Addendum 1.pdf
PDF 2 MB Posted
- Attached to
- FUEL SYSTEM/CORROSION CONTROL HANGAR AND SHOPS Federal contract opportunity
- Solicitation number
- W912L809R0004
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Addendum 3.pdf | ||
| Foundation Investigation.pdf | ||
| GeoTech Report.pdf | ||
| 600205C-100-C-100.PDF | ||
| Addendum2forFBO.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fuel Systems/Corrosion Control Hangar & Shops
130th Airlift Wing Charleston WV Project # LYBH009134
RFP # W912L8-09-R-0004
Addendum 1 July 29, 2009
130th Airlift Wing SUMMARY OF CHANGES TO SPECIFICATIONS West Virginia Air National Guard Fuel System/Corrosion Control Hangar and Shops Yeager Airport, Charleston, West Virginia LYBH009134
The Benham Companies, LLC 1 of 1 July 27, 2009
Specification Section Change
1. 01330 GENERAL
REQUIREMENTS
Paragraph 1.1 SCOPE, Item B, changed to read:
Each Bid Option shall be identified on the construction plans and shall also be fully described here.
2. 14240 LIMITED USE/LIMITED
APPLICATION ELEVATORS
Changed Paragraph 2.1 LIMITED USE/LIMITED APPLICATION ELEVATOR, subparagraph 2.1.1 Manufacturer, first sentence to read:
Provide the "Evolution LU/LA" elevator manufacturer by the national Wheel-O-Vator division of Thyssen Krupp Elevator company or approved equal.
END OF CHANGES
Fuel System/Corrosion Control Hangar & Shops LYBH009134 WV National Guard, 130th Airlift Wing, Charleston, WV
SECTION 01330
GENERAL REQUIREMENTS
01/06
PART 1 GENERAL
1.1 SCOPE
A. Project provides for furnishing all plant, labor, material, equipment and appliances to complete work as Project LYBH009134, Fuel System/Corrosion Control Hangar and Shops at the 130th Airlift Wing, Air National Guard Base, Charleston, West Virginia, as described herein and shown in these construction documents.
Provide the 130th Airlift Wing with a 71,000 SF (21,641 SM) Fuel System/Corrosion Control Hangar supporting specialized maintenance activities such as machine shops, administration and classrooms, security supplies and workable parts.
Construct a durable, maintainable, facility that will have a 30-year life span and reflect existing base architectural standards and colors. The design should reflect efficient and creative space use as well as an efficient environmental control system. The design shall reflect efficient and creative space use as well as an efficient environmental control system. Exterior aesthetics shall reflect a proposed consistency (future buildings) of design having a sloped roof, elements of beige or tan CMU, white door and window frames.
Site development shall provide for a location as indicated and shall meet all the requirements established in the Anti-Terrorism Force Protection guidelines and regulations as appropriate. Site plans shall be consistent with BCE recommendations. A Pad for mounting a Backup Emergency Power Generator shall be sited and connections for the backup generator provided in the facility design. Internal wiring shall ensure that the base emergency security system components are included in facility backup power systems so that all emergency security systems are operational during power outage conditions.
B. Each Bid Option shall be identified on the construction plans and shall also be fully described here.
1. Antenna Structure (All Cable and Antenna's are GF/GI) Includes Foundation $__________
2. Pavement Between Concrete Taxiways $__________
C. The Contractor will be held responsible for all requirements described in the contract documents and all work including that of his Subcontractor, if any, shall be done in accordance with the contract documents. Failure to familiarize himself with their requirements will not relieve the Contractor of his responsibility to comply.
SECTION 01330 Page 1
D. The organization of the specifications into divisions, sections, and articles, and the arrangement of the drawings shall not control the Contractor in dividing the work among Subcontractor or in establishing the extent of the work to be performed by any trade.
1.2 WORK SCHEDULING
A. Normal base work hours for the Contractor will be between the hours of 7:00 AM thru 4:30 PM, excluding Saturdays, Sundays, and Federal Holidays. If the Contractor desires to work during periods other than above, he must notify the Contracting Officer three (3) working days in advance of his intention to work during other periods to allow assignment of additional inspection forces and for notification of fire, security and safety. When the Contracting Officer determines that they are reasonably available, he may authorize the Contractor to perform work during periods other than normal duty hours/days.
However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of the inspection, at overtime rates, will be charged to the Contractor and will be deducted from the final payment of the Contract amount. (Note: If applicable, at time of award this paragraph will be modified to the negotiated schedule for this project).
B. The following Federal legal Holidays are observed by this Base:
Observed Federal Legal Holidays
New Year's Day 1st January
Martin Luther King's Birthday Third Monday of January
President's Day Third Monday of February
Memorial Day Last Monday of May
Independence Day 4th July
Labor Day First Monday in September
Columbus Day Second Monday in October
Veteran's Day 11th November
Thanksgiving Day Fourth Thursday in November
Christmas Day 25th December
C. NOTE: Any of the above holidays falling on a Saturday will be observed the preceding Friday, holidays falling on a Sunday will be observed on the following Monday.
D. Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more) commencement of any warranty work, and upon completion of warranty work, the Contractor must notify the Contracting Officer (or his/her Contracting Officer Representative). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the Contracting
SECTION 01330 Page 2
Officer's Representative is sufficient. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The above precautions are to ensure construction inspection and recording of work proceedings.
E. The organization of the specifications into divisions, sections, and articles, and the arrangement of the drawings shall not control the Contractor in dividing the work among Subcontractor or in establishing the extent of the work to be performed by any trade.
1.3 ENTRY TO BASE/ACCESS TO SITE
A. 130th Airlift Wing Air National Guard is a closed Base, pursuant to Sec 21, Internal Security Act of 1950, 50 U.S.C. 797 and, as such, only those persons granted permission may enter. It is, therefore, required that control be exercised over Contractor personnel while working on the Base. To maintain this control, a listing of all Contractor personnel who will be working under the contract, must be submitted to the Contracting Officer five working days prior to the start of work under the contract. The preferred method of providing this list is via email, to the contract administrator. The listing shall include, but not limited to: contract number, project number, employee name, and the estimated starting and ending date of each employee. Subsequent listings of all additions or deletions will be submitted as employees are hired or released.
B. During construction, the Contractor shall permit base personnel access to the facilities within the work area. The Contractor shall provide protection to persons and property throughout the progress of the work.
C. In the event of a declared National Emergency the Contracting Officer may be required to stop work on this contract for security reasons.
Contractor shall ensure the Contracting Officer has a current "Off Duty" contact name and telephone number at all times to facilitate notification.
1.4 UNAUTHORIZED PERSONNEL
The Contractor shall inform all personnel working under his jurisdiction (including sub-contractor and visiting supplier personnel) that access to areas outside of the immediate work area excluding, direct haul and access routes, contracting and Civil Engineering offices and point of supply and storage is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.
1.5 INSPECTION OF SITE
A. The Contractor shall be responsible for the complete coordination and proper relation of the work of all trades. Reference Contract Clauses FAR 52.236-3, "Site Investigation and Conditions Affecting the Work" and FAR 52.236-8, "Other Contracts".
B. It is recommended that prospective bidders visit the premises and thoroughly familiarize themselves with the details of the work and working conditions. It is the responsibility of all bidders to have compared the premises and the site with the Specifications and Drawings, and to have satisfied themselves as to all conditions of the
SECTION 01330 Page 3 premises, the existing obstructions, the actual elevations, and any other conditions affecting the execution and completion of the work prior to submission of his proposal. Reference Contract Clause FAR 52.236-3, "Site Investigation and Conditions Affecting the Work".
C. No allowances or extra construction on behalf of any Contractor will be permitted subsequently by reason of error or oversight on the part of the sub-contractor, or on account of interferences by the activities of the owner or others. Reference Contract Clause FAR 52.236-3, "Site Investigation and Conditions Affecting the Work".
D. All dimensions shown on the drawings are based on "as-built" record drawings and, to the extent possible, accurately represent existing conditions; however, there may be some variance between existing conditions and contract drawings. The Contractor is responsible for verifying all dimensions and for reporting to the Contracting Officer any discrepancies that may affect performance of the work represented by contract drawings and specifications. Reference Contract Clause DFARS 252.236-7001 "Contract Drawings, Maps, and Specifications".
1.6 CORRELATION OF DRAWINGS, SPECIFICATIONS AND CONTRACTS
The specifications, Contract and the accompanying Drawings are intended to describe and provide for a complete, new and usable facility.
They are intended to be cooperative and what is called for by one shall be as binding as if called for by all. The Contractor will understand that the work herein described shall be complete in every detail, not withstanding every item necessarily involved is not particularly mentioned, and the Contractor shall be held to provide all labor and material for the entire completion of the work intended to be described and shall not avail himself of any manifestly unintentional error or omission, should any exist. Should any error or inconsistency appear in the Drawings or Specifications, the Contractor, before proceeding with the work, shall make mention of same to the Contracting Officer for proper adjustment, and in no case shall he proceed with the work in uncertainty. Reference Contract Clause DFARS 252.236-7001, "Contract Drawings, Maps and Specifications".
1.7 REPORT OF ERROR AND DISCREPANCIES
A. The Contractor shall be responsible for any and all discrepancies in work due to failure to obtain dimensions and investigate conditions at the building before fabrication and installation.
B. The Contractor shall bear all costs in replacing all materials and labor due to not observing the above paragraph and such replaced materials shall meet the approval of the Contracting Officer.
C. The Contractor shall promptly notify the Contracting Officer in writing of any discrepancies.
D. Reference Contract Clauses FAR 52.236-21, "Specifications and Drawings for Construction". FAR 52.246-12 "Inspection of Construction", and DFARS 252.236-7001, "Contract Drawings, Maps and Specifications".
E. Any proposed changes to the specifications by the Contractor must be submitted in writing to the Contracting Officer for approval prior to implementation.
SECTION 01330 Page 4
1.8 DIVISION OF WORK
A. The various divisions of the Specifications shall not be considered as negotiations of the material and labor involved. The arrangement and order of these divisions have been made for convenience only, and it is not the intent, nor shall it be so construed, a particular trade or subcontractor must perform that work included in any one division.
B. Any item mentioned under any division heading must be supplied even though it is not specified under the heading for the respective work, but is shown on the Drawings. No claims for extras arising out of real or alleged error in such arrangement or order of the various divisions will be given consideration
C. The organization of the specifications into divisions, sections, and articles, and the arrangement of the drawings shall not control the Contractor in dividing the work among Subcontractor or in establishing the extent of the work to be performed by any trade.
D. Reference Contract Clause FAR 52.236-21, "Specifications and Drawings for Construction".
1.9 METHOD OF CARRYING ON THE WORK
A. All work under the Contract shall be arranged and carried on in such a manner as to complete work in the least possible time. The Contractor shall consult with the Contracting Officer as to methods or sequence of carrying on the work. A definite program of work shall be arranged before starting. Reference Contract Clause FAR 52.236-15, "Schedules for Construction Contracts".
B Activities in the vicinity of this project may be kept in full or partial operation during construction. The Contractor shall coordinate with the Contracting Officer and schedule construction activities.
Reference Contract Clause FAR 52.236-8, "Other Contracts".
1.10 STANDARDS OF MANUFACTURE
A. All recognized regulatory/code standards shall be the latest published edition prior to the date of release for bid/proposal of the contract documents.
B. For purpose of establishing the standard of construction and the requirements to be met in the work of all divisions, the drawings and these specifications are based on the use of products hereinafter specified, adapted to the installation as required to meet the condition.
C. Where brand names are shown, these names are intended to describe a quality of product, and in no way are intended to limit products of equal quality. Therefore, products of other manufacturers may be employed for this work provided they are equivalent materials and construction and equally adaptable to the conditions as approved by the Contracting Officer. Reference Contract Clause FAR 52.236-5, "Materials and Workmanship".
1.11 MEANING OF APPROVED, DIRECTED, ETC.
"Approved", "Directed", "Required", "Applicable", or words of like or
SECTION 01330 Page 5 similar effect, when used in the specifications shall be interpreted to mean "Approved By", "Directed By", etc., the Contracting Officer unless otherwise specifically stipulated.
1.12 MISPLACED MATERIALS
Any material that is deposited elsewhere than areas designated as approved by the Contracting Officer shall be rehandled and deposited where directed. No payment will be made for rehandling such material. The Contracting Officer will notify Contractor of any noncompliance with the foregoing provisions.
1.13 COMPLIANCE WITH CODES AND REGULATIONS
A. All work shall be done in accordance with the applicable codes and/or ordinances in force at the time of construction. It is the Contractor's responsibility to insure that where EPA, DEQ or other such regulations control the removal, handling, installation or disposal of materials, they shall be strictly adhered to whether or not specifically referenced in the construction documents.
B. Contractor shall have data sheets available at the site on any materials used to comply with West Virginia OSHA and EPA. Reference Contract Clause FAR 52.223-3, "Hazardous Material Identification and Material Safety Data".
C. Contractor shall implement a storm water pollution prevention plan and groundwater protection plan in accordance with environmental protection requirements and the National Pollution Discharge Elimination System (NPDES). Refer to project Stormwater Pollution Prevention Plan (SPPP) and Groundwater Protection Plan (GPP) attachments included in Appendix B.
1.14 MATERIAL TESTING BY NATIONAL LABORATORIES
A. Electrical materials and equipment shall be new and bear the UL label or be listed in UL Electrical Construction Materials Directory or Electrical Appliance and Utilization Equipment Directory, wherever standards have been established by the agency.
B. The Contractor shall submit proof that the material or equipment, which he proposes to furnish under this specification, conforms to the standards of Underwriters' Laboratories. The label of Underwriters Laboratories (UL) shall be accepted as conforming to this requirement.
C. In lieu of the label, the Contractor may submit a written certification from any recognized testing agency, adequately equipped and competent to perform such services, that the material or equipment has been tested and conforms to the standards, including the methods of testing used.
1.15 SUBMITTALS
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in
SECTION 01330 Page 6 producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to
SECTION 01330 Page 7 the equipment operating and maintenance personnel. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This Data is intended to be incorporated in an operations and maintenance manual or control system.
A. Shop Drawings and Product Data: The Contractor shall furnish submittals in the form of manufacturer's brochures, pamphlets, or written specifications on all items to be installed unless specifically directed otherwise by these specifications or by the Contracting Officer. Reference Contract Clause FAR 52.236-5, "Material and Workmanship", FAR 52.225-5, "Buy American Act-Construction Materials", FAR 52.223-3, "Hazardous Material Identification and Material Safety Data", and DFAR 252.227-7033, "Rights in Shop Drawings".
B. Approval of Materials: Prior to the purchase of material, the Contractor shall submit to the Contracting Officer, for material approval/disapproval, brochures and technical literature covering, in detail, the materials he proposes to supply. This shall include the specific catalog and model specification number designations.
Submittals shall demonstrate that the item conforms to all of the requirements. No unapproved or disapproved materials shall be used.
Submittals shall be made for the items listed on AF Form 66, Schedule of Material Submittals, or equivalent. Reference Contract Clause FAR 52.236-5, "Material and Workmanship". The AF Form 66 may not be all inclusive and additional submittals may be required. The Contractor shall maintain the AF Form 66. The Government will provide the Form in electronic format. Thereafter the Contractor shall maintain the complete register of all submittals, including completion of all data columns. Contractor shall not be relieved of responsibility for deviations from requirements of Contract Documents by Contracting Officer's review of Shop Drawings, Product Data, Samples, or similar submittals unless Contractor has specifically informed the Contracting Officer in writing of such deviation at time of submittal and Contracting Officer has given written acceptance to specific deviation.
Contractor shall not be relieved of responsibility for errors or omissions in Shop Drawings, Product Data, Samples, or similar submittals by Contracting Officer's review thereof. Direct specific attention, in writing or on resubmitted Shop Drawings, Product Data, Samples, or similar submittals, to revisions other than those requested by Contracting Officer on previous submittals.
C. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Include list of submittals and time requirements for scheduled performance of related submittal activities within the Contractor's Progress Schedule as defined in Paragraph 1.16 Progress Schedule.
SECTION 01330 Page 8
3. Coordinate transmittal of different types of submittals for related elements of the work so processing will not be delayed by the need to review submittals concurrently for coordination.
(a) The CONTRACTING OFFICER reserves the right to withhold action on a submittal requiring coordination with other submittals until all related submittals are received.
4. Processing: To avoid the need to delay installation as a result of the time required to process submittals, allow sufficient time for submittal review, including time for resubmittals.
(a) Allow three (3) weeks for initial review. Time for review shall commence on Architect's receipt of submittal. Allow additional time if the CONTRACTING OFFICER must delay processing to permit coordination with subsequent submittals.
(b) If an intermediate submittal is necessary, process the same as the initial submittal.
(c) Allow three (3) weeks for reprocessing each submittal.
Time for reprocessing shall commence on Architect's receipt of submittal.
(d) No extension of Contract Time will be authorized because of failure to transmit submittals to the CONTRACTING OFFICER sufficiently in advance of the work to permit processing.
5. Incomplete Submittal Submissions:
(a) CONTRACTING OFFICER will return the entire submittal for CONTRACTOR's revision/correction and resubmission without review.
Only complete submittal packages shall be submitted for each specification section.
(b) Submittals which do not clearly bear CONTRACTOR's specific written indication of CONTRACTOR review and approval of submittal or which are transmitted with an unsigned or uncertified submission form or as may otherwise be required will be returned to CONTRACTOR without review.
(c) Submittal packages may be resubmitted only once. After one resubmittal, a fee of $500 shall be charged to the CONTRACTOR for each resubmittal. Resubmit submittals until they are stamped with action by Contracting Officer allowing work to proceed.
D. Submittal Review and Stamp: CONTRACTOR shall review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Place a permanent label or title block on each submittal for identification. Indicate the name of the entity that prepared each submittal on the label or title block.
1. Provide a space approximately 4 by 5 inches (100 by 125 mm) on the label or beside the title block on Shop Drawings to record the CONTRACTOR's review and approval markings and the action taken.
2. Include the following information on the label for processing and recording action taken.
SECTION 01330 Page 9
(a) Project name.
(b) Date.
(c) Name and address of the CONTRACTING OFFICER.
(d) Name and address of the CONTRACTOR.
(e) Name and address of the subcontractor.
(f) Name and address of the supplier.
(g) Name of the manufacturer.
(h) Number and title of appropriate Specification Section.
(i) Drawing number and detail references, as appropriate.
(j) Name of Reviewer
(k) Date of Contractor's approval
(l) Statement that submittal has been reviewed, checked and approved for compliance with the Contract Documents.
3. Contracting Officer's Review:
(a) General:
(1) Contracting Officer will not review submittals that do not bear Contractor's approval stamp and will return them without action.
(2) Purpose of submittal is to demonstrate for those portions of Work for which submittals are required, manner in which Contractor proposes to conform to information given and design concept expressed on Contract Documents.
(3) Review is not conducted for purpose of determining accuracy and completeness of other details such as dimensions and quantities, or for substantiating instructions for installation or performance of equipment or systems, all of which remain responsibility of the Contractor.
(4) Compliance with specified characteristics is Contractor's responsibility and not considered part of Contracting Officer's review and indication of action taken.
(5) Acceptance of submittals with deviations shall not relieve Contractor from responsibility for additional costs of changes required to accommodate such deviations. Deviations included in submittals without prior acceptance are exempt from review of submittals whether noted or not on returned copy.
(6) Review of separate item shall not indicate acceptance of assembly of which item is part.
(7) Make only those revisions required or accepted by
SECTION 01330 Page 10
Contracting Officer.
(8) Notations by Contracting Officer which increase Contract Cost or Contract Time shall be brought to Contracting Officer's attention, in writing, before proceeding with Work.
(9) When professional certification of performance criteria of materials, systems, or equipment is required by Contract Documents, Contracting Officer shall be entitled to rely upon accuracy and completeness of such calculations and certifications.
(b) Required Submittals: Contracting Officer will review each submittal, make marks to indicate corrections or modifications required and will complete AF Form 3000 to indicate action recommended, then forward.
(c) Informational Submittals: Contracting Officer will review each submittal and will not return it, or will return it if it does not comply with requirements.
(d) Partial submittals are not acceptable, will be considered nonresponsive, and will be returned without review.
(e) Submittals not required by the Contract Documents may not be reviewed and may be discarded.
E. Submittal Transmittal: Package each submittal appropriately for transmittal and handling. Transmit each submittal from the CONTRACTOR to the ARCHITECT and ENGINEER using a transmittal form. The ARCHITECT and ENGINEER will not accept submittals received from sources other than the CONTRACTOR.
1. On the transmittal, record relevant information and requests for data. On the form, or separate sheet, record deviations from the Contract Document requirements, including variations and limitations. Include CONTRACTOR's certification that information complies with Contract Document requirements.
2. Accompany each submittal with an AF Form 3000. Distribution:
Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
F. Use for Construction: Use only final submittals with AF Form 3000 indicating approval from Base Civil Engineer and Contracting Officer.
G. Submittal Preparation: Prepare and submit Submittals required by individual Specification Sections. Submit Product Data, Shop Drawings and Samples concurrently. Submit three (3) copies of each submittal, unless copies are required for operation and maintenance manuals.
Follow submittal procedures outlined in paragraph 1.50. Contracting Officer will return one copy. Mark up and retain one returned copy as a Project Record Document and distribute as defined above.
1. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment. If information must be specially prepared for submittal because
SECTION 01330 Page 11 standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data. Mark each copy of each submittal to show which products and options are applicable. Include the following information, as applicable:
(a) Manufacturer's written recommendations.
(b) Manufacturer's product specifications.
(c) Manufacturer's installation instructions.
(d) Standard color charts.
(e) Manufacturer's catalog cuts.
(f) Wiring diagrams showing factory-installed wiring.
(g) Printed performance curves.
(h) Operational range diagrams.
(i) Mill reports.
(j) Standard product operation and maintenance manuals.
(k) Compliance with specified referenced standards.
(l) Testing by recognized testing agency.
(m) Application of testing agency labels and seals.
(n) Approval numbers of organizations or agencies as required by agencies having jurisdiction.
(o) Notation of dimensions verified by field measurement.
(p) Notation of coordination requirements.
2. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data. Fully illustrate requirements in the Contract Documents. Sheet Size:
Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 40 inches. Include the following information, as applicable:
(a) Dimensions.
(b) Identification of products.
(c) Fabrication and installation drawings.
(d) Roughing-in and setting diagrams.
(e) Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
(f) Shopwork manufacturing instructions.
SECTION 01330 Page 12
(g) Templates and patterns.
(h) Schedules.
(i) Design calculations.
(j) Compliance with specified standards.
(k) Notation of coordination requirements.
(l) Notation of dimensions established by field measurement.
(m) Relationship to adjoining construction clearly indicated.
(n) Seal and signature of professional engineer if specified.
(o) Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
3. Samples:
(a) General: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
Transmit Samples that contain multiple, related components such as accessories together in one submittal package. Identification:
Attach label on unexposed side of Samples that includes the following:
(1) Generic description of Sample.
(2) Product name and name of manufacturer.
(3) Sample source.
(4) Number and title of appropriate Specification Section.
(b) Disposition: Maintain sets of approved Samples at Project site, available for quality control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
(1) Samples not incorporated into the Work, or otherwise designated as Government's property, are the property of Contractor.
(c) Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
(d) Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected.
Samples include, but are not limited to, the following: partial
SECTION 01330 Page 13 sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
4. Informational Submittals:
(a) General: Prepare and submit Informational Submittals required by other Specification Sections.
(1) Contracting Officer will not return copies.
(2) Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
(3) Test and Inspection Reports: Comply with requirements specified in Paragraph 1.18 Inspection and Tests.
(b) Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities. At a minimum, provide coordination drawings for all utilities, fixtures, architectural elements, and structural components located in the maintenance mall corridors.
(1) Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data.
(2) Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
(3) Indicate required installation sequences. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer for resolution of such conflicts.
Minor dimension changes and difficult installations will not be considered changes to the Contract.
(4) Sheet Size: At least 11 X 17 inches but no larger than 30 by 40 inches.
(5) Coordination Drawings are submitted for information only. They will not be reviewed and they will not be returned.
(6) Refer to individual Sections for Coordination Drawing requirements for Work in those Sections.
(c) Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person.
Include lists of completed projects with project names and
SECTION 01330 Page 14 addresses, names and addresses of architects and owners, and other information specified.
(d) Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified.
(e) Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
(f) Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.
(g) Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
(h) Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
(i) Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
(j) Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
(k) Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:
(1) Name of evaluation organization.
(2) Date of evaluation.
(3) Time period when report is in effect.
(4) Product and manufacturers' names.
(5) Description of product.
(6) Test procedures and results.
(7) Limitations of use.
(l) Schedule of Tests and Inspections: Prepare in tabular form
SECTION 01330 Page 15 and include the following:
(1) Specification Section number and title.
(2) Description of test and inspection.
(3) Identification of applicable standards.
(4) Identification of test and inspection methods.
(5) Number of tests and inspections required.
(6) Time schedule or time span for tests and inspections.
(7) Entity responsible for performing tests and inspections.
(8) Requirements for obtaining samples.
(9) Unique characteristics of each quality-control service.
(m) Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
(n) Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
(o) Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
(p) Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements specified in paragraph
1.50 Operation and Maintenance Data.
(q) Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations.
Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.
5. Delegated Design
(a) Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, SECTION 01330 Page 16 provide products and systems complying with specific performance and design criteria indicated.
(1) If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Contracting Officer.
(b) Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit three copies of a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.
(c) Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.
1.16 PROGRESS SCHEDULE
The Contractor shall prepare a work progress schedule using AF 3064, required for completion of each of the various divisions of work. The AF 3064 Contract Progress Schedule is established to validate percentages of completion for verifying payment vouchers. The schedule shall be submitted to the Contracting Officer, in the number of copies as directed prior to start of construction. Reference Contract Clause FAR 52.236-15, "Schedules for Construction Contracts". No progress payments shall be made to the contractor unless a Schedule of Amounts for Contract Payments, (the format for which shall be furnished by the Contracting Officer), in accordance with Contract Clause FAR 52.232-5, "Payments Under Fixed-Price Construction Contracts" is received and approved by the Contracting Officer.
Construction Contracts in excess of $1 million will also be submitted on Microsoft Project (latest version) showing the critical path method (CPM) using the arrow diagramming method. Contractor shall also prepare and update on a monthly basis, a critical path method (CPM) construction schedule using the arrow diagramming method. This schedule shall include a line item for rough inspections by government personnel as outlined in the various sections of the specifications or on the plans. A rough inspection is required on all installed systems prior to sealing off or closing in a wall, pipe chase, suspended ceiling system etc. These system include but not limited to: domestic and heating water lines, communication and electric runs, all insulation material to be covered by other material (GWB, wood panel etc), duct runs, ceiling suspension systems, raised flooring, fire detection/protection /suppression systems etc. A second or finish inspection will be conducted after these systems are "hidden" to insure the quality of the finished product. The finish inspection does not constitute the final project inspection accomplished at project completion.
The Contractor shall request these inspections, through the Contracting Officer at least 5 workdays prior to the desired inspection date.
1.17 SAFETY ASSURANCE
A. Compliance with Regulations. All work including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926. Work involving the disturbance or dismantling of asbestos or asbestos-containing materials; the demolition of structures containing asbestos; and/or disposal and removal of asbestos, shall also comply with the requirement of 40 CFR, Part 61, Subparts A and B. ETL 1110-1-118 and DA Circular 40-83-4. All
SECTION 01330 Page 17 work shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply.
B. Contractor Responsibility. The Contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work. The Government shall not be held liable for any action on the part of the Contractor, his employees or Subcontractor, which result in illness, injury or death.
C. Crawl spaces and attics are to be treated as confined space entry.
Contractor must follow 29CFR 1910.146 and use Air Force Form 1024 when making an entry. NOTE: A confined space does not include areas above suspended acoustical tile ceiling.
D. Where an employee can fall more than 6 feet, a fall protection system must be used; 29 CFR 1926.500 stipulates where this occurs and the different types of fall arrest systems.
E. When the Contractor is working in buildings that are occupied by Government personnel, the Contractor must provide Material Safety Data Sheets (MSDS) to the Contracting Officer before they begin the work.
F. All references to protection of the site and adjacent buildings when trenching, shall include protection of all employees also.
G. Inspections, Tests and Reports. The required inspections, tests and reports made by the Contractor, Subcontractor, specially trained technicians, equipment manufacturers and other as required, shall be at the Contractor's expense.
H. Materials and Equipment. Special facilities, devices, equipment, clothing and similar items used by the Contractor in the execution of work shall comply with applicable regulations.
I. Traffic Control Devices. The Contractor shall comply with the recommendations contained in Part 6 of the U. S. Department of Transportation, Federal Highway Administrations "Manual on Uniform Traffic Control Devices (D6. -1978) to ensure proper warnings to motorists and adequate traffic control. The Contractor shall provide all warning lights, barricades and other traffic control devices and signs.
1.18 INSPECTIONS AND TESTS
Inspections and tests are for the sole benefit of the Government and shall not relieve the Contractor of the responsibility of providing quality control measures to ensure that the work strictly complies with the contract requirements. No inspection or test by the Government shall be construed as constituting or implying acceptance. Reference Contract Clause FAR 52.246-12, "Inspection of Construction".
1.19 QUALITY CONTROL/TESTS
A. Where work is specified to be in conformity with Standard Specifications of the American Society for Testing Materials (ATSM), or with Federal specifications or with specifications of well known recognized technical and trade organizations, but no tests are
SECTION 01330 Page 18 specifically stipulated in connection herewith, the Contractor shall furnish and pay for any tests or certifications required by the Contracting Officer to show that the proposed materials meet with the applicable requirements.
B. The Contractor shall submit written certification for use of Certified Independent Testing Laboratory, adequately equipped and competent to perform such services, that material or equipment has been tested and conforms to the standards, including the methods of testing used.
Contractor's testing agency must receive approval by Contracting Officer.
C. Wherever testing or analysis of material is required, such testing unless otherwise noted will be made at the Contractor's expense.
D. The contractor will accomplish subsequent testing of those materials, which fail to meet specifications, at no cost to the Government.
E. Contractor Quality Control (CQC) Program: The Contractor shall provide and maintain an effective quality control program in accordance with the contract. Within ten (10) days of the award of the contract, the Contractor shall provide three (3) copies of the project CQC plan to the Contracting Officer. This document, as a minimum, shall include name and address of the independent testing agency and the responsible principal with the firm; a summary of QC tests required by the specification and to be provided by the testing agency; and typical daily reports forms to be used for this project. The plan shall also indicate organizational procedures to immediately notify the Contracting Officer or his/her representative of test results in noncompliance with the specification and recommendations on correction. The testing agency must be an independent company and not owned or partially owned by the Contractor or any relation or employee of the Contractor.
F. Samples used for testing shall be selected as specified for the various tests elsewhere in the specifications but in every case the method of selecting samples and the location for selection shall be as approved by the Contracting Officer.
G. Tests shall be made in accordance with the specified testing procedures and/or methods and otherwise as required to provide compliance with all contract requirements. Tests shall be made by independent, commercial testing laboratories approved in writing by the Contracting Officer.
H. Results of all tests shall be recorded on certified test reports of the commercial testing laboratories. Reports shall include a statement that the materials tested do or do not meet the requirements of the Contract specifications. Six copies of all reports shall be forwarded directly to the Contracting Officer for approval within five (5) days of the actual performance of the test. The testing agency shall immediately notify (verbally) the Contracting Officer of any tests, which indicate failure to meet the contract requirements.
I. Any item, for which test reports show failure to meet all Contract requirements shall be retested as often as required to show full compliance with Contract requirements, at the Contractor's expense.
J. Contractor will provide an emergencies plan, with Contractors to accomplish the repairs in the event of utility and/or communications
SECTION 01330 Page 19 emergencies.
1.20 WARRANTY
A. In addition to the specific guarantees required by the specifications for certain…