Barkley Lock - Electrical Operating System Replacement Federal contract opportunity
Solicitation number
W912P518B0006
Issued by
Department of the Army Corps of Engineers Engineering District Nashville

About this file

W912P518B0006 Amendment 0002

View the file

Other files for this federal contract opportunity

Other files attached to Barkley Lock - Electrical Operating System Replacement, newest first.
File Type Posted
Bid_Abstract.pdf PDF
W912P518B0006_TPlans_Am2Sheets.pdf PDF
Site_Visit_Attendees.pdf PDF
W912P518B0006_TSpecs_Am2pgs.pdf PDF
W912P518B0006_Amend_0001_BAR_Electrical_Operating_System_Replacement.pdf PDF
TPLANS_BAR_LockElectOpSystReplace_RTA_Certified_Final.pdf PDF
W912P518B0006_TSpecs_RTA-certified_final.pdf PDF
W912P518B0006_Final.pdf PDF
Site_Visit_Request_Form.pdf PDF
Foreign_National_Site_Visit_Request_Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTING DIVISION (RK)

110 9TH AVENUE SOUTH, ROOM A680

NASHVILLE TN 37203

W38XDD73207038

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Project: Barkley Lock Electrical Operating System Replacement

1. Add Questions and Answ ers, and Site Visit Minutes from site visit on 21-May-2018.

2. Add Technical Changes document titled TechChanges-AM2.docx.

3. Post Technical Plan changes to FBO.Gov titled W912P518B0006_TPlan AM2Sheets.pdf, and Technical Specif ication changes titled W912P518B0006_TSpec AM2pgs.pdf

4. DFARS 252.204-7004, Alt A, is deleted.

5. FAR 52.252-3, Alterations in Solicitation, is updated.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Jun-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P518B0006

X 9B. DATED (SEE ITEM 11)

07-May-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Jun-2018

CODE

US ARMY CORPS OF ENGINEERS-CELRN-RC-N

DIRECTORATE OF CONTRACTING

110 9TH AVENUE SOUTH, RM A680

NASHVILLE TN 37203

W912P5 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912P5

FACILITY CODECODE

EMAIL:TEL:

W912P518B0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

QUESTIONS AND ANSWERS

Questions and Answers

Barkley Lock - Replacement of Electrical Operating System

1. During the pre-bid it was stated that we could take equipment across the emergency gate.

What type of time frame will there be before we could get it back across when finished?

ANSWER: The lock staff would need to be notified 24 hours in advance of needing to re-raise the emergency dam in order to move equipment. The emergency dam availability will also depend upon the Contractor’s means and methods for the controls work being done.

2. During the pre-bid it was said that the concrete lids which give access to the gallery levels have never been removed. What is USACE’s expectations for when 1) the hatches cannot be lifted off, 2) the lift is made, and they crumble due to their age causing them to be unusable?

ANSWER: There is no connection between the lids and the lock wall other than paint, water proofing, and corrosion over time. Therefore, bidders should assume the lids can be removed without damaging them. The method of removal shall be determined by the Contractor and approved by the Contracting Officer. It is the responsibility of the Contractor to select the appropriate methods and equipment necessary to complete the task.

3. Can an explanation of how the outage will be made available?

ANSWER: See Technical Specification Section 35 01 45 paragraph 1.4.1.

4. When is the expected start date of the project?

ANSWER: See FAR 52.211-10 Commencement, Prosecution, and Completion of Work, which is included in the Solicitation.

5. On the prints for the console cabinets and various panels, manufactures are given for the components. Is an “or equal” component satisfactory?

ANSWER: Yes. See Technical Specification Section 35 01 45.

6. Will detailed installation drawings need to be provided by the contractor as part of the preconstruction submittals?

ANSWER: Yes. See Technical Specification Section 35 01 45, 3.5.1 Shop/Installation Drawings.

7. Due to the short time between the walk through and the end of questions being able to be submitted can an extension be granted for questions? If further questions should arise during the preliminary job take off it could lead to an inflated quote from the contractors.

ANSWER: No. The deadline for receipt of questions will not be extended.

8. Will the site visit sign-in sheet be provided?

ANSWER: Yes. The site visit sign-in sheet and the Government’s responses to questions posed by prospective bidders were posted to FBO.gov.

9. Are there any mechanical drawings associated with the replacement of the motors and valves?

ANSWER: Information on the motors and valves can be found on the following reference drawings: Q9-31/4.3, Q9-33/9.1, Q9-25/1.3, Q9-25/2.4, Q9-25/3.3, Q9-25/4.3, and Q9-25/5.2.

10. Will the existing piping for the culvert and miter gate valves remain and be reused?

ANSWER: The existing hydraulic piping for culvert and miter gate valves will remain. It is the responsibility of the Contractor to ensure the new valves can be installed onto the existing piping.

11. Does any of the existing cabling and/or equipment to be removed contain asbestos or lead that would require abatement?

ANSWER: There is a possibility of lead and or asbestos within the facility. If the Contractor suspects the material they are working on contains lead or asbestos, they are responsible for having it tested. If it turns out that this is positive, a modification can be written to address the test and proper abatement of the substance. If it turns out to be negative, the cost of the test shall be on the Contractor.

12. Do the Hydraulic System Circulation Pumps needs replaced? If so, how many hydraulic circulation pumps are there?

ANSWER: No hydraulic system circulation pumps are being replaced.

13. I believe there are 4 hydraulic gate and valve pumps that need replaced. Can you confirm?

ANSWER: See the Government’s Response to Question # 12.

14. Is there a hydraulic system piping diagram available?

ANSWER: The hydraulic system piping can be seen on the following reference drawings: Q9- 27/2.1, Q9-27/3.3, Q9-27/4.1, Q9-27/5.2, Q9-27/8.2, and Q9-27/1.4.

15. Are the solenoids for the bubbler system being replaced?

ANSWER: The bubbler solenoids are not being replaced.

16. Are any mechanical components of the bubbler system being replaced?

ANSWER: No.

17. Is a guided wave radar measurement device acceptable for level measurement?

ANSWER: This sensor can be used as long as it meets the requirements of Technical Specification Section 35 01 45 Paragraph 2.1.4.1.

18. What is the maximum depth of the lock chamber?

ANSWER: Reference drawings Q9-3/13.2 and Q9-20/23.6.

19. Is the lock currently operational and if not, what is the reason?

ANSWER: The lock is operational.

20. General Question-Are we replacing any 480 vac Power cables other than for the tow Haulage? Worded another way- Are we replacing the 110v control wiring only except the 480 vac cables for tow Haulage?

ANSWER: It is the Government’s intent to reuse existing feeders. The Government will not allow the Contractor to extend the length of 480 VAC cable by splicing cable.

21. In Ref 2.1.2 of specs-Are we replacing the directional/proportional valves only and not the hydraulic cylinders for the gates and valves? Worded another way-Are we replacing any gate or valve hydraulic cylinders?

ANSWER: The hydraulic cylinders are not being replaced.

22. General Question- Are the motors to be replaced on the emergency lift gate and tow haulage to be brake/motor combos?

ANSWER: The lift gate and tow haulage shall be electric brake motors. See Technical Specification Section 26 60 14, 1.3 General Requirements.

23. What are the Governments expectations with respect to the prototype required in 35 01 45 paragraph 2.1.6.4? Does this prototype have to be a full scale working model or a computer model? Can it be built in the Contractor’s shop or must it be built on-site? Will the Government take possession of the prototype after a successful demonstration? How is success defined?

ANSWER: The Contractor shall build a physical, table-top scale model for the emergency gate and controls and demonstrate the operations of the scale model (i.e. operate the scale model up and down several cycles without any issue; demonstrate skew correction during operation;

demonstrate skew limit stoppage). It shall be built at the Contractor’s shop using components controls essentially the same as those being installed at the work site. The Government will take possession of the prototype after the Contractor finishes the work.

24. Does the 4 -20 mA signal wiring have to be in a separate conduit? Can they be in the cable tray or free-aired?

ANSWER: Bid as specified in drawings Q9-E23, Q9-E43 and Q9-E44. .

25. What is the approximate weight of each of the concrete access panels that we have to lift up?

ANSWER: Information on the concrete access panels can be found on the following reference drawings that have been added: Q9-20/60.3, Q9-20/63.1, and Q9-31/1.4.

26. Can we modify the concrete access panels for lift points? (drill holes for supporting anchors for the lift, etc)

ANSWER: Yes, if the Contractor wishes to install lifting points, they should prepare a sketch and plan for the installation, that will be approved by the COR prior to installation.

27. Will there be a designated site laydown area? There is not one on the drawings. If so, where it be located?

ANSWER: Yes, the Contactor will be given a portion of the fenced in area in the Lock Parking Lot.

28. For the replacement motor, where is the frame number found? We cannot find it in the drawings or specifications.

ANSWER: Information on the replacement motor frame numbers can be found in the following updated technical specifications: Section 26 60 13, Paragraph 1.3.1 General.

29 On Drawing Q9-E8, the plans call for a “Miter Gate Valve, Parker Hydraulics, Model D-41564 DV832”. We have been in contact with suppliers of Parker Hydraulics and they say that Parker Hydraulics does not make anything with that part number. Was this part number a typo? Can you please clarify?

ANSWER: Information on the appropriate Hydraulic Valves can be found on the following updated contract drawings: Q9-E4, Q9-E6, Q9-E8, and Q9-E10.

30. Can another sight visit be provided?

ANSWER: The only site visit scheduled for this project was on 21 May 2018. If you missed the scheduled site visit, no other arrangements will be made due to personnel and time restrictions.

SITE VISIT MINUTES

CELRN-RC-N 22 May 2018

MEMORANDUM FOR RECORD

SUBJECT: PRE-BID SITE VISIT BARKLEY ELECTRICAL OPERATION SYSTEM

REPLACEMENT

1. Purpose: To summarize the Site Visit held on 21 May 2018 AT 10:00 A.M.

2. Attendees:

Government:

Mr. Caleb Skinner, CELRN-OP-WKY/A Mr. Jamie Nabakowski, CELRN-EC-C Mr. Allan Steele, CELRN-EC-D-EM Mr. John Reed, CELRN-ECC-W Mr. Son Pham, CELRN-OP-N Mr. Edward Tefft, CELRN-ECC-W

Contractors:

Mr. Mike Wedekewer - Weeks Sales and Service Mr. Daniel Benoit - Current Technologies Inc. (CTI) Mr. Shane Garner - CEC Controls Mr. Ed Ferrell – Current Technologies Inc. (CTI) Mr. Anthony Andrews – Koontz Electric Company Inc.

Mr. Timothy Orr – Tybe Company LLC Mr. Jessie Almon – Whitehead Electric Company Inc.

Mr. Gary Whitehead – Whitehead Electric Company Inc.

Mr. Jim Povolny – The Povolny Group Inc.

Mr. Kevin Jones – Electrical Maintenance & Construction Mr. Bret Young – Government Contract Engineering Mr. Jonathan Craig - Government Contract Engineering Mr. Justin Perkins – Collier Electrical Services Mr. Greg Peyton - Collier Electrical Services

Welcome and introductions . . . . . . . . . . . . . . Ray Kendrick

Thank everyone for their interest and time. This is the pre-bid site visit for Barkley Electrical Operating System Replacement. The contract will be for 420 calendar days.

• Please sign the attendance sheet as it comes around.

• Introduce all of the Corps employees

• (Go around the room and have everyone introduce themselves)

• Today’s schedule will include:

o Highlights of the solicitation o Technical and Safety (Caleb Skinner) o We will address questions to the best of our ability, however anything said today is not official unless it is in writing in an issued amendment to this solicitation.

Questions shall be in writing and sent to Ray Kendrick at email address ray.kendrick@usace.army.mil no later than 22 May 2018 at 1:00 PM Central Time

Questions received after this deadline will not be addressed. If there is a discrepancy between what is said here today and what is written in the solicitation, the document governs.

Contract Clauses and Contract Information. .. . . . . . . Ray Kendrick

• This acquisition is a 100% Total Small Business.

• Type of contract: Firm Fixed-Price Construction contract

• Basis of Selection of Award: Award shall be made to the lowest priced bidder who is determined to be responsive and responsible. See Federal Acquisition Regulation (FAR) 52.214-19, Contract Award—Sealed Bidding—Construction, for more information.

• Bids are due 7 June 2018 NLT 1:00 pm Central Time. (At time of site visit; bids are now due on 26 June 2018 at 1:00 p.m. Central Time)

• Wage Rate Requirements (Construction) formerly known as the Davis Bacon Act o This solicitation includes Department of Labor wage rates under the Wage

Determinations Section of the solicitation. At a minimum you shall be required to pay your employees these rates plus fringe benefits for performance under this contract.

• Payment and Performance Bonds will be required.

• Please do not submit information that is not requested. Follow the guidelines in the solicitation. It is unnecessary to have special printing, binding color, or graphics.

• As a reminder, we will address questions to the best of our ability, however anything said today is not official unless it is in writing in an issued amendment to this solicitation.

Questions shall be in writing and sent to Ray Kendrick at email address ray.kendrick@usace.army.mil no later than 22 May 2018 at 1:00 PM central time Questions received after this deadline will not be addressed. If there is a discrepancy between what is said here today and what is written in the solicitation, the document governs.

o An amendment will be posted with the information and questions from today’s meeting on www.fbo.gov website.

Technical & Safety. .. . . . . . . Caleb Skinner mailto:ray.kendrick@usace.army.mil http://www.fbo.gov/

Caleb Skinner conducted a safety briefing before the site visit began.

Attendees toured the site which ended approximately at 1:30 P.M. Central Time.

TECHCHANGES - AM2

Solicitation No. W912P518B0006 Amendment No. 0002

CHANGES TO TECHNICAL SPECIFICATIONS

Section 26 60 13 LOW-VOLTAGE MOTORS (460 VAC) Remove Section 26 60 13 page 3 and replace with revised Section 26 60 13 page 3.

Section 35 01 45 BARKLEY LOCK CONTROL SYSTEM REHABILITATION

Remove Section 35 01 45 pages 11, 12, and 15 and replace with revised Section 35 01 45 pages 11, 12, and 15.

CHANGES TO CONTRACT DRAWINGS

The following CONTRACT DRAWING has been revised and replaced:

Drawing No. Description

Q9-E0 INDEX

Q9-E4 DOWNSTREAM RIVERWALL HYDRAULIC VALVE CONTROL SCHEMATICS

Q9-E6 UPSTREAM RIVERWALL HYDRAULIC VALVE CONTROL SCHEMATIC

Q9-E8 DOWNSTREAM LANDWALL HYDRAULIC VALVE CONTROL SCHEMATIC

Q9-E10 UPSTREAM LANDWALL HYDRAULIC VALVE CONTROL SCHEMATIC

The following new REFERENCE DRAWINGS have been added:

Drawing No. Description

Q9-3/13.2 LOCK - GENERAL PLAN

Q9-20/23.6 LOCK - FILLING AND EMPTYING SYSTEM – CHAMBER LATERALS

Q9-20/60.3 LOCK - COMPLETION OF LOCK WALLS MASONRY DETAILS NO.1

Q9-20/63.1 LOCK – MISCELLANEOUS METALS ARMOR, RECESS FRAMES & COVERS

Q9-25/1.3 LOCK - CULVERT SEGMENTAL VALVE – GENERAL ARRANGEMENT

Q9-25/2.4 LOCK - CULVERT SEGMENTAL VALVE – ELEVATIONS, SECTIONS AND DETAILS

Q9-25/3.3 LOCK - CULVERT SEGMENTAL VALVE – SEAL DETAILS

Q9-25/4.3 LOCK - CULVERT SEGMENTAL VALVE – TRUNNION BEARING DETAILS

Q9-25/5.2 LOCK - CULVERT SEGMENTAL VALVE – EMBEDDED METALS

Q9-27/1.4 LOCK - HYDRAULIC SYSTEM – SCHEMATIC DIAGRAM

Q9-27/2.1 LOCK - HYDRAULIC SYSTEM – OPERATING STATION L.L.W.

Q9-27/3.3 LOCK - HYDRAULIC SYSTEM – CYLINDER & CROSSOVER PIPING L.L.W.

Q9-27/4.1 LOCK - HYDRAULIC SYSTEM – OPERATING STATION U.L.W.

Q9-27/5.2 LOCK - HYDRAULIC SYSTEM – CYLINDER & CROSSOVER PIPING U.L.W.

Q9-27/8.2 LOCK - HYDRAULIC SYSTEM – VALVE CONTROLS AND DETAILS

Q9-31/1.4 LOCK - UPSTREAM EMERGENCY GATE HOIST ASSEMBLY

--- END OF AMENDMENT NO. 0002 TECHNICAL CHANGES---

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 0001:

PROJECT: BARKLEY LOCK ELECTRICAL OPERATING SYSTEM REPLACEMENT

This solicitation is being amended to extend the bid due date from 7 June 2018 to 26 June 2018 at 1 P.M. Central Time.

Amendment 0002:

Project: Barkley Lock Electrical Operating System Replacement

1. Add Questions and Answers, and Site Visit Minutes from site visit on 21-May-2018.

2. Add Technical Changes document titled TechChanges-AM2.docx.

3. Post Technical Plan changes to FBO.Gov titled W912P518B0006_TPlan AM2Sheets.pdf, and Technical Specification changes titled W912P518B0006_TSpec AM2pgs.pdf

4. DFARS 252.204-7004, Alt A, is deleted

The following have been deleted:

252.204-7004 Alt A

(End of Summary of Changes)

SUBJECT: PRE-BID SITE VISIT BARKLEY ELECTRICAL OPERATION SYSTEM REPLACEMENT
Solicitation No. W912P518B0006
Amendment No. 0002
CHANGES TO TECHNICAL SPECIFICATIONS
Section 26 60 13 LOW-VOLTAGE MOTORS (460 VAC)
Remove Section 26 60 13 page 3 and replace with revised Section 26 60 13 page 3.
Section 35 01 45 BARKLEY LOCK CONTROL SYSTEM REHABILITATION
Remove Section 35 01 45 pages 11, 12, and 15 and replace with revised Section 35 01 45 pages 11, 12, and 15.
CHANGES TO CONTRACT DRAWINGS
The following CONTRACT DRAWING has been revised and replaced:
The following new REFERENCE DRAWINGS have been added: