About this file

This is an amendment to a solicitation for dredging and related shore protection work for the Corpus Christi Ship Channel in Nueces County, Texas. The amendment revises the bid schedule to include twelve options for additional work including maintenance and new work dredging, dike construction, armoring, and demolition. Bids are due by January 27, 2020 to the US Army Corps of Engineers Galveston District. The selected contractor will have up to two years to complete the base work and optional items if exercised, awarded individually or together, and as funding allows. Pricing is solicited for dredging and construction quantities by line item.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W45VAK91002193 010383-1

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Unrestricted Procurement, Request f or Proposal, Low est Price Technically Acceptable for Corpus Christi Ship Channel, Texas, Low er Bay Reach in Nueces County, Texas, Channel Improvement Project in w hich proposals are due 27 Jan 20 @ 2:00 PM (CST) is hereby amended as follow s:

Continued on Page 2.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 20

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HY20R0001

X 9B. DATED (SEE ITEM 11)

12-Dec-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Jan-2020

CODE

US ARMY CORPS OF ENGINEERS

2000 FORT POINT ROAD

P.O. BOX 1229

GALVESTON TX 77553-1229

W912HY 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HY20R0001

A0007-2

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

1. The specifications for Solicitation No. W912HY20R0001, CORPUS CHRISTI SHIP CHANNEL, TEXAS LOWER BAY REACH IN NUECES COUNTY, TEXAS, are hereby amended as follows:

a) Specifications.

(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45 entitled BID SCHEDULE supersedes that issued with this Solicitation.

b) Drawings.

(1) None

c) Attached Files.

(1) None

2. This amendment shall be attached to and become a part of the solicitation.

1 Encl:

1. 00 11 00.00 45, BID SCHEDULE

SWG FILE NO.: NUECES 803-356 SOLICITATION NO.: W912HY20R0001

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 11 00.00 45

BID SCHEDULE AMENDMENT NO. 0007

PART 1 GENERAL

1.1 BID SCHEDULE

1.1.1 Schedule No. 1

1.2 Option No. 1 (AM#7)

1.3 Option No. 2 (AM#7)

1.4 Option No. 3 (AM#7)

1.5 Option No. 4 (AM#7)

1.6 Option No. 5 (AM#7)

1.7 Option No. 6 (AM#7)

1.8 Option No. 7 (AM#7)

1.9 Option No. 8 (AM#7)

1.10 Option No. 9

1.11 Option No. 10

1.12 Option No. 11

1.13 Option No. 12

1.14 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

-- End of Section Table of Contents --

DOCUMENT 00 11 00.00 45 Page 1

TO ACCOMPANY AMENDMENT NO. 0007 TO W912HY20R0001

THIS PAGE INTENTIONALLY LEFT BLANK

DOCUMENT 00 11 00.00 45 Page 2

SECTION 00 11 00.00 45

BID SCHEDULE

AMENDMENT NO. 0007

PART 1 GENERAL

1.1 BID SCHEDULE

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.1 Schedule No. 1

Item No.

Description Estimated Quantity

Unit Unit Price

Estimated Amount

SCHEDULE NO. 1

0001 Mobilization and Demobilization 1 JOB SUM $___________

0002 Pre-Dredging Hazard Survey

1 JOB SUM $___________

0003 Removal and Disposal of Pipelines A5 Thru A9, (Assume 900-LF/Each)

4,500 LF $_________$___________

0004 Dredging Maintenance, Current Authorized -47Ft Channel Template (Section No. 1 thru 10)*

587,113 CY $_________$___________

0005 Dredging New Work, New Work Authorized -54Ft Channel Template (Section No. 1 thru 10)*

7,080,264 CY $_________$___________

0006 Pipeline Management (Associated with Dredge Pipe)

1 JOB SUM $___________

0007 DMPA No. 6, Semi-compacted Containment Dike (Upland Embankment Construction)

380,000 CY $_________$___________

0008 DMPA No. 6, New Drop-Outlet

1 JOB SUM $___________

DOCUMENT 00 11 00.00 45 Page 3

Item No.

Description Estimated Quantity

Unit Unit Price

Estimated Amount

SCHEDULE NO. 1

0009 BUS-I Filling Dikes, Hydraulically Constructed Exterior Dike to Initial Target Elevation +8.0 MLLW minimum

8,212 LF $_________$___________

0010 BUS-I Filling Dikes, Install Settlement Plates and Conduct Survey Settlement Monitoring for 6-Months

1 JOB SUM $___________

0011 Final As-Built Drawings

1 JOB SUM $___________

TOTAL SCHEDULE NO. 1 $___________

NOTE: Completion time stated in SECTION 00 73 00.01 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work.

*Contract Line Items 0004 and 0005 excludes the Estimated Amount from Dredging Sections 1a, 5a, 7a and 8a as shown on Drawings and specified below in Option Nos. 9, 10, 11 and 12 respectively.

DOCUMENT 00 11 00.00 45 Page 4

BID SCHEDULE (CONT'D)

(TO BE ATTACHED TO STANDARD FORM 1442)

1.2 Option No. 1 (AM#7)

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 1

0012 Mobilization and Demobilization 1 JOB SUM $___________

0013 Dredging Maintenance, Current Authorized -47Ft Channel Template (Section No. 11 thru 13)

134,726 CY $_________ $___________

0014 Dredging New Work, New Work Authorized -54Ft Channel Template (Section No. 11 thru 13)

3,704,339 CY $_________ $___________

0015 BUS-CQ Filling Dikes, Hydraulically Constructed Exterior Dike to Initial Target Elevation +8.0 MLLW minimum

8,068 LF $_________ $___________

0016 BUS-CQ Filling Dikes, Install Settlement Plates and Conduct Survey Settlement Monitoring for 6-Months

1 JOB SUM $___________

TOTAL OPTION NO. 1 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1 $___________

NOTE FOR OPTION NO. 1: The Government may exercise this Option by written notice to the Contractor no later than 90 Calendar days after award. Award of Option No. 1 is contingent upon availability of funds. An additional time of 218 calendar days will be added to this Contract for completion of this Option.

DOCUMENT 00 11 00.00 45 Page 5

(TO BE ATTACHED TO STANDARD FORM 1442)

1.3 Option No. 2 (AM#7)

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 2

0017 Mobilization and Demobilization 1 JOB SUM $___________

0018 BUS-I, Construct Dike Revetment Armoring Shoreline Protection Berm (STA. 18+00 to STA. 82+00)

6,300 LF $_________ $___________

0019 BUS-I, Rip-Rap Wave Break Structure (STA. 18+00 to

STA. 82+00)

6,300 LF $_________ $___________

TOTAL OPTION NO. 2 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1 AND 2 $___________

NOTE FOR OPTION NO. 2: The Government may exercise Options No. 2 by written notice to the Contractor, singly or in combination with Option No.

3, no later than 210 calendar days after award. Award of this Option is contingent upon availability of funds. An additional time of 90 calendar days will be added to this Contract for completion of this Option whether awarded singly or in combination.

DOCUMENT 00 11 00.00 45 Page 6

(TO BE ATTACHED TO STANDARD FORM 1442)

1.4 Option No. 3 (AM#7)

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 3

0020 BUS-I, Construct Dike Revetment Armoring Shoreline Protection Berm (STA. 0+00 to STA.

18+00)

1,800 LF $_________ $___________

0021 BUS-I, Rip-Rap Wave Break Structure (STA.

0+00 to STA. 18+00)

1,800 LF $_________ $___________

TOTAL OPTION NO. 3 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1, 2 AND 3 $___________

NOTE FOR OPTION NO. 3: The Government may exercise this Option by written notice to the Contractor no later than 210 calendar days after award.

Award of this Option is contingent upon both availability of funds and award of OPTION No. 2. An additional time of 30 calendar days will be added to this Contract for completion of this Option.

DOCUMENT 00 11 00.00 45 Page 7

(TO BE ATTACHED TO STANDARD FORM 1442)

1.5 Option No. 4 (AM#7)

Item No.

Description Estimated Quantity

Unit Unit Price

Estimated Amount

OPTION NO. 4

0022 Mobilization and Demobilization 1 JOB SUM $___________

0023 BUS-CQ, Construct Dike Revetment Armoring Shoreline Protection Berm (STA. 23+00 to

STA. 61+00)

3,800 LF $_________$___________

0024 BUS-CQ, Rip-Rap Wave Break Structure (STA.

23+00 to STA. 61+00)

3,800 LF $_________$___________

TOTAL OPTION NO. 4 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3 AND 4 $___________

NOTE FOR OPTION NO. 4: The Government may exercise Options No. 4 by written notice to the Contractor, singly or in combination with Option No.

5, no later than 90 calendar days after award. Award of this Option is contingent upon availability of funds. An additional time of 90 calendar days will be added to this Contract for completion of this Option whether awarded singly or in combination.

DOCUMENT 00 11 00.00 45 Page 8

(TO BE ATTACHED TO STANDARD FORM 1442)

1.6 Option No. 5 (AM#7)

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 5

0025 BUS-CQ, Construct Dike Revetment Armoring Shoreline Protection Berm ("STA. 0+00 to STA.

23+00" AND "STA.

61+00 to STA. 80+69")

4,269 LF $_________ $___________

0026 BUS-CQ, Rip-Rap Wave Break Structure ("STA. 0+00 to STA.

23+00" AND "STA.

61+00 to STA. 80+69")

4,269 LF $_________ $___________

TOTAL OPTION NO. 5 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4 AND 5 $___________

NOTE FOR OPTION NO. 5: The Government may exercise this Option by written notice to the Contractor no later than 90 calendar days after award. Award of this Option is contingent upon both availability of funds and award of OPTION No. 4. An additional time of 30 calendar days will be added to this Contract for completion of this Option.

DOCUMENT 00 11 00.00 45 Page 9

(TO BE ATTACHED TO STANDARD FORM 1442)

1.7 Option No. 6 (AM#7)

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 6

0027 Mobilization and Demobilization 1 JOB SUM $___________

0028 DMPA No. 6, Emergent Wavebreak Constructed to Elevation +3.0 MLLW

7,357 LF $_________ $___________

TOTAL OPTION NO. 6 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5 AND 6 $___________

NOTE FOR OPTION NO. 6: The Government may exercise this Option by written notice to the Contractor, no later than 210 calendar days after award.

Award of this Option is contingent upon availability of funds. An additional time of 120 calendar days will be added to this Contract for completion of this Option.

DOCUMENT 00 11 00.00 45 Page 10

(TO BE ATTACHED TO STANDARD FORM 1442)

1.8 Option No. 7 (AM#7)

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 7

0029 Mobilization and Demobilization 1 JOB SUM $___________

0030 Nearshore DMPA No.6, Demolish and Dispose Drop-Outlet Structure

1 JOB SUM $___________

TOTAL OPTION NO. 7 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6 AND 7 $___________

NOTE FOR OPTION NO. 7: The Government may exercise this Option by written notice to the Contractor, no later than 210 calendar days after award.

Award of this Option is contingent upon availability of funds. No additional time will be added to this Contract for completion of this Option.

DOCUMENT 00 11 00.00 45 Page 11

(TO BE ATTACHED TO STANDARD FORM 1442)

1.9 Option No. 8 (AM#7)

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 8

0031 POCCA, Removal and Disposal of Pipelines A5 Thru A9, (Assume Addt'l. at 4,100-LF/Each)

20,500 LF $_________ $___________

TOTAL OPTION NO. 8 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6,7

AND 8

NOTE FOR OPTION NO. 8: The Government may exercise this Option by written notice to the Contractor no later than 90 calendar days after award. Award of this Option is contingent upon the availability of funds. No additional time will be added to this Contract for completion of this Option.

DOCUMENT 00 11 00.00 45 Page 12

(TO BE ATTACHED TO STANDARD FORM 1442)

1.10 Option No. 9

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 9

0032 Mobilization and Demobilization 1 JOB SUM $___________

0033 Dredging Maintenance, (Dredge Section 1a) Crossing For Pipeline ID "A2 & A3", (Volume to be added to Section No. 1) Sta.

7+000 to Sta. 7+200

4,903 CY $_________ $___________

0034 Dredging New Work, (Dredge Section 1a) Crossing For Pipeline ID "A2 & A3", (Volume to be added to Section No. 1) Sta.

7+000 to Sta. 7+200

30,487 CY $_________ $___________

TOTAL OPTION NO. 9 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6,7

8 AND 9

NOTE FOR OPTION NO. 9: The Government may exercise Options No. 9 by written notice to the Contractor at any time prior to completion of all authorized work. Award of Option No. 9 is contingent upon availability of funds. An additional time of 30 calendar days will be added to this Contract for completion of Option No. 9.

DOCUMENT 00 11 00.00 45 Page 13

(TO BE ATTACHED TO STANDARD FORM 1442)

1.11 Option No. 10

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 10

0035 Mobilization and Demobilization 1 JOB SUM $___________

0036 Dredging Maintenance, (Dredge Section 5a) Crossing For Pipeline ID "A4", (Volume to be added to Section No.

5) Sta. 30+727 to Sta.

30+927

4,642 CY $_________ $_________

0037 Dredging New Work, (Dredge Section 5a) Crossing For Pipeline ID "A4", (Volume to be added to Section No.

5) Sta. 30+727 to Sta.

30+927

32,921 CY $_________ $___________

TOTAL OPTION NO. 10 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6,7

8,9, AND 10

NOTE FOR OPTION NO. 10: The Government may exercise Options No. 10 through No. 12 by written notice to the Contractor, singly or in combination, the ACO on site will be required to ensure this Option is exercised within any time up to 30 days prior to completion of all authorized work. If the Option is not exercised within 30 days prior to the completion of work, USACE cannot award this Option. Award of Options No. 10 through No. 12 is contingent upon availability of funds. No additional time will be added to this Contract for completion of Options No. 10 through No. 12 whether options are awarded singly or in combination.

DOCUMENT 00 11 00.00 45 Page 14

(TO BE ATTACHED TO STANDARD FORM 1442)

1.12 Option No. 11

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 11

0038 Mobilization and Demobilization 1 JOB SUM $___________

0039 Dredging Maintenance, (Dredge Section 7a) Crossing For Pipeline ID "A10", (Volume to be added to Section No. 7) Sta. 39+813 to Sta. 40+013

949 CY $_________ $___________

0040 Dredging New Work, (Dredge Section 7a) Crossing For Pipeline ID "A10", (Volume to be added to Section No. 7) Sta. 39+813 to Sta. 40+013

30,597 CY $_________ $___________

TOTAL OPTION NO. 11 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6,7

8,9,10, AND 11

NOTE FOR OPTION NO. 11: The Government may exercise Options No. 10 through No. 12 by written notice to the Contractor, singly or in combination, the ACO on site will be required to ensure this Option is exercised within any time up to 30 days prior to completion of all authorized work. If the Option is not exercised within 30 days prior to the completion of work, USACE cannot award this Option. Award of Options No. 10 through No. 12 is contingent upon availability of funds. No additional time will be added to this Contract for completion of Options No. 10 through No. 12 whether options are awarded singly or in combination.

DOCUMENT 00 11 00.00 45 Page 15

(TO BE ATTACHED TO STANDARD FORM 1442)

1.13 Option No. 12

Item No.

Description Estimated Quantity

Unit Unit Price

Estimated Amount

OPTION NO. 12

0041 Mobilization and Demobilization 1 JOB SUM $___________

0042 Dredging Maintenance, (Dredge Section 8a) Crossing For Pipeline ID "A11", (Volume to be added to Section No. 8) Sta. 45+034 to Sta.

45+234

468 CY $________$___________

0043 Dredging New Work, (Dredge Section 8a) Crossing For Pipeline ID "A11", (Volume to be added to Section No. 8) Sta. 45+034 to Sta.

45+234

27,630 CY $________$___________

TOTAL OPTION NO. 12 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6,7

8,9,10,11, AND 12

NOTE FOR OPTION NO. 12: The Government may exercise Options No. 10 through No. 12 by written notice to the Contractor, singly or in combination, the ACO on site will be required to ensure this Option is exercised within any time up to 30 days prior to completion of all authorized work. If the Option is not exercised within 30 days prior to the completion of work, USACE cannot award this Option. Award of Options No. 10 through No. 12 is contingent upon availability of funds. No additional time will be added to this Contract for completion of Options No. 10 through No. 12 whether options are awarded singly or in combination.

DOCUMENT 00 11 00.00 45 Page 16

(TO BE ATTACHED TO STANDARD FORM 1442)

1.14 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

-- End of Document --

DOCUMENT 00 11 00.00 45 Page 17

THIS PAGE INTENTIONALLY LEFT BLANK

DOCUMENT 00 11 00.00 45 Page 18

SF-30_Amend-0007-W912HY20R0001
AMEND-0007_W912HY20R0001-page-2
00 11 00.00 45
00 11 00.00 45 - BID SCHEDULE AMENDMENT NO. 0007
00 11 00.00 45 - BID SCHEDULE
PART 1 GENERAL
1.1 BID SCHEDULE
1.1.1 Schedule No. 1
1.2 Option No. 1 AM#7
1.3 Option No. 2 AM#7
1.4 Option No. 3 AM#7
1.5 Option No. 4 AM#7
1.6 Option No. 5 AM#7
1.7 Option No. 6 AM#7
1.8 Option No. 7 AM#7
1.9 Option No. 8 AM#7
1.10 Option No. 9
1.11 Option No. 10
1.12 Option No. 11
1.13 Option No. 12
1.14 EVALUATION OF OPTIONS July 1990 FAR 52.217-5

File details come from the government source that posted it. Updated .