Statement of Work Summary

This is a Statement of Work (SOW) for a non-personal services contract to repaint the exterior of two buildings at the 1106th AVCRAD, California Army National Guard Base, located at 5168 E. Dakota Ave, Fresno, CA 93727. The contract number is W912LA26QA020, PN 26SUS001, with the project title TASMG-Paint AGSE & Sheet Metal Buildings, dated July 27, 2026.

The scope of work includes painting the complete exterior of the Aviation Ground Support Equipment (AGSE) building (approximately 4,234 sq. ft.) and the Sheet Metal building (approximately 13,942 sq. ft., including south structural support beams). The contractor is responsible for all materials, supplies, paint, equipment, tools, labor, personnel, transportation, supervision, and management necessary for preparation and repainting. All work must be completed within 90 calendar days of receiving a Notice to Proceed (NTP), and the contractor must provide a minimum one-year warranty for all workmanship and materials. Work hours are restricted to 0730 to 1600, Monday through Friday, excluding Federal holidays, and must be coordinated with the Government Representative at least five working days in advance. The contractor must comply with all federal, state, and local safety and health regulations and notify the Government POC and Safety Officer within one business day of any injuries or property damage.

Pre-construction deliverables include a Project Construction Schedule, Safety Plan, Quality Control Plan, and Schedule of Values. Within 10 days after NTP, the contractor must submit product data sheets and Safety Data Sheets (SDS) for all paints, primers, solvents, and sealants, along with physical paint samples (2'x2') applied on-site for color approval. The Government will conduct periodic inspections and a 100% pre-final and final inspection, with any discrepancies requiring correction within 10 days. Final payment and retainage release require submission of a contractor's letter of warranty, waste disposal manifests, electronic before-and-after photos, and a contractor release of claims. The Government will provide access to water and electricity; the contractor is responsible for all hoses, cords, and secured storage for materials.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

REPAINT EXTERIOR OF AGSE & SHEET METAL

BUILDING

July 27, 2026

1106TH AVCRAD

5168 East Dakota Ave, Fresno, CA 93727

CALIFORNIA ARMY NATIONAL GUARD

W912LA26QA020, PN 26SUS001

TASMG-Paint AGSE & Sheet Metal Buildings

Attachment 1 - SOW

TECHNICAL PROVISIONS

TABLE OF CONTENTS:

1. DESCRIPTION OF SERVICES………………………………………..….3

2. SITUS OF WORK………………………………………………………..…3

3. PROJECT SPECIFIC REQUIREMENTS………………………………..3

4. GENERAL REQUIREMENTS…………………………………………….3

5. SUBMITTALS………………………………………………………………4

6. CLOSEOUT DOCUMENTATION………………………………………..5

W912LA26QA020, PN 26SUS001

TASMG-Paint AGSE & Sheet Metal Buildings

1. DESCRIPTION OF SERVICES

1.1 Objectives: The purpose of this project is to “Repaint Exterior of AGSE and Sheet

Metal Buildings.”

1.2 Scope: This is a non-personal services contract. This Statement of Work (SOW) describes contractor requirements for the project. The contractor is responsible for work required to complete all items listed in this SOW, including but not limited to all necessary labor, furnishing and installation of materials, tools, equipment, planning, scheduling, and coordination. The contractor shall comply with all current federal, state, and local regulations. The contractor shall provide the Government a complete and usable product at the completion of the project.

2. SITUS OF WORK

2.1 All work will occur at the 1106th AVCRAD, California Army National Guard Base, 5168 E. Dakota Ave, Fresno, CA 93727.

3. PROJECT SPECIFIC REQUIREMENTS

3.1 The work includes painting the complete exterior of the Aviation Ground Support Equipment (AGSE) building and the Sheet Metal building.

AGSE Building: Approx. 4,234 sq. ft.

Sheet Metal Building: Approx. 13,942 sq. ft., including the south structural support beams.

Note: All dimensions are estimates. The contractor is responsible for verifying all dimensions and quantities in the field.

3.2. The Contractor Shall:

3.2.1. Provide all materials, supplies, paint, equipment, tools, labor, personnel, transportation, supervision, and management necessary for the preparation and repainting of the exteriors of the two specified buildings.

3.2.2. Complete all work within 90 calendar days of the contract being issued a Notice to Proceed (NTP).

3.2.3. Provide a warranty for all workmanship and materials for a minimum of one (1) year.

3.2.4. See Appendix B for full spectrum of technical Specification for this project.

4.0 GENERAL REQUIREMENTS

4.1. Contractor Submittals at Pre-Construction Conference: The contractor shall provide the following documents at the Pre-Construction Conference:

Project Construction Schedule Safety Plan Quality Control Plan Schedule of Values

4.2. Debris and Waste: Any waste or excess material resulting from the contract shall be removed and disposed of by the contractor at a proper disposal site off Government property.

Disposal must be coordinated with the installation Environmental Officer.

4.3. The Government will provide access to water and electricity. The contractor is responsible for all hoses and cords. Secured storage for contractor materials is the responsibility of the contractor.

4.4. Quality Control: The contractor shall develop and maintain a quality program to ensure work is performed as described in this SOW.

4.4.1. A combined Quality Control Manager/Superintendent is authorized.

4.5. Quality Assurance: The Government will maintain a Quality Assurance program.

4.5.1. Periodic inspections will be accomplished by the Government Representative.

4.5.2. A 100% pre-final and final inspection of the finished product will be accomplished.

All discrepancies noted in the pre-final inspection must be corrected by the contractor within 10 days of receipt of the report.

4.6. Hours of Operation: Work hours are 0730 to 1600, Monday through Friday, excluding Federal holidays. All work must be coordinated with the Government Representative at least five (5) working days in advance.

4.7. Safety: The contractor shall comply with all federal, state, and local safety and health regulations. The contractor shall notify the Government POC and Safety Officer within one

(1) business day of any injuries or damage to Government property.

4.8. Warranty: The contractor shall guarantee all workmanship and materials for a period of no less than one (1) year from the date of project acceptance.

5.0 SUBMITTALS

5.1. The contractor shall submit the following material approval submittals to the COR via email no later than 10 days after NTP and prior to ordering materials:

5.1.1. Product data sheets and Safety Data Sheets (SDS) for all paints, primers, solvents, and sealants.

5.1.2. Physical paint samples (2’x2’) applied on-site for color approval.

6.0 CLOSEOUT DOCUMENTATION

6.1. Final payment and/or retainage will be released upon receipt of the following items:

Contractor’s letter of warranty (1-year minimum).

Waste disposal manifests.

Electronic "before and after" photos of the project sites.

Contractor release of claims

APPENDIX A

The picture above shows the locations of the 2 buildings that will get painted. The RED box shows the AGSE BUILDING. The BLUE box shows the SHEET METAL BUILDING.

The picture above shows the exterior of the SHEET METAL BUILDING. This is the North and East side of this building. The 3 exhaust vents on top of the roof are considered the EXTERIOR of this building and will get painted to match the bottom tan color. The cinder block walls and red roof covering air compressor behind cinder block wall, will get painted. The overhang low roofline covering the metal stack racks will get painted.

The picture above shows the exterior of the SHEET METAL BUILDING. The East cinder block wall and the South metal support structure are shown in this photo.

The above picture shows the exterior of the SHEET METAL BUILDING. This is the West side of this building. The hangar doors slide open and there is a hangar bay on the SW corner of this building. The connex shipping containers in the center of this picture will get moved by the 1106th AVCRAD prior to NTP start date, to allow painter to access building.

The picture above shows the exterior of the SHEET METAL BUILDING. This shows the West and South sides of this building. The SW corner of the building is the hangar open air bay. The metal columns and support structures will get painted tan to match the cinder block walls and hangar door.

The above picture shows the SW corner open air bay on the SHEET METAL BUILDING. There is bird netting on the entire ceiling area by the ceiling rafters. Everything in the hangar bay will get moved away from the walls so that the painter can paint. Painters will cover equipment to ensure

W912LA26QA020, PN 26SUS001

TASMG-Paint AGSE & Sheet Metal Buildings no overspray gets on aviation maintenance equipment. The rafters ABOVE the bird netting will not get painted.

The picture above shows the exterior of the AGSE BUILDING. There are several roll up doors that will get painted to match the tan cinder block color. The red roof line trim will also match the other red areas in between each roll up door. This picture shows the East side wall and the South side roll up doors.

The picture above shows the exterior of the AGSE BUILDING. This is the North side of the AGSE building.

The picture above shows the exterior of the AGSE BUILDING. This shows the West side and the South side. All the roll up doors will get painted the tan color to match the cinder block walls. The fabric material red shade cover will not get painted. The red columns in between each roll up door will get painted to match the roof line.

END OF APPENDIX A