Construct_Pedestrian_Sidewalk_AirGuard_57th_RFI_Log.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Construct Sidewalks
- Solicitation number
- W912L6-17-B-0013
About this file
Updated RFI Worksheet
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AFSOC.pdf | ||
| ANG_logo.pdf | ||
| SOCOM.pdf | ||
| Amendment_2.pdf | ||
| Construct_Pedestrian_Sidewalk_AirGuard_57th_RFI_Log.xlsx | XLSX spreadsheet | |
| Construct_Sidewalk_RFI_Log.xlsx | XLSX spreadsheet | |
| Construct_Sidewalk_RFI_Log.xlsx | XLSX spreadsheet | |
| W912L6-17-B-0013_Construct_Sidewalks__Mod_I.pdf | ||
| Solicitation.pdf | ||
| Drawings_-_1523_ANG_-_SIDEWALK_MEMORIAL_-_160628.pdf | ||
| 152003_WRANGB_COMBINED_specs.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Pre-Bid RFI Log for Construct Sidewalk, YZEU152003
| Date: | RFI No. | RFP Reference (Sect/Para/Page) | QUESTION | GOVERNMENT RESPONSE |
| 8/16/17 | 1 | NA | Is this a lump sum bid or unit price? | Lump Sum |
| 8/16/17 | 2 | A-001 | Sheet A-001 detail 02 shows a Blue Granite Tile that sets in 2" reveal as a option #1 there is no information on this IE. dimensions and thickness can you please Clarify? | Blue Polished Granite, Construction Joints as shown are not required. Contractor to provide size and pattern as part of his submittal. Install as per MFG instructions |
| 8/16/17 | 3 | G-001 | If option #1 is not taken, what will be used to fill the reveal? | Option #1 will be awarded. Option is to tracking funding streams. |
| 8/16/17 | 4 | "fundraiser item shown in drawings ( including in base bid)" #1 Brick /5,000 sf. Are the pavers being supplied, contractor installed, and the engravings being done later by others. Or is this the contractor supply the brick paver, installing them and the engraving only will be done at a later date by others? | Contractor to supply and install the brick pavers. Engraving will be done at a later date. | |
| 8/16/17 | 5 | A-001 | Option #1 calls for 12" Bronze Lettering and a 36" Diameter Bronze Plaque. Is There a specific supplier that the ANG generally uses for these items? | Blue Granite - Azul Imperiale Quartzite, polished - MS International, Inc. or Equal |
36" Diameter Bronze Sidewalk Plaque (Military Seal), Air National Guard Logo - A.R.K. Ramos Signage Systems or Equal - 2015 Catalog (pg 3); Standard Border #504, Finish BR-400 (Satin Bronze Raised, Dark Oxidized Background), Pebble Texture, Concealed Stud Mounting
12" Bronze Futura Lettering - A.R.K. Ramos Signage Systems or Equal - 2015 Catalog (pg 7); A.R.K. Ramos Signage Systems or Equal - 2015 Price Book (pg 3); F-7 Bronze Finish. FM-4 Flush Mounting set in Adhesive ark-ramos-2015-catalog-reduced.pdf, ark-ramos-price-book-2015, MS International Inc Azul Imperiale Quartzite Slab.pdf
| 8/16/17 | 6 | NA | Will water be supplied by the base for use? | No, Water can be obtained via OKC Water through existing water hydrants on base with an OKC portable water meter. |
| 8/16/17 | 7 | G-001 | Where will construction equipment be stored? | Laydown Option is the SE corner of the parking lot near the memorial |
| 8/16/17 | 8 | NA | Will there be an area to waste spoils or will they need to be removed from the base? | Spoils to be become property of the contractor. Concrete and Asphalt to be recyled if possible. |
| 8/17/17 | 9 | NA | There isnt a spec on the masonry. Can you provide? | Full Specs have been upoladed on FBO. |
| 8/17/17 | 10 | C-301 | Can you provide a detail and plan sheet on the Cable Barrier Fence as well as the swing gates that are in the specs? | See detail 3 in referenced drawing |
| 8/17/17 | 11 | NA | Are there Automated Barrier Arms on Air Guard drive, if so can you provide the specs | There are none on Air Guard Drive |
| 8/21/17 | 12 | A-003 | On option #3 there is a 15'3" gap between the north and south screen walls. The government wants the wall to continue on connecting the north and south screen walls to make one continuous screen wall at all 4 locations. | Concur |
| 8/21/17 | 13 | A-003 | Can you provide sources and any additional information on the cast iron lids for the manhole covers in the memorial area. | Neenah Foundry or Equal http://www.nfco.com/municipal/products/manhole-frames-covers/custom-covers |
SS MANHOLE DIAMETER = 3.18' dia. total
THREE TOTAL CUSTOM LIDS ONLY (NO FRAMES) - SS, ELEC, TELE
ANG LOGO TO BE PROVIDED BY OWNER
SS LID DIAMETER = 2.33' dia. lid (24 11/32") ELEC AND TELEPHONE MANHOLE DIAMETER = 2.81' dia. total ELEC AND TELEPHONE LID DIAMETER = 2.65' dia. lid (24 5/8")
| 8/21/17 | 14 | E-001 | Plans call for a nema 4 enclosure. SOW calls for a 3R enclosure. Which one are we to use? (Note from sheet E-100) | NEMA 3R enclosure is correct. |
| 8/21/17 | 15 | C-201 | Where is the existing controller by the front entry gate to route the existing circuit? | Existing irrigation control box is indicated on Sheet C-201, west of the existing guard house. |
| 8/21/17 | 16 | A-001 | Can we get a logo to use on manhole lids? | See attachment RFI 15 |
| 8/21/17 | 17 | L-001 | what is the depth of the river rock need to be? Will it be throughout the entire bed areas and same questions for the mulch. The planting details on L-001 indicate some plants don't have the cypress mulch. Do all get mulch | Per GENERAL LANDSCPE PLAN NOTES, NOTE G: "RIVER ROCK MUST BE A MINIMUM 3/8" AND NOT TO EXCEED THE MAXIMUM OF 2" IN SIZE." INSTALL OVER WEED VEGETATION BARRIER. |
3/8" RIVER ROCK TO BE 2" THICK COVER
2" RIVER ROCK TO BE 4" THICK COVER. COVER WEED VEGETATION BARRIER SUFFICIENTLY TO NOT BE VISIBLE.
2. RIVER WALK WIL BE THROUGHOUT THE ENTIRE BED AREA WHERE INDICATED ON DETAIL 01/L-001.
3. NOTES MENTIONING CYPRUS MULCH ARE TO BE CHANGED TO RIVER ROCK IN LIEU OF CYPRUS MULCH.
| 7/6/17 | 18 | Amendment 6 | How does the pricing need to look? Should this be a lump sum or have option CLINs? | As per Amendment 6 which was posted to FBO, the pricing structure will have a base and four option CLINs. The bids need to follow this CLIN structure when submitted. |
| 7/6/17 | 19 | Do all amendments need to be acknowledged when bids are submitted? | Yes, all SF 30 amendments must be signed and acknowledged |