This document is a Standard Form 30 (SF-30) Amendment of Solicitation/Modification of Contract for Solicitation Number W912HZ25Q0014. The amendment extends the closing date to 19 May 2025 at 3:00 p.m. CST and provides clarifications for a pond cleanup and valve repair project at the Lewisville Aquatic Ecosystem Research Facility (LAERF) in Lewisville, Texas.
The amendment includes detailed responses to contractor questions, specifying that trees, brush, and aquatic vegetation will be disposed of on-site in a designated area, with debris hauled off-site. The project's success is defined as a pond free of trees, brush, vegetation, and debris that has been mowed and tilled to 6 inches. Additional details include approximately 3,200 feet of 8-inch underground pipe servicing the ponds, an expected 1-2 week drying period after dewatering, and identification of four known mainline leaks in specific ponds. No sediment removal, drainage pipe repairs, or drain valve repairs are required, with only raw water inlet valves to be addressed.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Reference Solicitation Number W912HZ25Q0014. The pupose if this amendment is to extend the closing date and answ er final questions:
a. The closing is extended to 19 May 2025 at 3:00 p.m CST.
b. Please see additional information for Questions and Answ ers.
Please see page 2 for additional information.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-May-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HZ25Q0014
X 9B. DATED (SEE ITEM 11)
26-Mar-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-May-2025
CODE
ERDC CONTRACTING OFFICE
3909 HALLS FERRY ROAD
VICKSBURG MS 39180-6199
W912HZ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HZ25Q0014
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
ADDITIONAL INFORMATION
1. The contractor shall provide services to remove and dispose do we have a designated area on site we want them to dispose of the trees, brush, aquatic vegetation, and debris?
Trees, brush, and aquatic vegetation disposed of on-site in designated area; debris hauled off (old wooden piers, fencing, etc.) by contractor.
2. Final question was what does success look like? A pond free of trees, brush, vegetation, and debris that has been moved and/or tilled? Would that statement suffice?
Success: pond free of trees, brush, vegetation, and debris that has been mowed and tilled (to 6-in);
use of attached photo titled “Sample Success Clean Pond” is appropriate to convey success.
3. What is the total length of underground pipe that services the area for the work will be performed that may require maintenance or testing to complete the sow There is approx. 160-ft between pond valves; approx. 3,200-ft underground 8” pipe servicing ponds listed in PWS.
4. What is a reasonable expectation from the time dewatering is completed until the pond areas will be dry enough to perform work without damaging the bentonite layer Once dewatered, it could take 1 – 2 weeks to for pond areas to dry completely depending on the amount of recent precipitation.
5. Are locations and number of mainline leaks know, what are expectations of clean out?
Yes, ponds where mainline leaks were known were listed in an amendment to W912HZ25Q0014 (13, 53, 38, 46 = 4 mainline leaks) and locations included on map in attached.pdf. Expectations of clean out see attachment photo titled “Sample Success Clean Pond” (see question #2 above).
6. Down to clay, mulching in place?
Do not remove soil, no mulching in place; all trees, and shrubs to be moved to on-site location. Once dry, ponds are to be mowed, thatch removed (if necessary) and tilled (6-in).
7. Sediment disposal?
No sediment is to be removed or disposed of.
8. Drainage pipes to be repaired?
There are no drainage pipes to be repaired.
9. Drain valves to be repaired?
No drain valves are to be repaired, only raw water inlet valves.
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 16-May-2025 05:00 PM to 19-May-2025 03:00 PM.
(End of Summary of Changes)