- Corpus Christi Ship Channel, Texas, Lower Bay Reach in Nueces County, Texas, Channel Improvement Project.
- Solicitation number
- W912HY20R0001
About this file
This solicitation is for a channel improvement project on the Corpus Christi Ship Channel in Nueces County, Texas. The project involves dredging maintenance and new work to deepen sections of the channel to authorized depths of -47 feet and -54 feet, as well as beneficial use of dredged material, pipeline removals, and construction of containment dikes and structures. The solicitation includes specifications for dredging operations, placement of excavated material, safety requirements, and instrumentation needed on dredging plant. Bids are due on January 27, 2020, and the completion time for the base work is stated in the special contract requirements section. The solicitation also contains 12 options that can be exercised after award related to additional dredging, dike construction, and pipeline removals.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W45VAK91002193 010383-1
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Unrestricted Procurement, Request for Proposal, Low est Price Technically Acceptable for Corpus Christi Ship Channel, Texas, Low er Bay Reach in Nueces County, Texas, Channel Improvement Project in w hich proposals are due 27 Jan 20 @ 2:00 PM (CST) is hereby amended as follow s:
Continued on Page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 47
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HY20R0001
X 9B. DATED (SEE ITEM 11)
12-Dec-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3.EFFECTIVE DATE
15-Jan-2020
CODE
US ARMY CORPS OF ENGINEERS
2000 FORT POINT ROAD
P.O. BOX 1229
GALVESTON TX 77553-1229
W912HY 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HY20R0001
A0006-2
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. The specifications for Solicitation No. W912HY20R0001, CORPUS CHRISTI SHIP CHANNEL, TEXAS LOWER BAY REACH IN NUECES COUNTY, TEXAS, are hereby amended as follows:
a) Specifications.
(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45 entitled BID SCHEDULE supersedes that issued with this Solicitation.
(2) SECTION 00 73 46, WAGE RATES – The enclosed SECTION 00 73 46 entitled WAGE RATES supersedes that issued with this Solicitation.
(3) SECTION 35 20 23.16 45 WATERWAY AND MARINE CONSTRUCTION – The enclosed SECTION 35 20 23.16 45 entitled WATERWAY AND MARINE CONSTRUCTION supersedes that issued with this Solicitation.
b) Drawings.
(1) None
c) Attached Files.
(1) None
2. This amendment shall be attached to and become a part of the solicitation.
03 Encls:
1. 00 11 00.00 45, BID SCHEDULE
2. 00 73 46, WAGE RATES
3. 35 20 23.16 45, WATERWAY AND MARINE CONSTRUCTION
SWG FILE NO.: NUECES 803-356 SOLICITATION NO.: W912HY20R0001
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 11 00.00 45
BID SCHEDULE AMENDMENT NO. 0006
PART 1 GENERAL
1.1 BID SCHEDULE
1.1.1 Schedule No. 1
1.2 Option No. 1 (AM#6)
1.3 Option No. 2 (AM#6)
1.4 Option No. 3 (AM#6)
1.5 Option No. 4 (AM#6)
1.6 Option No. 5 (AM#6)
1.7 Option No. 6
1.8 Option No. 7
1.9 Option No. 8
1.10 Option No. 9
1.11 Option No. 10
1.12 Option No. 11
1.13 Option No. 12
1.14 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)
-- End of Section Table of Contents --
DOCUMENT 00 11 00.00 45 Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
DOCUMENT 00 11 00.00 45 Page 2
SECTION 00 11 00.00 45
BID SCHEDULE
AMENDMENT NO. 0006
PART 1 GENERAL
1.1 BID SCHEDULE
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.1 Schedule No. 1
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
SCHEDULE NO. 1
0001 Mobilization and Demobilization
1 JOB SUM $___________
0002 Pre-Dredging Hazard Survey
1 JOB SUM $___________
0003 Removal and Disposal of Pipelines A5 Thru A9, (Assume 900-LF/Each)
4,500 LF $_________ $___________
0004 Dredging Maintenance, Current Authorized -47Ft Channel Template (Section No. 1 thru 10)*
587,113 CY $_________ $___________
0005 Dredging New Work, New Work Authorized -54Ft Channel Template (Section No. 1 thru 10)*
7,080,264 CY $_________ $___________
0006 Pipeline Management (Associated with Dredge Pipe) 1 JOB SUM $___________
0007 DMPA No. 6, Semi-compacted Containment Dike (Upland Embankment Construction)
380,000 CY $_________ $___________
DOCUMENT 00 11 00.00 45 Page 3
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
SCHEDULE NO. 1
0008 DMPA No. 6, New Drop-Outlet
1 JOB SUM $___________
0009 BUS-I Filling Dikes, Hydraulically Constructed Exterior Dike to Initial Target Elevation +8.0 MLLW minimum
8,212 LF $_________ $___________
0010 BUS-I Filling Dikes, Install Settlement Plates and Conduct Survey Settlement Monitoring for 6-Months
1 JOB SUM $___________
0011 Final As-Built Drawings
1 JOB SUM $___________
TOTAL SCHEDULE NO. 1 $___________
NOTE: Completion time stated in SECTION 00 73 00.01 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work.
*Contract Line Items 0004 and 0005 excludes the Estimated Amount from Dredging Sections 1a, 5a, 7a and 8a as shown on Drawings and specified below in Option Nos. 9, 10, 11 and 12 respectively.
DOCUMENT 00 11 00.00 45 Page 4
BID SCHEDULE (CONT'D)
(TO BE ATTACHED TO STANDARD FORM 1442)
1.2 Option No. 1 ( AM#6)
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 1
0012 Mobilization and Demobilization 1 JOB SUM $___________
0013 Dredging Maintenance, Current Authorized -47Ft Channel Template (Section No. 11 thru 13)
134,726 CY $_________ $___________
0014 Dredging New Work, New Work Authorized -54Ft Channel Template (Section No. 11 thru 13)
3,704,339 CY $_________ $___________
0015 BUS-CQ Filling Dikes, Hydraulically Constructed Exterior Dike to Initial Target Elevation +8.0 MLLW minimum
8,068 LF $_________ $___________
0016 BUS-CQ Filling Dikes, Install Settlement Plates and Conduct Survey Settlement Monitoring for 6-Months
1 JOB SUM $___________
TOTAL OPTION NO. 1 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1 $___________
NOTE FOR OPTI ON NO. 1: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or no l at er t han t hr ee mont hs af t er awar d. Awar d of Opt i on No. 1 i s cont i ngent upon avai l abi l i t y of f unds. An addi t i onal t i me of 218 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s
DOCUMENT 00 11 00.00 45 Page 5
Option.
DOCUMENT 00 11 00.00 45 Page 6
(TO BE ATTACHED TO STANDARD FORM 1442)
1.3 Option No. 2 ( AM#6)
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 2
0017 Mobilization and Demobilization 1 JOB SUM $___________
0018 BUS-I, Construct Dike Revetment Armoring Shoreline Protection Berm (STA. 18+00 to STA. 82+00)
6,300 LF $_________ $___________
0019 BUS-I, Rip-Rap Wave Break Structure (STA. 18+00 to STA.
82+00)
6,300 LF $_________ $___________
TOTAL OPTION NO. 2 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1 AND 2 $___________
NOTE FOR OPTI ON NO. 2: The Gover nment may exer ci se Opt i ons No. 2 by wr i t t en not i ce t o t he Cont r act or , s i ngl y or i n combi nat i on wi t h Opt i on No.
3, no l at er t han seven mont hs af t er awar d. Awar d of t hi s Opt i on i s cont i ngent upon avai l abi l i t y of f unds. An addi t i onal t i me of 90 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on whet her awar ded si ngl y or i n combi nat i on.
DOCUMENT 00 11 00.00 45 Page 7
(TO BE ATTACHED TO STANDARD FORM 1442)
1.4 Option No. 3 ( AM#6)
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 3
0020 BUS-I, Construct Dike Revetment Armoring Shoreline Protection Berm (STA. 0+00 to STA. 18+00)
1,800 LF $_________ $___________
0021 BUS-I, Rip-Rap Wave Break Structure (STA. 0+00 to
STA. 18+00)
1,800 LF $_________ $___________
TOTAL OPTION NO. 3 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1, 2 AND 3 $___________
NOTE FOR OPTI ON NO. 3: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or no l at er t han seven mont hs af t er awar d. Awar d of t hi s Opt i on i s cont i ngent upon bot h avai l abi l i t y of f unds and awar d of OPTI ON No. 2. An addi t i onal t i me of 30 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.
DOCUMENT 00 11 00.00 45 Page 8
(TO BE ATTACHED TO STANDARD FORM 1442)
1.5 Option No. 4 ( AM#6)
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 4
0022 Mobilization and Demobilization 1 JOB SUM $___________
0023 BUS-CQ, Construct Dike Revetment Armoring Shoreline Protection Berm (STA. 23+00 to STA. 61+00)
3,800 LF $_________ $___________
0024 BUS-CQ, Rip-Rap Wave Break Structure (STA. 23+00 to
STA. 61+00)
3,800 LF $_________ $___________
TOTAL OPTION NO. 4 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3 AND 4 $___________
NOTE FOR OPTI ON NO. 4: The Gover nment may exer ci se Opt i ons No. 4 by wr i t t en not i ce t o t he Cont r act or , s i ngl y or i n combi nat i on wi t h Opt i on No.
5, no l at er t han t hr ee mont hs af t er awar d. Awar d of t hi s Opt i on i s cont i ngent upon avai l abi l i t y of f unds. An addi t i onal t i me of 90 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on whet her awar ded si ngl y or i n combi nat i on.
DOCUMENT 00 11 00.00 45 Page 9
(TO BE ATTACHED TO STANDARD FORM 1442)
1.6 Option No. 5 ( AM#6)
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 5
0025 BUS-CQ, Construct Dike Revetment Armoring Shoreline Protection Berm ("STA. 0+00 to STA.
23+00" AND "STA. 61+00 to
STA. 80+69")
4,269 LF $_________ $___________
0026 BUS-CQ, Rip-Rap Wave Break Structure ("STA.
0+00 to STA. 23+00" AND "STA. 61+00 to STA.
80+69")
4,269 LF $_________ $___________
TOTAL OPTION NO. 5 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4 AND 5 $___________
NOTE FOR OPTI ON NO. 5: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or no l at er t han t hr ee mont hs af t er awar d. Awar d of t hi s Opt i on i s cont i ngent upon bot h avai l abi l i t y of f unds and awar d of OPTI ON No. 4. An addi t i onal t i me of 30 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.
DOCUMENT 00 11 00.00 45 Page 10
(TO BE ATTACHED TO STANDARD FORM 1442)
1.7 Option No. 6
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 6
0027 Mobilization and Demobilization 1 JOB SUM $___________
0028 DMPA No. 6, Emergent Wavebreak Constructed to Elevation +3.0 MLLW
7,357 LF $_________ $___________
TOTAL OPTION NO. 6 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5 AND 6 $___________
NOTE FOR OPTION NO. 6: The Government may exercise this Option by written notice to the Contractor prior to completion of all authorized work. Award of this Option is contingent upon availability of funds. An additional time of 120 calendar days will be added to this Contract for completion of this Option.
DOCUMENT 00 11 00.00 45 Page 11
(TO BE ATTACHED TO STANDARD FORM 1442)
1.8 Option No. 7
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 7
0029 Mobilization and Demobilization 1 JOB SUM $___________
0030 Nearshore DMPA No.6, Demolish and Dispose Drop-Outlet Structure
1 JOB SUM $___________
TOTAL OPTION NO. 7 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6 AND 7 $___________
NOTE FOR OPTION NO. 7: The Government may exercise this Option by written notice to the Contractor at any time prior to the completion of all authorized work. In this situation, the ACO on site will be required to ensure this Option is exercised within 365 days after NTP. If the Option is not exercised within 365 days after the NTP, USACE cannot award this Option. Award of this Option is contingent upon availability of funds.
No additional time will be added to this Contract for completion of this Option.
DOCUMENT 00 11 00.00 45 Page 12
(TO BE ATTACHED TO STANDARD FORM 1442)
1.9 Option No. 8
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 8
0031 POCCA, Removal and Disposal of Pipelines A5 Thru A9, (Assume Addt'l. at 4,100-LF/Each)
20,500 LF $_________ $___________
TOTAL OPTION NO. 8 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6,7
AND 8
NOTE FOR OPTI ON NO. 8: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or at any t i me pr i or t o t he compl et i on of al l aut hor i zed Wor k. Awar d of t hi s Opt i on i s cont i ngent upon t he avai l abi l i t y of f unds. No addi t i onal t i me wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.
DOCUMENT 00 11 00.00 45 Page 13
(TO BE ATTACHED TO STANDARD FORM 1442)
1.10 Option No. 9
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 9
0032 Mobilization and Demobilization 1 JOB SUM $___________
0033 Dredging Maintenance, (Dredge Section 1a) Crossing For Pipeline ID "A2 & A3", (Volume to be added to Section No. 1) Sta. 7+000 to Sta. 7+200
4,903 CY $_________ $___________
0034 Dredging New Work, (Dredge Section 1a) Crossing For Pipeline ID "A2 & A3", (Volume to be added to Section No. 1) Sta. 7+000 to Sta. 7+200
30,487 CY $_________ $___________
TOTAL OPTION NO. 9 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6,7
8 AND 9
NOTE FOR OPTI ON NO. 9: The Gover nment may exer ci se Opt i ons No. 9 by wr i t t en not i ce t o t he Cont r act or at any t i me pr i or t o compl et i on of al l aut hor i zed wor k. Awar d of Opt i on No. 9 i s cont i ngent upon avai l abi l i t y of f unds. An addi t i onal t i me of 30 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of Opt i on No. 9.
DOCUMENT 00 11 00.00 45 Page 14
(TO BE ATTACHED TO STANDARD FORM 1442)
1.11 Option No. 10
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 10
0035 Mobilization and Demobilization 1 JOB SUM $___________
0036 Dredging Maintenance, (Dredge Section 5a) Crossing For Pipeline ID "A4", (Volume to be added to Section No. 5) Sta.
30+727 to Sta. 30+927
4,642 CY $_________ $_________
0037 Dredging New Work, (Dredge Section 5a) Crossing For Pipeline ID "A4", (Volume to be added to Section No.
5) Sta. 30+727 to Sta.
30+927
32,921 CY $_________ $___________
TOTAL OPTION NO. 10 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6,7
8,9, AND 10
NOTE FOR OPTION NO. 10: The Government may exercise Options No. 10 through No. 12 by written notice to the Contractor, singly or in combination, the ACO on site will be required to ensure this Option is exercised within any time up to 30 days prior to completion of all authorized work. If the Option is not exercised within 30 days prior to the completion of work, USACE cannot award this Option. Award of Options No. 10 through No. 12 is contingent upon availability of funds. No additional time will be added to this Contract for completion of Options No. 10 through No. 12 whether options are awarded singly or in combination.
DOCUMENT 00 11 00.00 45 Page 15
(TO BE ATTACHED TO STANDARD FORM 1442)
1.12 Option No. 11
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 11
0038 Mobilization and Demobilization 1 JOB SUM $___________
0039 Dredging Maintenance, (Dredge Section 7a) Crossing For Pipeline ID "A10", (Volume to be added to Section No. 7) Sta.
39+813 to Sta. 40+013
949 CY $_________ $___________
0040 Dredging New Work, (Dredge Section 7a) Crossing For Pipeline ID "A10", (Volume to be added to Section No. 7) Sta. 39+813 to Sta. 40+013
30,597 CY $_________ $___________
TOTAL OPTION NO. 11 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6,7
8,9,10, AND 11
NOTE FOR OPTI ON NO. 11: The Gover nment may exer ci se Opt i ons No. 10 t hr ough No. 12 by wr i t t en not i ce t o t he Cont r act or , s i ngl y or i n combi nat i on, t he ACO on si t e wi l l be r equi r ed t o ensur e t hi s Opt i on i s exer ci sed wi t hi n any t i me up t o 30 days pr i or t o compl et i on of al l aut hor i zed wor k. I f t he Opt i on i s not exer ci sed wi t hi n 30 days pr i or t o t he compl et i on of wor k, USACE cannot awar d t hi s Opt i on. Awar d of Opt i ons No. 10 t hr ough No. 12 i s cont i ngent upon avai l abi l i t y of f unds. No addi t i onal t i me wi l l be added t o t hi s Cont r act f or compl et i on of Opt i ons No. 10 t hr ough No. 12 whet her opt i ons ar e awar ded si ngl y or i n combi nat i on.
DOCUMENT 00 11 00.00 45 Page 16
(TO BE ATTACHED TO STANDARD FORM 1442)
1.13 Option No. 12
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 12
0041 Mobilization and Demobilization 1 JOB SUM $___________
0042 Dredging Maintenance, (Dredge Section 8a) Crossing For Pipeline ID "A11", (Volume to be added to Section No. 8) Sta.
45+034 to Sta. 45+234
468 CY $_________ $___________
0043 Dredging New Work, (Dredge Section 8a) Crossing For Pipeline ID "A11", (Volume to be added to Section No. 8) Sta.
45+034 to Sta. 45+234
27,630 CY $_________ $___________
TOTAL OPTION NO. 12 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NOs. 1,2,3,4,5,6,7
8,9,10,11, AND 12
NOTE FOR OPTI ON NO. 12: The Gover nment may exer ci se Opt i ons No. 10 t hr ough No. 12 by wr i t t en not i ce t o t he Cont r act or , s i ngl y or i n combi nat i on, t he ACO on si t e wi l l be r equi r ed t o ensur e t hi s Opt i on i s exer ci sed wi t hi n any t i me up t o 30 days pr i or t o compl et i on of al l aut hor i zed wor k. I f t he Opt i on i s not exer ci sed wi t hi n 30 days pr i or t o t he compl et i on of wor k, USACE cannot awar d t hi s Opt i on. Awar d of Opt i ons No. 10 t hr ough No. 12 i s cont i ngent upon avai l abi l i t y of f unds. No addi t i onal t i me wi l l be added t o t hi s Cont r act f or compl et i on of Opt i ons No. 10 t hr ough No. 12 whet her opt i ons ar e awar ded si ngl y or i n combi nat i on.
DOCUMENT 00 11 00.00 45 Page 17
(TO BE ATTACHED TO STANDARD FORM 1442)
1.14 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
-- End of Document --
DOCUMENT 00 11 00.00 45 Page 18
Section 00 73 46 - Page 1
TO ACCOMPANY AMENDMENT 0006 OF SOLICITATION NO. W912HY20R0001
"General Decision Number: TX20200051 01/03/2020 Superseded General Decision Number: TX20190051 State: Texas
Construction Type: Heavy Dredging Counties: Texas Statewide.
DREDGING PROJECTS ALONG THE TEXAS GULF COAST AREA INCLUDING ALL PUBLIC
CHANNELS, HARBORS, RIVERS, TRIBUTARIES AND THE GULF INTRACOASTAL
WATERWAYS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.
If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020
*SUTX1994-001 01/18/1994
Rates Fringes Derrick Operator.................$ 7.25 Dozer Operator...................$ 7.25
Dredge 16"" and Over
DECKHAND....................$ 7.25
DREDGE TENDER OPERATOR......$ 7.25
FIREMAN.....................$ 7.25
FIRST ASSISTANT ENGINEER....$ 7.25
LEVERMAN....................$ 7.25
OILER.......................$ 7.25
SECOND ASSISTANT ENGINEER...$ 7.25
SHOREMAN....................$ 7.25
http://www.dol.gov/whd/govcontracts
Section 00 73 46 - Page 2
TO ACCOMPANY AMENDMENT 0006 OF SOLICITATION NO. W912HY20R0001
THIRD ASSISTANT ENGINEER....$ 7.25
TRUCK DRIVER................$ 7.25
WELDER......................$ 7.25
Dredge Under 16""
DECKHAND.................$ 7.25
DREDGE,TENDER, OPERATOR..$ 7.25
LEVERMAN.................$ 7.25
OILER....................$ 7.25
WELDER...................$ 7.25
Hydraulic Dredging
FIRST COOK...............$ 7.25
HANDYMAN.................$ 7.25
JANITOR-CABIN, PERSON....$ 7.25
MESS PERSON..............$ 7.25
SECOND COOK..............$ 7.25
Marsh Buggy Dragline OILER.....$ 7.25
OPERATOR................$ 7.25
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis- Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking.
Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
http://www.dol.gov/whd/govcontracts
Section 00 73 46 - Page 3
TO ACCOMPANY AMENDMENT 0006 OF SOLICITATION NO. W912HY20R0001
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate). Union Rate Identifiers A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example: PLUM0198- 005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana.
2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data.
EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage
Section 00 73 46 - Page 4
TO ACCOMPANY AMENDMENT 0006 OF SOLICITATION NO. W912HY20R0001
determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part
1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review
Section 00 73 46 - Page 5
TO ACCOMPANY AMENDMENT 0006 OF SOLICITATION NO. W912HY20R0001
Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"
SECTION TABLE OF CONTENTS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
SECTION 35 20 23.16 45
DREDGING AMENDMENT NO. 0006
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.3 MEASUREMENT AND PAYMENT
1.4 WORK COVERED BY CONTRACT PRICE
1.4.1 Existing Conditions
1.5 REFERENCES
1.6 SUBMITTALS
1.7 Work Plan for Pipeline Removals (AM#6)
1.8 CHARACTER OF MATERIAL TO BE REMOVED
1.8.1 Debris Within the Dredging Limits
1.9 EASEMENTS
1.10 UTILITIES ACROSS THE LIMITS OF DREDGING
1.10.1 Known Pipeline/Utility Crossings
1.11 ORDER OF WORK
1.11.1 Dredging Options
1.12 OBSTRUCTION OF CHANNEL
1.13 TEMPORARY REMOVAL OF AIDS TO NAVIGATION
1.14 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS
1.15 SIGNAL LIGHTS
1.16 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM
1.17 PLANT
1.17.1 General Requirements
1.17.2 Capacity
1.17.3 Inspectors (Government Agents) Transportation
1.18 INSPECTION
1.18.1 Equipment
1.18.2 Transportation
1.19 QUANTITY SURVEYS
1.19.1 General
1.19.2 Dredging Sections
1.19.3 Submittals
1.20 FINAL EXAMINATION AND ACCEPTANCE
1.20.1 Acceptance
1.21 SHOALS
1.22 UNANTICIPATED SHOALING
1.23 VARIATIONS IN ESTIMATED QUANTITIES - DREDGING
1.24 CONTINUITY OF WORK
PART 2 PRODUCTS
2.1 BRIDGE-TO-BRIDGE RADIOTELEPHONE EQUIPMENT
2.2 LOOKOUTS AND RADIO COMMUNICATIONS
PART 3 EXECUTION
SECTION 35 20 23.16 45 Page 1
3.1 ESTIMATED QUANTITY OF MATERIAL
3.1.1 Quantity Summary
3.1.2 Required Dredging Prism
3.1.3 Allowable Overdepth
3.1.4 Side And End Slopes
3.1.5 Excessive Dredging
3.2 AREAS TO BE DREDGED
3.3 CONDUCT OF DREDGING WORK
3.3.1 Pre-Operations Safety Coordination Meeting
3.3.2 Protection of Existing Waterways
3.3.3 Adjacent Property and Structures
3.4 PLACEMENT OF EXCAVATED MATERIAL
3.4.1 General
3.4.1.1 Misplaced Material
3.4.1.2 Placement Operations Inspection
3.4.1.3 Placement Area Drainage
3.4.1.4 Maintenance of Existing Dike and Drop-outlet Structures
3.4.2 Spillway Operations
3.4.3 Placement Area and/or BUS Sites
3.4.3.1 Beneficial Use Sites (BUS), "I" and "CQ"
3.4.3.2 DMPA NO. 6 - Upland Confined Placement
3.5 PRESERVATION OF PUBLIC AND PRIVATE PROPERTY
3.5.1 Damages
3.5.2 Accountability and Restoration
3.6 ALTERNATE PLACEMENT AREA(S) PROPOSED BY CONTRACTOR WITH BID AFTER
AWARD OF CONTRACT
3.6.1 Data Submittal
3.7 METHOD OF PLACEMENT
3.7.1 Pipeline Route
3.8 DISPOSAL IN PLACEMENT AREA
3.8.1 Utilities within the Placement Area and/or BUS
3.8.2 Unauthorized Placement of Material
3.8.3 Debris Disposal
3.9 DREDGE PIPELINES
3.9.1 Submerged Pipeline
3.9.2 Submerged Pipeline Lighting Requirements
3.9.3 Floating Pipeline
3.9.4 Pipeline Leaks
3.9.5 Pre-dredging Hazard Survey Report
3.9.6 Magnetometer Survey Report
3.10 WORK IN THE VICINITY OF OTHER GOVERNMENT CONTRACTORS
3.11 DREDGING AND DREDGE RELATED MARINE WORK (CESWG)
3.12 AUTOMATIC IDENTIFICATION SYSTEM
3.13 DREDGE PLANT INSTRUMENTATION
3.13.1 Hydraulic Pipeline Dredges
ATTACHMENTS:
Appendix 1 - QUANTITY SUMMARY TABLE
-- End of Section Table of Contents --
SECTION 35 20 23.16 45 Page 2
SECTION 35 20 23.16 45
DREDGING
AMENDMENT NO. 0006
PART 1 GENERAL
1.1 SUMMARY
The work in this Section consists of furnishing plant, labor, materials, and equipment and performing the operations necessary for the removal of materials to the required dimensions shown, satisfactory disposal thereof, and other operations incidental thereto.
1.2 DEFINITIONS
(a) Plant: Hydraulic pipeline (i.e. cutterhead, plain suction, sidecaster) dredges; Mechanical Type (Bucket) or clamshell dredges;
Hopper dredges, etc.
(b) Dredging Equipment: Machinery, structures, equipment, piping, vessels, dredges, dump scows, tugs, boats, barges, and systems purchased, owned, rented or leased by Contractor for use in accomplishing the Work, but not intended for incorporation into the Dredging Project as a permanent structure.
(c) Dredging: The underwater excavation of soils for channel and/or harbor deepening. Removal of loose or hard, compacted materials, either for maintenance or new work projects.
1.3 MEASUREMENT AND PAYMENT
Measurement and payment for DREDGING will be paid for in accordance with provisions of the SECTION 01 22 00.10 MEASUREMENT AND PAYMENT.
1.4 WORK COVERED BY CONTRACT PRICE
Base bids on the quantity of dredging indicated. If the total quantity of dredging varies from that specified as the basis for bidding, the Contract price will be adjusted in accordance with the CONTRACT CLAUSE entitled CHANGES. The dredging conditions specified and indicated describe conditions which are known. However, the Contractor is responsible for other conditions encountered which are not unusual when compared to the conditions recognized in the dredging business as usual in dredging activities such as those required under this Contract. The Contract price for dredging will include the cost of removal and placement of the material as specified in the Paragraphs: CHARACTER OF MATERIAL and PLACEMENT OF EXCAVATED MATERIAL. The Contract price for dredging will include the costs for maintenance of dikes and ditches necessary to confine the material within the areas shown.
1.4.1 Existing Conditions
The drawings already prepared as specified in the CONTRACT CLAUSES Paragraph entitled CONTRACT DRAWINGS AND SPECIFICATIONS represent
SECTION 35 20 23.16 45 Page 3 conditions existing as of the date of their preparation using average existing conditions. However, to reflect anticipated shoaling or scour occurring between the dates of preparation of the drawings and the dates of the "Before-dredging" surveys sections, the estimated dredging quantities stated in the Bid Schedule have been adjusted accordingly. The depths and elevations shown will be verified and corrected by fathometer soundings taken by the Government before dredging. The Government will normally use a frequency of 200 kHz to conduct hydrographic surveys. If the surveys indicate the presence of fluff in the channel, a frequency of 40 kHz will be used. Determination of quantities removed and the deductions made from them to determine quantities by in-place measurement to be paid for in the area specified, after having once been made will not be reopened, except on evidence of collusion, fraud, or obvious error.
1.5 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-2-5025 (2015) Dredging and Dredged Material Management
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.6 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Notification Prior To Commencement of Dredging Operations ; G
Indicate commencement of dredging operations, and location of dredge(s).
Temporary Removal of Aids To Navigation ; G
Work Plan for Pipeline Removals ; G
Contractor Work Plan for pipeline removals to be submitted for acceptance as specified below.
SD-02 Shop Drawings
Submerged Pipeline ; G
Indicate pipeline location and installation details as outlined in the Subparagraph: Submerged Dredge Pipeline.
Pipeline Route ; G
SECTION 35 20 23.16 45 Page 4
A detailed pipeline diagram for each Placement Area detailing the pipeline route and anchor locations are to be submitted prior to commencing work on this project.
SD-06 Test Reports
Pre-dredging Hazard Survey Report ; G
Magnetometer Survey Report ; G
Report to be submitted as specified.
1.7 Work Plan for Pipeline Removals (AM#6)
Within 10 calendar days from award date, submit for acceptance in writing the Work Plan for Pipeline Removals . The purpose of the Work Plan is to present a comprehensive overview of known or potential pipeline removal issues which the Contractor shall address prior to and or during dredging construction operations in the area of these five pipelines indicated on construction Contract Drawings and denoted A5 thru A9 in table Paragraph:
Known Pipeline/Utility Crossings. Accordingly as part of the work the Contractor is responsible for removal and disposal of these lines.
Project sponsors (Port of Corpus Christi Authority) will perform the due diligence to contact original owners and steps necessary for Contractor to be released to perform the work. Include in the Work Plan for Pipeline Removals , but not limited to, the following:
(1) Contractor to make statutory OneCall notices 48-72 hours in advance of the work on the pipeline.
(2) Contractor to perform pre-work including the following:
a. Verify and confirm location by performing a survey of the pipeline to be removed, including proposed cut/tie-in points
b. If isolation valves are identified, pipeline section to be closed off
c. If existing taps are present, confirm line is depressurized and void of product
(3) If no isolation valves found, perform hot tap on pipeline to confirm if line has been depressured and/or if any product remains in the line.
(4) Contractor to install containment booms at perimeter of work area to contain inadvertent returns/spills.
(5) Contractor to have ready/on-site additional containment booms to be deployed within bay/ship channel traffic lanes if necessary to collect inadvertent returns/spills
(6) Contractor to coordinate/schedule with Port on ship traffic avoidance
(7) Contractor to acquire/secure temporary work areas onshore/within bay
(8) Contractor to perform dredge (clam bucket typical)/jetting
SECTION 35 20 23.16 45 Page 5 activities to remove soil above pipelines, loading debris onto material barge(s)
(9) Contractor to coordinate/schedule with Port on ship traffic avoidance
(10) To the extent practicable, run cleaning pigs with an approved, environmentally suitable cleaning solution – minimum requirements would be 1.5 x volume of pipeline being removed - dispose of same in frac tanks onshore/barges or thru temporary pigging facilities
(11) Cold cut the line for section of pipeline to be removed
(12) Contractor to remove pipelines and place onto material barge(s)
(13) Divers to be deployed to jet out, re-attach pull sections that may break off and/or to collect any asbestos containing material (ACM) – if present (typically found as external pipe coating on older pipelines) for placement into material barges
(14) Contractor to maintain prior authorized channel profile during/after work is complete
(15) Contractor to dispose of removed material to an appropriate/ approved landfill/salvage site
(16) Contractor to cap/blind flange off any pipes to be abandoned in-place onshore or outside of channel profile ( As neccessary ).
Ensure ends of abandoned line is buried at least 3 ft and cover with cement sand bags.
1.8 CHARACTER OF MATERIAL TO BE REMOVED
All MAINTENANCE material can be dredged and disposed of as per NEW WORK material. Explorations, including core borings, to determine the character of materials to be removed have been obtained by the Government and the results are indicated. The borings data is for information purposes only.
Borings were drilled during the 1960s, 1970s, 2000, and in 2018. Portions of the boring logs have been previously dredged.
Bidders are expected to examine the worksite and the records of previous dredging activities, which are available upon request from the Galveston District Southern Area Resident Office and after investigation, decide for themselves the character of materials.
1.8.1 Debris Within the Dredging Limits
Debris including but not limited to, metal bands, pallets, pieces of broken cable, rope, stumps, and broken piles may be encountered. The Government has no knowledge of existing wrecks, wreckage, or other material of that size or character as to require the use of explosives or special or additional plant for its economical removal. Debris removed from the dredged area is to be removed from the water. Disposal is to be the responsibility of the Contractor and disposal is to be outside the limits of Government property. If the actual conditions differ from those stated or shown, an adjustment in Contract price or time of completion, or both, will be made in accordance with the CONTRACT CLAUSE entitled
DIFFERING SITE CONDITIONS.
SECTION 35 20 23.16 45 Page 6
1.9 EASEMENTS
Permits authorizing the laying of shore pipe, and for placement of dredge material in the Placement Area(s), are on file and available for examination in the Corpus Christi Resident Office of the U.S. Army Corps of Engineers, 1920 N. Chaparral, Corpus Christi, Texas 78401. The instruments authorizing the laying of shore pipelines may contain certain restrictions relative to specific route, location, and general use of the land. These instruments form a part of these specifications and the Contractor is to strictly comply with the terms thereof.
1.10 UTILITIES ACROSS THE LIMITS OF DREDGING
It is the Contractor's responsibility to investigate the location of utility crossings. The Contractor is to take precautions against damages which can result from dredging operations in the vicinity of the utility crossings. If damage occurs as a result of dredging operations, the Contractor will be required to suspend dredging until the damage is repaired and approved. Costs of these repairs and downtime of the dredge and attendant plant is to be at the Contractor's expense.
1.10.1 Known Pipeline/Utility Crossings
There are pipelines and or utilities which are within the work limits.
The following pipeline/utilities cross the area(s) to be dredged:
Approximate Station
LINE "ID"
ACTION
REQUIRED
Permit No.
Description Owner
7+099 (A2) R/R by Owner, If Required
8135 One 8-inch Electrical Conduit
AEP/Central Power & Light
7+102 (A3) R/R by Owner, If Required
7757 One 20-inch (Water line)
Nueces County Water District#4
30+827 (A4) R/R by Owner, If Required
9369 One 6 inch Gas RILEY
38+099 (A5) Removal by Corp Contractor
1885 One 16-inch pipeline (Gas)
BOSS
Exploration
38+099 (A6) Removal by Corp Contractor
1885 One 12-inch pipeline (Gas)
BOSS
Exploration
38+099 (A7) Removal by Corp Contractor
1885 One 6-inch pipeline (Gas)
BOSS
Exploration
SECTION 35 20 23.16 45 Page 7
Approximate Station
LINE "ID"
ACTION
REQUIRED
Permit No.
Description Owner
38+099 (A8) Removal by Corp Contractor
1885 One 4-inch pipeline (Gas)
BOSS
Exploration
38+099 (A9) Removal by Corp Contractor
1885 One 4-inch pipeline (Gas)
BOSS
Exploration
39+913 (A10) R/R by Owner, If Required
7045 One 12-inch pipeline (Gas)
RILEY
45+134 (A11) R/R by Owner, If Required
1347 One 12-inch pipeline (Gas)
SOUTHCROSS
EVERY EFFORT HAS BEEN MADE TO GIVE ALL PERTINENT DETAILS ON THE LOCATION
OF PIPELINES/UTILITIES. THE DATA FURNISHED ON THE PLANS ARE BELIEVED TO
BE SUBSTANTIALLY CORRECT. HOWEVER, THE EXACT LOCATIONS MAY VARY FROM THAT
SHOWN: THEREFORE THE CONTRACTOR IS TO COOPERATE WITH THE RESPECTIVE
OWNERS TO ESTABLISH THE ACTUAL POSITION OF THE PIPELINES/UTILITIES. THE
U.S. ARMY CORPS OF ENGINEERS PERMITS OF THE RESPECTIVE PIPELINES AND
PREVIOUS SURVEYS ARE AVAILABLE IN THE CORPUS CHRISTI RESIDENT OFFICE.
LINES IDENTIFIED IN THIS SECTION MAY BE PRESENT IN THE TEMPLATE AT THE
TIME THE NOTICE TO PROCEED IS ISSUED THAT MAY REQUIRE THE CONTRACTOR TO
STEP DREDGE AND/OR SKIP DREDGE IN PROXIMITY OF SUCH LINES AND RETURN AFTER
LINE REMOVAL TO COMPLETE THE AREA LATER. CONTRACTOR TO PROVIDE AND
INCLUDE IN THE CONTRACTORS PIPELINE REMOVAL WORK PLAN PROCEDURES/PLAN FOR
NON-CONTINUOUS WORK CONDITIONS.
THE FOLLOWING IS FURNISHED FOR INFORMATION ON VERIFYING PIPELINE
OWNERSHIPS:
Lonestar Notification Center 1-800-545-6005 or online at www.Lonestar811.com
Texas 811 (Dig-Tess) 1-800-344-8377
1.11 ORDER OF WORK
Both Maintenance and New Work ship channel improvement construction work will be allowed to be dredged and disposed of simultaneously.
The Contractor shall order dredging work such that Beneficial Use Site
SECTION 35 20 23.16 45 Page 8
(BUS) "I" is completed first.
The start and completion of non-dredging upland earthwork construction efforts at DMPA No. 6 may be done any time prior to placement.
In the event that Option No. 1 is not exercised and BUS I is complete but additional material remains; the contractor will be directed to place material in alternate site BUS CQ by the Contracting Officer.
For bidding purposes, material shall be distributed to the sites as shown in the Appendix 1-Quantity Summary Table, attachment to this SECTION. The Government may change the order of work at any time and at no additional cost to the Government.
1.11.1 Dredging Options
Dredging Options, if awarded by the Government, will be as specified in
SECTION 00 11 00.00 45 BID SCHEDULE.
1.12 OBSTRUCTION OF CHANNEL
The Government will not undertake to keep the Channel free from vessels or other obstructions, except to the extent of applicable regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work using a method that will obstruct navigation as little as possible, and if the Contractor's plant does obstruct the Channel and makes passage of vessels difficult or endangers them, the plant is to be promptly moved on the approach of a vessel as far as may be necessary to afford a practicable passage. Upon completion of the work, promptly remove plant, including ranges, buoys, piles, and other marks placed under this Contract.
1.13 TEMPORARY REMOVAL OF AIDS TO NAVIGATION
The temporary removal or changes in locations of channel markers may be required to facilitate dredging operations. Notify the Contracting Officer at least 21 days prior to the date that the removal or change in location of channel markers will be required so the U.S. Coast Guard can perform the work and so navigation interests may be informed sufficiently in advance of the proposed removal or change in location.
The Contractor is not to remove, change the location of, obstruct, willfully damage, make fast to, or interfere with aids to navigation.
Indicate temporary removal or changes in locations of channel markers required to facilitate dredging operations.
1.14 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS
Notify the Resident Engineer, Corpus Christi Resident Office, in writing, at least 10 days prior to commencement of dredging operations, the location or locations at which a dredge or dredges will be placed on the work. This information is required in addition to the progress charts and schedule provided for in the CONTRACT CLAUSE entitled SCHEDULE FOR
CONSTRUCTION CONTRACTS.
1.15 SIGNAL LIGHTS
Display signal lights and conduct operations in accordance with the
SECTION 35 20 23.16 45 Page 9
General Regulations of the Department of the Army and of the U.S. Coast Guard governing the:
i) lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations;
ii) lights to be displayed on dredge pipe lines;
iii) day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel;
iv) and the passing by other vessels of floating plant working in navigable channels as set forth in United States Coast Guard publication entitled Navigation Rules and Regulations Handbook. Web site location:
http://www.navcen.uscg.gov/?pageName=navRuleChanges
1.16 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM
The work under this Contract requires use of the National Dredging Quality Management Program (DQM), formerly known as Silent Inspector (SI) to monitor the dredge's status at all times during this Contract in accordance with the SECTION 35 20 23.33 NATIONAL DREDGING QUALITY
MANAGEMENT PROGRAM PIPELINE HYDRAULIC DREDGE.
If the Contractor elects to use a Mechanical Type (Bucket) or clamshell dredge plant to monitor the scow's status at all times during this Contract it will do so in accordance with the SECTION 35 20 23.13 NATIONAL
DREDGING QUALITY MANAGEMENT PROGRAM SCOW - TRACKING PROFILE.
1.17 PLANT
1.17.1 General Requirements
Keep the necessary dredge equipment and attendant plant on the job to meet the requirements of the work. The dredge equipment and attendant plant is to be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in specifications and…