Value_Adjusted_Total_Evaluation_Price_-VATEP.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
MOARNG - Lease - 5 EA John Deere Excavators Federal contract opportunity
Solicitation number
W912NS-19-Q-2001
Issued by
Department of the Army Missouri Army National Guard

About this file

Value Adjusted Total Evaluation Price And Examples

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

TIMELINEOPTIONSDESCRIPTIONAPPROXIMATE DATEPRICE EVALUATION - DELIVERY TIMELINEEXAMPLE 1
FEB 2019Contract Award1 FEB 19
MAR 2019Month 1Early DeliveryPrior to 1 APR 1915% Discount Price Evaluation - Less than 59 Days After AwardVendorTotal QuotedDelivery TimelineDiscount EvaluatedEvaluated Total PriceTechnically Acceptable
APR 2019Month 2Month 1Early Delivery2 APR 19-1 MAY 1910% Discount Price Evaluation - 60 to 89 Days After AwardA$ 300,000.00150$ 300,000.00YES
MAY 2019Month 3Month 2Month 1Early Delivery2-31 MAY 195% Discount Price Evaluation - 90 to 119 Days After AwardB$ 320,000.001252%$ 313,600.00YES
JUN 2019Month 4Month 3Month 2Month 1Early Delivery1-30 JUN 192% Discount Price Evaluation - 120 to 149 Days After AwardC$ 340,000.001005%$ 323,000.00YES
JUL 2019Month 5Month 4Month 3Month 2Month 1No Later Than Delivery1-31 JUL 19No Price Evaluation - 150 Days to 180 Days After AwardD$ 360,000.007510%$ 324,000.00YES
AUG 2019Month 6Month 5Month 4Month 3Month 2Month 1Not Acceptable - Greater then 180 Days After Award - Approximately after 1 AUG 19E$ 370,000.005015%$ 314,500.00YES
SEP 2019Month 7Month 6Month 5Month 4Month 3Month 2F$ 275,000.0030N/ANot EvaluatedNO - not JD 230G/240G/250G
OCT 2019Month 8Month 7Month 6Month 5Month 4Month 3G$ 250,000.00190N/ANot EvaluatedNO - Does not meet minimum delivery timeline
NOV 2019Month 9Month 8Month 7Month 6Month 5Month 4
DEC 2019Month 10Month 9Month 8Month 7Month 6Month 5Early FY2020 Funds NeededIn this scenerio: Vendor B would win, and receive and award for $320K. Look how competive Vendor E is at $50k more
JAN 2020Month 11Month 10Month 9Month 8Month 7Month 6
FEB 2020Month 12Month 11Month 10Month 9Month 8Month 7Early Start OPTION 1
MAR 2020Month 13Month 12Month 11Month 10Month 9Month 8EXAMPLE 2
APR 2020Month 14Month 13Month 12Month 11Month 10Month 9
MAY 2020Month 15Month 14Month 13Month 12Month 11Month 10Late FY2020 Funds NeededVendorTotal QuotedDelivery TimelineDiscount EvaluatedEvaluated Total PriceTechnically Acceptable
JUN 2020Month 16Month 15Month 14Month 13Month 12Month 11A$ 190,000.00175$ 190,000.00YES
JUL 2020Month 17Month 16Month 15Month 14Month 13Month 12Late Start OPTION 2B$ 215,000.006510%$ 193,500.00YES
AUG 2020Month 18Month 17Month 16Month 15Month 14Month 13Early End ContractC$ 204,000.00955%$ 193,800.00YES
SEP 2020Month 18Month 17Month 16Month 15Month 14D$ 212,000.005010%$ 190,800.00YES
OCT 2020Month 18Month 17Month 16Month 15E$ 235,000.004515%$ 199,750.00YES
NOV 2020Month 18Month 17Month 16F$ 205,000.001005%$ 194,750.00YES
DEC 2020Month 18Month 17G$ 220,000.008010%$ 198,000.00YES
JAN 2021Month 18Late End Contract
In this scenerio: Vendor D would win, and receive and award for $212k