W912P420B0016 0001_Vermillion Repair Amendment Package.pdf
PDF 498 KB Posted
- Attached to
- Vermilion East Pier Repair
- Solicitation number
- W912P420B0016
About this file
This document contains a solicitation amendment and bid schedule for repairs to the deteriorated east pier in Vermilion Harbor, Ohio. The U.S. Army Corps of Engineers is seeking bids to mobilize, survey the existing pier, excavate and remove deteriorated sections, install new mass concrete, precast concrete blocks, underlayer and armor stone, and dispose of materials. The schedule provides estimated quantities and unit pricing for various tasks under the base requirement and optional additional repairs. Bids are due by 1 September 2020, with award to the lowest bidder. The government reserves the right to exercise any combination or quantity of the options after contract award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to correct Option C by removing line 27. Option C w ill go from a total of 36 lines to a total of 35 lines. Call-In Information: 20 August 2020 from 10:00 A.M. (ET) to 11:00 A.M. (ET).
TELECONFERENCE: Cal-in (877) 336-1839 Access Code: 3856856 PW:1234
WEBEX
https://usace.w ebex.com/meet/geoffrey.k.hintz
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Aug-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P420B0016
X 9B. DATED (SEE ITEM 11)
14-Aug-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Aug-2020
CODE
U.S. ARMY ENGINEER DISTRICT, BUFFALO
1776 NIAGARA STREET
BUFFALO NY 14207-3199
W912P4 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P420B0016
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS
The following have been added by full text:
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:
Amenetment 0001
- Option C, Line 27, “Survey after underlayer stone placement” has been removed from Bid sheet.
- Pre-bid has been set for 20 August 2020 from 10:00 A.M. (ET) till 11:00 A.M. (ET).
- Call-In Information:
- TELECONFERENCE:
- Call-in: (877) 336-1839
- Access Code: 3856856
- Passcode: 1234
- WEBEX
- https://usace.webex.com/meet/geoffrey.k.hintz
If there are any questions before or after the pre-bid meeting, please e-mail me at Peter.R.Gembala@usace.army.mil or call me at 716-879-4221 by 01 September 2020 03:00 P.M. Est..
(End of Provision)
(End of Summary of Changes)
SECTION 00 10 00
BIDDING SCHEDULE
VERMILION HARBOR, EAST PIER, VERMILION, OHIO
Item Estimated Unit No. Description Quantity Unit Price
Estimated Amount
1 Mobilization and Demobilization 1 JA $
Repair From End of Pier to Sta. 2+12.2 And All Concrete From End of Pier to Sta. 2+16.2
2 Closeout Submittals (As-built and Record Drawings and files)
1 JA $
3 Before Survey of Pier 1 EA $ $
4 Excavation, Removals, Stockpiling
1872 CY $ $
5 Survey After Excavation and Removals
1 EA $ $
6 Mass Concrete with Dowels 263 CY $ $
7 Survey After Mass Concrete Placement
1 EA $ $
8 Precast Concrete Blocks with Grout
35 CY $ $
9 Survey After Precast Concrete Blocks Placement
1 EA $ $
10 New Underlayer Stone Placement 384 TN $ $
11 Survey After Underlayer Stone Placement
1 EA $ $
12 Unused Core Stone Disposal 282 TN $ $
13 New Armor Stone Placement 1375 TN $ $
14 Survey After New Armor Stone Placement
1 EA $ $
15 Removed Cover Stone Disposal 64 EA $ $
16 Disposal of All Other Materials Not Reused
1 JA
Total estimated amount (Items 1 through 16)
Option "A"
17 Mass Concrete 80 CY $ $
Option "B" New Navigation Light Foundation
18 Removal of Old Foundation And 14 CY $ $ Placement of New Concrete Navigation Foundation
Option "C" Repair From Sta. 2+12.2 to 3+44.2 And All Concrete From St 2+16.2 to +3+48.2
19 Closeout Submittals (As-built and Record Drawings and files)
1 JA $
20 Before Survey of Pier for Portion of Option Exercised
1 EA $ $
21 Excavation, Removals, Stockpiling
1521 CY $ $
22 Survey After Excavation and Removals
1 EA $ $
23 Mass Concrete with Dowels 538 CY $ $
24 Survey After Mass Concrete Placement
1 EA $ $
25 Precast Concrete Blocks with 61 CY $ $ Grout
26 Survey After Precast Concrete 1 EA $ $ Blocks Placement
27 New Armor Stone Placement 1360 TN $ $ 28 Survey After New Armor Stone 1 EA $ $
Placement
29 Reused Core Stone Placement 293 TN $ $
30 Unused Core Stone Disposal 662 TN $ $
31 Reused Cover Stone Placement 352 EA $ $
32 Additional Armor Stone in Place of Cover Stone
18 EA $ $
33 Survey After Reused Cover Stone Placement
1 EA $ $
34 Disposal of All Other Materials Not Reused
1 JA $
35 Geotextile 4213 SF $ $
Total estimated amount (Items 19 through 35)
Option "D"
36 Removed Cover Stone Disposal 100 EA $ $
Total estimated amount all items (Items 1 through 36) $
Note 1: The Government will evaluate offers for award purposes by adding the total price of the options to the total price for the basic requirement. Award will be made to the lowest bid. Evaluation of the options will not obligate the Government to exercise the option(s).
Note 2: For bid evaluation purposes, the total bid will be based upon the total of the base bid items and the option items shown above.
Note 3: The Government may elect to exercise any combination of Options, or none of the Options. If an Option is exercised, the Government reserves the right to limit the quantity of material up to the estimated quantities of each Option and each line item within Option "C". Additionally, the Government may elect to exercise any Option at any time after Contract award.