RFP No. W912P5-15-R-0006
US Army Corps Of Engineers Nashville District
TAINTER GATES MODIFICATIONS AND
PAINTING
Cheatham Lock and Dam Cheatham and Dickson Counties, Tennessee
Technical Specifications
April 2015
THIS PAGE INTENTIONALLY LEFT BLANK
FOR DUPLEX PRINTING
Tainter Gates Modifications and Painting Cheatham Lock and Dam W912P5-15-R-0006 Cheatham and Dickson Counties, TN
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK / GENERAL CONDITIONS
01 22 00 MEASUREMENT AND PAYMENT
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 01 QUALITY CONTROL
01 45 02 QUALITY CONTROL SYSTEM (QCS)
01 57 20 ENVIRONMENTAL PROTECTION
01 78 00 CLOSEOUT SUBMITTALS
01 95 00 FORMS AND ATTACHMENTS
DIVISION 05 - METALS
05 50 14 STRUCTURAL METAL FABRICATIONS
DIVISION 09 - FINISHES
09 97 02 PAINTING: HYDRAULIC STRUCTURES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
1.2 "FOR INFORMATION ONLY" Drawings
1.3 COORDINATION CONFERENCES
1.4 PARTNERING
1.5 REFERENCES
1.6 SUBMITTALS
1.7 PROJECT SIGNS
1.8 PROJECT SITE SECURITY AND AT/OPSEC REQUIREMENTS
1.8.1 Employee Identification and Control Procedure
1.8.2 Pre-Screening Contractor's On-Site Employees
1.8.3 Employee Required Training
1.8.3.1 AT Level I Training
1.8.3.2 Suspicious Activity Reporting Training
1.8.3.3 Level I OPSEC Training
1.8.4 Access and General Protection/Security Policy and Procedures
1.8.5 Employee Escorts
1.8.6 Protection of DOD Information
1.8.7 Media Provided by the Contractor
1.8.8 Security Requirement Amendments
1.8.9 Background Investigation Requirements
1.9 VEHICLES
1.9.1 Use of Private Vehicles
1.9.2 Identification of Vehicles
1.10 CONTRACTOR'S STAGING AREA
1.11 DAILY CLEANUP AND DISPOSAL
1.12 STORAGE OF EQUIPMENT AND MATERIALS
1.13 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.14 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK
1.15 EVALUATION OF CONTRACTOR PERFORMANCE
1.16 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.17 MEASUREMENT AND PAYMENT
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
SECTION 01 00 00 Page 1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
This section comprises an explanation of general contract requirements needed to accomplish the work. This section is not intended to be all encompassing in the descriptions. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and contract drawings. A detailed scope of work is described in Section 01 11 00 SUMMARY OF WORK / GENERAL CONDITIONS.
1.2 "FOR INFORMATION ONLY" Drawings
The drawings listed below are provided "FOR INFORMATION ONLY". The drawings are furnished for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from these drawings by the Contractor.
a. Q12-48/2.4 TAINTER GATE, SKIN PLATE ARRANGEMENT
b. Q12-48/3.5 TAINTER GATE, FRAMING PLANS & TRUNNION ASSEMBLY
c. Q12-48/4.5 TAINTER GATE, END FRAMING
d. Q12-48/5.4 TAINTER GATE, SEAL AND TRUNNION DETAILS
e. Q12-48/6.4 TAINTER GATE, EMBEDDED SILL AND SIDE SEAL GUIDES
f. Q12-48/20.1 TAINTER GATE MODIFICATION, END FRAMING
g. Q12-48/21.2 TAINTER GATE MODIFICATION, SIDE AND BOTTOM SEALS
h. Q12-48/22.1 TAINTER GATE MODIFICATION, SIDE SEAL
i. Q12-48/23.2 TAINTER GATE MODIFICATION, BOTTOM GIRDER
j. Q12-48/24.1 TAINTER GATE MODIFICATION, EMBEDDED SIDE SEAL GUIDE, PIER 8
k. Q12-58/1.4 TAINTER GATE MODIFICATIONS, GENERAL DETAILS
l. Q12-58/2.3 TAINTER GATE MODIFICATIONS, DETAILS OF ROLLER HOUSING AND
ROLLER
m. VH 401C Cheatham Lock and Dam, Hydrographic Survey, 2011 Scour Survey, Sheet 1 of 4
n. VH 402C Cheatham Lock and Dam, Hydrographic Survey, 2011 Scour Survey, Sheet 2 of 4
o. VH 403C Cheatham Lock and Dam, Hydrographic Survey, 2011 Scour Survey, Sheet 3 of 4
p. VH 404C Cheatham Lock and Dam, Hydrographic Survey, 2011 Scour Survey, Sheet 4 of 4
1.3 COORDINATION CONFERENCES
Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this project. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to this construction. The Corps of Engineers and the Contractor will be represented at each of these meetings. Coordination conferences will be scheduled to occur when notified by the Contracting Officer.
SECTION 01 00 00 Page 2
1.4 PARTNERING
In order to most effectively accomplish this contract, the Government urges the contractor to join the Government in establishing a cohesive and professional project management team. Through this "partnering" relationship both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project's intended results are achieved, within budget and on schedule. This endeavor seeks an environment that nurtures team building, cooperation and trust between the Government and the Contractor. The partnering relationship would be bilateral in makeup, and participation will be totally voluntary.
The first step in initiating the concept would be a joint project management team "partnering" conference attended by multiple officers from each organization representing management and the key jobsite staff of each entity. The initial conference would be held within the first thirty (30) days following contract award. The Resident Engineer would chair the conference, establish its agenda and distribute minutes of the meeting. A professional facilitator acceptable to both parties would lead the participants of the session, through the steps of team building and the formation of a problem solving mechanism within the group. The conference duration would be no more than one day. Location of the conference would be offsite within a 60 mile radius of the jobsite at a facility which offers conference rooms and food service. All costs in connection with rented facilities and the facilitator would be shared equally by the Government and the Contractor. Each organization would pay other costs of its respective employees attending the conference.
Additional partnering sessions would be held no less than biannually.
Implementation of the partnering concept and philosophy would be an on-going process.
1.5 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 310-1-6a (2006) Sign Standards Manual, VOL 1
EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices
1.6 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Verified/Eligible On-Site Employees Employee Identification and Control Procedure; G Investigation Package Foreign Nationals
SECTION 01 00 00 Page 3
Submittal requirements for site security are detailed in the Nashville District Public Website as described in paragraph
PROJECT SITE SECURITY AND AT/OPSEC REQUIREMENTS.
1.7 PROJECT SIGNS
a. General. The Contractor shall furnish and erect, within 30 days after issue of the Notice to Proceed, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN at the location directed. The signs shall be lettered on one side only and shall conform to EP 310-1-6a, EP 310-1-6b, and to the details and colors shown on the sketches attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS. The name of the project shall be as follows:
TAINTER GATES MODIFICATIONS AND PAINTING
b. Materials. The sign shall be constructed with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material. Screws shall be commercial quality and of sizes shown.
c. Painting. The signs and posts shall be given one prime coat and two finish coats of exterior oil paint before lettering. Letters and trim shall be applied to one side only using one coat of enamel of color, style, and size shown.
d. Erection and Maintenance. The signs shall be erected at the designated locations. Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs throughout the life of the contract. The signs shall be maintained in good condition until completion of the contract, shall remain the property of the Contractor, and shall be removed from the site upon final acceptance of the contract work.
1.8 PROJECT SITE SECURITY AND AT/OPSEC REQUIREMENTS
The entire Cheatham Lock and Dam area is not open to the public. Depending upon the level of security threat, some Project areas may or may not be open to the Contractor and Contractor employees. The security of the Contractor's property and items furnished under this contract, until items are accepted by the Government, are the Contractor's responsibility whether stored inside or outside the site. Guidance and forms for project site security requirements are available on the Nashville District Public Website:
http://www.lrn.usace.army.mil/BusinessWithUs/ContractSecurityRequirements.aspx
1.8.1 Employee Identification and Control Procedure
An employee identification and control procedure shall be submitted for approval for identification and control of employees entering or leaving the project site. It is expected that this will include a unique photo identification card for each contractor and subcontractor employees working at the Cheatham Powerhouse project site.
1.8.2 Pre-Screening Contractor's On-Site Employees
The Contractor must pre-screen on-site employees using the E-verify Program website (http://www.dhs.gov/E-Verify) to meet the established employment eligibility requirements. The Contractor must ensure that each on-site
SECTION 01 00 00 Page 4 employee has two valid forms of Government issued identification prior to ensuring the correct information is entered into the E-verify system. An initial list of verified/eligible on-site employees must be provided to the COR no later than 3 business days after the initial contract award.
1.8.3 Employee Required Training
1.8.3.1 AT Level I Training
All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: https://atlevel1.dtic.mil/at/; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.
1.8.3.2 Suspicious Activity Reporting Training
The Contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
1.8.3.3 Level I OPSEC Training
All new Contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all Contractor employees must complete annual OPSEC awareness training. The Contractor shall submit certificates of completion for each affected Contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training.
OPSEC awareness training is available at the following websites:
https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.
1.8.4 Access and General Protection/Security Policy and Procedures
All Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The Contractor shall also provide all information required for background checks or background investigation and to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal
SECTION 01 00 00 Page 5 identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in Contractor security matters or processes.
1.8.5 Employee Escorts
All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted by Government personnel in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
1.8.6 Protection of DOD Information
Neither the Contractor, nor Contractor personnel, shall divulge or release data or information developed or obtained under performance of this work statement, except to authorized Government personnel or upon written approval of the Contracting Officer. The Contractor shall not use, disclose, or reproduce proprietary data which bears a restrictive legend, other than as specified in this work statement.
Neither the Contractor nor the Contractor's employees shall disclose or cause to be disseminated, any information concerning the operations of the activity which could result in, or increase the likelihood of, the possibility of a breach of the activities, security or interrupt the continuity of its operation.
All inquiries received by the Contractor for information concerning work performed under this contract shall be referred to the Government for evaluation under the Freedom of Information Act of 1975, Public Law 93-502, 5 U.S.C., Section 552. The determination of whether records will be released will remain with the Government. The Contractor shall assist the COR in compiling information or records for submission upon request by the Government.
The Contractor shall not release any information (including photographs, files, public announcements, statements, denials, or confirmations) on any portion of the subject matter of this contract or any phase of any program hereunder without the prior written approval of the COR. All documentation showing individuals, names or other personal information will be controlled and protected. The provisions of the Privacy Act of 1974, Public Law 93-579, 5 U.S.C., Section 552a, shall apply.
1.8.7 Media Provided by the Contractor
The Contractor shall ensure all media, electronic files, etc., it provides to the Government shall be free of viruses, Trojan horses, bots, worms, malware, defects, or any other harmful item of a destructive nature.
1.8.8 Security Requirement Amendments
Security requirements are subject to change in accordance with HSPD-12, OPM, Regulation or Policy changes, etc. Amendments will be added as a modification to the contract and forwarded to the Contractor by the Contracting Office or the Contracting Officer's Representative (COR).
SECTION 01 00 00 Page 6
1.8.9 Background Investigation Requirements
The scope of this contract involves seasonal work with each construction season lasting approximately 6 months. Since the work is being done within a controlled area, the investigation requirements fall under Category B1 for US Citizens and Category C for foreign nationals for those employees who will be on-site for a time not exceeding one construction season (6 months). Contract employees will need to be supervised / escorted by a Corps employee while within the restricted area. For those employees that will be on-site for more than 6 months throughout the life of the contract, the Contractor will need to comply with the requirements in Category B2 for US Citizens. Extensions to a short term approval will not be granted for subsequent construction seasons. Additionally the Contractor may not resubmit a short term application for employees that are on-site in excess of 6 months. Guidance and forms for the security requirements are available on the Nashville District Public Website:
http://www.lrn.usace.army.mil/BusinessWithUs/ContractSecurityRequirements.aspx.
1.9 VEHICLES
1.9.1 Use of Private Vehicles
Parking of private vehicles shall be restricted to the areas designated by the Government.
1.9.2 Identification of Vehicles
The Contractor shall supply the Powerhouse Control room operators with an up-to-date vehicle list that identifies contractor vehicles by license plate number, make and model of vehicle.
1.10 CONTRACTOR'S STAGING AREA
The Contractor will be assigned a portion of the Cheatham Lock and Dam parking lot and/or other areas for use as a staging area. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times maintained in a satisfactory manner. Temporary Contractor facilities provided during construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.
1.11 DAILY CLEANUP AND DISPOSAL
Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.
1.12 STORAGE OF EQUIPMENT AND MATERIALS
Storage of equipment and materials will be permitted only in designated staging areas. A minimum access space of three feet shall be maintained between the Contractor's stored items and existing facility equipment.
SECTION 01 00 00 Page 7
1.13 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.
1.14 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK
The Government will limit interference with the Contractor's work to the maximum reasonable extent and the Government and Contractor shall coordinate as necessary.
1.15 EVALUATION OF CONTRACTOR PERFORMANCE
The Contractor's performance will be evaluated in accordance with FAR Part
42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum. The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section
01 95 00 FORMS AND ATTACHMENTS.
The Contractor's review of the evaluation shall be completed electronically at the CPARS / CCASS website, http://www.cpars.gov. This website also includes guidance and the user's manual.
Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.
1.16 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran employment information at:
http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance:
http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act:
http://benefits.va.gov/vow/
Army Wounded Warrior Program:
http://wtc.army.mil/modules/employers/index.html
SECTION 01 00 00 Page 8
U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material:
http://www.whitehouse.gov/sites/default/files/docs/white_house_business_council_-_ guide_to_hiring_veterans_0.pdf
1.17 MEASUREMENT AND PAYMENT
No separate payment will be made for the work covered under this section.
The costs thereof shall be included in the item to which the work pertains.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
SECTION 01 00 00 Page 9
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK / GENERAL CONDITIONS
PART 1 GENERAL
1.1 SCOPE
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.3 OCCUPANCY OF PREMISES
1.4 WORKING HOURS
1.4.1 REGULAR WORKING HOURS
1.4.2 WORK OUTSIDE REGULAR HOURS
1.5 EXCLUSIONARY WORK PERIOD
1.6 SEQUENCE of WORK
1.7 EXISTING WORK
1.8 GOVERNMENT PROVIDED UTILITIES
1.8.1 Contractor Notification
1.9 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
1.10 GOVERNMENT-INSTALLED WORK
1.11 SALVAGE MATERIAL AND EQUIPMENT
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK / GENERAL CONDITIONS
PART 1 GENERAL
1.1 SCOPE
The work covered by these specifications consists of furnishing all plant, equipment, supplies, and labor to complete repair and painting of 7 double skin plated Tainter Gates (interior and exterior) and 1 Bulkhead lifting beam at Cheatham Lock and Dam. Additional work covered by these specifications includes fabrication, painting and installation of 2 sets of downstream bulkhead seal angles (4 total seal angles). Repair requirements are specified herein and on the contract drawings. Tainter gate repairs are typical for all gates, unless noted on the drawings. The extent and limits of repair are defined on the drawings. Painting requirements for components within this contract are specified in 09 97 02 PAINTING:
HYDRAULIC STRUCTURES. The Contractor is alerted that all gates contain varying quantities of debris and mud which may require removal prior to performing repairs. All debris and mud shall be removed during preparation for painting operations.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes repair and painting of 7 Tainter Gates, 1 Bulkhead lifting beam, and incidental related work as necessary to complete the contract requirements.
1.2.2 Location
The work shall be located at the Cheatham Lock and Dam, near Ashland City, TN. The contractor shall be provided a storage / staging area for construction operations on the upstream left bank (looking downstream).
The area is unsecured and accessible by boat. An additional fenced area will be provided to the Contractor adjacent to the Powerhouse for more secure storage. The exact location will be determined by the Contracting Officer. Contractor personnel shall park all vehicles and enter the premises from the Powerhouse side of the project.
1.3 OCCUPANCY OF PREMISES
Building(s) will not be occupied by the contractor during performance of work under this Contract. Contractor is responsible for provide all necessary washdown and restroom facilities for his workforce.
1.4 WORKING HOURS
1.4.1 REGULAR WORKING HOURS
Regular working hours consist of a 10 hour period, between 6:30 A.M. and 4:30 P.M., Monday through Saturday, excluding Government holidays.
SECTION 01 11 00 Page 2
1.4.2 WORK OUTSIDE REGULAR HOURS
Work outside regular working hours requires Contracting Officer approval.
Make application 10 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, and type of work to be performed.
Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer and in accordance with EM 385-1-1.
1.5 EXCLUSIONARY WORK PERIOD
The Contractor shall assume low water conditions (below spillway bulkheads) for a six month duration (1 June through November 30) each year. Work outside the defined low water period is at the Contractor's risk.
Historical data in regards to headwater and tailwater elevations can be provided for information only. The total period of performance for this contract is 42 months from Notice to Proceed (NTP), including the exclusionary period. The contract shall not be modified to account for lost production due to bulkhead overtopping while working outside the defined low water period.
1.6 SEQUENCE of WORK
The Contractor must complete work on Tainter Gates 5, 6 & 7 prior to completing the remaining 4 gates. The Contractor may choose his work order after completion of gates 5, 6 & 7. Spillway bulkhead lifting beam remediation and painting shall not begin until completion of all work on the 7 Tainter Gates. Downstream spillway bulkhead seal angles must be installed before bulkheads can be placed in the downstream slots of gate bays 1-7. Two sets of bulkhead seal angles shall be fabricated as part of this contract. The Contractor shall install the bulkhead seal angles in a manner in which they can be removed and reused on adjacent gate bays.
Steel inserts shall be installed in the concrete slots to allow future seal angle installation by the Government. Contractor shall remove seal angles and store adjacent to the spillway bulkead storage area after completion of all tainter gate repairs and painting. The Contractor is responsible for removing existing structural steel and anchorage devices that interfere with the installation of the new bulkhead seal angles.
1.7 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.8 GOVERNMENT PROVIDED UTILITIES
The Government will make available to the Contractor the following power supply capabilities (480 VOLT and 120 VOLT) for performance of work under
SECTION 01 11 00 Page 3 this contract:
a. (2) 480 VOLT, 125 AMP circuits (receptacles are at one end of the spillway section) or (1) 480 VOLT, 125 AMP circuit and (2) 480 VOLT, 60 AMP circuits (125 AMP circuit receptacle located at the end of the spillway section and the 60 AMP circuit receptacles are placed at third points of the spillway section)
b. (8) 120 VOLT, 20 AMP circuits located inside each machinery enclosure
The exact locations of each power source will be identified during the pre-bid site visit. The power sources provided are available to the Contractor, but are not necessarily adequate to support the full performance of work under this contract. The Contractor shall supply all power requirements in access of those identified in this paragraph and as necessary to satisfactorily perform the work in an efficient manner.
Contractor is responsible for extension of power from the powerhouse or dam to any associates machinery or other necessary equipment. The Government reserves the right to interrupt supplied power upon the recognition of faulty Contractor supplied equipment or cabling leading to circuit breaker tripping or as identified by the Powerhouse ground detection system.
Contractor shall provide his own comressed air source for blasting and painting operations. Contractor shall provide all water pumps necessary for washdown of gates and bulkheads.
1.8.1 Contractor Notification
Notify the Contracting Officer at least 7 days prior to needing Government supplied power in a unique location.
1.9 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Government shall provide power as indicated in paragraph 1.8. Additionally Government shall provide ten (10) spillway bulkheads for the 2015 construction season and twelve (12) additional bulkheads for the 2016 construction season and beyond for unwatering Tainter Gate Bays 1-7.
Existing Spillway bulkheads and lifting beam will be in good working order for immediate use upon Notice to Proceed. Contractor is responsible for the placement of the spillway bulkheads. Bulkhead placement requires the use of floating marine plant. Spillway bulkheads are stored on-site just upstream of the Powerhouse. The ten (10) existing spillway bulkheads shall be removed from the site and disposed of by the Contractor upon completion of the Tainter Gate painting and repairs. The Contractor shall coordinate with the Contracting Officer before discarding the existing bulkheads.
1.10 GOVERNMENT-INSTALLED WORK
There is no Government-Installed work as part of this contract. Government personnel will be responsible for operation of the Tainter Gate Machinery.
Changes to gate position shall be made to the Contracting Office 24 hours in advance.
1.11 SALVAGE MATERIAL AND EQUIPMENT
There are no items designated to be salvaged. All items removed as part of this contract become the property of the Contractor and shall be disposed
SECTION 01 11 00 Page 4 of in accordance with all applicable Federal and State regulations.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 11 00 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 PAYMENT ITEMS
1.1.1 Mobilization and Demobilization
1.1.2 Tainter Gate Repair
1.1.3 Tainter Gate Painting
1.1.4 Spillway Bulkhead Support Steel Painting
1.1.5 Lower Seal Plate Repair
1.1.6 Additional Strut Arm to Girder Flange Bolt Replacement
1.1.7 Additional Downstream Intercostal Replacement
1.1.8 Furnish Downstream Bulkhead Seal Angles
1.1.9 Install Downstream Bulkhead Seal Angles
1.1.10 Furnish and Install Side Seals
1.1.11 Welding
1.1.12 Disposal of Existing Spillway Bulkheads
1.1.13 Lifting Beam Repair & Painting (Contract Option)
1.1.14 Tainter Gate Painting (Contract Option)
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 PAYMENT ITEMS
Payment items for the work required under this contract are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular payment item, shall be included in the listed item most closely associated with the work involved. Payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, equipment, tools, supplies, and incidentals necessary to complete the work, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Mobilization and Demobilization
Payment for mobilization and demobilization shall be done in accordance with Contract Clause 252.236-7004, PAYMENT FOR MOBILIZATION AND DEMOBILIZATION. The total amount paid will not exceed the contract amount bid for the following payment items:
Mobilization and Demobilization (Season 1) Mobilization and Demobilization (Season 2) Mobilization and Demobilization (Season 3) Mobilization and Demobilization (Season 4)
1.1.2 Tainter Gate Repair
Payment for performing all required repair work for tainter gates, as required in the technical specifications and contract drawings, will be made at the contract unit price per Each for "Tainter Gate Repair".
1.1.3 Tainter Gate Painting
Payment for performing all required work for tainter gate painting, as specified in the technical specifications and shown in the contract drawings, will be made at the contract unit price per Each for "Tainter Gate Painting (Interior)" and "Tainter Gate Painting (Exterior)".
1.1.4 Spillway Bulkhead Support Steel Painting
Payment for performing all required work for painting the spillway bulkhead support steel, as specified in the technical specifications and shown in the contract drawings, will be made at the contract price per Job for "Spillway Bulkhead Support Steel Painting".
1.1.5 Lower Seal Plate Repair
Payment for repairs of portions of the lower seal plates, as described in the technical specifications and shown in the contract drawings, will be
SECTION 01 22 00 Page 2 made. Payment for repaired lenghts of seal plate will be made at the contract unit price per linear foot (LF) for "Lower Seal Plate Repair (All 7 Gates)".
1.1.6 Additional Strut Arm to Girder Flange Bolt Replacement
Payment for performing all required work for additional strut arm to girder flange bolt replacement, as required in the technical specifications and shown in the contract drawings, will be made at the contract unit price per Each for "Additional Strut Arm to Girder Flange Bolt Replacement".
1.1.7 Additional Downstream Intercostal Replacement
Payment for performing all required work for additional downstream intercostal replacement (WT6x17.5), as required in the technical specifications and shown in the contract drawings, will be made at the contract unit price per Each for "Additional Downstream Intercostal Replacement (WT6x17.5)".
1.1.8 Furnish Downstream Bulkhead Seal Angles
Payment for furnishing downstream bulkhead seal angles, as required in the technical specifications and shown in the contract drawings, will be made at the contract unit price per Each for "Furnish Downstream Bulkhead Seal Angles".
1.1.9 Install Downstream Bulkhead Seal Angles
Payment for installing downstream bulkhead seal angles, as required in the technical specifications and shown in the contract drawings, will be made at the contract unit price per Each for "install Downstream Bulkhead Seal Angles".
1.1.10 Furnish and Install Side Seals
Payment for furnishing and installing side seals, as required in the technical specifications and shown in the contract drawings, will be made at the contract unit price per Each for "Furnish and Install Side Seals".
1.1.11 Welding
Welding associated with work specified in the technical specifications and shown in the contract drawings will be included in the corresponding payment items and will not be measured and paid separatelly.
Separate payment will be made for unanticipated welding work (Bid Items 0015, 0016, 0017, 0018, and 0019) as directed by the Contracting Officer.
Payment for the following, unanticipated welds, will be made at the contract unit price per Each:
"Skin Plate Plug Welding (1 square inch - 1/4" deep)" "Type A. Misc. Weld Repair (5/16" Fillet Weld - 0" to 6")" "Type C. Misc. Weld Repair (Groove Weld - 0" to 6")"
Payment for the following, unanticipated welds, will be made at the contract unit price per linear inch (LI):
"Type B. Misc. Weld Repair (5/16" Fillet Weld - Additional Weld Beyond
SECTION 01 22 00 Page 3
6")"
"Type D. Misc. Weld Repair (Groove Weld - Additional Weld Beyond 6")"
1.1.12 Disposal of Existing Spillway Bulkheads
Payment for performing all required work for disposing of the ten (10) existing spillway bulkheads, as specified in the technical specifications and shown in the contract drawings, will be made at the contract price per Job for "Disposal of Ten (10) Existing Spillway Bulkheads".
1.1.13 Lifting Beam Repair & Painting (Contract Option)
Payment for performing the contract option work for lifting beam repair & painting, as specified in the technical specifications and shown in the contract drawings, will be made at the contract price per Job for "Lifting Beam Repair & Painting - Option".
1.1.14 Tainter Gate Painting (Contract Option)
Payment for performing the contract option work for tainter gate painting, as specified in the technical specifications and shown in the contract drawings, will be made at the contract unit price per Each for "Tainter Gate Painting (Interior) - Option" and "Tainter Gate Painting (Exterior) - Option".
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 22 00 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
2.1.2.1 Primavera
2.1.2.2 Other Than Primavera
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
3.3.2 Activity Durations
3.3.3 Procurement Activities
3.3.4 Mandatory Tasks
3.3.5 Government Activities
3.3.6 Standard Activity Coding Dictionary
3.3.6.1 Workers Per Day (WRKP)
3.3.6.2 Responsible Party Coding (RESP)
3.3.6.3 Area of Work Coding (AREA)
3.3.6.4 Modification Number (MODF)
3.3.6.5 Bid Item Coding (BIDI)
3.3.6.6 Phase of Work Coding (PHAS)
3.3.6.7 Category of Work Coding (CATW)
3.3.6.8 Feature of Work Coding (FOW)
3.3.7 Contract Milestones and Constraints
3.3.7.1 Project Start Date Milestone and Constraint
3.3.7.2 End Project Finish Milestone and Constraint
3.3.7.3 Interim Completion Dates and Constraints
3.3.7.3.1 Start Phase
3.3.7.3.2 End Phase
3.3.8 Calendars
3.3.9 Open Ended Logic
3.3.10 Default Progress Data Disallowed
3.3.11 Out-of-Sequence Progress
3.3.12 Added and Deleted Activities
SECTION 01 32 01 Page 1
3.3.13 Original Durations
3.3.14 Leads, Lags, and Start to Finish Relationships
3.3.15 Retained Logic
3.3.16 Percent Complete
3.3.17 Remaining Duration
3.3.18 Cost Loading of Closeout Activities
3.3.18.1 As-Built Drawings
3.3.18.2 O & M Manuals
3.3.19 Anticipated Adverse Weather
3.3.20 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 Initial Project Schedule Submission
3.4.3 Periodic Schedule Updates
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CD/DVDs
3.5.2 Narrative Report
3.5.3 Schedule Reports
3.5.3.1 Activity Report
3.5.3.2 Logic Report
3.5.3.3 Total Float Report
3.5.3.4 Earnings Report by CLIN
3.5.3.5 Schedule Log
3.5.4 Network Diagram
3.5.4.1 Continuous Flow
3.5.4.2 Project Milestone Dates
3.5.4.3 Critical Path
3.5.4.4 Banding
3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram
3.6 PERIODIC SCHEDULE UPDATE
3.6.1 Periodic Schedule Update Meetings
3.6.2 Update Submission Following Progress Meeting
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Time Impact Analysis (Prospective Analysis)
3.8.3 Forensic Schedule Analysis (Retrospective Analysis)
3.8.4 Fragmentary Network (Fragnet)
3.8.5 Time Extension
3.8.6 Impact to Early Completion Schedule
3.9 FAILURE TO ACHIEVE PROGRESS
3.9.1 Artificially Improving Progress
3.9.2 Failure to Perform
3.9.3 Recovery Schedule
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01 Page 2
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this
SECTION 01 32 01 Page 3 specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
SECTION 01 32 01 Page 4
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission, review and acceptance of features require design completion
c. Submission of mechanical/electrical/information systems layout drawings.
d. Long procurement activities
e. Submission and approval of O & M manuals.
f. Submission and approval of as-built drawings.
g. Submission and approval of DD1354 data and installed equipment lists.
SECTION 01 32 01 Page 5
h. Submission and approval of testing and air balance (TAB).
i. Submission of TAB specialist design review report.
j. Submission and approval of fire protection specialist.
k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
l. Air and water balancing.
m. Building commissioning - Functional Performance Testing.
n. Controls testing plan submission.
o. Controls testing.
p. Performance Verification testing.
q. Other systems testing, if required.
r. Contractor's pre-final inspection.
s. Correction of punch list from Contractor's pre-final inspection.
t. Government's pre-final inspection.
u. Correction of punch list from Government's pre-final inspection.
v. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. All Activity Codes shall be developed and assigned to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil.
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
SECTION 01 32 01 Page 6
Field Activity Code Length Description
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day shall be the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for…