W912P5-16-B-0006-TSpecs.pdf

PDF 3 MB Posted

Attached to
Poor Fork Channel Modification, City of Cumberland, KY
Solicitation number
W912P5-16-B-0006
Issued by

About this file

Technical Specifications

View the file

Other files

File Type Posted
Bid_Abstract.pdf PDF
W912P5-16-B-0006-TSpecs-Am2pgs.pdf PDF
Amendment_0002.pdf PDF
Prebidsitevisitattendancelist.pdf PDF
Amendment0001.pdf PDF
W912P5-16-B-0006-TSpecs-Am1pgs.pdf PDF
W912P5-16-B-0006.pdf PDF
W912P5-16-B-0006-Plans.pdf PDF
W912P5-16-B-0006-AppA.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. W912P5-16-B-0006

US Army Corps Of Engineers Nashville District

POOR FORK PROJECT

Local Protection Project Cumberland, Kentucky

Technical Specifications

June 2016

THIS PAGE INTENTIONALLY LEFT BLANK

FOR DUPLEX PRINTING

Poor Fork City of Cumberland, Kentucky W912P5-16-B-0006

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 22 00 PRICE AND PAYMENT PROCEDURES

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 01 QUALITY CONTROL

01 45 02 QUALITY CONTROL SYSTEM (QCS)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

01 95 00 FORMS AND ATTACHMENTS

DIVISION 02 - EXISTING CONDITIONS

02 41 16 DEMOLITION AND REMOVAL

DIVISION 31 - EARTHWORK

31 05 22 GEOTEXTILES USED AS FILTERS

31 11 00 CLEARING, GRUBBING, AND EARTHWORK

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 11 23 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE

32 92 19 TOPSOILING AND SEEDING

32 93 43 PLANTING TREES

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 31 19 STONE PROTECTION

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

1.2 REFERENCES

1.3 WARRANTY

1.4 CONTRACT EMPLOYEES

1.5 SUBMITTALS

1.6 CONTRACTOR'S STAGING AND AREA USE PLAN

1.7 DAILY CLEANUP AND DISPOSAL

1.8 STORAGE OF EQUIPMENT AND MATERIALS

1.9 ENVIRONMENTAL PROTECTION

1.10 PROJECT SIGNS

1.10.1 General

1.10.2 Materials

1.10.3 Painting

1.10.4 Erection and Maintenance

1.11 ACCIDENT PREVENTION

1.11.1 Non-Compliance of Safety Requirements

1.12 EVALUATION OF CONTRACTOR PERFORMANCE

1.13 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

1.14 PARTNERING

1.15 MEASUREMENT AND PAYMENT

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 00 00 Page 1

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

This section comprises an explanation of the general contract requirements needed to accomplish the work for the items described in the bidding schedule. This section is not intended to be all encompassing in the descriptions. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and contract drawings. The Contractor shall bid each type of work under the applicable bid item. Compensation for any item of work described in the contract documents, but not listed in the bid schedule shall be included in the price for the item of work to which it is made subsidiary.

1.2 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

EP 310-1-6a (2006) Sign Standards Manual, VOL 1

EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices

1.3 WARRANTY

The Contractor shall provide the Government a one year warranty from the date of final acceptance by the Contracting Officer's Representative (COR), and comply with applicable warranty requirements of Section 01 78 00 CLOSEOUT SUBMITTALS. The warranty shall cover defective materials, design and workmanship. In instances where the material or equipment manufacturer's advertised minimum warranty is in excess of one year, it shall remain in force for its full period. Upon receipt of notice from the Contracting Officer of failure of any of the material or equipment during the warranty period, the Contractor shall promptly furnish and install new replacement parts at no additional cost to the Government.

1.4 CONTRACT EMPLOYEES

a. Contractor, subcontractors, and their employees shall conduct themselves in a proper manner at all times. No alcoholic beverages or controlled substances shall be consumed by the Contractor, subcontractor or his/her employees while on duty.

b. The Contractor expressly agrees to remove from the site any individual whose continued employment is deemed by the COR to be contrary to the

SECTION 01 00 00 Page 2 public interest or inconsistent with the best interest of the Government.

c. The COR may require the Contractor to immediately remove from the work site any employee who is incompetent or who endangers persons or property or whose physical or mental condition is such that it would impair the employee's ability to satisfactorily perform the work.

Notification to the Contractor shall be promptly made in writing if time and circumstances permit.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Area Use Plan; G The Contractor shall submit an area use plan for this contract as required in paragraph 1.6 CONTRACTOR'S STAGING AND AREA USE

PLAN.

1.6 CONTRACTOR'S STAGING AND AREA USE PLAN

The Contractor will be assigned an area near the jobsite for use as a staging area. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner.

Temporary Contractor facilities provided during site operations shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.

The Contractor shall submit an Area Use Plan to the Contracting Officer, for approval, within ten (10) days after receipt of the Notice to Proceed.

The Area Use Plan shall show the following:

a. Location of Contractor offices trailers and sheds.

b. Location of all Contractor storage areas.

c. Location of Contractor staging areas.

d. Temporary utility tie-ins.

e. Location of haul roads.

f. Required telephone service and locations.

1.7 DAILY CLEANUP AND DISPOSAL

Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site to an approved facility at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.

1.8 STORAGE OF EQUIPMENT AND MATERIALS

Storage of equipment and materials will be permitted only in designated staging areas.

SECTION 01 00 00 Page 3

1.9 ENVIRONMENTAL PROTECTION

The Contractor shall comply with the contract requirements stated in Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS. Contractor shall maintain all work within and outside the project boundaries free from environmental pollution that would be in violation of any federal, state, local regulations or permits.

1.10 PROJECT SIGNS

1.10.1 General

The Contractor shall furnish and erect, within 30 days after issue of the Notice to Proceed, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN at the location directed at the entrance to the jobsite. The signs shall be lettered on one side only and shall conform to EP 310-1-6a, EP 310-1-6b, and to the details and colors shown on the sketches attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS. The name of the project shall be as follows:

Poor Fork Channel Modification Local Protection Project

1.10.2 Materials

The sign shall be constructed with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material. Screws shall be commercial quality and of sizes shown.

1.10.3 Painting

The signs and posts shall be given one prime coat and two finish coats of exterior oil paint before lettering. Letters and trim shall be applied to one side only using one coat of enamel of color, style, and size shown.

1.10.4 Erection and Maintenance

The signs shall be erected at the designated locations. Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs out the life of the contract. The signs shall be maintained in good condition until completion of the contract, shall remain the property of the Contractor, and shall be removed from the site upon final acceptance of the contract work.

1.11 ACCIDENT PREVENTION

The Contractor shall comply with all applicable provisions of EM 385-1-1 Safety and Health Requirements Manual and Section 01 35 26 GOVERNMENTAL

SAFETY REQUIREMENTS.

1.11.1 Non-Compliance of Safety Requirements

If the Contractor fails or refuses to promptly comply with the safety requirements, the COR may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stoppage shall be made subject to claim for extension of time or for excess costs or damages to the Contractor. The Contractor

SECTION 01 00 00 Page 4 will not be paid for work not performed as a result of the stop order.

Work shall not resume until the Contractor provides evidence to the COR that he/she has complied or will comply with appropriate safety regulations.

1.12 EVALUATION OF CONTRACTOR PERFORMANCE

The Contractor's performance will be evaluated in accordance with FAR Part

42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum. The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section

01 95 00 FORMS AND ATTACHMENTS.

The Contractor's review of the evaluation shall be completed electronically at the CPARS website, http://www.cpars.gov. This website also includes guidance and the user's manual.

Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.

1.13 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

Federal Veteran employment information at:

http://www.fedshirevets.gov/index.aspx

Department of Labor Veterans Employment Assistance:

http://www.dol.gov/vets/

Department of Veterans Affairs-VOW to Hire Heroes Act:

http://benefits.va.gov/vow/

Army Wounded Warrior Program:

http://wtc.army.mil/modules/employers/index.html

U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/

Guide to Hiring Veterans - Reference Material:

http://www.whitehouse.gov/sites/default/files/docs/white_house_business_council_-_guide_t

1.14 PARTNERING

In order to most effectively accomplish this contract, the Government urges the Contractor to join the Government in establishing a cohesive and

SECTION 01 00 00 Page 5 professional project management team. Through this "partnering" relationship both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project's intended results are achieved, within budget and on schedule. This endeavor seeks an environment that nurtures team building, cooperation and trust between the Government and the Contractor. The partnering relationship would be bilateral in make-up, and participation will be totally voluntary.

At the discretion of each entity, a joint project management team "partnering" conference will be scheduled. The conference will be attended by multiple officers from each organization representing management and the key jobsite staff of each entity. An appointed individual would chair the conference and the Contractor will be responsible to establish its agenda and distribute minutes of the meeting. A professional facilitator acceptable to both parties would lead the participants of the session, through the steps of team building and the formation of a problem solving mechanism within the group. The conference duration would be no more than one day. Location and accommodations for the conference would be agreed upon by both entities. All costs in connection with rented facilities and the facilitator would be shared equally by the Government and the Contractor. Each organization would pay other costs of its respective employees attending the conference.

Additional partnering sessions would be held intermittently.

Implementation of the partnering concept and philosophy would be an on-going process.

1.15 MEASUREMENT AND PAYMENT

No separate payment will be made for the work covered under this section, except as otherwise provided. The costs thereof shall be included in the item to which the work pertains. Payment for the work required under this contract will made as listed in the bidding schedule and as described in Section 01 22 00 PRICE AND PAYMENT PROCEDURES.

PART 2 PRODUCTS

NOT USED.

PART 3 EXECUTION

NOT USED.

-- End of Section --

SECTION 01 00 00 Page 6

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 PAYMENT ITEMS

1.1.1 Mobilization and Preparatory Work

1.1.1.1 Payment

1.1.1.2 Unit of Measure

1.1.2 Performance and Payment Bonds

1.1.2.1 Payment

1.1.2.2 Unit of Measure

1.1.3 Geotextile Fabric

1.1.3.1 Payment

1.1.3.2 Measurement

1.1.3.3 Unit of Measure

1.1.4 Clearing and Grubbing

1.1.4.1 Payment

1.1.4.2 Measurement

1.1.4.3 Unit of Measure

1.1.5 Excavation

1.1.5.1 Payment

1.1.5.2 Measurement

1.1.5.3 Unit of Measure

1.1.6 Graded Chrushed Aggregate Base

1.1.6.1 Payment

1.1.6.2 Measurement

1.1.6.3 Unit of Measure

1.1.7 Demolition and Removal

1.1.7.1 Payment

1.1.7.2 Unit of Measure

1.1.8 Permanent Turf Grass Seeding

1.1.8.1 Payment

1.1.8.2 Measurement

1.1.8.3 Unit of Measure

1.1.9 Temporary Seeding

1.1.9.1 Payment

1.1.9.2 Measurement

1.1.9.3 Unit of Measure

1.1.10 Trees and Shrubbery

1.1.10.1 Payment

1.1.10.2 Unit of Measure

1.1.11 Rip Rap Channel Lining

1.1.11.1 Payment

1.1.11.2 Measurement

1.1.11.3 Unit of Measure

1.1.12 Stock Fence (Remove and Relocate)

1.1.12.1 Payment

1.1.12.2 Unit of Measure

SECTION 01 22 00 Page 1

1.1.13 Chain Link Fence (Remove and Relocate)

1.1.13.1 Payment

1.1.13.2 Unit of Measure

1.1.14 Dog Kennel (Remove and Relocate)

1.1.14.1 Payment

1.1.14.2 Unit of Measure

1.1.15 Shed on Foundation (Remove and Relocate)

1.1.15.1 Payment

1.1.15.2 Unit of Measure

1.1.16 Shed Without Foundation (Relocate)

1.1.16.1 Payment

1.1.16.2 Unit of Measure

1.1.17 Carport Without Foundation (Relocate)

1.1.17.1 Payment

1.1.17.2 Unit of Measure

1.1.18 Driveway Restoration

1.1.18.1 Payment

1.1.18.2 Unit of Measure

1.2 FIELD SURVEYS

1.2.1 Surveys of Riprap Areas

1.2.2 Surveys of Excavated Areas

1.3 SUBMITTALS

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 CONTRACT COST BREAKDOWN

SECTION 01 22 00 Page 2

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 PAYMENT ITEMS

Payment items for the work of this contract for which payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Mobilization and Preparatory Work

1.1.1.1 Payment

Mobilization and preparatory work shall be paid for at the contract price per Job for "Mobilization and Preparatory Work". Payment shall be done in accordance with FAR 252.236-7003, PAYMENT FOR MOBILIZATION AND PREPARATORY WORK, and as described below:

The Contractor shall receive payment from the Government under the procedures in this paragraph for mobilization and preparatory work. Payment shall be made to the Contractor for construction of plant(s), rental equipment, material, computers, office trailers, and supporting expenditures to establish access roads, temporary construction entrances, trailer courts, disposal areas, and other site development needed for the job prior to the start of construction. The Contractor shall provide supporting documentation for payment of each item and shall not receive payment until the Contracting Officer has receipts to prove that payment for all items claimed have been validated. All construction plant, material, equipment, and the mobilization and preparatory work shall be performed and determined to be suitable for efficiency in performing the work before payment is made.

1.1.1.2 Unit of Measure

Unit of measure: Job.

1.1.2 Performance and Payment Bonds

1.1.2.1 Payment

Payment will be made for costs associated with performance and payment bonds. In accordance with Contract Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, the premiums for performance and payment bonds shall be included in the contract price. Payment for the premiums for performance and payment bonds will be made at the contract

SECTION 01 22 00 Page 3 price per Job for "Performance & Payment Bonds." Payments made under this provision shall not exceed the amount included for "Performance & Payment Bonds," which payment shall take into consideration any discounts or rebates to the Contractor from the Surety. The Contractor is advised that the pay item "Performance & Payment Bonds" is only for the cost of bonds.

Other costs should be allocated to the appropriate bid items.

1.1.2.2 Unit of Measure

Unit of measure: Job.

1.1.3 Geotextile Fabric

1.1.3.1 Payment

Payment will be made for costs associated with procuring and installing geotextile as shown in the contract drawings and specified in Section 31 05 22 GEOTEXTILES USED AS FILTERS. Payment for placing geotextile fabric will be made at the contract unit price per square yard (SY) for "Geotextile Fabric," and will constitute full compensation to the Contractor for providing all plant, labor, material, and equipment and performing all operations necessary for the complete and satisfactory installation of the geotextile.

1.1.3.2 Measurement

Installed geotextiles will be measured for payment in place to the nearest square yard of protected area. The following items are included in the unit price for Geotextiles and will not be counted a second time in the process of determining the extent of geotextile placed: Material and associated equipment and operation used in laps, seams, or extra length;

securing pins and associated material, equipment, and operations. No payment will be made for geotextiles replaced because of waste, contamination, damage, repair, or due to Contractor fault or negligence.

1.1.3.3 Unit of Measure

Unit of measure: square yard (SY).

1.1.4 Clearing and Grubbing

1.1.4.1 Payment

Payment will be made for clearing and grubbing satisfactorily performed in accordance with the contract drawings and specified in Section 31 11 00 CLEARING, GRUBBING, AND EARTHWORK. Payment for clearing and grubbing will be made at the contract unit price per Acre for "Clearing and Grubbing".

This price shall include consideration for all required equipment, materials and associated work, and disposal of all associated materials.

1.1.4.2 Measurement

Measurement for payment will be made to the nearest acre of satisfactorily cleared and grubbed areas.

1.1.4.3 Unit of Measure

Unit of measure: Acre.

SECTION 01 22 00 Page 4

1.1.5 Excavation

1.1.5.1 Payment

Payment will be made for costs associated with excavation activities as shown in the contract drawings and specified in Section 31 11 00 CLEARING, GRUBBING, AND EARTHWORK. Payment for excavation will be made at the contract unit price per cubic yard (CY) for "Excavation". Payment will constitute full compensation for all labor, equipment, tools, supplies, and incidentals necessary to complete all the work required under this section. Disposal of excavated materials shall be considered incidental to this pay item.

1.1.5.2 Measurement

Excavation will be measured by the cubic yard in place, based on the average end area method from cross sections taken before and after the excavation operations.

1.1.5.3 Unit of Measure

Unit of measure: Cubic Yard (CY).

1.1.6 Graded Chrushed Aggregate Base

1.1.6.1 Payment

Payment will be made for costs associated with furnishing, transporting, stockpiling (if applicable), and placing Graded Chrushed Aggregate Base, as specified in Section 32 11 23 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE and as shown in the drawings. Payment will be made at the contract unit price per ton for "Graded Chrushed Aggregate Base".

1.1.6.2 Measurement

Measure Graded Chrushed Aggregate Base for payment by the ton (2,000 pounds) by weighing each truckload to the nearest 0.1 ton, and the final quantity of each truckload is rounded to the nearest whole ton. Weigh for payment on approved scales before being placed in the work. Quarry weights will not be accepted. Use scales of sufficient length to permit simultaneous weighing all axle loads. Scales must be inspected, tested and sealed as directed to assure accuracy with 0.5 percent throughout the range of the scales. Certify scales located at the site of the work as to accuracy by an acceptable scales company representative prior to weighing any material. Scales will be checked and certified before hauling and rechecked and recertified whenever a variance is suspected. Furnish the scales. If commercial scales are readily available in close proximity, 10 miles of site of work, the Contracting Officer may approve the use of the scales. Weigh material in the presence of the Government representative.

The Contracting Officer may elect to accept certified weight certificates furnished by a public weighmaster in lieu of scale weights at the jobsite.

1.1.6.3 Unit of Measure

Unit of measure: TON (2,000 pounds).

SECTION 01 22 00 Page 5

1.1.7 Demolition and Removal

1.1.7.1 Payment

Payment will be made for costs associated with demolition and removal of items as shown in the contract drawings and specified in Section 02 41 16 DEMOLITION AND REMOVAL. Payment for demolition and removal will be made per job for "Demolition and Removal".

1.1.7.2 Unit of Measure

Unit of measure: Job (JOB).

1.1.8 Permanent Turf Grass Seeding

1.1.8.1 Payment

Payment will be made for costs associated with installing permanent turf grass seeding as specified in Section 32 92 19 TOPSOILING AND SEEDING.

Payment for the complete turf grass seeding operation will be made at the contract unit price per MSF for "Permanent Turf Grass Seeding"; which price shall include all costs in connection with tilling, seeding, fertilizing, erosion control blanket, incorporating, protecting, and maintaining.

1.1.8.2 Measurement

The unit of measurement for permanent turf grass seeding will be per 1,000

sq. ft. (MSF). The areas to be paid for shall be those actually seeded computed to the nearest 1,000 sq. ft. Measurement and payment will also be made of areas that are required to be reseeded by the Contracting Officer, if such reseeding is necessitated through no fault of the Contractor.

1.1.8.3 Unit of Measure

Unit of measure: Thousand Square Feet (MSF).

1.1.9 Temporary Seeding

1.1.9.1 Payment

Payment will be made for costs associated with installing temporary grass seeding as specified in Section 32 92 19 TOPSOILING AND SEEDING. Payment for the temporary seeding operation will be made at the contract unit price per MSF for "Temporary Seeding;" which price shall include all costs in connection with fertilizing, tilling, seeding, incorporating, protecting, and maintaining.

1.1.9.2 Measurement

The unit of measurement for temporary seeding will be per 1,000 sq. ft.

(MSF). The areas to be paid for shall be those actually seeded computed to the nearest 1,000sq. ft.

1.1.9.3 Unit of Measure

Unit of measure: Thousand Square Feet (MSF).

SECTION 01 22 00 Page 6

1.1.10 Trees and Shrubbery

1.1.10.1 Payment

Payment will be made for costs associated with plantings as shown in the contract drawings and specified in Section 32 93 43 PLANTING TREES. Payment for plantings will be made per job for "Trees and Shrubbery".

1.1.10.2 Unit of Measure

Unit of measure: Job (JOB).

1.1.11 Rip Rap Channel Lining

1.1.11.1 Payment

Payment for riprap acceptably placed will be made at the applicable contract unit price per ton for "Rip Rap Channel Lining" and as specified in Section 35 31 19 STONE PROTECTION. Price and payment shall constitute full compensation for furnishing, hauling, handling, placing, and maintaining the riprap until final acceptance by the Government.

1.1.11.2 Measurement

No payment will be made for excess riprap left in place. Existing stone placed in lieu of new stone from off-site sources will be excluded from measurement and payment. Riprap will be measured for payment by the ton in the presence of the Contracting Officer, by weighing on approved, accurately calibrated scales furnished by and at the expense of the Contractor. The scales shall be capable of printing a weight ticket including time, date, truck number, and weight. Weight certificates furnished by a public weighmaster will be acceptable. Quantities shall be computed to the nearest whole ton.

1.1.11.3 Unit of Measure

Unit of measure: Ton (TON).

1.1.12 Stock Fence (Remove and Relocate)

1.1.12.1 Payment

Payment will be made for costs associated with removal and relocation of stock fence as shown in contract drawing no. Q1P-64/109. Payment will be made per job for "Stock Fence (Remove and Relocate)".

1.1.12.2 Unit of Measure

Unit of measure: Job (JOB).

1.1.13 Chain Link Fence (Remove and Relocate)

1.1.13.1 Payment

Payment will be made for costs associated with removal and relocation of chain link fence as shown in contract drawing no. Q1P-64/109. Payment will be made per job for "Chain Link Fence (Remove and Relocate)".

SECTION 01 22 00 Page 7

1.1.13.2 Unit of Measure

Unit of measure: Job (JOB).

1.1.14 Dog Kennel (Remove and Relocate)

1.1.14.1 Payment

Payment will be made for costs associated with removal and relocation of chain link fence as shown in contract drawing no. Q1P-64/109. Payment will be made per job for "Dog Kennel (Remove and Relocate)".

1.1.14.2 Unit of Measure

Unit of measure: Job (JOB).

1.1.15 Shed on Foundation (Remove and Relocate)

1.1.15.1 Payment

Payment will be made for costs associated with removal and relocation of shed with foundation as shown in contract drawing no. Q1P-64/109. Payment will be made per job for "Shed on Foundation (Remove and Relocate)".

1.1.15.2 Unit of Measure

Unit of measure: Job (JOB).

1.1.16 Shed Without Foundation (Relocate)

1.1.16.1 Payment

Payment will be made for costs associated with relocation of shed without foundation as shown in contract drawing no. Q1P-64/109. Payment will be made per job for "Shed Without Foundation (Relocate)".

1.1.16.2 Unit of Measure

Unit of measure: Job (JOB).

1.1.17 Carport Without Foundation (Relocate)

1.1.17.1 Payment

Payment will be made for costs associated with relocation of car port without foundation as shown in contract drawing no. Q1P-64/109. Payment will be made per job for "Carport Without Foundation (Relocate)".

1.1.17.2 Unit of Measure

Unit of measure: Job (JOB).

1.1.18 Driveway Restoration

1.1.18.1 Payment

Payment will be made for costs associated with restoration of driveway as shown in contract drawing no. Q1P-64/109. Payment will be made per job for "Driveway Restoration".

SECTION 01 22 00 Page 8

1.1.18.2 Unit of Measure

Unit of measure: Job (JOB).

1.2 FIELD SURVEYS

No separate payment will be made for field surveys. All costs for surveys shall be considered incidental to the closest associated feature of work.

The volume of material for payment of excavation shall be determined by the average end area method and the pre- and post excavation surveys. The Contractor will not be paid for material remaining outside of the specified tolerances.

Pre- and post-placement survey cross sections shall be performed for the excavation, embankment fill, and riprap; and the results submitted to the Contracting Officer. Surveys shall be performed by a land surveyor with current Commonwealth registration. The Contractor shall notify the Contracting Officer not less than three working days in advance of each survey. Surveys shall be conducted in the presence of the Contracting Officer or his designated representative unless this requirement is waived.

In the event of unavailability of the Contracting Officer, the Contractor shall perform the survey and certify that it complies with the specifications.

The Contractor will be responsible for establishing, protecting and maintaining a baseline. A schematic of the baseline shall be provided to the Contracting Officer along with horizontal coordinates at the endpoints and at all changes in alignment. These horizontal coordinates shall be in the Kentucky State Plane, NAD 83 coordinate system and shall be to the nearest foot with accuracy of +/- 0.5 foot.

Drawings shall utilize A/E/C CADD standards, Latest Release. All electronic drawings shall be submitted to the Government in MicroStation ".dgn" format and ".pdf" portable document format. Drawings should be developed using Arial Font for text, and A/E/C CADD standard ".dgnlibs" for level assignment, line weights, line styles, and line color. A copy of the "dgnlibs" will be furnished. Civil site plan drawings shall utilize a standard engineering drawing scale. Additionally, provide all CAD files to include but not limited to .dtm, .alg, .eav, .xyz, .xls, .xsc, and .ASCII or .XML file types used to generate electronic drawings such as contours, .dtms, plan views, profiles, and cross sections so that USACE may be able to regenerate those profiles, cross sections, contours, alignments, etc as needed during the design process.

Cross-sections shall be surveyed perpendicular to the channel alignment and shall be no more than 25 feet apart as measured along the baseline. The readings shall be at 5-foot intervals and at breaks in grade unless otherwise specified. Additional sections at closer spacing for significant changes in topography may be required as determined appropriate by the Contracting Officer. The station at which the cross-section intersects the baseline shall be used to identify it. Surveyed elevations shall reference the same datum used on the drawings and shall be to the nearest tenth of a foot with an accuracy of +/- 0.1 foot. Additional elevations shall be taken if the Contracting Officer deems such to be necessary or advisable.

The top elevation of placed riprap shall be determined by the use of a leveling instrument and a rod having a base 12 inches in diameter.

SECTION 01 22 00 Page 9

1.2.1 Surveys of Riprap Areas

In order to define the original ground surface, the Contractor shall take cross sections of the area to receive riprap after preparation of the foundation and prior to placing material. Another survey at the same sections shall be performed after riprap has been placed. The Contractor shall perform partial surveys as the work progresses to verify lines, grades and thickness established for completed work. Surveys made are required to determine that the material has been acceptably placed. At least one in-progress survey shall be made by the Contractor as determined appropriate by the Contracting Officer. Following placement, the cross-sections shall be approved by the Contracting Officer before proceeding with the next section of work. Approval of cross-sections based upon in-progress surveys shall not constitute final acceptance of the work.

A final as-built survey shall be performed after all riprap has been placed. Survey results shall include electronic scaled drawings of data submitted as cross section plots. The Contracting Officer may also require the Contractor to submit survey field notes. For the purpose of coordinating with the Government, the Contractor shall schedule surveys during the normal business hours of Monday through Friday 7:00 a.m. to 3:30 p.m. Central Time with the exception of Federal Holidays.

1.2.2 Surveys of Excavated Areas

For surveys of excavation, the same procedures specified above shall be followed. The initial survey shall be taken after clearing and grubbing has been completed and prior to excavation. The final survey shall be taken after excavation and grading is complete. The volume of excavated material for payment shall be determined by the average end area method based on these two surveys. Survey results shall be submitted to the Government.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Weight Certificates

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 CONTRACT COST BREAKDOWN

The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late

SECTION 01 22 00 Page 10 payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.

SECTION 01 22 00 Page 11

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 BASIS FOR PAYMENT AND COST LOADING

3.2.1 Activity Cost Loading

3.2.2 Withholdings / Payment Rejection

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

3.3.2 Activity Durations

3.3.3 Procurement Activities

3.3.4 Mandatory Tasks

3.3.5 Government Activities

3.3.6 Standard Activity Coding Dictionary

3.3.6.1 Workers Per Day (WRKP)

3.3.6.2 Responsible Party Coding (RESP)

3.3.6.3 Area of Work Coding (AREA)

3.3.6.4 Modification Number (MODF)

3.3.6.5 Bid Item Coding (BIDI)

3.3.6.6 Phase of Work Coding (PHAS)

3.3.6.7 Category of Work Coding (CATW)

3.3.6.8 Feature of Work Coding (FOW)

3.3.7 Contract Milestones and Constraints

3.3.7.1 Project Start Date Milestone and Constraint

3.3.7.2 End Project Finish Milestone and Constraint

3.3.7.3 Interim Completion Dates and Constraints

3.3.7.3.1 Start Phase

3.3.7.3.2 End Phase

3.3.8 Calendars

3.3.9 Open Ended Logic

3.3.10 Default Progress Data Disallowed

3.3.11 Out-of-Sequence Progress

3.3.12 Added and Deleted Activities

3.3.13 Original Durations

3.3.14 Leads, Lags, and Start to Finish Relationships

3.3.15 Retained Logic

SECTION 01 32 01 Page 1

3.3.16 Percent Complete

3.3.17 Remaining Duration

3.3.18 Cost Loading of Closeout Activities

3.3.18.1 As-Built Drawings

3.3.18.2 O & M Manuals

3.3.19 Anticipated Adverse Weather

3.3.20 Early Completion Schedule and the Right to Finish Early

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Preliminary Project Schedule Submission

3.4.2 Initial Project Schedule Submission

3.4.3 Periodic Schedule Updates

3.5 SUBMISSION REQUIREMENTS

3.5.1 Data CD/DVDs

3.5.2 Narrative Report

3.5.3 Schedule Reports

3.5.3.1 Activity Report

3.5.3.2 Logic Report

3.5.3.3 Total Float Report

3.5.3.4 Earnings Report by CLIN

3.5.3.5 Schedule Log

3.5.4 Network Diagram

3.5.4.1 Continuous Flow

3.5.4.2 Project Milestone Dates

3.5.4.3 Critical Path

3.5.4.4 Banding

3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram

3.6 PERIODIC SCHEDULE UPDATE

3.6.1 Periodic Schedule Update Meetings

3.6.2 Update Submission Following Progress Meeting

3.7 WEEKLY PROGRESS MEETINGS

3.8 REQUESTS FOR TIME EXTENSIONS

3.8.1 Justification of Delay

3.8.2 Time Impact Analysis (Prospective Analysis)

3.8.3 Forensic Schedule Analysis (Retrospective Analysis)

3.8.4 Fragmentary Network (Fragnet)

3.8.5 Time Extension

3.8.6 Impact to Early Completion Schedule

3.9 FAILURE TO ACHIEVE PROGRESS

3.9.1 Artificially Improving Progress

3.9.2 Failure to Perform

3.9.3 Recovery Schedule

3.10 OWNERSHIP OF FLOAT

3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS

SECTION 01 32 01 Page 2

SECTION 01 32 01

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application. The designated representative for the Contractor must be available for on-site meetings and conferences.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules

SECTION 01 32 01 Page 3 required herein must be capable of meeting all requirements of this specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development.

Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.

Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

SECTION 01 32 01 Page 4

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

b. Long procurement activities

c. Submission and approval of as-built drawings.

d. Contractor's pre-final inspection.

e. Correction of punch list from Contractor's pre-final inspection.

f. Government's pre-final inspection.

g. Correction of punch list from Government's pre-final inspection.

h. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.6 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site:

http://rms.usace.army.mil.

The SDEF format is as follows:

SECTION 01 32 01 Page 5

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

3 AREA 4 Area of work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work*

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.6.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.

3.3.6.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);

ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).

3.3.6.3 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities cannot have more than one Work Area Code.

SECTION 01 32 01 Page 6

Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.

3.3.6.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.

3.3.6.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.6.6 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.6.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.

3.3.6.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.

Definable Feature of Work is defined in Section 01 45 01 QUALITY CONTROL.

An activity can have only one Feature of Work Code.

3.3.7 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for

SECTION 01 32 01 Page 7 approval on a case by case basis.

3.3.7.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.7.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

3.3.7.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.7.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.7.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.8 Calendars

Schedule activities on a Calendar to which the activity logically belongs.

Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.

If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the…