This abstract of offers summarizes bids received in response to Solicitation Number W912HY21B0009 for pipeline dredging of the Houston Ship Channel between Bayport and Morgan's Cut with Bayport and Barbours Flare in Harris County, Texas. Five contractors submitted bids for the base work and four option periods to be performed between April 2021 and May 2028. The apparent low bidder was Inland Dredging Company at 30.31% below the government's estimate of $31,874,882 for the total project. Bids ranged from Inland Dredging's low of $24,236,800 to Orion Marine Construction's high of $34,700,000. The work includes pipeline dredging of specified sections of the ship channel, dredging of dock areas at Bayport and Barbours, debris removal, and management and protection measures over the duration of the contract.

View the file

Other files

File Type Posted
B.08.03 Amend 0004 W912HY21B0009 20210524.pdf PDF
AMEND0003_W912HY21B0009_19 May 2021.pdf PDF
XYZ_Section 16_Amend0002.txt TXT text file
XYZ_Section 5_Amend0002.txt TXT text file
XYZ_Section 3_Amend0002.txt TXT text file
XYZ_Section 10_Amend0002.txt TXT text file
XYZ_Section 1_Amend0002.txt TXT text file
XYZ_Section 17_Amend0002.txt TXT text file
XYZ_Section 13_Amend0002.txt TXT text file
XYZ_Section 12_Amend0002.txt TXT text file
XYZ_Section 8_Amend0002.txt TXT text file
XYZ_Section 11_Amend0002.txt TXT text file
AMEND-0002_W912HY21B0009.pdf PDF
XYZ_Section 9_Amend0002.txt TXT text file
XYZ_Section 2_Amend0002.txt TXT text file
XYZ_Section 15_Amend0002.txt TXT text file
XYZ_Section 14_Amend0002.txt TXT text file
XYZ_Section 6_Amend0002.txt TXT text file
XYZ_Section 7_Amend0002.txt TXT text file
XYZ_Section 4_Amend0002.txt TXT text file
AMEND0001_W912HY21B0009_14 May 2021.pdf PDF
B.08.02 Solicitation W912HY21B0009-PLANS - SIGNED Final 20210416.pdf PDF
B.08.02 Solicitation W912HY21B0009-Specs - SIGNED Final 20210416.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT

PRICE TOTAL

1 JB 2,306,800.00 $2,306,800.00

1 JB $762,300.00 $762,300.00

1,022,300 CY 7.61$ $7,779,703.00

1,833,300 CY $6.37 $11,678,121.00

1 JB $76,000.00 $76,000.00

1 JB 99,000.00 $99,000.00

$22,701,924.00

182,700 CY $8.69 $1,587,663.00

30 TON $2,560.00 $76,800.00

100 HOUR $2,500.00 $250,000.00

$1,914,463.00

169,600 CY $10.23 $1,735,008.00

$1,735,008.00

153,700 CY $13.91 $2,137,967.00

30 TON $2,560.00 $76,800.00

100 HOUR $2,500.00 $250,000.00

$2,464,767.00

423,000 CY $6.64 $2,808,720.00

1 JOB $250,000.00 $250,000.00

$3,058,720.00

$31,874,882.00

0008 Debris Removal

ABSTRACT OF OFFERS Page 1 of 6

Solicitation No.: W912HY21B0009 Date Issued: 16 Apr 2021 Date Opened: 27 May 2021 Issuing Office: USAED-Galveston Project Title: FY 21 Pipeline Dredging Deep Draft Houston Ship Channel Bayport to Morgan’s with Bayport and Barbours Flare Harris, County, Texas Unrestricted Procurement

TOTAL OPTION NO. 1

0001 Mobilization and Demobilization

Pipeline Management

Dredging, HSC, Section 1 through 7

Number of Amendments Issued: 0001, 0002, 0003 and 0004

Government Estimate (Without Profit)

OPTION NO. 1

TOTAL SCHEDULE NO. 1

OPTION NO. 3

TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

THRU 4

Dredging PHA Docks at Bayport Section 15

0010 Dredging Barbours Flare, Section 14

Pipeline Management

OPTION NO. 4

* The apparent low bidder is, *INLAND DREDGING COMPANY, L.L.C. at 30.31 % below the Government's Estimate.

TOTAL OPTION NO. 3

TRACI D. ROBICHEAUX

CONTRACTING OFFICER

DESCRIPTION QUANTITY

SCHEDULE NO. 1ITEM

0004 Dredging Bayport Channel, Sections 8 through 13

Sound Protection Measures

Site Management

NO.

TOTAL OPTION NO. 2

Standby for Docks

Standby for Docks

Dredging PHA Docks at Barbours Sections 16 and 17

Debris Removal

Re-Dredging Bayport Flare, Section 8

TOTAL OPTION NO. 4

OPTION NO. 2

I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.

1 JB 4,300,000.00 $4,300,000.00

1 JB $1,600,000.00 $1,600,000.00

1,022,300 CY $8.48 $8,669,104.00

1,833,300 CY $4.22 $7,736,526.00

1 JB $15,000.00 $15,000.00

1 JB 1,250,000.00 $1,250,000.00

$23,570,630.00

182,700 CY $5.75 $1,050,525.00

30 TON $15,000.00 $450,000.00

100 HOUR $3,550.00 $355,000.00

$1,855,525.00

169,600 CY $4.51 $764,896.00

$764,896.00

153,700 CY $13.16 $2,022,692.00

30 TON $15,000.00 $450,000.00

100 HOUR $3,550.00 $355,000.00

$2,827,692.00

423,000 CY $6.94 $2,935,620.00

1 JOB $950,000.00 $950,000.00

$3,885,620.00

$32,904,363.00

TOTAL OPTION NO. 2

Dredging Barbours Flare, Section 14

TOTAL OPTION NO. 1

OPTION NO. 3

0011 Dredging PHA Docks at Barbours Sections 16 and 17

OPTION NO. 4

Re-Dredging Bayport Flare, Section 8

TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

THRU 4

NO.

0009 Standby for Docks

Mobilization and Demobilization

DESCRIPTION

ITEM SCHEDULE NO. 1

Pipeline Management

TOTAL OPTION NO. 3

OPTION NO. 1

Dredging, HSC, Section 1 through 7

Debris Removal

QUANTITY

Project Title: FY 21 Pipeline Dredging Deep Draft Houston Ship Channel Bayport to Morgan’s with Bayport and Barbours Flare Harris, County, Texas Unrestricted Issuing Office: USAED-Galveston

0013 Standby for Docks

Dredging PHA Docks at Bayport Section 15

Debris Removal

Offeror 1: Crosby Dredging, LLC, 17771 Highway 3235 Galliano, Louisiana 70354-3578, United States Business Size: Large

Solicitation No.: W912HY21B0009 Date Issued: 16 Apr 2021 Date Opened: 27 May 2021

Dredging Bayport Channel, Sections 8 through 13

Sound Protection Measures

TOTAL OPTION NO. 4

OPTION NO. 2

Pipeline Management

TOTAL SCHEDULE NO. 1

0006 Site Management

ABSTRACT OF OFFERS (CONT'D) Page 2 of 6

1 JB 2,150,000.00 $2,150,000.00

1 JB $1,835,000.00 $1,835,000.00

1,022,300 CY $4.50 $4,600,350.00

1,833,300 CY $4.00 $7,333,200.00

1 JB $120,000.00 $120,000.00

1 JB 64,000.00 $64,000.00

$16,102,550.00

182,700 CY $4.95 $904,365.00

30 TON $1,000.00 $30,000.00

100 HOUR $2,150.00 $215,000.00

$1,149,365.00

169,600 CY $5.00 $848,000.00

$848,000.00

153,700 CY $10.90 $1,675,330.00

30 TON $1,000.00 $30,000.00

100 HOUR $2,150.00 $215,000.00

$1,920,330.00

423,000 CY $4.75 $2,009,250.00

1 JOB $185,000.00 $185,000.00

$2,194,250.00

$22,214,495.00

TOTAL OPTION NO. 2

DESCRIPTION

OPTION NO. 3

Dredging Barbours Flare, Section 14

OPTION NO. 2

TOTAL OPTION NO. 1

0002 Pipeline Management

0003 Dredging, HSC, Section 1 through 7

0004 Dredging Bayport Channel, Sections 8 through 13

0005 Sound Protection Measures

0006 Site Management

0001 Mobilization and Demobilization

SCHEDULE NO. 1

Business Size: Large

ITEM

NO. QUANTITY

ABSTRACT OF OFFERS (CONT'D) Page 3 of 6

Solicitation No.: W912HY21B0009 Date Issued: 16 Apr 2021 Date Opened: 27 May 2021

Issuing Office: USAED-Galveston Project Title: FY 21 Pipeline Dredging Deep Draft Houston Ship Channel Bayport to Morgan’s with Bayport and Barbours Flare Harris, County, Texas Unrestricted Procurement

Offeror 2: *INLAND DREDGING COMPANY, L.L.C. 103 N King AVE Dyersburg, Tennessee 38024-4609, United States

TOTAL SCHEDULE NO. 1

0007 Dredging PHA Docks at Bayport Section 15

Standby for Docks

TOTAL OPTION NO. 4

0012 Debris Removal

0013 Standby for Docks

TOTAL OPTION NO. 3

0008 Debris Removal

OPTION NO. 1

OPTION NO. 4

0011 Dredging PHA Docks at Barbours Sections 16 and 17

TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

THRU 4

0014 Re-Dredging Bayport Flare, Section 8

0015 Pipeline Management

1 JB 1,150,000.00 $1,150,000.00

1 JB $750,000.00 $750,000.00

1,022,300 CY $7.00 $7,156,100.00

1,833,300 CY $4.50 $8,249,850.00

1 JB $175,000.00 $175,000.00

1 JB 45,000.00 $45,000.00

$17,525,950.00

182,700 CY $6.50 $1,187,550.00

30 TON $1,600.00 $48,000.00

100 HOUR $2,000.00 $200,000.00

$1,435,550.00

169,600 CY $7.00 $1,187,200.00

$1,187,200.00

153,700 CY $13.00 $1,998,100.00

30 TON $1,600.00 $48,000.00

100 HOUR $2,000.00 $200,000.00

$2,246,100.00

423,000 CY $4.00 $1,692,000.00

1 JOB $150,000.00 $150,000.00

$1,842,000.00

$24,236,800.00

TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

THRU 4

0014 Re-Dredging Bayport Flare, Section 8

0015 Pipeline Management

TOTAL OPTION NO. 4

0012 Debris Removal

0013 Standby for Docks

TOTAL OPTION NO. 3

OPTION NO. 4

0010 Dredging Barbours Flare, Section 14

TOTAL OPTION NO. 2

OPTION NO. 3

0011 Dredging PHA Docks at Barbours Sections 16 and 17

0008 Debris Removal

0009 Standby for Docks

TOTAL OPTION NO. 1

OPTION NO. 2

Site Management

TOTAL SCHEDULE NO. 1

OPTION NO. 1

0007 Dredging PHA Docks at Bayport Section 15

Mobilization and Demobilization

0002 Pipeline Management

0003 Dredging, HSC, Section 1 through 7

0004 Dredging Bayport Channel, Sections 8 through 13

ABSTRACT OF OFFERS (CONT'D) Page 4 of 6

Solicitation No.: W912HY21B0009 Date Issued: 16 Apr 2021 Date Opened: 27 May 2021

Issuing Office: USAED-Galveston Project Title: FY 21 Pipeline Dredging Deep Draft Houston Ship Channel Bayport to Morgan’s with Bayport and Barbours Flare Harris, County, Texas Unrestricted Procurement

Offeror 3: ORION MARINE CONSTRUCTION, INC. 1715 N West Shore BLVD STE 875 Tampa, Florida 33607-3919, United States Business Size: Large

ITEM SCHEDULE NO. 1

NO. DESCRIPTION QUANTITY

0005 Sound Protection Measures

1 JB 5,536,600.00 $5,536,600.00

1 JB $500,000.00 $500,000.00

1,022,300 CY $8.30 $8,485,090.00

1,833,300 CY $5.30 $9,716,490.00

1 JB $30,000.00 $30,000.00

1 JB 15,165.00 $15,165.00

$24,283,345.00

182,700 CY $7.85 $1,434,195.00

30 TON $3,600.00 $108,000.00

100 HOUR $6,675.00 $667,500.00

$2,209,695.00

169,600 CY $7.80 $1,322,880.00

$1,322,880.00

153,700 CY $16.90 $2,597,530.00

30 TON $3,600.00 $108,000.00

100 HOUR $6,675.00 $667,500.00

$3,373,030.00

423,000 CY $8.20 $3,468,600.00

1 JOB $42,450.00 $42,450.00

$3,511,050.00

$34,700,000.00

TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

THRU 4

0014 Re-Dredging Bayport Flare, Section 8

0015 Pipeline Management

TOTAL OPTION NO. 4

0012 Debris Removal

0013 Standby for Docks

TOTAL OPTION NO. 3

OPTION NO. 4

0010 Dredging Barbours Flare, Section 14

TOTAL OPTION NO. 2

OPTION NO. 3

0011 Dredging PHA Docks at Barbours Sections 16 and 17

0008 Debris Removal

0009 Standby for Docks

TOTAL OPTION NO. 1

OPTION NO. 2

0006 Site Management

TOTAL SCHEDULE NO. 1

OPTION NO. 1

0007 Dredging PHA Docks at Bayport Section 15

0001 Mobilization and Demobilization

0002 Pipeline Management

0003 Dredging, HSC, Section 1 through 7

0004 Dredging Bayport Channel, Sections 8 through 13

0005 Sound Protection Measures

Issuing Office: USAED-Galveston Project Title: FY 21 Pipeline Dredging Deep Draft Houston Ship Channel Bayport to Morgan’s with Bayport and Barbours Flare Harris, County, Texas Unrestricted Procurement

Offeror 4: GREAT LAKES DREDGE & DOCK COMPANY, LLC 9811 Katy Fwy STE 1200 Houston, Texas 77024-1273, United States Business Size: Large

ITEM SCHEDULE NO. 1

NO. DESCRIPTION QUANTITY

ABSTRACT OF OFFERS (CONT'D) Page 5 of 6

Solicitation No.: W912HY21B0009 Date Issued: 16 Apr 2021 Date Opened: 27 May 2021

1 JB 4,250,000.00 $4,250,000.00

1 JB $1,750,000.00 $1,750,000.00

1,022,300 CY $8.00 $8,178,400.00

1,833,300 CY $6.75 $12,374,775.00

1 JB $150,000.00 $150,000.00

1 JB 150,000.00 $150,000.00

$26,853,175.00

182,700 CY $9.00 $1,644,300.00

30 TON $2,500.00 $75,000.00

100 HOUR $5,000.00 $500,000.00

$2,219,300.00

169,600 CY $6.00 $1,017,600.00

$1,017,600.00

153,700 CY $12.00 $1,844,400.00

30 TON $2,500.00 $75,000.00

100 HOUR $5,000.00 $500,000.00

$2,419,400.00

423,000 CY $5.00 $2,115,000.00

1 JOB $10,000.00 $10,000.00

$2,125,000.00

$34,634,475.00TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

ABSTRACT OF OFFERS Page 6 of 6

Project Title: FY 21 Pipeline Dredging Deep Draft Houston Ship Channel Bayport to Morgan’s with Bayport and Barbours Flare Harris, County, Texas Unrestricted

Offeror 5: Weeks Marine, Inc. 304 Gaille Drive Covington, LA 70433 Business Size: Large

QUANTITY

0001 Mobilization and Demobilization

0006 Site Management

OPTION NO. 4

Re-Dredging Bayport Flare, Section 8 Pipeline Management

TOTAL OPTION NO. 4

OPTION NO. 3

0011 Dredging PHA Docks at Barbours Sections 16 and 17 0012 Debris Removal 0013 Standby for Docks

TOTAL OPTION NO. 3

OPTION NO. 2

0010 Dredging Barbours Flare, Section 14

TOTAL OPTION NO. 2

OPTION NO. 1

0007 Dredging PHA Docks at Bayport Section 15

0009 Standby for Docks

TOTAL OPTION NO. 1

0008 Debris Removal

0003 Dredging, HSC, Section 1 through 7 0004 Dredging Bayport Channel, Sections 8 through 13

TOTAL SCHEDULE NO. 1

0005 Sound Protection Measures

DESCRIPTION

Pipeline Management

ITEM SCHEDULE NO. 1

NO.

Solicitation No.: W912HY21B0009 Date Issued: 16 Apr 2021 Date Opened: 27 May 2021 Issuing Office: USAED-Galveston

2021-05-28T08:39:17-0500
ROBICHEAUX.TRACI.D.1260353990

File details come from the government source that posted it. Updated .