Attachment 7-KELL162006_66.xls
XLS spreadsheet 166 KB Posted
- Solicitation number
- W912L1-20-B-6002
- Issued by
-
Department of the Army National Guard
About this file
This document contains a submittal schedule for a federal construction contract to modify a simulator area and vault to meet intelligence community standards. The schedule lists over 200 submittal items required from the contractor organized by construction discipline. Key submittals include construction schedules, sustainability plans, shop drawings, product data and samples for various building systems and components. The contract duration is 300 days from notice to proceed and is set aside 100% for small businesses with a NAICS code of 238290 and size standard of $16.5 million. The contractor must provide all labor, equipment and materials to complete the renovation project to a LEED Silver certification level in accordance with the specifications, drawings and basis of design documents.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal 1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT NAME | SOLICITATION /CONTRACT NUMBER | ||||||||||||||||||||
| KELL162006 | MODIFY SIMULATOR AREA AND VAULT | ||||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | |||||||||||||||||||||||
| SUBMITTAL NUMBER | PRECONSTRUCTION | SHOP DRAWINGS | PRODUCT DATA | SAMPLES | DESIGN DATA | TEST REPORTS | CERTIFICATES | MANUFACTURER'S INSTRUCTIONS | MANUFACTURER'S FIELD REPORTS | OPERATION AND MAINTENANCE DATA | CLOSEOUT | APPROVING AUTORITY | SUSTAINABILITY ENOTEBOOK | REQUIRED SUBMISSION DATE | DATE TO CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | APPROVED | DISAPPROVED | CONTRACTOR SUBMITTAL | FINAL APPROVAL | |
| GENERAL | GENERAL | ||||||||||||||||||||||
| 1 | SALVAGE PLAN | X | X | PRECONSTRUCTION | |||||||||||||||||||
| 2 | EARNED VALUE REPORT | X | AE | X | PRECONSTRUCTION | ||||||||||||||||||
| 3 | VIEW LOCATION MAP | X | PRECONSTRUCTION | ||||||||||||||||||||
| 4 | PROGRESS AND COMPLETION PICTURES | X | PRECONSTRUCTION | ||||||||||||||||||||
| 5 | COLOR BOARDS | X | AE | 90 DAYS AFTER AWARD | |||||||||||||||||||
| 6 | CONSTRUCTION SCHEDULE | X | AE | PRECONSTRUCTION | |||||||||||||||||||
| 7 | PRELIMINARY HIGH PERFORMANCE AND SUSTAINABLE | X | PRECONSTRUCTION | ||||||||||||||||||||
| 8 | SUSTAINABILITY ACTION PLAN | X | PRECONSTRUCTION | ||||||||||||||||||||
| 9 | PRELIMINARY SUSTAINABILITY ENOTEBOOK | X | PRECONSTRUCTION | ||||||||||||||||||||
| 10 | FINAL HIGH PERFORMANCE AND SUSTAINABLE | X | |||||||||||||||||||||
| 11 | FINAL SUSTAINABILITY ENOTEBOOK | X | |||||||||||||||||||||
| 12 | AMMENDED FINAL HIGH PERFORMANCE AND SUSTAINABLE | X | |||||||||||||||||||||
| 13 | AMMENDED FINAL SUSTAINABILITY ENOTEBOOK | X | |||||||||||||||||||||
| 14 | QUALITY CONTROL PLAN | X | WITHIN 15 DAYS AFTER AWARD | ||||||||||||||||||||
| 15 | WASTE MANAGEMENT PLAN | X | PRECONSTRUCTION | ||||||||||||||||||||
| 16 | OPERATION AND MAINTENANCE MANUALS | X | |||||||||||||||||||||
| 17 | AS-BUILT DRAWINGS | X | 30 DAYS PRIOR TO BOD | ||||||||||||||||||||
| 18 | FINAL DD 1354 | X | 60 DAYS PRIOR TO ACCEPTANCE OF WORK | ||||||||||||||||||||
| 19 | CHECKLIST FOR DD FORM 1354 | X | |||||||||||||||||||||
| DEMO | DEMOLITION | ||||||||||||||||||||||
| 20 | DEMOLITION PLAN | X | PRECONSTRUCTION | ||||||||||||||||||||
| 21 | NOTIFICATION | X | |||||||||||||||||||||
| CONCRETE | MISCELLANEOUS CAST-IN-PLACE CONCRETE | ||||||||||||||||||||||
| 22 | INSTALLATION DRAWINGS | X | |||||||||||||||||||||
| 23 | MIX DESIGN | X | |||||||||||||||||||||
| 24 | CONCRETE MIXTURE PROPORTIONS | X | |||||||||||||||||||||
| 25 | COMPRESSIVE STRENGTH TESTING | X | |||||||||||||||||||||
| 26 | SLUMP | X | |||||||||||||||||||||
| MASONRY | UNIT MASONRY | ||||||||||||||||||||||
| 27 | REINFORCEMENT DETAIL DRAWING | X | |||||||||||||||||||||
| 28 | CLAY OR SHALE BRICK | X | X | ||||||||||||||||||||
| 29 | CEMENT | X | |||||||||||||||||||||
| 30 | CEMENTIOUS MATERIALS | X | |||||||||||||||||||||
| 31 | CONCRETE MASONRY UNITS (CMU) | X | |||||||||||||||||||||
| 32 | ADMIXTURES FOR MASONRY MORTAR | X | |||||||||||||||||||||
| 33 | ANCHORS, TIES, AND BAR POSITIONERS | X | |||||||||||||||||||||
| 34 | JOINT REINFORCEMENT | X | |||||||||||||||||||||
| 35 | CLAY MASONRY EXPANSION-JOINT MATERIALS | X | |||||||||||||||||||||
| CARPENTRY | ROUGH CARPENTRY | ||||||||||||||||||||||
| 36 | CERTIFIED SUSTAINABILITY HARVESTED WOOD | X | |||||||||||||||||||||
| 37 | CERTIFIED SUSTAINABILITY PLYWOOD | X | |||||||||||||||||||||
| 38 | INDOOR AIR QUALITY FOR FIBERBOARD WALL SHEATHING | X | |||||||||||||||||||||
| 39 | INDOOR AIR QUALITY FOR AEROSOL ADHESIVES | X | |||||||||||||||||||||
| JOINTS | JOINT SEALANTS | ||||||||||||||||||||||
| 40 | SEALANTS | X | |||||||||||||||||||||
| 41 | PRIMERS | X | |||||||||||||||||||||
| 42 | BOND BREAKERS | X | |||||||||||||||||||||
| 43 | BACKSTOPS | X | |||||||||||||||||||||
| 44 | INDOOR AIR QUALITY | X | |||||||||||||||||||||
| 45 | INDOOR AIR QUALITY FOR INTERIOR SEALANTS | X | |||||||||||||||||||||
| DOORS | STEEL DOORS AND FRAMES | ||||||||||||||||||||||
| 46 | DOORS | X | X | ||||||||||||||||||||
| 47 | FRAMES | X | X | ||||||||||||||||||||
| 48 | ACCESSORIES | X | X | ||||||||||||||||||||
| 49 | WEATHERSTRIPPING | X | X | ||||||||||||||||||||
| 50 | SCHEDULE OF DOORS | X | |||||||||||||||||||||
| 51 | SCHEDULE OF FRAMES | X | |||||||||||||||||||||
| DOORS | WOOD DOORS | ||||||||||||||||||||||
| 52 | DOORS | X | X | ||||||||||||||||||||
| 53 | SOUND TRANSMISSION RATING | X | |||||||||||||||||||||
| 54 | DOOR FINISH COLORS | X | |||||||||||||||||||||
| 55 | CERTIFIED SUSTAINABILITY HARVESTED FLUSH WOOD DOORS | X | |||||||||||||||||||||
| DOORS | DOOR HARDWARE | ||||||||||||||||||||||
| 56 | MANUFACTURER'S DETAIL DRAWING | X | |||||||||||||||||||||
| 57 | VERIFICATION OF EXISTING CONDITIONS | X | |||||||||||||||||||||
| 58 | HARDWARE SCHEDULE | X | |||||||||||||||||||||
| 59 | KEYING SYSTEM | X | |||||||||||||||||||||
| 60 | HARDWARE ITEMS | X | X | ||||||||||||||||||||
| GYPSUM | GYPSUM BOARD | ||||||||||||||||||||||
| 61 | METAL SUPPORT SYSTEMS | X | X | ||||||||||||||||||||
| 62 | ASBESTOS FREE MATERIALS | X | |||||||||||||||||||||
| FLOORING | RESILIENT FLOORING | ||||||||||||||||||||||
| 63 | RESILIENT FLOORING AND ACCESSORIES | X | X | X | |||||||||||||||||||
| 64 | RESILIENT FLOORING AND ACCESSORIES ADHESIVES | X | |||||||||||||||||||||
| 65 | MOISTURE, ALKALINITY AND BOND TESTS | X | |||||||||||||||||||||
| 66 | SURFACE PREPERATION | X | |||||||||||||||||||||
| 67 | INSTALLATION | X | |||||||||||||||||||||
| FLOORING | CARPETING | ||||||||||||||||||||||
| 68 | MOLDINGS | X | |||||||||||||||||||||
| 69 | RECYCLED CONTENT FOR CARPETING | X | |||||||||||||||||||||
| 70 | INDOOR AIR QUALITY FOR AEROSOL ADHESIVES | X | |||||||||||||||||||||
| 71 | INDOOR AIR QUALITY FOR NON-AEROSOL ADHESIVES | X | |||||||||||||||||||||
| 72 | INDOOR AIR QUALITY FOR CONCRETE PRIMER | X | |||||||||||||||||||||
| PAINT | PAINTS AND COATINGS | ||||||||||||||||||||||
| 73 | COATING | X | X | ||||||||||||||||||||
| 74 | COLOR | X | |||||||||||||||||||||
| 75 | QUALIFICATION TESTING LABORATORY FOR COATINGS | X | |||||||||||||||||||||
| VISUAL | VISUAL DISPLAY UNITS | ||||||||||||||||||||||
| 76 | VISUAL DISPLAY BOARD | X | X | ||||||||||||||||||||
| 77 | ALUMINUM | X | |||||||||||||||||||||
| 78 | PORCELAIN ENAMEL | X | |||||||||||||||||||||
| 79 | MATERIALS | X | |||||||||||||||||||||
| LIFT | VERTICAL WHEELCHAIR LIFT | ||||||||||||||||||||||
| 80 | TYPICAL DETAILS OF ASSEMBLY, ERECTION AND ANCHORAGE | X | |||||||||||||||||||||
| 81 | MANUFACTURER'S INSTALLATION INSTRUCTIONS | X | |||||||||||||||||||||
| FIRE | WET PIPE SPRINKLER SYSTEM | ||||||||||||||||||||||
| 82 | FIRE PROTECTION SPECIALIST | X | PRECONSTRUCTION | ||||||||||||||||||||
| 83 | SPRINKLER SYSTEM INSTALLER | X | PRECONSTRUCTION | ||||||||||||||||||||
| 84 | SHOP DRAWINGS | X | |||||||||||||||||||||
| 85 | AS-BUILT DRAWINGS | X | |||||||||||||||||||||
| 86 | MATERIALS AND EQUIPMENT | X | |||||||||||||||||||||
| 87 | HYDRAULIC CALCULATIONS | X | |||||||||||||||||||||
| 88 | PRELIMINARY TEST PROCEDURES | X | |||||||||||||||||||||
| 89 | PRELIMINARY TEST REPORT | X | |||||||||||||||||||||
| 90 | FINAL ACCEPTANCE TEST PROCEDURES | ||||||||||||||||||||||
| 91 | FINAL ACCEPTANCE TEST REPORT | ||||||||||||||||||||||
| 92 | CERTIFICATION BY FIRE PROTECTION SPECIALIST | X | |||||||||||||||||||||
| 93 | OPERATION AND MAINTENANCE MANUALS | X | |||||||||||||||||||||
| HVAC | HVAC | ||||||||||||||||||||||
| 94 | DETAIL DRAWINGS | X | |||||||||||||||||||||
| 95 | DUCT ACCESS DOORS | X | |||||||||||||||||||||
| 96 | MANUAL BALANCING DAMPERS | X | X | ||||||||||||||||||||
| 97 | AIR HANDLING UNITS | X | X | ||||||||||||||||||||
| 98 | VARIABLE VOLUME, SINGLE DUCT TERMINAL UNITS | X | X | ||||||||||||||||||||
| 99 | REHEAT UNITS | X | X | ||||||||||||||||||||
| 100 | PERFORMANCE TESTS | X | |||||||||||||||||||||
| 101 | DAMPER ACCEPTANCE TEST | X | |||||||||||||||||||||
| 102 | OPERATION AND MAINTENANCE MANUALS | X | |||||||||||||||||||||
| 103 | CENTRIFUGAL FANS | X | |||||||||||||||||||||
| 104 | ENERGY EFFICIENT EQUIPMENT | X | |||||||||||||||||||||
| 105 | REDUCE VOLATILE ORGANIC COMPOUNDS | X | |||||||||||||||||||||
| 106 | INDOOR AIR QUALITY DURING CONSTRUCTION | X | |||||||||||||||||||||
| 107 | OZONE DEPLETING SUBSTANCES FOR REFRIGERANTS | X | |||||||||||||||||||||
| HVAC | TESTTING AND BALANCING | ||||||||||||||||||||||
| 108 | TAB SCHEMATIC DRAWINGS AND REPORT FORMS | X | AE | ||||||||||||||||||||
| 109 | EQUIPMENT AND PERFORMANCE DATA | X | X | ||||||||||||||||||||
| 110 | COMPLETED PRE-FINAL DALT REPORT | X | |||||||||||||||||||||
| 111 | CERTIFIED FINAL DALT REPORT | X | |||||||||||||||||||||
| 112 | INDEPENDENT TAB AGENCY AND PERSONNEL QUALIFICATIONS | X | |||||||||||||||||||||
| HVAC | THERMAL INSULATION | ||||||||||||||||||||||
| 113 | MICA PLATES | X | |||||||||||||||||||||
| 114 | PIPE INSULATION SYSTEMS | X | X | ||||||||||||||||||||
| 115 | DUCT INSULATION SYSTEMS | X | X | ||||||||||||||||||||
| 116 | EQUIPMENT INSULATION SYSTEMS | X | X | ||||||||||||||||||||
| 117 | THERMAL INSULATION | X | |||||||||||||||||||||
| 118 | DISPLAY SAMPLES | X | |||||||||||||||||||||
| 119 | REDUCE VOC FOR CAULKING, SEALANTS AND ADHESIVE | X | |||||||||||||||||||||
| 120 | RECYCLED CONTENT FOR PIPE AND DUCTWORK INSULATION | X | |||||||||||||||||||||
| HVAC | GAS PIPING | ||||||||||||||||||||||
| 121 | GAS PIPING SYSTEM | X | X | ||||||||||||||||||||
| 122 | PIPE AND FITTINGS | X | |||||||||||||||||||||
| 123 | GAS EQUIPMENT CONNECTORS | X | |||||||||||||||||||||
| 124 | PIPE COATING MATERIALS | X | X | ||||||||||||||||||||
| 125 | PRESSURE REGULATORS | X | |||||||||||||||||||||
| 126 | TRANSITION FITTINGS | X | |||||||||||||||||||||
| 127 | VALVES | X | |||||||||||||||||||||
| 128 | WARNING AND IDENTIFICATION TAPE | X | |||||||||||||||||||||
| 129 | TESTING | X | |||||||||||||||||||||
| 130 | PRESSURE TESTS | X | |||||||||||||||||||||
| 131 | TEST WITH GAS | X | |||||||||||||||||||||
| 132 | WELDERS PROCEDURES AND QUALIFICATIONS | X | |||||||||||||||||||||
| 133 | ASSIGNED NUMBER, LETTER, OR SYMBOL | X | |||||||||||||||||||||
| 134 | PE PIPES AND FITTINGS | X | |||||||||||||||||||||
| 135 | GAS FACILITY SYSTEM AND EQUIPMENT OPERATION | X | |||||||||||||||||||||
| 136 | GAS FACILITY SYSTEM MAINTENANCE | X | |||||||||||||||||||||
| 137 | GAS FACILITY EQUIPMENT MAINTENANCE | X | |||||||||||||||||||||
| HVAC | REFRIGERANT PIPING | ||||||||||||||||||||||
| 138 | REFRIGERANT PIPING SYSTEM | X | |||||||||||||||||||||
| 139 | MAINTENANCE | X | |||||||||||||||||||||
| 140 | OPERATION AND MAINTENANCE MANUALS | X | |||||||||||||||||||||
| 141 | DEMONSTRATIONS | X | |||||||||||||||||||||
| HVAC | HEATING BOILERS | ||||||||||||||||||||||
| 142 | OPERATION AND MAINTENANCE INSTRUCTIONS | X | |||||||||||||||||||||
| 143 | WATER TREATMENT SYSTEM | X | |||||||||||||||||||||
| 144 | ENERGY EFFICIENT EQUIPMENT FOR BOILERS | X | |||||||||||||||||||||
| 145 | INDOOR AIR QUALITY DURING CONSTRUCTION | X | X | ||||||||||||||||||||
| HVAC | UNITARY HEATING AND COOLING EQUIPMENT | ||||||||||||||||||||||
| 146 | DEMONSTRATIONS | X | |||||||||||||||||||||
| 147 | REFRIGERANT TESTS, CHARGING, AND START-UP | X | |||||||||||||||||||||
| 148 | SYSTEM PERFORMANCE TESTS | ||||||||||||||||||||||
| 149 | OPERATION AND MAINTENANCE MANUALS | X | |||||||||||||||||||||
| ELECTRICAL | ELECTRICAL | ||||||||||||||||||||||
| 150 | CONDUITS AND RACEWAY | X | |||||||||||||||||||||
| 151 | WIRE AND CABLE | X | |||||||||||||||||||||
| 152 | SPLICES AND CONNECTORS | X | |||||||||||||||||||||
| 153 | SWITCHES | X | |||||||||||||||||||||
| 154 | RECEPTACLES | X | |||||||||||||||||||||
| 155 | OUTLET BOXES, PULL BOXES AND JUNCTION BOXES | X | |||||||||||||||||||||
| 156 | CIRCUIT BREAKERS | X | |||||||||||||||||||||
| 157 | PANELBOARDS | X | X | ||||||||||||||||||||
| 158 | DIRECTORY CARD AND HOLDER | X | |||||||||||||||||||||
| 159 | LAMPS AND LIGHTING FIXTURES | X | |||||||||||||||||||||
| 160 | DRY-TYPE DISTRIBUTION TRANSFORMERS | X | |||||||||||||||||||||
| 161 | CONTINUITY TEST | X | |||||||||||||||||||||
| 162 | PHASE-ROTATION TESTS | X | |||||||||||||||||||||
| 163 | INSULATION RESISTANCE TESTS | X | |||||||||||||||||||||
| ELECTRICAL | INSULATED WIRE AND CABLE | ||||||||||||||||||||||
| 164 | WIRE AND CABLE | X | |||||||||||||||||||||
| 165 | CONDUCTORS | X | |||||||||||||||||||||
| ELECTRICAL | INSPECTION AND TESTING | ||||||||||||||||||||||
| 166 | ACCEPTANCE TESTS AND INSPECTIONS | X | X | ||||||||||||||||||||
| 167 | QUALIFICATIONS OF ORGANIZATION | X | |||||||||||||||||||||
| ELECTRICAL | LIGHTING CONTROL DEVICES | ||||||||||||||||||||||
| 168 | INSTALLATION DRAWINGS | X | |||||||||||||||||||||
| 169 | TIME SWITCH | X | |||||||||||||||||||||
| 170 | OCCUPANCY SENSORS | X | |||||||||||||||||||||
| 171 | MOTION SENSORS | X | |||||||||||||||||||||
| ELECTRICAL | INTERIOR DISTRIBUTION SYSTEM | ||||||||||||||||||||||
| 172 | PANELBOARDS | X | |||||||||||||||||||||
| 173 | TRANSFORMERS | X | X | ||||||||||||||||||||
| 174 | CABLE TRAYS | X | |||||||||||||||||||||
| 175 | WIREWAYS | X | |||||||||||||||||||||
| 176 | LOAD CENTERS FOR HOUSING UNITS | X | X | ||||||||||||||||||||
| 177 | MARKING STRIPS DRAWINGS | X | |||||||||||||||||||||
| 178 | RECEPTACLES | X | |||||||||||||||||||||
| 179 | CIRCUIT BREAKERS | X | |||||||||||||||||||||
| 180 | SWITCHES | X | |||||||||||||||||||||
| 181 | ENCLOSED CIRCUIT BREAKERS | X | |||||||||||||||||||||
| 182 | MANUAL MOTOR STARTERS | X | |||||||||||||||||||||
| 183 | RESIDINTIAL LOAD CENTERS | X | |||||||||||||||||||||
| 184 | CATV OUTLETS | X | |||||||||||||||||||||
| 185 | SURGE PROTECTIVE DEVICES | X | |||||||||||||||||||||
| 186 | 600-VOLT WIRE TESTING | X | |||||||||||||||||||||
| 187 | GROUNDING SYSTEM TEST | X | |||||||||||||||||||||
| 188 | TRANSFORMER TESTS | X | |||||||||||||||||||||
| 189 | GROUND-FAULT RECEPTACLE TEST | X | |||||||||||||||||||||
| 190 | FUSES | X | |||||||||||||||||||||
| ELECTRICAL | PANELBOARDS | ||||||||||||||||||||||
| 191 | DETAIL DRAWINGS | X | |||||||||||||||||||||
| 192 | PANELBOARDS | X | |||||||||||||||||||||
| 193 | DIRECTORY CARD AND HOLDER | X | |||||||||||||||||||||
| 194 | CONTINUITY TESTS | X | |||||||||||||||||||||
| 195 | INSULATION TESTS | X | |||||||||||||||||||||
| 196 | CERTIFICATION | X | |||||||||||||||||||||
| 197 | MANUFACTURER'S INSTRUCTIONS | X | |||||||||||||||||||||
| ELECTRICAL | AUTOMATIC TRANSFER SWITCH | ||||||||||||||||||||||
| 198 | TESTING | X | |||||||||||||||||||||
| 199 | SWITCHING EQUIPMENT | X | |||||||||||||||||||||
| 200 | INSTRUCTIONS | X | |||||||||||||||||||||
| ELECTRICAL | INTERIOR LIGHTING | ||||||||||||||||||||||
| 201 | LUMINAIRE DRAWINGS | X | X | ||||||||||||||||||||
| 202 | OCCUPANCY /VACANCY SENSOR COVERAGE LAYOUT | X | X | ||||||||||||||||||||
| 203 | LIGHT SOURCES | X | X | ||||||||||||||||||||
| 204 | DRIVERS, BALLASTS AND GENERATORS | X | |||||||||||||||||||||
| 205 | LED LUMINAIRE WARRANTY | X | |||||||||||||||||||||
| 206 | VACANCY SENSORS | X | |||||||||||||||||||||
| 207 | DIMMING CONTROLLERS | X | |||||||||||||||||||||
| 208 | TIME SWITCH | X | |||||||||||||||||||||
| 209 | POWER HOOK LUMINAIRE HANGARS | X | |||||||||||||||||||||
| 210 | EXIT SIGNS | X | |||||||||||||||||||||
| 211 | EMERGENCY LIGHTING UNIT | X | |||||||||||||||||||||
| 212 | LED EMERGENCY DRIVERS | X | |||||||||||||||||||||
| 213 | OCCUPANCY SENSORS | X | |||||||||||||||||||||
| 214 | AMBIENT LIGHT LEVEL SENSOR | X | |||||||||||||||||||||
| 215 | LED LUMINAIRE | X | |||||||||||||||||||||
| 216 | ENERGY EFFICIENCY | X | |||||||||||||||||||||
| 217 | LUMINAIRE USEFUL LIFE CERTIFICATE | X | |||||||||||||||||||||
| 218 | LED DRIVER AND DIMMING SWITCH COMPATIBILITY | X | |||||||||||||||||||||
| ELECTRICAL | EXTERIOR LIGHTING | ||||||||||||||||||||||
| 219 | PHOTOMETRIC PLAN | X | PRECONSTRUCTION | ||||||||||||||||||||
| 220 | LED LUMINAIRE WARRANTY | X | PRECONSTRUCTION | ||||||||||||||||||||
| 221 | LUMINAIRE DRAWINGS | X | |||||||||||||||||||||
| 222 | LED LUMINAIRES | X | X | ||||||||||||||||||||
| 223 | LUMINAIRE LIGHT SOURCES | X | X | ||||||||||||||||||||
| 224 | TIME SWITCH | X | |||||||||||||||||||||
| 225 | MOTION SENSORS | X | |||||||||||||||||||||
| 226 | DESIGN DATA FOR LUMINAIRES | X | |||||||||||||||||||||
| 227 | LUMINAIRE USEFUL LIFE CERTIFICATE | X | |||||||||||||||||||||
| COMM | BUILDING TELECOMMUNICATIONS CABLING | ||||||||||||||||||||||
| 228 | TELECOMMUNICATION DRAWINGS | X | |||||||||||||||||||||
| 229 | TELECOMMUNICATION SPACE DRAWINGS | X | |||||||||||||||||||||
| 230 | TELECOMMUNICATION CABLING | X | |||||||||||||||||||||
| 231 | PATCH PANELS | X | |||||||||||||||||||||
| 232 | TELECOMMUNICATIONS OUTLET | X | |||||||||||||||||||||
| 233 | EQUIPMENT SUPPORT FRAME | X | |||||||||||||||||||||
| 234 | CONNECTOR BLOCKS | X | |||||||||||||||||||||
| 235 | SPARE PARTS | X | |||||||||||||||||||||
| 236 | TELECOMMUNICATION CABLING TESTING | X | |||||||||||||||||||||
| 237 | TELECOMMUNICATION CONTRACTOR QUALIFICATIONS | X | |||||||||||||||||||||
| 238 | KEY PERSONNEL QUALIFICATIONS | X | |||||||||||||||||||||
| 239 | MANUFACTURER QUALIFICATIONS | X | |||||||||||||||||||||
| 240 | TEST PLAN | X | |||||||||||||||||||||
| 241 | FACTORY REEL TESTS | X | |||||||||||||||||||||
| 242 | TELECOMMUNICATIONS CABLING AND PATHWAY SYSTEM | X | |||||||||||||||||||||
| 243 | RECORD DOCUMENTATION | X | |||||||||||||||||||||
| SECURITY | GROUNDING AND BONDING FOR ELECTRONIC SAFETY | ||||||||||||||||||||||
| 244 | GROUNDING SYSTEMS | X | |||||||||||||||||||||
| 245 | GROUND RODS | X | |||||||||||||||||||||
| 246 | GROUND WIRES | X | |||||||||||||||||||||
| 247 | CONNECTORS AND FASTNERS | X | |||||||||||||||||||||
| 248 | BONDING MATERIALS | X | |||||||||||||||||||||
| 249 | BOND RESISTANCE TEST | X | |||||||||||||||||||||
| 250 | GROUND RESISTANCE TEST | X | |||||||||||||||||||||
| 251 | GROUND ISOLATION TEST | X | |||||||||||||||||||||
| 252 | CONTINUITY ISOLATION TEST | X | |||||||||||||||||||||
| UTILITIES | UNDERGROUND ELECTRICAL DISTRIBUTION | ||||||||||||||||||||||
| 253 | PRECAST UNDERGROUND STRUCTURES | X | |||||||||||||||||||||
| 254 | FIELD ACCEPTANCE CHECKS AND TESTS | X | |||||||||||||||||||||
| 255 | CABLE INSTALLER QUALIFICATIONS | X |