Amend-0001_W912HY21B0001-Spec-Final-Signed.pdf

PDF 5 MB Posted

Attached to
Corpus Christi Ship Channel, Texas, Channel Improvement Project, Upper Bay Reach in Nueces County, Texas, Pipeline Dredging.
Solicitation number
W912HY21B0001
Issued by

About this file

This is a solicitation for pipeline dredging services for the Corpus Christi Ship Channel in Texas. Bids are due on July 20, 2021 for dredging an estimated 14.3 million cubic yards of material from the ship channel. The work includes dredging to deepen and widen sections of the channel to depths between 47 to 54 feet, as well as dredging barge lanes. The solicitation includes pricing schedules for base work and eleven options that could be awarded. The total value of the contract is estimated between $100-250 million. The Army Corps of Engineers is the contracting agency and work must be completed within 500 calendar days of award.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL FOR

DEPARTMENT OF THE ARMY

GALVESTON DISTRICT, CORPS OF ENGINEERS

P.O. BOX 1229

GALVESTON, TEXAS

"INCREASE PROFIT - SUBMIT VECP'S"

SWG FILE NO.: CCSC 803-360 SOLICITATION NO.: W912HY21B0001

PROJECT TABLE OF CONTENTS

DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS

00 00 00 SOLICITATION, OFFER AND AWARD, SF-1442

00 11 00.00 45 BID SCHEDULE

00 21 00 INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

00 31 32.13 45 SUBSURFACE DRILLING AND SAMPLING INFORMATION

00 45 00 REPRESENTATION AND CERTIFICATIONS

00 72 00 CONTRACT CLAUSES

00 73 00.01 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD

00 73 46 WAGE RATES

00 73 53.00 45 SECURITY PROCEDURES

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 00 10 SUMMARY OF WORK

01 10 00.01 45 NON-REGULATED SPECIAL CONTRACT REQUIREMENTS

01 22 00.10 MEASUREMENT AND PAYMENT

01 32 01.00 45 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26.01 45 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)

01 45 01.00 QUALITY CONTROL

01 50 00.00 45 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20.00 45 ENVIRONMENTAL PROTECTION

01 58 13.01 45 PROJECT IDENTIFICATION

01 58 13.04 45 BULLETIN BOARD

01 78 00.00 45 CLOSEOUT SUBMITTALS

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 21 00.00 45 CONDITION SURVEY AND RECORD DRAWINGS

02 21 00.10 45 CONSTRUCTION SURVEYS

02 30 00 SUBSURFACE INVESTIGATION

02 41 00.10 45 DEMOLITION OF EXISTING DROP-OUTLET STRUCTURES

DI VI SI ON 03 - CONCRETE

03 31 00.00 45 CONCRETE FOR MINOR STRUCTURES

DI VI SI ON 05 - METALS

05 05 23.00 45 STRUCTURAL WELDING

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 10 00.00 35 PLASTIC LUMBER

DI VI SI ON 09 - FI NI SHES

09 97 02 PAINTING: HYDRAULIC STRUCTURES

DI VI SI ON 31 - EARTHWORK

31 11 00.10 45 CLEARING, GRUBBING, AND REMOVAL OF DEBRIS

31 14 13.23 45 STRIPPING

31 23 16.18 45 EXCAVATION, FILLING, AND BACKFILLING FOR STRUCTURE

PROJECT TABLE OF CONTENTS Page 1

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 92 00.00 45 TURF

DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON

35 20 23.16 45 PIPELINE DREDGING

35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM PIPELINE

HYDRAULIC DREDGE

35 20 30.00 45 DROP-OUTLET STRUCTURE

35 41 00.01 45 EMBANKMENT CONSTRUCTION

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 2

W45VAK01292342

This requirement is an Unrestricted Procurement for Corpus Christi Ship Channel, Texas, Upper Bay Reach in Nueces County, Texas, Channel Improvement Project.

Per AFARS 5132.702 (a)(ii)(B) “Funds are not presently available for this acquisition. No contract aw ard w ill be made until appropriated funds are made available."

Disclosure of Magnitude of Construciton Projects (DFARS 236.204) - The estimated price range of the proposed construction is between $100,000,000.00 and $250,000,000.00.

PRE-BID TELECONFERENCE: June 30, 2021 @ 1:00 PM (CDT).

Weblink: https://usace1.w ebex.com/meet/carlos.d.tate **Best w ay to call-in is to use the “Call me at: “ w ebex Option** Audio Conference:

If only joining by phone, below is the conference number information:

+1-844-800-2712 US Toll Free Access code: 199 394 9507 Meeting Number, enter if asked: 199 394 9507

X

LUCILLE R SMITH 409 766 3845

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

NEGOTIATED

16-Jun-2021

(RFP)

(IFB)

CALL:

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________500 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________00 73 00.01 45

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________0 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________20 Jul 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

US ARMY CORPS OF ENGINEERS

2000 FORT POINT ROAD

P.O. BOX 1229

GALVESTON TX 77553-1229

W912HY

PAGE OF PAGES

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

014340

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: 409 766 3850 TEL: FAX:

W912HY21B0001 5 OF 458

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

U.S. Army Corps of Engineers Galveston District Office PO Box 1229 Galveston, Texas 77553-1229

USAED, Finance Center

ATTN: CEFC-AO-P

5722 Integrity Drive Millington, TN 38054-5000

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 11 00.00 45

BID SCHEDULE

PART 1 GENERAL

1.1 BID SCHEDULE

1.1.1 Schedule No. 1

1.1.2 Option No. 1

1.1.3 Option No. 2

1.1.4 Option No. 3

1.1.5 Option No. 4

1.1.6 Option No. 5

1.1.7 Option No. 6

1.1.8 Option No. 7

1.1.9 Option No. 8

1.1.10 Option No. 9

1.1.11 Option No. 10

1.1.12 Option No. 11

1.2 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

-- End of Section Table of Contents --

DOCUMENT 00 11 00.00 45 Page 1

THIS PAGE INTENTIONALLY LEFT BLANK

DOCUMENT 00 11 00.00 45 Page 2

SECTION 00 11 00.00 45

BID SCHEDULE

PART 1 GENERAL

1.1 BID SCHEDULE

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.1 Schedule No. 1

Item No.

Description Estimated Quantity Unit Unit Price Estimated Amount

SCHEDULE NO. 1

0001 Mobilization and Demobilization - Dredging Equipment

1 JOB SUM $___________

0002 Pre-Dredging Hazard Survey 1 JOB SUM $___________

0003 Dredging Pipeline Management 1 JOB SUM $___________

0004 Dredging - Maintenance, Current Authorized -47Ft Channel Template (Sections No. 1 thru 22, Section No. 4A, and Section No. 22A)

1,592,510 CY $_________ $___________

0005 Dredging - New Work, New Work Authorized -54Ft Channel Template (Sections No. 1 thru 22 and 4A)

11,735,330 CY $_________ $___________

0006 Dredging - Barge Lanes - Green Side, New Work (Section No. 30 thru 38)

679,360

CY $_________ $_________

0007 Dredging - Barge Lanes - Red Side, New Work (Section No. 39 thru 49)

382,810 CY $_________ $_________

0008 Pipeline Profile 5 Ea

DOCUMENT 00 11 00.00 45 Page 3

Item No.

Description Estimated Quantity Unit Unit Price Estimated Amount

SCHEDULE NO. 1

TOTAL SCHEDULE NO. 1 $___________

NOTE: Completion time stated in SECTION 00 73 00.01 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work.

DOCUMENT 00 11 00.00 45 Page 4

BID SCHEDULE (CONT'D)

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.2 Option No. 1

Item No.

Description Estimated Quantity Unit Unit Price Estimated Amount

OPTION NO. 1

0009 Dredging Pipeline Management 1 JOB SUM $___________

0010 Dredging - New Work, New Work Authorized -54Ft Channel Template (Section No. 4B)

257,690

CY $_________ $___________

TOTAL OPTION NO. 1 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1 $___________

NOTE FOR OPTI ON NO. 1: The Gover nment may exer ci se Opt i on No. 1 by wr i t t en not i ce t o t he Cont r act or no l at er t han 60 days pr i or t o t he compl et i on of al l ot her dr edgi ng wor k. Addi t i onal t i me of 12 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 1.

DOCUMENT 00 11 00.00 45 Page 5

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.3 Option No. 2

Item No. Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 2

0011 Dredging Pipeline Management 1 JOB SUM $___________

0012 Dredging - New Work, New Work Authorized -54Ft Channel Template (Section No. 22B)

100,640 CY $_________ $___________

TOTAL OPTION NO. 2 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NO. 1 AND 2 $___________

NOTE FOR OPTI ON NO. 2: The Gover nment may exer ci se Opt i on No. 2 by wr i t t en not i ce t o t he Cont r act or no l at er t han 60 days pr i or t o t he compl et i on of al l ot her dr edgi ng wor k. Addi t i onal t i me of 7 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 2.

DOCUMENT 00 11 00.00 45 Page 6

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.4 Option No. 3

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 3

0013 Dredging Pipeline Management 1 JOB SUM $___________

0014 Dredging - Maintenance, Current Authorized -47Ft Channel Template (Sections No. 23 thru 27, Section No. 26A, Section No. 26B, and Section No. 27A)

45,990

CY $_________ $___________

0015 Dredging - New Work, New Work Authorized -54Ft Channel Template (Sections No. 23 thru 27)

1,958,770

CY $_________ $___________

0016 Dredge Standby (Section 23 thru 27) 50 HR $_________ $___________

TOTAL OPTION NO. 3 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NO. 1,2, AND 3 $___________

NOTE FOR OPTI ON NO. 3: The Gover nment may exer ci se Opt i on No. 3 by wr i t t en not i ce t o t he Cont r act or no l at er t han 60 days pr i or t o t he compl et i on of al l ot her dr edgi ng wor k. Addi t i onal t i me of 80 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 3. Thi s addi t i onal t i me wi l l not ext end t he al l owed cal endar days f or compl et i on of Schedul e No. 1 i ndi cat ed i n SECTI ON 00 73 00. 01 45 SPECI AL CONTRACT

REQUI REMENTS, STANDARD.

DOCUMENT 00 11 00.00 45 Page 7

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.5 Option No. 4

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 4

0017 Dredging Pipeline Management 1 JOB SUM $___________

0018 Dredging - New Work, New Work Authorized -54Ft Channel Template (Section No. 26C)

59,870 CY $_________ $___________

TOTAL OPTION NO. 4 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NO. 1,2,3, AND 4 $___________

NOTE FOR OPTI ON NO. 4: The Gover nment may exer ci se Opt i on No. 4 by wr i t t en not i ce t o t he Cont r act or no l at er t han 60 days pr i or t o t he compl et i on of al l ot her dr edgi ng wor k. Addi t i onal t i me of 6 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 4. Thi s addi t i onal t i me wi l l not ext end t he al l owed cal endar days f or compl et i on of Schedul e No. 1 i ndi cat ed i n SECTI ON 00 73 00. 01 45 SPECI AL CONTRACT

DOCUMENT 00 11 00.00 45 Page 8

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.6 Option No. 5

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 5

0019 Dredging Pipeline Management 1 JOB SUM $___________

0020 Dredging - New Work, New Work Authorized -54Ft Channel Template (Section No. 26D)

83,560

CY $_________ $___________

TOTAL OPTION NO. 5 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NO. 1,2,3,4, AND 5 $___________

NOTE FOR OPTI ON NO. 5: The Gover nment may exer ci se Opt i on No. 5 by wr i t t en not i ce t o t he Cont r act or no l at er t han 60 days pr i or t o t he compl et i on of al l ot her dr edgi ng wor k. Addi t i onal t i me of 6 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 7. Thi s addi t i onal t i me wi l l not ext end t he al l owed cal endar days f or compl et i on of Schedul e No. 1 i ndi cat ed i n SECTI ON 00 73 00. 01 45 SPECI AL CONTRACT

DOCUMENT 00 11 00.00 45 Page 9

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.7 Option No. 6

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 6

0021 Dredging Pipeline Management 1 JOB SUM $___________

0022 Dredging - New Work, New Work Authorized -54Ft Channel Template (Section No. 27B)

62,920 CY $_________ $___________

TOTAL OPTION NO. 6 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NO. 1,2,3,4,5, AND 6 $___________

NOTE FOR OPTI ON NO. 6: The Gover nment may exer ci se Opt i on No. 6 by wr i t t en not i ce t o t he Cont r act or no l at er t han 60 days pr i or t o t he compl et i on of al l ot her dr edgi ng wor k. Addi t i onal t i me of 6 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 6. Thi s addi t i onal t i me wi l l not ext end t he al l owed cal endar days f or compl et i on of Schedul e No. 1 i ndi cat ed i n SECTI ON 00 73 00. 01 45 SPECI AL CONTRACT

DOCUMENT 00 11 00.00 45 Page 10

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.8 Option No. 7

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 7

0023 Dredging Pipeline Management 1 JOB SUM $___________

0024 Dredging - Maintenance, Current Authorized -47Ft Channel Template (Sections No. 28 and 29)

73,130 CY $_________ $___________

0025 Dredging - New Work, New Work Authorized -54Ft Channel Template (Sections No. 28 and 29)

1,085,850 CY $_________ $___________

0026 Dredge Standby (Section 28 and 29) 50 HR $_________ $___________

TOTAL OPTION NO. 7 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NO. 1,2,3,4,5,6, AND 7 $___________

NOTE FOR OPTI ON NO. 7: The Gover nment may exer ci se Opt i on No. 7 by wr i t t en not i ce t o t he Cont r act or no l at er t han 60 days pr i or t o t he compl et i on of al l ot her dr edgi ng wor k. Addi t i onal t i me of 47 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 7. Thi s addi t i onal t i me wi l l not ext end t he al l owed cal endar days f or compl et i on of Schedul e No. 1 i ndi cat ed i n SECTI ON 00 73 00. 01 45 SPECI AL CONTRACT REQUI REMENTS, STANDARD or t he al l owed cal endar days f or compl et i on of any ot her dr egdi ng opt i on above t hat has been exer ci sed.

DOCUMENT 00 11 00.00 45 Page 11

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.9 Option No. 8

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 8

0027 Mobilization and Demobilization PA 1-2 1 JOB SUM $___________

0028 Mobilization and Demobilization PA 3A 1 JOB SUM $___________

0029 Final As-Built Drawings PA 1-2 1 JOB SUM $___________

0030 Final As-Built Drawings PA 3A 1 JOB SUM $___________

0031 PA 1-2 Existing Drop-Outlet Structure Modification

1 JOB SUM $___________

0032 PA 3A Existing Drop-Outlet Structure Modification

1 JOB SUM $___________

0033 PA 1-2 Training Dike Weirs 1 JOB SUM $___________

0034 PA 1-2 Turfing

1 JOB SUM $___________

0035 PA 3A Turfing

1 JOB SUM $___________

0036 Stripping at PA 1-2

1 JOB SUM $___________

0037 Stripping at PA 3A

1 JOB SUM $___________

0038 PA 1-2 Site Management

1 JOB SUM $___________

DOCUMENT 00 11 00.00 45 Page 12

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 8

0039 PA 3A Site Management

1 JOB SUM $___________

0040 PA 1-2 Final Surveys

1 JOB SUM $___________

0041 PA 3A Final Surveys

1 JOB SUM $___________

0042 PA 1-2 Dike Raise

534,878 CY $_________ $___________

0043 PA 3A Dike Raise

376,449 CY $_________ $___________

TOTAL OPTION NO. 8 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NO. 1,2,3,4,5,6,7, AND 8 $___________

NOTE FOR OPTI ON NO. 8: The Gover nment may exer ci se Opt i on No. 8 by wr i t t en not i ce t o t he Cont r act or no l at er t han 30 days af t er t he Cont r act or r ecei ves t he Not i ce t o Pr oceed. No addi t i onal t i me wi l l be added t o t hi s cont r act f or compl et i on of Opt i on No. 8.

DOCUMENT 00 11 00.00 45 Page 13

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.10 Option No. 9

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 9

0044 PA 1-2 Additional Turfing 1 JOB SUM $___________

0045 PA 1-2 Additional Stripping 1 JOB SUM $___________

0046 PA 1-2 3 Foot Additional Dike Raise

(PCCA)

365,749 CY $_________ $___________

TOTAL OPTION NO. 9 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NO. 1,2,3,4,5,6,7,8, AND 9 $___________

NOTE FOR OPTI ON NO. 9: The Gover nment may exer ci se Opt i on No. 9 by wr i t t en not i ce t o t he Cont r act or no l at er t han 30 days af t er t he Cont r act or r ecei ves t he Not i ce t o Pr oceed. Addi t i onal t i me wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 9 equal t o t he number of days bet ween t i me of Not i ce t o Pr oceed ( NTP) and exer ci s i ng t he Opt i on.

Thi s addi t i onal t i me wi l l not ext end t he al l owed cal endar days f or compl et i on of Schedul e No. 1 i ndi cat ed i n SECTI ON 00 73 00. 01 45 SPECI AL

CONTRACT REQUI REMENTS, STANDARD.

DOCUMENT 00 11 00.00 45 Page 14

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.11 Option No. 10

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 10

0047 PA 1-2 Additional Turfing 1 JOB SUM $___________

0048 PA 1-2 Additional Stripping 1 JOB SUM $___________

0049 PA 1-2 1 Foot Additional Dike Raise (O&M)

138,476 CY $_________ $___________

TOTAL OPTION NO. 10 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NO. 1,2,3,4,5,6,7,8,9, AND 10 $___________

NOTE FOR OPTI ON NO. 10: The Gover nment may exer ci se Opt i on No. 10 by wr i t t en not i ce t o t he Cont r act or no l at er t han 30 days af t er t he Cont r act or r ecei ves t he Not i ce t o Pr oceed. Addi t i onal t i me of 98 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 10. Thi s addi t i onal t i me wi l l not ext end t he al l owed cal endar days f or compl et i on of Schedul e No. 1 i ndi cat ed i n SECTI ON 00 73 00. 01 45 SPECI AL CONTRACT

DOCUMENT 00 11 00.00 45 Page 15

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.12 Option No. 11

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 11

0050 Mobilization and Demobilization PA 3B 1 JOB SUM

0051 Final As-Built Drawings PA 3B 1 JOB SUM

0052 PA 3B Existing Drop-Outlet Structure Modification

1 JOB SUM $___________

0053 PA 3B Turfing

1 JOB JOB $___________

0054 Stripping at PA 3B

1 JOB SUM $___________

0055 PA 3B Site Management

1 JOB SUM $___________

0056 PA 3B Final Surveys

1 JOB SUM $___________

0057 PA 3B Dike Raise

432,363 CY $_________ $___________

TOTAL OPTION NO. 11 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NO. 1,2,3,4,5,6,7,8,9,10, AND 11

NOTE FOR OPTI ON NO. 11: The Gover nment may exer ci se Opt i on No. 11 by wr i t t en not i ce t o t he Cont r act or no l at er t han 240 days af t er t he Cont r act or r ecei ves t he Not i ce t o Pr oceed. No addi t i onal t i me wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 11.

DOCUMENT 00 11 00.00 45 Page 16

(TO BE ATTACHED TO STANDARD FORM 1442)

1.2 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

-- End of Document --

DOCUMENT 00 11 00.00 45 Page 17

DOCUMENT 00 11 00.00 45 Page 18

Document 00 21 00 - Page 1

Section 00 21 00 - Instructions, Conditions and Notices to Offerors

1.1 ESTIMATED CONSTRUCTION PRICE RANGE (FAR 36.204)

The estimated price range of the proposed construction is between $100,000,000 and $250,000,000.

1.2 AVAILABILITY OF PLANS AND SPECIFICATIONS ON SAM.GOV WEBSITE (FAR

5.102(a)(1))

After solicitation issuance, contractors may register to be placed on the Interested Vendors List, view and/or download this solicitation and all amendments at https://sam.gov/content/home.

Plans and specifications will not be available in paper format or on compact disc. It is the offeror’s responsibility to monitor the Beta Sam website daily (using the above link) for amendments to the solicitation. You must be registered in the System For Award Management (SAM) to receive a government contract award. The website for SAM https://sam.gov/content/home.

1.3 TECHNICAL INFORMATION DREDGING (FAR 14.211)

(a) For technical information regarding the plans and specifications submit questions in PROJNET, see paragraph 1.9 of this section for details.

(b) The Contractor [ ] shall [X] shall not be permitted to use self-propelled hopper dredges to perform the work specified herein.

1.4 PREAWARD INFORMATION DREDGING (FAR 9.105-1)

The apparent low bidder shall submit within (3) working days after Bid Opening, the following information:

(a) A statement as to whether he is now or ever has been engaged in performing dredging of [X] deep or [ ] shallow draft channels.

(b) A list of key personnel available for the current project and their qualifications.

(c) A copy of the bidder's latest financial statement, including the names of banks or other financial institutions with which the bidder conducts business. If the financial statement is more than 60 days old, a certificate should be attached stating that the financial condition is substantially the same, or if not the same, the changes that have taken place. Such statement will be treated as confidential.

(d) A list of present commitments, including the dollar value thereof, name of office under which the work is being performed, the scheduled completion date of each, days ahead or behind schedule and the name of the dredge(s) to be used on the job.

(e) Name and location of the firm's dredging plant to perform the work under this contract, the date this plant will commence work, and the plants capability to perform the work as required by the specifications.

(f) A preliminary schedule showing anticipated dates for start of work, based upon availability of contractor resources, and the plan for completing work within the contract performance period. For dredging contracts, this includes production rates for proposed dredging equipment together with an analysis showing how work will be accomplished within the contract performance period.

(g) If bidder is a Large Business, a Sub-Contracting Plan, if required, must be submitted within (3) working days after Bid Opening.

https://sam.gov/ https://sam.gov/content/home

Document 00 21 00 - Page 2

1.5 DISPOSAL OF EXCAVATED MATERIAL

The following owners in the vicinity of the work to be accomplished under this Invitation for Bids are known to desire fill material:

NAME ADDRESS

If any of the areas owned by the above-listed owners are proposed to be utilized by the Contractor in the performance of the work, the provision for use of alternate areas DREDGING: PLACEMENT OF EXCAVATED MATERIAL of the specifications will be applicable.

1.6 BIDDER'S QUALIFICATIONS (FAR 9.105-1)

Before a bid is considered for award, the bidder may be requested by the Government to submit a statement regarding his previous experience in performing comparable work, his business and technical organization, financial resources, and plant available to be used in performing the work.

1.7 NOTICE TO BIDDERS (FAR 52.214-18)

All information required by the terms of the solicitation must be furnished.

MISTAKES OR OMISSIONS CAN BE COSTLY. Important items for you to check are included in but not limited to, those listed below. This checklist is furnished only to assist you in submitting a proper offer. Check as you read.

Have you acknowledged all amendments?

Have you completed SECTION 00 45 00, REPRESENTATIONS &

CERTIFICATIONS portion of the solicitation package to include 52.204-24 and 52.204-26?

Is your offer properly signed?

If a bid guarantee is required, is it included with your offer?

(A late bid guarantee is treated the same as a late offer).

Is your bid guarantee in the proper amount? Bid guarantee shall be in the amount of 20 percent of the amount of the offer, or $3 million, whichever is less.

If your bid guarantee is in the form of a bid bond, is the bond properly signed by both the bidder and surety and are all required seals affixed?

Is the name in which you submitted the offer the same as your bid bond?

If required have you entered a unit price for each item? (The solicitation will specifically state when this is necessary).

Are decimals in unit prices in the proper places? Are your figures legible?

Are the extensions of your unit prices, and your total offer price correct?

Are all erasures or corrections initialed by the person signing the offer?

I have not restricted my offer by altering the provisions of the solicitation.

REMINDER TO BIDDERS

REMINDER #1 - Acknowledge all Amendments on the reverse side of SF 1442, Item 19, Solicitation, Offer, and Award.

REMINDER #2 - The Contracting Officer signing this contract is the Primary Contracting Officer. However, any Contracting Officer assigned to the Galveston

Document 00 21 00 - Page 3

District may take formal action. See Section entitled "Specific Project Requirements".

1.8 SPECIAL INSTRUCTIONS PERTAINING TO ELECTRONIC BID SUBMISSION: (FAR

14.302 and 14.304)

Bids and a copy of the SF24 Bid Bond must be submitted via email to SWG-CT- Execution-Proposals@usace.army.mil , not later than the response date and time indicated in the solicitation. Identify the Solicitation Number W912HY21B0001 in subject line of the emai1.

The bid opening will be held by teleconference. Teleconference No. 844-800- 2712, Access code 199 872 8430.

1.9 BIDDER INQUIRY – PROJNET (FAR 14.211)

1. Prospective Offerors should submit questions concerning this solicitation via Bidder Inquiry in ProjNet at www.projnet.org/projnet .

A. To submit and review bid inquiry items, bidders will need to be a current registered user or self register into the system. To self-register, go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your email address, and then click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

***Please Note: Offerors shall only submit one question per inquiry.

Inquiries containing multiple questions may be rejected.

B. From this page, you may view all bidder inquiries or add inquiry.

C. Offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

D. The Solicitation Number is: W912HY21B0001 The Bidder Inquiry Key is: I8N4ED-ZZQ45S

2. The Bidder Inquiry System will be unavailable for new inquires fifteen

(15) calendar days prior to offer submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary.

3. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

4. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

1.10 CONSTRUCTION WAGE RATE REQUIREMENTS (FAR 52.222-6)

Paragraph entitled CONSTRUCTION WAGE RATE REQUIREMENTS of (CONTRACT CLAUSES - Section 00 72 00, FAR 52.222-6) is applicable to this solicitation. Wage mailto:SWG-CT-Execution-Proposals@usace.army.mil mailto:SWG-CT-Execution-Proposals@usace.army.mil http://www.projnet.org/projnet

Document 00 21 00 - Page 4

Rates will be incorporated by amendment, if they are not included in this

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-22 Alternative Line Item Proposal JAN 2017 52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids DEC 2016 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and

Withdrawals of Bids

NOV 1999

52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-

Construction

AUG 1996

52.214-34 Submission Of Offers In The English Language

APR 1991

52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.217-5 Evaluation Of Options JUL 1990 52.232-13 Notice Of Progress Payments APR 1984 52.232-14 Notice Of Availability Of Progress

Payments Exclusively For Small Business Concerns

APR 1984

52.232-38 Submission of Electronic Funds Transfer Information with Offer

JUL 2013

CLAUSES INCORPORATED BY FULL TEXT

52.214-15 PERIOD FOR ACCEPTANCE OF BIDS (APR 1984)

In compliance with the solicitation, the bidder agrees, if this bid is accepted within 60 calendar days from the date specified in the solicitation for receipt of bids, to furnish any or all items upon which prices are bid at the price set opposite each item, delivered at the designated point(s), within the time specified in the Schedule.

(End of clause)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed Price contract resulting from this solicitation.

(End of provision)

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK

(MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph

Document 00 21 00 - Page 5

(a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of provision)

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

Nueces County – 41.7%

6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

Document 00 21 00 - Page 6

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is SMSA Nueces County, Texas.

(End of provision)

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from the Contracting Officer, US Army Corps of Engineers, Galveston District, PO Box 1229, Galveston, Texas 77553-1229, submitting the protest at SWG-CT-protests@usace.army.mil .

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Name: Mr. Andrew Smith, Resident Engineer Address: US Army Corps of Engineers, Corpus Christi Resident Office, 1920 N. Chaparral, Corpus Christi, Texas 78401-1114 Telephone: 361-884-3385 Ext. 2216

(End of provision)

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

mailto:SWG-CT-protests@usace.army.mil mailto:SWG-CT-protests@usace.army.mil

Document 00 21 00 - Page 7

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text.

Upon request, the Contracting Officer will make their full text available.

The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.

In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/content/regulations

(End of provision)

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Defense Acquisition Regulation (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

https://www.acquisition.gov/content/regulations

Document 00 21 00 - Page 8

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DOCUMENT 00 31 32.13 45

SUBSURFACE DRILLING AND SAMPLING INFORMATION

PART 1 GENERAL

1.1 SUMMARY

1.2 GEOTECHNICAL DATA

-- End of Section Table of Contents --

DOCUMENT 00 31 32.13 45 Page 1

DOCUMENT 00 31 32.13 45 Page 2

DOCUMENT 00 31 32.13 45

SUBSURFACE DRILLING AND SAMPLING INFORMATION

PART 1 GENERAL

1.1 SUMMARY

This section provides subsurface drilling and sampling information for the project.

1.2 GEOTECHNICAL DATA

The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made. See Appendices to the specification I to VII for Geotechnical investigation data.

-- End of Document --

DOCUMENT 00 31 32.13 45 Page 3

DOCUMENT 00 31 32.13 45 Page 4

Document 00 45 00 - Page 1

Section 00 45 00 - Representations and Certifications

52.204-16 Commercial and Government Entity Code

Reporting

AUG 2020

52.204-19 Incorporation by Reference of Representations and Certifications.

DEC 2014

252.247-7022 Representation of Extent of Transportation by Sea.

JUN 2019

CLAUSES INCORPORATED BY FULL TEXT

52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

(a) The offeror certifies that --

(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –

(i) Those prices,

(ii) The intention to submit an offer, or

(iii) The methods of factors used to calculate the prices offered:

(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and

(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.

(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --

(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or

(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision ___________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);

Document 00 45 00 - Page 2

(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and

(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.

(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.

(End of Provision)

52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.

(2) The small business size standard is $30,000,000.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

( ) Paragraph (d) applies.

( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

Document 00 45 00 - Page 3

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation.

This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.204-26, Covered Telecommunications Equipment or Services-- Representation. This provision applies to all solicitations.

(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations--Representation.

(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(x) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

Document 00 45 00 - Page 4

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.

(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements.

This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA- designated items.

(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xxi) 52.225-4, Buy American--Free Trade Agreements--Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225- 3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $83,099, the provision with its Alternate II applies.

Document 00 45 00 - Page 5

(D) If the acquisition value is $83,099 or more but is less than $100,000, the provision with its Alternate III applies.

(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--Certification. This provision applies to all solicitations.

(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certification. This provision applies to all solicitations.

(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[Contracting Officer check as appropriate.]

X (i) 52.204-17, Ownership or Control of Offeror.

X (ii) 52.204-20, Predecessor of Offeror.

(iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

(iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Certification.

(v) 52.222-52 Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Certification.

(vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).

(vii) 52.227-6, Royalty Information.

(A) Basic.

(B) Alternate I.

(viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov.