1 Payment
Payment will be made for costs associated with the Hydraulic Local Control Panel. Payment will be made at the single job pay item for "Hydraulic Local Control Panels" in accordance with contract plans and specifications Section 35 01 45 BARKLEY LOCK CONTROL SYSTEM REHABILITATION.
1.1.6.2 Unit of Measure
Unit of measure: Job.
1.1.7 Operations Building Interface Panel Modifications
1.1.7.1 Payment
Payment will be made for costs associated with the Operations Building Interface Panel Modifications. Payment will be made at the single job pay item for "Operations Building Interface Panel Modifications" in accordance with contract plans and specifications Section 35 01 45 BARKLEY LOCK
CONTROL SYSTEM REHABILITATION.
SECTION 01 22 00 Page 4
1.1.7.2 Unit of Measure
Unit of measure: Job.
1.1.8 Emergency Gate Control
1.1.8.1 Payment
Payment will be made for costs associated with emergency gate control.
Payment will be made at the single job pay item for "Emergency Gate Control" in accordance with contract plans and specifications Section 26 60 13 LOW-VOLTAGE MOTORS (460VAC) and Section 35 01 45 BARKLEY LOCK
CONTROL SYSTEM REHABILITATION.
1.1.8.2 Unit of Measure
Unit of measure: Job.
1.1.9 Motor Control Centers (MCC's)
1.1.9.1 Payment
Payment for furnishing all equipment, materials, and performing all operations required for the installation of two MCC's and other miscellaneous items as specified in Section 26 28 00 MOTOR CONTROL CENTERS AND PANELBOARDS, and shown in the contract drawings, will be made at the contract price per Job for "Motor Control Centers".
1.1.9.2 Unit of Measure
Unit of measure: Job.
1.1.10 Tow Haulage Control
1.1.10.1 Payment
Payment for providing and installing the tow haulage control as specified in Section 26 60 13 LOW-VOLTAGE MOTORS (460VAC) and Section 35 01 45 BARKLEY LOCK CONTROL SYSTEM REHABILITATION, and shown in the contract drawings, will be made at the contract price per Job.
1.1.10.2 Unit of Measure
Unit of measure: Job.
1.1.11 Field Device Installation
1.1.11.1 Payment
Payment for furnishing all equipment, materials, methods, labor and performing all operations required for the installation of Field Devices as specified in Section 35 01 45 BARKLEY LOCK CONTROL SYSTEM REHABILITATION. This payment item includes items listed in Tasks 10 and 12.
1.1.11.2 Unit of Measure
Unit of measure: Job.
SECTION 01 22 00 Page 5
1.1.12 Installation and Wiring of the New Control Systems
1.1.12.1 Payment
Payment will be made for costs associated with installation and wiring of the new control systems. Payment will be made at the single job pay item for "Installation and Wiring of the New Control Systems" in accordance with contract plans and specifications Section 35 01 45 BARKLEY LOCK
CONTROL SYSTEM REHABILITATION.
1.1.12.2 Unit of Measure
Unit of measure: Job.
1.1.13 Factory Acceptance Tests
1.1.13.1 Payment
Payment will be made for costs associated with factory acceptance tests.
Payment will be made at the single job pay item for "Factory Acceptance Tests" in accordance with contract plans and specifications 35 01 45
BARKLEY LOCK CONTROL SYSTEM REHABILITATION.
1.1.13.2 Unit of Measure
Unit of measure: Job.
1.1.14 Start-up and Commissioning Services
1.1.14.1 Payment
Payment will be made for costs associated with providing start-up and commissioning services. Payment will be made at the single job pay item for "Start-up and Commissioning Services" in accordance with contract plans and specifications Section 35 01 45 BARKLEY LOCK CONTROL SYSTEM
REHABILITATION.
1.1.14.2 Unit of Measure
Unit of measure: Job.
1.1.15 Operation and Maintenance Manuals
1.1.15.1 Payment
Payment will be made for costs associated with proving operation and maintenance manuals. Payment will be made at the single job pay item for "Operation and Maintenance Manuals" in accordance with contract plans and specifications Section 35 01 45 BARKLEY LOCK CONTROL SYSTEM REHABILITATION.
1.1.15.2 Unit of Measure
Unit of measure: Job.
1.1.16 Training Services
1.1.16.1 Payment
Payment will be made for costs associated with proving training services.
SECTION 01 22 00 Page 6
Payment will be made at the single job pay item for "Training Services" in accordance with contract plans and specifications Section 35 01 45 BARKLEY
LOCK CONTROL SYSTEM REHABILITATION.
1.1.16.2 Unit of Measure
Unit of measure: Job.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
SECTION 01 22 00 Page 7
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
3.3.2 Activity Durations
3.3.3 Procurement Activities
3.3.4 Mandatory Tasks
3.3.5 Government Activities
3.3.6 Standard Activity Coding Dictionary
3.3.6.1 Workers Per Day (WRKP)
3.3.6.2 Responsible Party Coding (RESP)
3.3.6.3 Area of Work Coding (AREA)
3.3.6.4 Modification Number (MODF)
3.3.6.5 Bid Item Coding (BIDI)
3.3.6.6 Phase of Work Coding (PHAS)
3.3.6.7 Category of Work Coding (CATW)
3.3.6.8 Feature of Work Coding (FOW)
3.3.7 Contract Milestones and Constraints
3.3.7.1 Project Start Date Milestone and Constraint
3.3.7.2 End Project Finish Milestone and Constraint
3.3.7.3 Interim Completion Dates and Constraints
3.3.7.3.1 Start Phase
3.3.7.3.2 End Phase
3.3.8 Calendars
3.3.9 Open Ended Logic
3.3.10 Default Progress Data Disallowed
3.3.11 Out-of-Sequence Progress
3.3.12 Added and Deleted Activities
3.3.13 Original Durations
3.3.14 Leads, Lags, and Start to Finish Relationships
SECTION 01 32 01 Page 1
3.3.15 Retained Logic
3.3.16 Percent Complete
3.3.17 Remaining Duration
3.3.18 Cost Loading of Closeout Activities
3.3.18.1 As-Built Drawings
3.3.18.2 O & M Manuals
3.3.19 Anticipated Adverse Weather
3.3.20 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 Initial Project Schedule Submission
3.4.3 Periodic Schedule Updates
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CD/DVDs
3.5.2 Narrative Report
3.5.3 Schedule Reports
3.5.3.1 Activity Report
3.5.3.2 Logic Report
3.5.3.3 Total Float Report
3.5.3.4 Earnings Report by CLIN
3.5.3.5 Schedule Log
3.5.4 Network Diagram
3.5.4.1 Continuous Flow
3.5.4.2 Project Milestone Dates
3.5.4.3 Critical Path
3.5.4.4 Banding
3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram
3.6 PERIODIC SCHEDULE UPDATE
3.6.1 Periodic Schedule Update Meetings
3.6.2 Update Submission Following Progress Meeting
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Time Impact Analysis (Prospective Analysis)
3.8.3 Forensic Schedule Analysis (Retrospective Analysis)
3.8.4 Fragmentary Network (Fragnet)
3.8.5 Time Extension
3.8.6 Impact to Early Completion Schedule
3.9 FAILURE TO ACHIEVE PROGRESS
3.9.1 Artificially Improving Progress
3.9.2 Failure to Perform
3.9.3 Recovery Schedule
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01 Page 2
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this
SECTION 01 32 01 Page 3 specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6 version 8.4.
2.1.2 Contractor Software
Scheduling software used by the contractor must be Primavera P6 version
7.0 or later.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate
SECTION 01 32 01 Page 4 level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks,as applicable, in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission, review and acceptance of features require design completion
c. Submission of mechanical/electrical/information systems layout drawings.
d. Long procurement activities
e. Submission and approval of O & M manuals.
f. Submission and approval of as-built drawings.
g. Submission and approval of DD1354 data and installed equipment lists.
h. Submission and approval of testing and air balance (TAB).
i. Submission of TAB specialist design review report.
j. Submission and approval of fire protection specialist.
k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
l. Air and water balancing.
m. Building commissioning - Functional Performance Testing.
SECTION 01 32 01 Page 5
n. Controls testing plan submission.
o. Controls testing.
p. Performance Verification testing.
q. Other systems testing, if required.
r. Contractor's pre-final inspection.
s. Correction of punch list from Contractor's pre-final inspection.
t. Government's pre-final inspection.
u. Correction of punch list from Government's pre-final inspection.
v. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
SECTION 01 32 01 Page 6
Field Activity Code Length Description
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities cannot have more than one Work Area Code.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
SECTION 01 32 01 Page 7
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are Each activity can have only one Phase of Work code.
a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.
b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 00 QUALITY CONTROL.
An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the
SECTION 01 32 01 Page 8 longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.7.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.3.7.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.3.7.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated days provided in the contract clause TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends .
3.3.9 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.10 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
SECTION 01 32 01 Page 9
3.3.11 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.
Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.12 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.3.13 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.3.14 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
b. Start to Finish (SF) relationships are prohibited.
3.3.15 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.
3.3.16 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.
3.3.17 Remaining Duration
Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.
SECTION 01 32 01 Page 10
3.3.18 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
3.3.18.1 As-Built Drawings
If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, which ever is greater, up to $200,000. Activity will be declared 100 percent complete upon the Government's approval.
3.3.18.2 O & M Manuals
Cost load the "Submission and approval of O & M manuals" activity not less than $20,000. Activity will be declared 100 percent complete upon the Government's approval of all O & M manuals.
3.3.19 Anticipated Adverse Weather
Paragraph applicable to contracts with clause entitled TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Reflect the number of anticipated adverse weather delays allocated to a weather sensitive activity in the activity's calendar.
3.3.20 Early Completion Schedule and the Right to Finish Early
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.
b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data CD/DVD, reports, and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.4.1 Preliminary Project Schedule Submission
Within 15…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.