addendum_1.docx

DOCX document 13 KB Posted

Attached to
Vehicle Barrier System Federal contract opportunity
Solicitation number
W912K6-15-R-0013
Issued by
Department of the Army Maryland Army National Guard

About this file

Addendum to the SOW. It clarifies 3 paragraphs within the original SOW.

View the file

Other files for this federal contract opportunity

Other files attached to Vehicle Barrier System, newest first.
File Type Posted
W912K6-15-R-0013-0001.pdf PDF
RFI_Net_Barrier.docx DOCX document
W912K6-15-R-0013.pdf PDF
SOW.docx DOCX document
175th_WING_INSTALLATION_ACCESS_APPLICATION.pdf PDF
DOD_Anti-Ram_Vehicle_Barriers_May_2015.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Barrier Net System (Statement of Work) Addendum 1

6.14 System must have controlled heating elements inside the below pavement housing to melt snow or ice that may accumulate. The system is required to operate in all weather conditions with a redundant electrical backup system such as batteries. Thermostats must automatically turn the heating unit(s) on and off.

6.16 Contractor will provide and install all signs, warning lights, traffic lights, flashing lights, safe loops and alarms. All work is to be completed in compliance with all Department of Defense and Army Corp of Engineers Protective Design Center regulation and standards.

6.31 Contractor is to provide training of operation and maintenance of barrier net system. The training should be comprehensive enough for the end use to be able to provide daily, monthly, quarterly and yearly maintenance on net barrier system.