A-7_Site_Visit_and__Q&A.docx

DOCX document 16 KB Posted

Attached to
Furnish and Install Cable
Solicitation number
W912K3-19-Q-5001
Issued by

About this file

Site Visit Q&A - remove CAT6E and add transceivers due to run length

View the file

Other files

File Type Posted
A-1_Revised_Final_SOW.doc DOC document
A-1_Revised_SOW_13_Dec_18_Infrastructure_Installation.doc DOC document
A-7_Combo_(Final-Revised).docx DOCX document
A-1_Attach_1_-_BATS_Cable_Distribution_Plan.pptx PPTX presentation
A-1_Attach_2_-_Cable_Specs_-_Nov16.doc DOC document
A-7_Site_Visit_and__Q&A.docx DOCX document
Attach_2_-_Cable_Specs_-_Nov16.doc DOC document
Attach_1_-_BATS_Cable_Distribution_Plan_(Revised).pptx PPTX presentation

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FURNISH AND INSTALL CABLE (WADS, JBLM, WA)

Solicitation# W912K3-19-Q-5001

SITE VISIT NOTES (28 November, 2018) The site visit was held at 1:00pm local time at the Western Air Defense Sector (WADS) on Joint Base Lewis-McChord. 3 potential offerors were in attendance. There was a quick walk through the site to discuss the information covered in the solicitation and supporting documents (all of which were posted to FBO). There were no questions asked on site, see the consolidated list of questions asked via email below:

Q&A

1. Are these 2 building shown on Comm Cabling Site Plan – are these 2 physically separate buildings or is it 1 building? Bldg. 852 and BATS. See attached page 1.

A: They are two separate buildings, connected with an underground 4 inch conduit. Which reappears above ground near the BATS shelter/temporary building. As the drawing and contract verbiage states A rigid galvanized pipe, or suitable substitute, will need to be installed between the NEMA box and the shelter to protect the cabling from the elements.

1. If 2 physically separate buildings, what is approximate distance between them?

A: About 70 feet.

1. See attached page 3 – do we need to run voice/data drops to each desk or voice/data drops to each desk is not part of this project?

A: The interior voice/data drops are being handled by a separate contract. This contract only provides the connectivity from the WADS/Bldg. 852 Network Control Center to the BATS Shelter.