This document contains an abstract of offers and bidding schedules for the Great Sodus Harbor Breakwall Repair project. The project consists of repairing an existing sea wall and confined disposal facility and will be awarded as a firm fixed price contract not to exceed $5 million. Work must be completed within 123 days and is solicited from small businesses. The required work includes items such as mobilization, clearing, excavation, installation of stone fill, armor stone, and geotextile fabrics. The wage determination is IL20200018. Bids are due by May 24, 2019 and must include a bid guarantee of 20% of the bid not to exceed $3 million. The selected contractor will be awarded the contract by the Department of the Army Corps of Engineers Buffalo District.

View the file

Other files for this federal contract opportunity

Other files attached to Great Sodus Harbor Breakwall Repair, newest first.
File Type Posted
Abstract IGE adjusted_Sodus_20.xls XLS spreadsheet
Amendment 0002_25Jun2020.pdf PDF
Amendment 0001_11Jun2020.pdf PDF
Final Great Sodus East Breakwater Repair SOL.PDF PDF
W912P420B0013Solicitation Final.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule A

Date Issued:Date OpenedPage 1 of 1
Solicitation Number24-May-19
Revised ABSTRACT OF OFFERS - CONSTRUCTIONI CERTIFY that I have opened, read, and recorded on this abstract all offers received in
W912P4-20-B-0013response to this solicitation.
Issuing OfficeDate Signed
Department Of The Army
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2NO. 3
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROROFFEROR
Great Lakes Dock and MaterialsRybaBidco Marine Group
FY20 Great SodusA. HIRED LABORMuskegon, MICheboygan, MIBuffalo, NY
Buffalo NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 644,892.05$ 812,010.00$ 453,400.00$ 608,000.00
2Record (As-built) Draw1JA$ 56,845.20$ 32,400.00$ 50,000.00$ 58,000.00
3Clearing1JA$ 19,582.59$ 125,902.00$ 60,000.00$ 112,000.00
4Excavation1JA$ 203,214.66$ 156,546.00$ 121,000.00$ 345,000.00
5Stone Fill2,900TN$ 94.37$ 273,673.00$ 114.00$ 330,600.00$ 146.00$ 423,400.00$ 168.00$ 487,200.00
6Underlayer Stone4,436TN$ 98.87$ 438,587.32$ 164.00$ 727,504.00$ 163.00$ 723,068.00$ 212.00$ 940,432.00
7Armor Stone4815TN$ 212.48$ 1,023,091.20$ 160.00$ 770,400.00$ 233.00$ 1,121,895.00$ 275.00$ 1,324,125.00
8Geotextile4,094SY$ 34.36$ 140,669.84$ 24.00$ 98,256.00$ 31.25$ 127,937.50$ 71.00$ 302,956.00
9Cutting of Existing Sheet118LF$ 325.45$ 38,403.10$ 232.00$ 27,376.00$ 67.00$ 7,906.00$ 64.00$ 7,552.00
Total Estimated Amount (Items 1~9)$ 2,838,958.96$ 3,080,994.00$ 3,088,606.50$ 4,185,265.00
Option A Repair from STA. 4+16~5+25
10Excavation1JA$ 136,487.41$ 37,011.00$ 35,000.00$ 75,000.00
11Stone Fill1,261TN$ 89.93$ 113,401.73$ 114.00$ 143,754.00$ 140.00$ 176,540.00168$ 211,848.00
12Underlayer Stone1,382TN$ 94.50$ 130,599.00$ 164.00$ 226,648.00$ 155.00$ 214,210.00212$ 292,984.00
13Armor Stone1,371TN$ 212.46$ 291,282.66$ 160.00$ 219,360.00$ 255.00$ 308,475.00275$ 377,025.00
14Geotextile1,220SY$ 36.34$ 44,334.80$ 27.00$ 32,940.00$ 31.25$ 38,125.0074$ 90,280.00
15Cutting of Existing Sheet64LF$ 325.16$ 20,810.24$ 232.00$ 14,848.00$ 62.00$ 3,968.0064$ 4,096.00
Total Estimated Amount (Items 10-15)$ 737,275.84$ 674,561.00$ 776,318.00$ 1,051,233.00
Total Estimated Amount (Items 1~15)$ 3,576,234.80$ 3,755,555.00$ 3,864,924.50$ 5,236,498.00

Schedule B

Date Issued:Date OpenedPage 1 of 1
Solicitation Number24-May-19
Revised ABSTRACT OF OFFERS - CONSTRUCTIONI CERTIFY that I have opened, read, and recorded on this abstract all offers received in
W912P4-20-B-0013response to this solicitation.
Issuing OfficeDate Signed
Department Of The Army
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2NO. 3
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROROFFEROR
Great Lakes Dock and MaterialsRybaBidco Marine Group
FY20 Great SodusA. HIRED LABORMuskegon, MICheboygan, MIBuffalo, NY
Buffalo NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 866,661.15$ 959,769.00$ 955,000.00$ 796,000.00
2Record (As-built) Draw1JA$ 50,267.53$ 32,400.00$ 100,000.00$ 76,000.00
3Clearing1JA$ 19,579.74$ 125,902.00$ 100,000.00$ 147,000.00
4Excavation1JA$ 196,899.80$ 156,546.00$ 260,000.00$ 452,000.00
5Stone Fill2,900TN$ 94.35$ 273,615.00$ 111.00$ 321,900.00$ 150.00$ 435,000.00$ 220.00$ 638,000.00
6Underlayer Stone4,436TN$ 98.80$ 438,276.00$ 159.00$ 705,324.00$ 175.00$ 776,300.00$ 278.00$ 1,233,208.00
7Armor Stone4815TN$ 212.45$ 1,022,946.75$ 159.00$ 765,585.00$ 240.00$ 1,155,600.00$ 360.00$ 1,733,400.00
8Geotextile4,094SY$ 34.30$ 140,424.20$ 24.00$ 98,256.00$ 40.00$ 163,760.00$ 97.00$ 397,118.00
9Cutting of Existing Sheet118LF$ 325.40$ 38,397.20$ 232.00$ 27,376.00$ 100.00$ 11,800.00$ 84.00$ 9,912.00
Total Estimated Amount (Items 1~9)$ 3,047,068.17$ 3,193,058.00$ 3,957,460.00$ 5,482,638.00
Option A Repair from STA. 4+16~5+25
10Excavation1JA$ 182,536.95$ 37,011.00$ 100,000.00$ 98,000.00
11Stone Fill1,261TN$ 89.92$ 113,389.12$ 111.00$ 139,971.00$ 150.00$ 189,150.00220$ 277,420.00
12Underlayer Stone1,382TN$ 94.47$ 130,557.54$ 159.00$ 219,738.00$ 175.00$ 241,850.00278$ 384,196.00
13Armor Stone1,371TN$ 205.84$ 282,206.64$ 159.00$ 217,989.00$ 240.00$ 329,040.00360$ 493,560.00
14Geotextile1,220SY$ 36.33$ 44,322.60$ 27.00$ 32,940.00$ 40.00$ 48,800.0097$ 118,340.00
15Cutting of Existing Sheet64LF$ 325.11$ 20,807.04$ 232.00$ 14,848.00$ 100.00$ 6,400.0084$ 5,376.00
Total Estimated Amount (Items 10-15)$ 773,819.89$ 662,497.00$ 915,240.00$ 1,376,892.00
Total Estimated Amount (Items 1~15)$ 3,820,888.06$ 3,855,555.00$ 4,872,700.00$ 6,859,530.00