Abstract IGE adjusted_Sodus_20.xls

XLS spreadsheet 58 KB Posted

Attached to
Great Sodus Harbor Breakwall Repair Federal contract opportunity
Solicitation number
W912P420B0013
Issued by
Department of the Army Corps of Engineers Engineering District Buffalo

About this file

This document contains an abstract of bids and federal contract opportunity notice for repair work on the Great Sodus Harbor Breakwall. The abstract of bids details three bids received in response to solicitation number W912P4-20-B-0013 for repair of the existing seawall and confined disposal facility. The work includes items such as mobilization, clearing, excavation, stone fill, armor stone, and geotextiles. Bid amounts ranged from approximately $3.7 to $5.2 million. The related federal contract opportunity provides additional details on the solicitation. Federal agency is the Department of the Army Corps of Engineers Buffalo District. Repair work must be completed within 123 days. Only small businesses as defined by FAR 52.219-6 are eligible to compete. The cost is estimated between $1-5 million and a bid guarantee of 20% of the bid amount up to $3 million is required. Questions are due by a certain date and bids must be submitted in accordance with instructions in section 00 21 13.

View the file

Other files for this federal contract opportunity

Other files attached to Great Sodus Harbor Breakwall Repair, newest first.
File Type Posted
Abstract.xls XLS spreadsheet
Amendment 0002_25Jun2020.pdf PDF
Amendment 0001_11Jun2020.pdf PDF
Final Great Sodus East Breakwater Repair SOL.PDF PDF
W912P420B0013Solicitation Final.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule A

Date Issued:Date OpenedPage 1 of 1
Solicitation Number24-May-19
Revised ABSTRACT OF OFFERS - CONSTRUCTIONI CERTIFY that I have opened, read, and recorded on this abstract all offers received in
W912P4-20-B-0013response to this solicitation.
Issuing OfficeDate Signed
Department Of The Army
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2NO. 3
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROROFFEROR
Great Lakes Dock and MaterialsRybaBidco Marine Group
FY20 Great SodusA. HIRED LABORMuskegon, MICheboygan, MIBuffalo, NY
Buffalo NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 644,892.05$ 812,010.00$ 453,400.00$ 608,000.00
2Record (As-built) Draw1JA$ 56,845.20$ 32,400.00$ 50,000.00$ 58,000.00
3Clearing1JA$ 19,582.59$ 125,902.00$ 60,000.00$ 112,000.00
4Excavation1JA$ 203,214.66$ 156,546.00$ 121,000.00$ 345,000.00
5Stone Fill2,900TN$ 94.37$ 273,673.00$ 114.00$ 330,600.00$ 146.00$ 423,400.00$ 168.00$ 487,200.00
6Underlayer Stone4,436TN$ 98.87$ 438,587.32$ 164.00$ 727,504.00$ 163.00$ 723,068.00$ 212.00$ 940,432.00
7Armor Stone4815TN$ 212.48$ 1,023,091.20$ 160.00$ 770,400.00$ 233.00$ 1,121,895.00$ 275.00$ 1,324,125.00
8Geotextile4,094SY$ 34.36$ 140,669.84$ 24.00$ 98,256.00$ 31.25$ 127,937.50$ 71.00$ 302,956.00
9Cutting of Existing Sheet118LF$ 325.45$ 38,403.10$ 232.00$ 27,376.00$ 67.00$ 7,906.00$ 64.00$ 7,552.00
Total Estimated Amount (Items 1~9)$ 2,838,958.96$ 3,080,994.00$ 3,088,606.50$ 4,185,265.00
Option A Repair from STA. 4+16~5+25
10Excavation1JA$ 136,487.41$ 37,011.00$ 35,000.00$ 75,000.00
11Stone Fill1,261TN$ 89.93$ 113,401.73$ 114.00$ 143,754.00$ 140.00$ 176,540.00168$ 211,848.00
12Underlayer Stone1,382TN$ 94.50$ 130,599.00$ 164.00$ 226,648.00$ 155.00$ 214,210.00212$ 292,984.00
13Armor Stone1,371TN$ 212.46$ 291,282.66$ 160.00$ 219,360.00$ 255.00$ 308,475.00275$ 377,025.00
14Geotextile1,220SY$ 36.34$ 44,334.80$ 27.00$ 32,940.00$ 31.25$ 38,125.0074$ 90,280.00
15Cutting of Existing Sheet64LF$ 325.16$ 20,810.24$ 232.00$ 14,848.00$ 62.00$ 3,968.0064$ 4,096.00
Total Estimated Amount (Items 10-15)$ 737,275.84$ 674,561.00$ 776,318.00$ 1,051,233.00
Total Estimated Amount (Items 1~15)$ 3,576,234.80$ 3,755,555.00$ 3,864,924.50$ 5,236,498.00

Schedule B

Date Issued:Date OpenedPage 1 of 1
Solicitation Number24-May-19
Revised ABSTRACT OF OFFERS - CONSTRUCTIONI CERTIFY that I have opened, read, and recorded on this abstract all offers received in
W912P4-20-B-0013response to this solicitation.
Issuing OfficeDate Signed
Department Of The Army
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2NO. 3
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROROFFEROR
Great Lakes Dock and MaterialsRybaBidco Marine Group
FY20 Great SodusA. HIRED LABORMuskegon, MICheboygan, MIBuffalo, NY
Buffalo NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 866,661.15$ 959,769.00$ 955,000.00$ 796,000.00
2Record (As-built) Draw1JA$ 50,267.53$ 32,400.00$ 100,000.00$ 76,000.00
3Clearing1JA$ 19,579.74$ 125,902.00$ 100,000.00$ 147,000.00
4Excavation1JA$ 196,899.80$ 156,546.00$ 260,000.00$ 452,000.00
5Stone Fill2,900TN$ 94.35$ 273,615.00$ 111.00$ 321,900.00$ 150.00$ 435,000.00$ 220.00$ 638,000.00
6Underlayer Stone4,436TN$ 98.80$ 438,276.00$ 159.00$ 705,324.00$ 175.00$ 776,300.00$ 278.00$ 1,233,208.00
7Armor Stone4815TN$ 212.45$ 1,022,946.75$ 159.00$ 765,585.00$ 240.00$ 1,155,600.00$ 360.00$ 1,733,400.00
8Geotextile4,094SY$ 34.30$ 140,424.20$ 24.00$ 98,256.00$ 40.00$ 163,760.00$ 97.00$ 397,118.00
9Cutting of Existing Sheet118LF$ 325.40$ 38,397.20$ 232.00$ 27,376.00$ 100.00$ 11,800.00$ 84.00$ 9,912.00
Total Estimated Amount (Items 1~9)$ 3,047,068.17$ 3,193,058.00$ 3,957,460.00$ 5,482,638.00
Option A Repair from STA. 4+16~5+25
10Excavation1JA$ 182,536.95$ 37,011.00$ 100,000.00$ 98,000.00
11Stone Fill1,261TN$ 89.92$ 113,389.12$ 111.00$ 139,971.00$ 150.00$ 189,150.00220$ 277,420.00
12Underlayer Stone1,382TN$ 94.47$ 130,557.54$ 159.00$ 219,738.00$ 175.00$ 241,850.00278$ 384,196.00
13Armor Stone1,371TN$ 205.84$ 282,206.64$ 159.00$ 217,989.00$ 240.00$ 329,040.00360$ 493,560.00
14Geotextile1,220SY$ 36.33$ 44,322.60$ 27.00$ 32,940.00$ 40.00$ 48,800.0097$ 118,340.00
15Cutting of Existing Sheet64LF$ 325.11$ 20,807.04$ 232.00$ 14,848.00$ 100.00$ 6,400.0084$ 5,376.00
Total Estimated Amount (Items 10-15)$ 773,819.89$ 662,497.00$ 915,240.00$ 1,376,892.00
Total Estimated Amount (Items 1~15)$ 3,820,888.06$ 3,855,555.00$ 4,872,700.00$ 6,859,530.00