Bid_Abstract_Lake_Pump_17Sept2018.xls
XLS spreadsheet 45 KB Posted
- Attached to
- Lake County Raw Water Pump Station Mitigation
- Solicitation number
- W912P418B0022
About this file
Please see above attached bid abstract.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID A (1)
| Date Issued: | Date Opened | Page 1 of 1 | |||||||||||||||
| Solicitation Number | 16-Aug-18 | 17-Sep-18 | |||||||||||||||
| ABSTRACT OF OFFERS - CONSTRUCTION | I CERTIFY that I have opened, read, and recorded on this abstract all offers received in | ||||||||||||||||
| W912P4-18-B-0022 | response to this solicitation. | ||||||||||||||||
| Issuing Office | Date Signed | ||||||||||||||||
| Department Of The Army | |||||||||||||||||
| US Army Engineer District, Buffalo | O F F E R S | ||||||||||||||||
| 1776 Niagara Street | |||||||||||||||||
| Buffalo, NY 14207-3199 | NO. 1 | NO. 2 | NO. 3 | NO. 4 | NO. 5 | NO. 5 | |||||||||||
| Project Title | GOVERNMENT ESTIMATE | OFFEROR | OFFEROR | ||||||||||||||
| Huffman Equipment Rental | Chivers Construction Company | Geo Gradel Company | Eclipse Company | Kovilic Construction Company | |||||||||||||
| Lake County Raw Water Pump | A. HIRED LABOR | Eastlake, OH 44095 | Fairview, PA 16415 | Toledo, OH 43605 | Chagrin Falls, OH 44023 | Franklin Park, IL 60131 | |||||||||||
| Lake County | d | ||||||||||||||||
| Painesville, OH | B. REASONABLE CONTRACT | BID SECURITY (type & amount) | BID SECURITY (type & amount) | BID SECURITY (type & amount) | BID SECURITY (type & amount) | BID SECURITY (type & amount) | BID SECURITY (type & amount) | ||||||||||
| XX | (without profit) | Bid bond - 20% of Bid | Bid bond - 20% of bid | Bid bon - 20 % of bid | Bid bon - 20 % of bid | Bid bon - 20 % of bid | Bid bon - 20 % of bid | ||||||||||
| NUMBER OF ADDENDA ISSUED: | C. REASONABLE CONTRACT | ADDENDA ACKNOWLEDGED | ADDENDA ACKNOWLEDGED | ADDENDA ACKNOWLEDGED | ADDENDA ACKNOWLEDGED | ADDENDA ACKNOWLEDGED | ADDENDA ACKNOWLEDGED | ||||||||||
| (including profit) | |||||||||||||||||
| Item | Est. | Unit | Estimated | Unit | Estimated | Unit | Estimated | Unit | Estimated | Unit | Estimated | Unit | Estimated | Unit | Estimated | ||
| No. | Description of Offered Item | Quantity | Unit | Price | Amount | Price | Amout | Price | Amout | Price | Amout | Price | Amout | Price | Amout | Price | Amout |
| Bidding Schedule | |||||||||||||||||
| 1 | Mobilization & Demobilization | 1 | JA | $153,560.00 | $153,560.00 | $349,300.00 | $349,300.00 | $35,730.00 | $35,730.00 | $75,000.00 | $75,000.00 | $1,040,958.30 | $1,040,958.30 | $200,000.00 | $200,000.00 | ||
| 2 | Temp Construct Facilities | 1 | JA | $142,240.00 | $142,240.00 | $10,000.00 | $10,000.00 | $38,940.00 | $38,940.00 | $190,000.00 | $190,000.00 | $21,000.00 | $21,000.00 | $30,000.00 | $30,000.00 | ||
| 3 | Record (As-built) Drawings (including all surveys and photographs) | 1 | JA | $78,360.00 | $78,360.00 | $35,000.00 | $35,000.00 | $15,360.00 | $15,360.00 | $10,000.00 | $10,000.00 | $40,000.00 | $40,000.00 | $20,000.00 | $20,000.00 | ||
| 4 | Seeding | 1.20 | AC | $4,105.00 | $4,926.00 | $10,000.00 | $12,000.00 | $14,009.42 | $16,811.30 | $13,100.00 | $17,030.00 | $4,603.06 | $5,523.67 | $5,000.00 | $6,000.00 | ||
| 5 | Excavation for Revetment Toe | 3,530 | CY | $6.70 | $23,651.00 | $15.00 | $52,950.00 | $62.00 | $218,860.00 | $25.00 | $88,250.00 | $42.00 | $148,260.00 | $45.00 | $158,850.00 | ||
| 6 | Excavation for 2:1Slope Above Revetment | 11,125 | CY | $6.10 | $67,862.50 | $13.00 | $144,625.00 | $34.00 | $378,250.00 | $24.00 | $267,000.00 | $30.00 | $333,750.00 | $40.00 | $445,000.00 | ||
| 7 | Granular Fill-Above Crest-on 1V:2H Slope | 305 | TN | $50.95 | $15,539.75 | $35.00 | $10,675.00 | $54.00 | $16,470.00 | $67.00 | $20,435.00 | $48.30 | $14,731.50 | $50.00 | $15,250.00 | ||
| 8 | Bedding Stone | 1970.00 | TN | $80.50 | $158,585.00 | $61.50 | $121,155.00 | $62.00 | $122,140.00 | $84.00 | $165,480.00 | $98.96 | $194,951.20 | $100.00 | $197,000.00 | $0.00 | |
| 9 | Underlayer Stone | 8,600 | TN | $98.15 | $844,090.00 | $69.75 | $599,850.00 | $68.00 | $584,800.00 | $96.00 | $825,600.00 | $93.35 | $802,810.00 | $125.00 | $1,075,000.00 | ||
| 10 | Armor Stone | 11,100 | TN | $126.10 | $1,399,710.00 | $76.35 | $847,485.00 | $81.50 | $904,650.00 | $120.00 | $1,332,000.00 | $105.00 | $1,165,500.00 | $150.00 | $1,665,000.00 | ||
| 11 | Geotextile-Revetment | 4,700 | SY | $9.35 | $43,945.00 | $4.00 | $18,800.00 | $3.15 | $14,805.00 | $28.00 | $131,600.00 | $3.25 | $15,275.00 | $5.00 | $23,500.00 | ||
| 12 | Geotextile-Access Road | 950 | SY | $8.60 | $8,170.00 | $2.00 | $1,900.00 | $2.12 | $2,014.00 | $4.00 | $3,800.00 | $3.25 | $3,087.00 | $5.00 | $4,750.00 | ||
| 13 | Concrete Manhole | 1 | JA | $292,130.00 | $292,130.00 | $200,000.00 | $200,000.00 | $532,700.00 | $532,700.00 | $67,000.00 | $670,000.00 | $105,000.00 | $105,000.00 | $450,000.00 | $450,000.00 | ||
| 14 | Excavation for Access Road | 8,500 | CY | $6.80 | $57,800.00 | $13.00 | $110,500.00 | $8.10 | $68,850.00 | $25.00 | $212,500.00 | $35.00 | $297,500.00 | $40.00 | $340,000.00 | ||
| 15 | Granular Fill-Access Road | 325 | TN | $64.85 | $21,076.25 | $35.00 | $11,375.00 | $41.00 | $13,325.00 | $67.00 | $21,775.00 | $46.48 | $15,106.00 | $50.00 | $16,250.00 | $0.00 | |
| 16 | 20" Steel Pipe Extension | 1 | JA | $10,080.00 | $10,080.00 | $5,000.00 | $5,000.00 | $2,615.00 | $2,615.00 | $5,500.00 | $5,500.00 | $4,837.46 | $4,837.46 | $3,000.00 | $3,000.00 | $0.00 | |
| Total Estimated Amount (Items 1 through 16) | $3,321,725.50 | $2,530,615.00 | $2,966,320.30 | $4,035,970.00 | $4,208,290.13 | $4,649,600.00 | |||||||||||
| 17 | Option "A" Live Stakes | 7,090 | EA | $6.40 | $45,376.00 | $9.60 | $68,064.00 | $5.20 | $36,868.00 | $9.50 | $67,355.00 | $9.28 | $65,795.20 | $10.00 | $70,000.00 | ||
| 18 | Option "B" Seed Protection | 52,500 | SF | $1.10 | $57,750.00 | $0.30 | $15,750.00 | $0.25 | $13,125.00 | $0.45 | $23,625.00 | $0.66 | $34,650.00 | $0.35 | $18,375.00 | ||
| 19 | Option "c" Wattles | 4,000 | LF | $43.85 | $175,400.00 | $4.50 | $18,000.00 | $5.20 | $20,800.00 | $5.50 | $22,000.00 | $20.48 | $81,920.00 | $25.00 | $100,000.00 | ||
| 20 | Option "D" Lake Bottom Stone Re-use | 140 | EA | $468.45 | $65,583.00 | $250.00 | $35,000.00 | $79.60 | $11,144.00 | $250.00 | $35,000.00 | $59.98 | $8,397.20 | $100.00 | $14,000.00 | ||
| 21 | Option "E" Pre-cast Cast Concrete Blocks | 236 | EA | $465.75 | $109,917.00 | $375.00 | $88,500.00 | $395.00 | $93,220.00 | $265.00 | $62,540.00 | $224.33 | $52,941.88 | $250.00 | $59,000.00 | ||
| 22 | Bedding Stone for Chinking | 700 | TN | $88.25 | $61,775.00 | $60.80 | $42,560.00 | $54.00 | $37,800.00 | $110.00 | $77,000.00 | $89.37 | $62,559.00 | $125.00 | $87,500.00 | ||
| 23 | Option "G" Sand Fill | 14000 | CY | $28.80 | $403,200.00 | $40.00 | $560,000.00 | $49.50 | $693,000.00 | $52.00 | $728,000.00 | $75.33 | $1,054,620.00 | $65.00 | $910,000.00 | ||
| Total | $4,240,726.50 | $3,358,489.00 | $3,872,277.30 | $5,051,490.00 | $5,569,173.41 | $5,908,475.00 |