Pre-Proposal_Minutes_B48_Roof_Project.pdf

PDF 113 KB Posted

Attached to
Replace EPDM Roofs Bldg. 48 Federal contract opportunity
Solicitation number
W912JC-18-B-5003
Issued by
Department of the Army

About this file

Pre-Proposal Minutes B48 Roof Project

View the file

Other files for this federal contract opportunity

Other files attached to Replace EPDM Roofs Bldg. 48, newest first.
File Type Posted
W912JC-18-C-5004.pdf PDF
B48_Roof_Abstract_of_Offers.pdf PDF
PRQE172428_Addendum_2.pdf PDF
AMENDMENT_2_VUVB_109002_Range_Training_Support_Facilities.pdf PDF
RFI_W912JC-18-B-5003_–_Bldg._48_Roof.pdf PDF
AMENDMENT_1_PRQE172428_Replace_Building_48_EPDM_Roofs.pdf PDF
Sheet_S-2_Add1.pdf PDF
SITE_VISIT_Sign_in_Sheet_B48_EPDM_Roofs.pdf PDF
PRQE172428_Addendum_1.pdf PDF
TPO_Spec_075400L.pdf PDF
PRQE172428_B48_EPDM_Roofs_SOW.pdf PDF
184_KANG_CES_Specifications.pdf PDF
Wage_Determination.pdf PDF
PRQE172478_Drawings.pdf PDF
PRQE_172478_Replace_B48_EPDM_Roof_Submittal_Listing.xlsx XLSX spreadsheet
W912JC-18-B-5003.pdf PDF
SITE_VISIT_INFORMATION_B48_EPDM_Roofs.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NGB February 2017 A-145

MEMORANDUM FOR RECORD

SUBJECT: MINUTES OF PRE-PROPOSAL CONFERENCE AND SITE VISIT, SOLICITATION W912JC-

18-5003, REPLACE BUILDING 48 EPDM ROOFS

Date: 12 June 2018 - 0000-1130 hours

1. The list of contractors attending the meeting is shown on the attached sign-in sheet. The following

Government representatives attended the subject meeting:

Name Position Darin Brun Base Contracting Officer Dave Clement CES Project Manager Capt. Baird Ihme Deputy Base Civil Engineer

2. The following items were discussed during the Pre-proposal Conference:

a. The Contract period is 59 days. This includes all work to include cleanup and punch list. We anticipate award of the contract in mid-July. Following receipt and approval of bonds we will hold a pre-construction conference and issue NTP.

b. Interested offerors must be registered in SAM. To register go to:

https://www.sam.gov/portal/public/SAM/. You will need your DUNS number register.

3. A review of the drawings was conducted. It was noted that the posted specifications did not cover the TPO roof. It is imperative that the government provide the correct project specifications. The bid requirements were reviewed and reiterated that evaluation criteria for the most advantageous bid considering price only.

4. All questions must be submitted in writing via email to: darin.l.brun.mil@mail.mil . DO NOT

CONTACT the Government Engineers. All questions must be routed through the Contracting Office.

All Contractor questions when answered will be posted to the website. If a question arises that will result in a change to the plans or specifications, an official amendment will be issued. All correspondence, questions and answers, amendments etc. will be issued or posted at https://www.fbo.gov/

5. The attendees were driven out to building 48 and we were able to access two of the three roof locations. The roof on the tower was not accessible due to active RF antennas. The government will be coordinating the shutdown of the antennas and rescheduling the site visit to the tower roof. We are trying to coordinate this for 20 June 2018 @ 10:00 AM.

Questions:

6. What are the roof warranty requirements for both wind and time?

Included in Addendum 1 specification 075400L

7. What specifications govern the TPO roof?

8. Will this be a complete tear off and replace, if not, when will a core sample of the roofs be provided to the contractors?

Included in Addendum 1 Sheet S-2 http://www.sam.gov/portal/public/SAM/ mailto:darin.l.brun.mil@mail.mil http://www.fbo.gov/

NGB February 2017 A-146

9. Will the new roof be fully adhered or mechanically attached?

10. What is the average R-value required for the new roofs?

11. What is the taper of the roof?

12. Existing lightning protection is only attached with silicon at parapet walls. Detach lightning protection from wall as needed and reattach in similar fashion at completion of work. No certification of system will be required at project completion.

13. Any amendments that are issued will be posted to the web site. Contractors were advised to check the website frequently.

14. The pre-proposal conference and site visit concluded at 1130 hours.

Darin L Brun, SMSgt, KANG

CONTRACTING OFFICER