-The Government estimated magnitude price in accordance w ith FAR 36.204(c) is betw een $100,000. and $250,000.

-Work to be performed: Black Rock Lock, Buffalo, New York, Low er West Gate Hydraulic Ram Connection Repair.

-Description of w ork required: See Statement of Work.

-Timeline: All w ork must be completed w ithin 45 days follow ing the initial aw ard of the contract.

-Liquidated Damages: $950 dollars for each calendar day of delay until the w ork is completed or accepted.

-Site Visit: There w ill be one(1) scheduled pre-bid site visit for prospective bidders. The date w ill be 1 March 2017 at 10:00 AM to 11:00 AM.

The location w ill be U.S. Army Corps of Engineer, Black Rock Lock, 1776 Niagara St., Buffalo, NY 14207.

-Proposals: Should be e-mailed to dorothy.j.jones@usace.army.mil or to frank.j.dandrea@usace.army.mil or mailed to either party at U. S. Army Corps of Engineers, 1776 Niagara St., Buffalo, NY 14207-3111 or faxed to either party at 716-879-4353 no later than 29 March 2017 by 3:00 P.M.

-NAICS: 811310 Commercial and Industrial Machinery and Equipment Repair and Maintenance.

Size Standard:$7,500,000.00 -This is a 100% Small Business

DOROTHY J JONES 716-879-4253

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

27-Feb-2017

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________45 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

U.S. ARMY ENGINEER DISTRICT, BUFFALO

1776 NIAGARA STREET

BUFFALO NY 14207-3199

W912P4

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

(hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: 716.879.4173 TEL: FAX:

W912P4-17-T-0010 10

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W912P4-17-T-0010

Section 00010 - Solicitation Contract Form

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

BASE BID ITEM 1

FFP

Remove and replace connection from hydraulic cylinder to gate. See Statement of Work for detailed inforamtion.

FOB: Destination

NET AMT

0002 1 Job

OPTIONAL BID ITEM 2

FFP

Replace corroded sections of the steel upper west catwalk structure. See Statement of Work for detailed inforamtion.

0003 1 Job

OPTIONAL BID ITEM 3

FFP

Supply steel plank/walkway grating. See Statement of Work for detailed inforamtion.

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

0001 18-MAY-2017 1 NY/PA OPER/MAINT OFFICE

DAVID MASTRIANO

1776 NIAGARA STREET

BUFFALO NY 14207-3199

716-879-4140

9623ER

0002 18-MAY-2017 1 (SAME AS PREVIOUS LOCATION)

0003 18-MAY-2017 1 (SAME AS PREVIOUS LOCATION)

Section 00700 - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-3 Gratuities APR 1984 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-17 Contractor Employee Whistleblower Rights and Requirement

To Inform Employees of Whistleblower Rights

APR 2014

52.204-3 Taxpayer Identification OCT 1998 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber

Content Paper

MAY 2011

52.204-7 System for Award Management OCT 2016 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-50 Combating Trafficking in Persons MAR 2015 52.223-18 Encouraging Contractor Policies To Ban Text Messaging

While Driving

AUG 2011

52.225-12 Notice of Buy American Requirement - Construction Materials Under Trade Agreements

MAY 2014

52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-14 Inconsistency Between English Version And Translation Of

Contract

FEB 2000

52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.

OCT 2015

52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-5 Material and Workmanship APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-19 Organization and Direction of the Work APR 1984 52.236-28 Preparation of Proposals--Construction OCT 1997 52.243-1 Changes--Fixed Price AUG 1987 52.244-6 Subcontracts for Commercial Items JAN 2017 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

JUN 2012

CLAUSES INCORPORATED BY FULL TEXT

TO BE FILLED-IN BY VENDOR

52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2017)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is [insert NAICS code].

(2) The small business size standard is [insert size standard].

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

( ) Paragraph (d) applies.

( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2; Prohibition on Contracting with Inverted Domestic Corporations--Representation.

(vii) 52.209-5; Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding elinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.222-57, Representation Regarding Compliance with Labor Laws (Executive Order 13673). This provision applies to solicitations expected to exceed $50 million which are issued from October 25, 2016 through April 24, 2017, and solicitations expected to exceed $500,000, which are issued after April 24, 2017.

Note to paragraph (c)(1)(xvi): By a court order issued on October 24, 2016, 52.222-57 is enjoined indefinitely as of the date of the order. The enjoined paragraph will become effective immediately if the court terminates the injunction. At that time, DoD, GSA, and NASA will publish a document in the Federal Register advising the public of the termination of the injunction.

(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA- designated items.

(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xxi) 52.225-4, Buy American--Free Trade Agreements--Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225- 3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $77,533, the provision with its Alternate II applies.

(D) If the acquisition value is $77,533 or more but is less than $100,000, the provision with its Alternate III applies.

(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--Certification. This provision applies to all solicitations.

(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certification. This provision applies to all solicitations.

(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[Contracting Officer check as appropriate.]

(i) 52.204-17, Ownership or Control of Offeror.

(ii) 52.204-20, Predecessor of Offeror.

(iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

(iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Certification.

(v) 52.222-52 Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Certification.

(vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA- Designated Products (Alternate I only).

(vii) 52.227-6, Royalty Information.

(A) Basic.

(B) Alternate I.

(viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The offeror has completed the annual representations and certifications electronically via the SAM website accessed through https://www.acquisition.gov. After reviewing the SAM database information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause Title Date Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

(End of provision)

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than .45 days. The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) -

ALTERNATE I (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 45 days. .

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by March 20, 2017. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

52.216-24 LIMITATION OF GOVERNMENT LIABILITY (APR 1984)

(a) In performing this contract, the Contractor is not authorized to make expenditures or incur obligations exceeding the contract dollar amount..

(b) The maximum amount for which the Government shall be liable if this contract is terminated is $0.00 dollars.

52.216-25 CONTRACT DEFINITIZATION (OCT 2010)

(a) A firm fixed priceddefinitive contract is contemplated. The Contractor agrees to begin promptly negotiating with the Contracting Officer the terms of a definitive contract that will include (1) all clauses required by the Federal Acquisition Regulation (FAR) on the date of execution of the letter contract, (2) all clauses required by law on the date of execution of the definitive contract, and (3) any other mutually agreeable clauses, terms, and conditions. The Contractor agrees to submit a fixed price proposal, including data other than certified cost or pricing data, and certified cost or pricing data, in accordance with FAR 15.408, Table 15-2, supporting its proposal.

(b) The schedule for definitizing this contract is at time of award of contract.

(c) If agreement on a definitive contract to supersede this letter contract is not reached by the target date in paragraph (b) above, or within any extension of it granted by the Contracting Officer, the Contracting Officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with Subpart 15.4 and Part 31 of the FAR, subject to Contractor appeal as provided with completion of the contract, subject only to the Limitation of Government Liability clause.

(1) After the Contracting Officer's determination of price or fee, the contract shall be governed by--

(i) All clauses required by the FAR on the date of execution of this letter contract for either fixed-price or cost-reimbursement contracts, as determined by the Contracting Officer under this paragraph (c);

(ii) All clauses required by law as of the date of the Contracting Officer's determination; and

(iii) Any other clauses, terms, and conditions mutually agreed upon.

(2) To the extent consistent with subparagraph (c)(1) above, all clauses, terms, and conditions included in this letter contract shall continue in effect, except those that by their nature apply only to a letter contract.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer at U. S. Army Corps of Engineers (addressed as follows) by obtaining written and dated acknowledgment of receipt from Mr. Frank J. D’Andrea, 1776 Niagara Street, Buffalo, NY 14207.

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil/ https://www.acquisition.gov/?q=browsefar http://www.acq.osd.mil/dpap/dars/far.html

U.S. Army Corps of Engineers® Buffalo District

Statement of Work Black Rock Lock, Buffalo, New York Lower West Gate Hydraulic Ram Connection Repair

Customer:

Lockmaster, Black Rock Lock

Prepared By:

David Mastriano, PE, PMP New York and Pennsylvania Operations & Maintenance U.S. Army Corps of Engineers Buffalo District 1776 Niagara Street Buffalo, NY 14207

February 2017

1 General Description of Work

1.1 Base Bid Item(s)

1.1.1 Base Bid Item 1 – Remove and Replace Connection from Hydraulic Cylinder to Gate

1.2 Optional Bid Item(s)

1.2.1 Optional Bid Item 2 – Replace Corroded Sections of the Steel Catwalk Structure

1.2.2 Optional Bid Item 3 – Supply Steel Walkway Grating

2 Point of Contact 3 Pre-Bid Site Visit 4 Project/Contractual References 5 Detailed Description of Work

5.1 Detailed Description of Work – Base Bid Item(s)

5.1.1 Base Bid Item 1 – Remove and Replace Connection from Hydraulic Cylinder to Gate

5.2 Detailed Description of Work –Optional Bid Item(s)

5.2.1 Optional Bid Item 2 – Replace Corroded Sections of the Steel Catwalk Structure

5.2.2 Optional Bid Item 3 – Supply Steel Walkway Grating

6 Project Information

6.1 Basis for Award

6.2 Period of Performance

6.2.1 Pre-Construction Submittals

6.3 Pre-Construction Meeting

6.4 Work Schedule

6.5 Material/Equipment Information

6.6 Dimension/Quantity Verification

6.7 Material Storage

6.8 Site Cleanup

7 Quality Assurance (QA)

7.1 Overview

7.1.1 Government Project Manager (PM)

7.1.2 Government Quality Assurance (QA)

7.1.3 Government Inspections

7.1.4 Product Data Sheets

8 Communication 9 Repair/Restoration of Government Property 10 Work Stoppage, Contract Cancellation Actions 11 Material Change Orders 12 Liquidated Damages 13 Inspection/Testing

13.1 Pre-Final/Final Inspection

14 Completion 15 Payment 16 Safety 17 Security

17.1 Access and General Protection/Security Policy and Procedures

17.1.1 Candidate Pre-Screening

17.1.2 Background Investigation

17.1.3 Access Badge

17.1.4 Suspicious Activity Reporting Training

17.2 Start of Work

17.3 Arrival/Departure

17.4 Video/Camera Equipment

18 Submittals

18.1 Bid Submittals

18.2 Pre-Construction Submittals

18.3 Project Completion Submittals

Attachment #1 – Drawings Attachment #2 – Bid Schedule Attachment #3 – Directions to Black Rock Lock Attachment #4 – Government Safety Requirements Attachment #5 – Accident Prevention Plan Checklist Attachment #6 – Blank Activity Hazard Analysis Attachment #7 – USACE Buffalo District Monthly Man Hour Exposure Report

1 General Description of Work The contractor shall perform the following work under this contract:

1.1 Base Bid Item(s)

1.1.1 Base Bid Item 1 – Remove and Replace Connection from Hydraulic Cylinder to Gate

1.2 Optional Bid Item(s)

1.2.1 Optional Bid Item 2 – Replace Corroded Sections of the Steel Catwalk Structure

1.2.2 Optional Bid Item 3 – Supply Steel Walkway Grating

2 Point of Contact For scheduling project site visits and/or questions regarding this Statement of Work:

U.S. Army Corps of Engineers, Buffalo District Attn: Contracting Officer 1776 Niagara Street Buffalo, New York 14207

Phone: 716-879-4126 Facsimile: 716-879-4353

3 Pre-Bid Site Visit There will be one (1) scheduled pre-bid site visit for prospective bidders. The date and time of the visit will be posted on FBO. The location of the visit will be Black Rock Lock at US Army Corps of Engineers Buffalo District Reservation, 1776 Niagara Street, Buffalo, New York 14207. Prospective bidders are urged to attend to gain information that will be necessary in the preparation of bid submittals. Due to maintenance, operation and security requirements, unscheduled visits will not be honored. Following a visit to the project site, a question and answer session will be held. During this session, prospective bidders are asked to direct all questions concerning the project to the Buffalo District Contracting Office (DCO).

4 Project/Contractual References

• EM 385-1-1, 30 Nov 2014, U.S. Army Safety and Health Requirements Manual

• Wide-Flange Beam Drawings (Sheets D1-D7 within Attachment #1)

5 Detailed Description of Work

5.1 Detailed Description of Work – Base Bid Item(s)

5.1.1 Base Bid Item 1 – Remove and Replace Connection from Hydraulic Cylinder to Gate The 76 ton operating gates at the Black Rock Lock open and close via an 8” diameter hydraulic cylinder which connects to the gate via a clevis eye mounted to a wide flange beam, which is mounted to the main gate structure.

The W14x90 wide flange beam has failed due to a crack in the flange on the left-hand side of the beam, along with failed bolts, and requires replacement.

Construction drawings for the repair work are shown in Attachment #1. The contractor shall submit shop drawings for government approval prior to beginning fabrication. The work is described below.

The contractor shall have the following structural steel sections fabricated prior to the start of work. The contractor shall field verify all dimensions, bolt spacing and sizing, shown and drawings and stated herein prior to fabricating. The contractor shall note the gate structure is over 100 years old, and rivet/bolt spacing may not be consistent throughout a whole member, and members may not be plumb, level, or square. A template or laser scan of the removed sections may help fabricating the new structural steel. Lead based paint has been abated from the gates. All materials shall be submitted to the government as a pre-construction submittal prior to ordering:

Wide flange beam

• W14x211 beam, ASTM A992 Grade 50 high strength low alloy steel, approximately 60” in length. Apply a

G100 hot-dipped galvanized coating meeting ASTM A123. Quantity of one (1). The beam shall be notched at each end on one flange where it shall bear against the vertical angles, as shown in Detail B on Sheet D7, and may be shop-drilled or field-drilled. Verify hydraulic cylinder mounting plate bolt spacing prior to drilling.

Hot-dipped galvanized coating shall be applied after any shop drilling is performed. Apply cold galvanizing compound to all field drilled or modified surfaces.

Bulkhead plate

• Approximate size of 8’ 8 ½” x 3’ 10 3/8” x ¾”, ASTM A572 Grade 50 steel plate. Apply a G100 hot-dipped galvanized coating meeting ASTM A123. Quantity of one (1). Refer to Sheet D5. Holes may require field-drilled as rivet spacing is not consistent. Apply cold galvanizing compound to all drilled surfaces.

Diaphragm plates and connecting angles

• Approximate plate size of 3’ 11 5/8” x 3’ 5/8” x 3/8”, ASTM A36 steel plate. Apply a G100 hot-dipped galvanized coating meeting ASTM A123. Quantity of two (2). Holes shall be field-drilled as rivet spacing is not consistent. Apply cold galvanizing compound to all drilled surfaces.

• L3 ½ x 3 ½ x 3/8”, lengths as shown on Sheet D6, ASTM A36 steel. Apply a G100 hot-dipped galvanized coating meeting ASTM A123. Quantity of eight (8). Each diaphragm will have three angles replaced on the inside and one on the outside at the front of the gate with these. Reuse of the other existing on the outside is acceptable.

o Note: All fasteners connected to these angles are ¾” ASTM A325 bolts.

• L4 x 3 ½ x 3/8”, lengths as shown on Sheet D6, ASTM A36 steel. Apply a G100 hot-dipped galvanized coating meeting ASTM A123. Quantity of two (2). These angles will connect the front of the diaphragm to the bulkhead plate, and where the beam connects to.

o Note: All fasteners connected to these angles are ¾” ASTM A325 bolts.

Beam flange to diaphragm plate

• L4 x 4 x ½” angles, 7” length, ASTM A572 Grade 50 steel. Apply a G100 hot-dipped galvanized coating meeting ASTM A123. Quantity of four (4), two (2) on each end of beam. Refer to Sheet D6.

o Note: All fasteners connected to these angles are 1” ASTM A325 bolts.

Beam flange angle to diaphragm plate connection

• Hex head bolts, galvanized, 1”-8 x 2 ½”, Grade ASTM A325. Quantity of twelve (12).

• Hex nuts, galvanized, 1”-8, Grade DH meeting ASTM A563. Quantity of twelve (12).

• 1” structural washers, galvanized, ASTM F436 Type 1. Quantity of twelve (12).

• 1” galvanized direct-tension indicating washers with dye, meeting ASTM F436 Type 1. Quantity of twelve

(12).

Hydraulic cylinder mounting plate to beam flange

• Hex head bolts, galvanized, 7/8”-9 x 6”, Grade ASTM A325. Quantity of fourteen (14).

• Hex nuts, galvanized, 7/8”-9, Grade DH meeting ASTM A563. Quantity of fourteen (14).

• 7/8” structural washers, galvanized, ASTM F436 Type 1. Quantity of twenty-eight (28).

• 7/8” galvanized direct-tension indicating washers with dye, meeting ASTM F436 Type 1. Quantity of fourteen (14).

o A total of two (2) structural washers, one (1) direct-tension indicating washer, and one (1) nut shall be used on each bolt.

Diaphragm and bulkhead plates to angle connection

• Hex head bolts, galvanized, 3/4”-10 x 2 ½”, Grade ASTM A325. Estimated quantity of two-hundred (200).

• Hex nuts, galvanized, 3/4”-10, Grade DH meeting ASTM A563. Estimated quantity of two-hundred (200).

• 3/4” structural washers, galvanized, ASTM F436 Type 1. Estimated quantity of two-hundred (200).

• 3/4” galvanized direct-tension indicating washers with dye, meeting ASTM F436 Type 1. Estimated quantity of two-hundred (200).

Beam flange to bulkhead plate connection

• Hex head bolts, galvanized, 1”-8 x 4”, Grade ASTM A325. Quantity of sixteen (16).

• Hex nuts, galvanized, 1”-8, Grade DH meeting ASTM A563. Quantity of sixteen (16).

• 1” structural washers, galvanized, ASTM F436 Type 1. Quantity of thirty-two (32).

• 1” galvanized direct-tension indicating washers with dye, meeting ASTM F436 Type 1. Quantity of sixteen

(16).

o A total of two (2) structural washers, one (1) direct-tension indicating washer, and one (1) nut shall be used on each bolt.

The contractor shall remove and replace the wide-flange beam and various structural components in the following proposed order. Prior to the start of work, the government and contractor will agree on the order work shall be completed:

1) The government will operate the gate into the opened or recessed position. From here, the contractor can enter a pit to access the work area, or work can be done via a barge and scaffolding from the water. Confined space entry permits are required to access the gate pocket. Air monitoring is required if hot work is performed as oxygen levels may diminish.

2) The contractor shall secure the gate in the opened position via anchors in the top of the concrete wall and come-alongs attached to the gate. The contractor shall coordinate with the government to establish two separate anchor points. Each anchor point shall be capable of supporting a minimum 4 tons of force.

3) Remove the single section of timber fender and steel channel on the outside (water side) of the gate. The channel is welded to the gate. Set aside as the channel and fender shall be replaced later.

4) Block the 8” diameter hydraulic cylinder in the rear under the house. This will prevent damage to the cylinder and the clevis from rising when it is disconnected in the next step.

5) Disconnect the twelve (12) 7/8” diameter rods which secure the clevis to the wide flange beam. Four (4) of these rods penetrate through the outer bulkhead plate. Discard bolts.

6) Coordinate with the government to fully retract the cylinder, pulling it away from the W14x90 beam. The contractor shall expect only a fraction of an inch of retraction. The cylinder cannot be moved from here unless the body is unbolted, hydraulic lines disconnected, and physically moved back. Retain the steel shim plate for reuse.

7) On the outside or water side of the gate, there is a large plate known as the bulkhead plate. The bulkhead plate is approximately 8’ 8 ½” x 3’ 10 3/8”, and there are two layers of it, along with a filler plate between the inside layer and the beam. At each side of the bulkhead plate to be removed, there are 10” wide vertical plates to be removed which secures the bulkhead plate. At the pivoting side of the gate, there are two layers of plates. The outer plate is a 10” x 1” plate, which can be removed and set aside for later reuse. The inner plate is 10” x 5/8” and runs the full height of the gate. The plate shall be cut just below where the bulkhead plate to be removed is. The top of the 10” plate shall then be unbolted from the gate and disposed of, while the lower section of this plate shall remain. There is a variety of solid rivets and bolts which shall be removed. Retain the other 10” x 1” vertical plate as it shall be reinstalled later. Dispose of the removed rivets and bolts, as longer ones will be required later.

8) Remove the rivets on the angles at the top and bottom of the bulkhead plate. These angles will be replaced with new angles, of an equal size, galvanized A36 steel. Refer to the drawings for angles to be replaced.

9) Remove the W14x90 beam and recycle off-site. Care must be taken not to damage the hydraulic cylinder.

Any damage to government property shall be repaired or replaced by the contractor at the contractor’s expense.

10) In each side of the gate pocket, there are steel plates, known as diaphragm plates. Remove the diaphragm plates and angles as shown in the drawings. Recycle the plates and angles off-site.

11) Drill two (2) new 15/16” holes in both the clevis eye mounting and shim plate. The plate shall be modified in place, as removal of the plate includes removing the pressed-in pin from the bearing inside the clevis eye. One hole will go in each the top and bottom row of bolts. Two (2) new 7/8” bolts will be added later, for a new total of fourteen (14) bolts to secure the plate to the beam.

12) The government will inspect all work and determine if demolition is complete. The new plates and beams shall not be installed until government approval is given.

13) Apply two (2) coats of cold galvanizing compound to any areas where paint has been damaged or surface modified.

14) Insert the two (2) new diaphragm plates onto each side of the beam, including angles. The diaphragm plates are approximately 3’ 11 5/8” x 3’ 5/8” x 3/8”. Bolt the perimeter of each plate to the new angles using 3/4” hex head bolts. Use a direct tension indicating washer and tighten until dye is seen.

15) Insert the new W14x211 beam from the water side of the gate and secure to the vertical angle with 3/4” hex head bolts. Use a direct tension indicating washer and tighten until dye is seen. Verify proper mounting location as the hydraulic cylinder clevis eye mounting plate will later be joined to this. There is some small play allowed in the two axes of the hydraulic cylinder assembly.

16) Insert the bulkhead plate and bolt to the flange of the beam and the angles, using 1” bolts. The bolts shall be installed with 1” tension-indicating washers. Install a structural washer between the tension-indicating and nut or bolt head. Tighten until indicating dye is seen.

17) Install the new 10” x 5/8” vertical plate on the water side of the gate using new bolts, length to be determined by the contractor. Install the existing 10” x 1” plate which was removed and set aside earlier. New A325 bolts are required. The contractor shall determine the length of fasteners required, as there is now extra thickness and a longer length is required than what was removed. Use a direct tension indicating washer and tighten until dye is seen.

18) The government will extend the hydraulic cylinder for the clevis eye mounting plate to meet the beam. Insert the shim plate that was removed earlier. The nuts shall be on the hydraulic cylinder side. Use thread locker on the nuts.

19) Bolt the mounting plate to the beam using 7/8” bolts. Install a 7/8” tension-indicating washer. Install a structural 1” washer between the tension-indicating and nut or bolt head. Tighten until indicating dye is seen.

20) The government will perform a joint inspection with the contractor.

21) After inspection acceptance is given, reinstall the timber fender and steel channel by welding the channel back to the gate.

22) Remove the come-alongs securing the gate.

23) The government will operate the gate and perform a final inspection with the contractor to ensure work meets the contractual requirements.

The contractor shall supply to the government red-lined construction drawings as part of a project closeout submittal.

Payment for this line item will be one lump-sum payment when the final inspection is accepted by the government.

5.2 Detailed Description of Work –Optional Bid Item(s)

5.2.1 Optional Bid Item 2 – Replace Corroded Sections of the Steel Catwalk Structure The steel catwalk on the Upper West gate has several members which are corroded and require replacement. The contractor shall remove and replace two (2) existing wide flange beams.

The contractor shall have the following structural steel sections fabricated prior to start of work. The contractor shall field verify all dimensions, existing channel spacing, weld locations, and any bolt size and spacing. All materials shall be submitted to the government as a preconstruction submittal prior to ordering:

• W4x13 beam, ASTM A992 high strength low alloy steel, approximately 140”. Quantity of one (1). Apply a

G100 hot-dipped galvanized coating meeting ASTM A123.

• W4x13 beam, ASTM A992 high strength low alloy steel, approximately 48”. Quantity of one (1). Apply a

G100 hot-dipped galvanized coating meeting ASTM A123.

• 2” x 2” x ¼” tee bar, A36 steel. Quantity of one (1). Apply a G100 hot-dipped galvanized coating meeting

ASTM A123.

The contractor shall remove and replace the existing approximate 4”x4”x140” beam and the supporting members of the catwalk as follows:

1) The government will operate the gate into the opened or recessed position. In this position the contractor is not required to use fall protection. If work is done in the closed gate position, fall protection or PFD’s will be required.

2) The contractor shall attempt to leave the angle supporting the guardrail in place, and remove the beam welded underneath it for replacement.

3) Remove the plates and angle used for the ramp support at the end of the gate, but keep the side ramp mounting brackets in place. Also remove the lateral beam that connects between the two main beams.

4) Remove the existing 140” beam and recycle off site.

5) The government will inspect all work and determine if demolition is complete. The new steel shall not be installed until government approval is given.

6) Insert the new W4x13 beams (field workers will determine the order of installation), and weld into place.

7) Install the tee bar upside down above the lateral beam to support the ramp by welding to both guardrail angles and the beam.

8) Apply two (2) coats of galvanizing compound to any areas where paint has been damaged or welds have been placed.

9) The government will operate the gate and perform a final inspection with the contractor to ensure work meets the contractual requirements.

Payment for this line item will be one lump-sum payment when the final inspection is accepted by the government.

5.2.2 Optional Bid Item 3 – Supply Steel Walkway Grating

Contractor shall supply to the government a variety of plank grating for the catwalks, delivered to the Black Rock Lock. The following materials shall be supplied:

• 3 diamond wide plank grating, 7” width, 12 gauge ASTM A653 steel, serrated surface, 2 ½” depth, G90 galvanized coating meeting ASTM A123, cut to 48” in length. Quantity of one-hundred thirty (130).

• 2 diamond wide plank grating, 4 ¾” width, 12 gauge ASTM A653 steel, serrated surface, 2 ½” depth, G90 galvanized coating meeting ASTM A123, cut to 48” in length. Quantity of twenty (20).

Payment for this line item will be one lump-sum payment when the materials have been delivered to the government and acceptance is completed.

6 Project Information

6.1 Basis for Award

The government shall award the contract to the offeror who provides the lowest priced technically acceptable offer.

The evaluated price shall include the base work plus all option(s). In order to be considered technically acceptable, the contractor shall:

• Have a minimum of (5) years’ experience on projects of a similar nature. The contractor shall supply the names, locations, and client contact information for two (2) projects of similar size and scope that have been accomplished within the previous five (5) years as part of the bid submittals.

6.2 Period of Performance

The project completion date is set at forty-five (45) days following the initial award of the contract. In the event the contractor is unable to meet the project completion date, requests for extensions must be made in writing. The request must explain, in detail, why the original project completion date will not be met. The request shall be sent to the DCO along with an informational copy to the Project Manager (PM). The request shall be made as soon as possible, but not later than ten (10) days prior to the original completion date. This request shall not negate penalties for liquidated damages unless an extension is granted by the DCO in writing.

6.2.1 Pre-Construction Submittals

All pre-construction submittals, as stated in Section 18.2 of this SOW, shall be provided to the government within fourteen (14) days following the award of the contract. The contractor shall allow up to twenty-one (21) days from time of receipt for government review of submittals. Work may not begin until government approval of all submittals required in Section 18.2 of this Statement of Work.

6.2.1.1 Project Timeline

As part of the pre-construction submittals, the contractor shall supply a timeline or schedule for accomplishing the work showing the following minimum milestones and completion dates: submittal completion date, start date, 100% completion date.

6.3 Pre-Construction Meeting

Following the award of the contract and review and acceptance of the contractor’s pre-construction submittals, the prime contractor must attend a mandatory pre-work conference. The meeting shall be scheduled by the government, and conducted on-site, at the US Army Corps of Engineers Buffalo District Reservation, at a time and date to be announced following the award of the contract.

6.4 Work Schedule

All scheduled work is to be performed Monday through Friday 0700-1930 hours, excluding federal holidays. If the contractor desires to work beyond the previously stated hours and days, written permission to do so shall be obtained from the government. Schedule changes shall be requested at minimum 24 hours in advance, unless there is an emergency situation.

6.5 Material/Equipment Information

Contractor shall provide all labor, tools, ladders, scaffolding, equipment, supplies and materials needed to complete the work described herein, unless otherwise noted herein that any of these items will be provided by the government.

6.6 Dimension/Quantity Verification

Contractor shall independently measure and verify all dimensions and quantities given herein prior to ordering materials and supplies for the project. This information shall be provided to the government QA person as part of the pre-work submittals.

6.7 Material Storage

If temporary storage of project material is requested, the contractor shall make a written request to the government’s QA person and receive written approval from the government. If material is found to be hazardous, flammable, combustible, etc., the contractor will be required to provide the appropriate hazardous material storage locker. Storage locations will be discussed at the pre-bid site visit and during the pre-con meeting. See Section 16 of this SOW for further information.

6.8 Site Cleanup

All excess, waste, and removed material related to this project shall become the contractor’s property and shall be promptly removed from the site and disposed of or reused/recycled in accordance with applicable local, state, and federal regulations. Documentation describing disposal of material shall be furnished to the government as part of the project closeout files. The contractor shall not dispose of any project generated waste in government receptacles or on government grounds.

7 Quality Assurance (QA)

7.1 Overview

7.1.1 Government Project Manager (PM)

The government has appointed a Project Manager (PM) for this project. The PM shall ensure all questions of a technical nature concerning the contractual work are answered.

7.1.2 Government Quality Assurance (QA)

The government will appoint a Quality Assurance (QA) person to ensure all work is accomplished in accordance with contractual documents. The QA person for this contract will be identified after the contract is awarded. The QA person serves as the liaison between the contractor, PM, and the DCO. The QA person does not have the authority to modify contractual agreements.

7.1.3 Government Inspections

Contractor shall allow inspection by the government PM, QA person, DCO personnel, and District Safety and Health personnel, at any time during the life cycle of the project. The contractor shall provide safe access for government personnel visiting the project.

7.1.4 Product Data Sheets

The contractor shall provide to the government product data sheets from the manufacturer for all materials used on this job, as part of the pre-construction submittals. All materials shall be delivered to the project site in new condition, in their original containers and wrapping material, with labels clearly showing all product information.

8 Communication

During the execution of the contract, the PM shall receive weekly status reports from the contractor on issues such as milestones met and/or missed, and issues standing in the way of project completion. The DCO shall be the communication hub for the government QA Person, PM, and the contractor regarding clarification of contractual issues. By adhering to the established lines of communication, it will reduce or avoid generation of duplicate requests for information, which may inadvertently result the government or the contractor to the acceptance of contractual changes without official approval by the DCO.

9 Repair/Restoration of Government Property Contractor, at no expense to the government, is required to protect all government facilities, grounds, equipment, sidewalks, and pavement during construction. All government structures, grounds, and equipment disturbed by contractor during the performance of work shall be returned to a pre-work condition prior to request of final payment.

Damages to government property that were caused by contractor and/or sub-contractor will be repaired at no expense to the government by the prime contractor.

10 Work Stoppage, Contract Cancellation Actions The Lock Master of Black Rock Lock, PM, or government QA person may issue temporary “Stop Work” notification if they find activities or job site conditions are in violation of Federal, Department of Defense, State or local health, safety and/or environmental standards, laws and regulations.