The following questions and answers are provided for informational purposes only:
Question 1: Reference ITEM 0002. Does the contractor have to have a DCAA system in-place prior to contract award or is after ok?
Answer: See page 76 of the solicitation; The Contractor must have a DCAA system in place prior to award. Or, Evidence in the form of (a) Third party audited financial statements to include audit of accounting system and methods, (b) Current Defense Contract Audit Agency (DCAA) cost accounting system audit report, or (c) Current certified DCAA Standard Form 1408 shall be accepted for the Offeror and the Offeror’s proposed teaming partners and/or subcontractors. Third party audits must include an opinion of the vendor’s accounting system and its adequacy for accumulating and billing costs under Government contracts. Self-certification or unsubstantiated statements of possessing an adequate accounting system or acceptable purchasing system is insufficient and may render the Offeror’s proposal non-responsive.
Question 2: Reference General Requirement. How are these services being provided currently? If by contractor, who is the contractor? If by contractor, what is the contract #?
FY 2015 contract value?
Answer: This is a new requirement; however, portions of this requirement have been satisfied through the use of Indefinite Delivery Indefinite Quantity (IDIQ) contract W912HZ-10-D-0004 ($9,800,000.00, Bowhead Science and Technology, LLC) and W912HZ-15-D-0005 ($4,000,000.00, Bowhead Professional Solutions, LLC).
Question 3: Reference Section 2.6. Location and Hours of Work – Q – what are the OCONUS locations, if any?
Answer: There are no OCONUS locations.
Question 4: Reference Section 4.1.15. What % of labor requires a secret clearance versus a top secret clearance?
Answer: That information is unknown at this time. The Contractor shall possess at a minimum a SECRET clearance; however, each Task Order will contain specific information.